HISTORY
UPP BARAT
UPP PUSAT
UPP SELATAN
CILIWUNG RIVER
June 1997 : Cooperation Agreement between PAM Jaya (DKI Water Operator) and Suez
Environnement (Western Jakarta) and with Thames Water (Eastern Jakarta) :
boundary of Ciliwung River.
Form of Cooperation: Delegation of PAM Jaya water service to the private
operators by way of concession. Utilities’ asset will be returned to PAM Jaya
after the end of cooperation period. 3
3
INSTITUTIONAL STAKEHOLDERS MAPPING
4
4
PALYJA SHARE HOLDING
51% 49%
Suez Environnement Astratel Nusantara
Water supply
- Production
- Distribution
- Customer services
(metering – billing –
collection)
- Maintenance & Repair
- Investment
Contract performances
measured in terms of
≈ 4.5 million
P opulation
407,000
C onnections
≈ 5,300 km
N etw ork
159,8M m3
Volum e B illed 2012
≈ 1,400
E m ployees
≈ 1,171 BIDR
R evenue 2012
≈ 1,7 BIDR*
Investm7ent
* 1 9 9 8 -2 0 1 2
HEALTH AND SAFETY
8
HEALTH AND SAFETY
M e d ica l ch e ck u p fo r a ll PA LY JA e m p lo ye e s
Ve h icle R a te A ccid e n t
**fre qu e n cy ra te : N u m b e r o f a ccid e n t p e r to ta l o f h o u rs w o rke d b y a ll
e m p lo ye e s.
***se ve rity ra te : N u m b e r o f d a ys a w a y fro m w o rk d u e to w o rk p la ce
in ju ry o r illn e ss p e r to ta l n u m b e r o f h o u rs w o rke d b y a ll e m p lo ye e s. 9
Water Operating System
10
10
JAKARTA MAIN WATER RESOURCES
1%
1% 61%
33%
4%
11
PALYJA WATER TREATMENT
PLANTS AND DISTRIBUTION
CENTERS
BTW
Cikokol
Max 100 l/s WTP
Pejompongan 1&2
Max 2000 + 3600 l/s
DCR 4
2,200 l/s
Raw Water
DCR 5 PJT-II
1,100 l/s
Max 6200 l/s
BTW
Cisadane
Max 2900 l/s WTP
Cilandak
400 l/s
Current water
delivery to the system
8.1 m3/sec
12
12
WATER TREATMENT PLANTS
AND MAJOR RESERVOIRS
13
13
Distribution Network
PALYJA NETWORK
- TOTAL Network length: 5,300 km
- Network Extension 1,320 km
- PALYJA rehabilitation 1,008 km of pipe.
Materials:
CI: C a st Iro n
DCI: D u ctile C a st Iro n GIP: G a lva n ize d Iro n
HDPE: H ig h D e n sity P o lye th yle n e PVC: P o lyvin yl C h lo rid e
STL: S te e l Others: A sb e sto s-C e m e n t a n d u n kn o w n
14
14
Network maintenance
2012 Figures
M ore than 63,000 Visible and invisible leaks repaired
HELIUM DETECTION:
4,665 km of network inspected to find leakages
2,999 invisible leakages detected
15
15
Key Performance Indicators
16
16
KEY PERFORMANCE INDICATORS
Volume Sold
+ 6.5 m illions m 3
17
17
KPI improvements - 1998 to 2011
18
Improvement of Supply Conditions
1998 2012
In 15 years, around 2300 km of pipe have been laid for rehabilitating or extending the netw ork
19
19
TARIFFS
20
TARIFF STRUCTURE SINCE JANUARY 2007
UPPER CLASS & SMALL UPPER CLASS & SMALL NON DOMESTIC
BUSINESS (KIIIB) BUSINESS (KIVA) (KIVB)
22
22
CROSS SUBSIDIZED STRUCTURE
Customers, Volume sold and Revenue per Tariff group
23
23
CROSS SUBSIDIZED STRUCTURE
Water Tariff per Tariff group (volumetric)
24
24
Evolution of Customer database
1998 / 2012
1998 : 201,668
2012: 407,470
+ 52%
+ 92%
+ 43%
+ 78%
+ 842%
+ 72%
D om estic and in particular low incom e population (K 2
+ K 3A ) benefited the m ost of C overage extension and
increase in connections 25
25
ISO Certifications
26
26
Certifications
ISO 17025 / ISO 9001 / OHSAS
28
CORPORATE SOCIAL RESPONSIBILITY
29
29
PALYJA CORPORATE SOCIAL
RESPONSIBILITIES VISION
30
THANK YOU
Melayani Dengan Hati