Method Statment For Earthing Installation

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

Method Statement for Installation of Earthing works

610555-CB2007-A15-0006-01

NASS Contracting Company W.L.L Abu Dhabi


PROJECT: CB2007-​MEP​ WORKS –POWER ISLAND.UNIT # 61

METHOD STATEMENT

FOR

Installation of Earthing works.

Doc. No: --------------------------


NASS DOC: ------------------------------

REASON FOR ORIGIN BY PROJECT


REV DATE HATCH (EPCM)
REVISION Devanand MANAGER

Method Statement ​for Installation of UPVC Pipes


Page no. 1
Method Statement for Installation of Earthing works
610555-CB2007-A15-0006-01

CONTENTS:

1. PURPOSE

2. SCOPE

3. METHOD

4. REFERENCE DOCUMENTS

5. CONSTRUCTION RESOURCES

6. HEALTH & SAFETY

7. ENVIRONMENTAL ISSUE

8. QUALITY CONTROL REQUIRMENT

Method Statement ​for Installation of UPVC Pipes


Page no. 2
Method Statement for Installation of Earthing works
610555-CB2007-A15-0006-01

Method Statement for Installation of Earthing works

1. Purpose:
The purpose of generating this Method statement is to define the procedure step by step to
implement the correct practices for ​Installation of Earthing works ​through the guidelines
herein so as to ensure that the job execution complies with the requirements and serves the
intended function to a satisfactory level. 

2. Scope:

The Method Statement covers general requirements and all operations in connection with
Earthing works on the package CB2007-CONCRETE WORKS-POWER ISLAND. UNIT #61 at
Al Taweelah Alumina.

3. Method:

3.1 Preparation of work:

Before the commencement of any installation activity, the following procedures are required to
be carried out:

3.1.1 Ensure that the work area is ready and safe to start the installation of Earthing
works.

3.1.2 Ensure the installation of Earthing system are carried out in accordance with
manufacturer’s installation recommendations, requirement of applicable
standards and in accordance with recognized industrial practices and specified in
project specifications to ensure that installation complies with requirements.

3.1.3 Prior to start the installation, refer to the approved shop drawings related to the
area of installation and ensure that required materials are available at site as per
approved material submittals.

3.1.4 Ensure that the issued materials are of approved specifications/ submittals and
as per the requirement of the shop drawings.

Method Statement ​for Installation of UPVC Pipes


Page no. 3
Method Statement for Installation of Earthing works
610555-CB2007-A15-0006-01

3.2 Storage of Material:

3.2.1 Materials that comes to the site premises, shall be clearly identified by tagging or
labeling and stored within the concerned site area or at the designated space
and shall remain under the custody of the concerned division who ensures
adequate storage.

3.2.2 Ensure the materials are stored properly and there is no mark of damage or
deformity of any kind before issuing the material from site store. All materials and
accessories shall also be free from dust, scale or oil.

3.2.3 Inspect products on delivery to ensure compliance with the specifications,


undamaged and properly protected.

3.2.4 Items that are damaged or bad or unusable or non-conforming shall be


segregated and labels to be provided to avoid accidental use.

3.3 Installation of Earthing works:

3.3.1 Concerned Electrical site supervisor shall ensure the locations of all earth pits as
per the approved shop drawings. Ensure the location of earth pits are
coordinated with other external services like water supply pipe line, drainage
pipe lines, gas pipe lines and other services.

3.3.2 Adjacent earth electrodes shall be spaced at least 2.4 mtrs. apart.

3.3.3 The copper bonded earth rods shall be driven in earth using driving studs. After
achieving a minimum depth of approximately 3mtrs, the earth resistance shall be
measured.

3.3.4 The earth pit shall be installed after completion of installation of earth rods
connections and clear gap of 50 mm shall be maintained between top of earth
electrode and earth pit cover. The top of earth pit shall be in level with the
finished level in the area.

3.3.5 Earth pits shall be checked for recommended earth values and same shall be
recorded.

Method Statement ​for Installation of UPVC Pipes


Page no. 4
Method Statement for Installation of Earthing works
610555-CB2007-A15-0006-01

3.3.6 The PVC sheathed single core earthing cables of specified size shall be laid
between the earth pit and the earth bar and terminated with proper compression
type lugs/ clamps as per the approved shop drawings and specifications.

3.3.7 All earthing connections shall be made after cleaning the surface thoroughly and
tightness checks for each connection shall be performed.

