The document outlines 16 punchpoints that need to be addressed at a cell site, including creating space for equipment, installing doors and ladders, addressing earthing and power supply issues, commissioning air conditioning and generators, sealing openings properly, and completing other infrastructure work like painting the tower and installing antenna mounts. Several items require establishing connections, such as earthing pits and bus bars, as well as installing new components like energy meters, DC power supplies, and aviation lamps. Overall, the punchpoint list identifies necessary infrastructure work that must be completed before the cell site is fully operational.
The document outlines 16 punchpoints that need to be addressed at a cell site, including creating space for equipment, installing doors and ladders, addressing earthing and power supply issues, commissioning air conditioning and generators, sealing openings properly, and completing other infrastructure work like painting the tower and installing antenna mounts. Several items require establishing connections, such as earthing pits and bus bars, as well as installing new components like energy meters, DC power supplies, and aviation lamps. Overall, the punchpoint list identifies necessary infrastructure work that must be completed before the cell site is fully operational.
The document outlines 16 punchpoints that need to be addressed at a cell site, including creating space for equipment, installing doors and ladders, addressing earthing and power supply issues, commissioning air conditioning and generators, sealing openings properly, and completing other infrastructure work like painting the tower and installing antenna mounts. Several items require establishing connections, such as earthing pits and bus bars, as well as installing new components like energy meters, DC power supplies, and aviation lamps. Overall, the punchpoint list identifies necessary infrastructure work that must be completed before the cell site is fully operational.
The document outlines 16 punchpoints that need to be addressed at a cell site, including creating space for equipment, installing doors and ladders, addressing earthing and power supply issues, commissioning air conditioning and generators, sealing openings properly, and completing other infrastructure work like painting the tower and installing antenna mounts. Several items require establishing connections, such as earthing pits and bus bars, as well as installing new components like energy meters, DC power supplies, and aviation lamps. Overall, the punchpoint list identifies necessary infrastructure work that must be completed before the cell site is fully operational.
Space for Space is not available for BTS 4 Space need to be created Equipments and TRSM Rack Artistatic mat is not available Create artstatic mat and make 5 Floor and not lavelled ground and lavelled it Door is not available for Set locking system and 6 Door locking sealing in door Create extra ID ladder for 7 ID ladder Space is not available space Light not working and no Created socket for charging 8 Light sockets for laptop charging and commission the light Create Connection of Earthing 9 Earthing System Earthing pits are not connected Pit Create EGB and IGB and 10 Earthing bus bar EGB and IGB not available make connection Create termination and check 11 PIU/ACDB No termination at PIU/ACDB commisioned
12 Mains Incomer No Energy Meter installed Install the Energy Meter
DC Power not available and Create DC Power and need to
13 DC Power supply MCB is not available for BTS put the MCB
14 DG Not Commissioned Need to commission
Sealing not done and not Create sealing and
15 Air-Conditioning commissioned commission it
16 WFT Roxtec are not properly sealed Create sealing
Not painted in body of tower Create platform and paint the
17 Tower and no platform tower Space is not available for Created space for HCT and 19 Cable ladder HCT and VCT VCT LA is not connected to 21 Lighting Protection Need to connect earthing pits earthing pit Aviation lamp is not 22 Aviation lamp Need to commission commissiond Need to installed antenna 24 Antenna mount Antenna mount is not installed mount