3.3.8 Jointing of cables​: Permanent cable conductors joints shall be made by


exothermic welding below ground or crimping for above ground connections.
Method for Exothermic welding as shown below:
a) Position cleaned conductors in mould after ensuring mould is dry, by
pre-heating or making a test joint.
b) Lock mould with handle clamp and place metal retaining disc in bottom of
mould crucible.
c) Pour weld powder into mould and place small amount of starting powder on
edge of mould for easy ignition.
d) Close mould lid securely.
e) Ignite starting powder using flint gun.
f) Reaction takes place. Wait several seconds to allow metal to solidify before
opening mould.
g) Remove weld and clean mould carefully before making next connection.

3.3.9 Ensure the installation is in line with the approved shop drawings and
manufacturer’s recommendations.

3.3.10 Ensure all the earth bars are properly fixed to the wall and are freely accessible.

3.3.11 On completion of reasonable part of work area wise an inspection checklist will
be generated and respective engineers will be called for inspection.

3.4 Commissioning procedure:

3.4.1 Ensure the earth bars are in level using spirit level.
3.4.2 Check the continuity of the earth cables from the respective earth bar to the main
earth bar.
3.4.3 Check the earth resistance values at the earth pits individually and ensure that
the values are less than one ohm.

4. Reference Documents:

● IFC drawings and BOQ received from Main contractor.


● Scope of works.
● Environment, health and safety plan - 610555-CB2007-A01-0002-00.
● Project Quality Plan - 610555-CB2007-A01-0003-00.

Method Statement ​for Installation of UPVC Pipes


Page no. 5
Method Statement for Installation of Earthing works
610555-CB2007-A15-0006-01

5. Construction Resources:
5.1 Manpower:
In general the following Supervision & resources will be in deployed:
● Project Manager
● Site Supervisor
● General Labour

5.2 Plant & Equipment:


● Portable Hand tools.
● Portable Drill Machine
● Earth resistance tester
● Continuity tester.
● Mould
● Handle clamp

5.3 Materials:
The specific materials for which approvals are required prior commencement of works are as
follow:
● Earth pits
● Earthing rods
● Earthing cables
● Crimp connections.
● Connection lugs
● Earth bus bar with disconnecting link.
● Weld powder

5.4 PERSONAL​ PROTECTIVE EQUIPMENTS TO BE USED:

Method Statement ​for Installation of UPVC Pipes


Page no. 6
Method Statement for Installation of Earthing works
610555-CB2007-A15-0006-01
All workers will be issued and trained in use of the required PPE equipment to comply with contract
procedures and local regulations and will be supplemented with PPE as required by MSDS & COSHH
assessments. This will include but will not be limited to;

● Hard Hats
● Safety Boots with ankle support and steel toe caps
● Safety Goggles
● High Visibility Vests / Overalls with integrated reflective strips
● Chemical corrosion resistant hand gloves
● Face Mask , if recommended by MSDS depending on Product

6. Health & Safety

6.1 Risk Assessment Process Summary


● The Health Safety and Environment Project Management Plan institutes the overall
mechanism for the risk management processes with regard to the Project. Processes
are implemented at the earliest stages within the project cycle, identifying risk and
facilitating opportunity for the application of appropriate mitigation strategies. As an
integral part of the planning process, prior to the commencement of any operational
activity a suitable and sufficient specific assessment of the risks associated with the
works should be undertaken.

6.2 Risk Assessments


● A variety of mechanisms, such as method statement briefings and tool box talks will be
implemented to ensure all relevant personnel are appropriately informed. STARRT Card
is explained to all workmen before start of Installation.

● In addition to their safety induction received at their arrival on site, all the workers will
have a toolbox meeting in order to be briefed about the risks of their specific work task,
prior to start of works. Identification and application of control measures are based on
the following hierarchy; Eliminate, Reduce, Isolate, Control, Provide, Direct

● A detailed risk assessment is attached to this Method Statement​.

6.3 General Work Instructions

● Starting instructions will be given by the supervisors at the start of each activity to
explain the methodology of works and to communicate safe working procedures to the
operatives. These talks are structured in a way to highlight to major risks involved in the
activity and the various control measures required in order to minimize the risk. It is
delivered in a manner such as the key points will be remembered by the operatives
receiving it.

Method Statement ​for Installation of UPVC Pipes


Page no. 7
Method Statement for Installation of Earthing works
610555-CB2007-A15-0006-01

● Tool box talk meetings will be held for each crew, on group of employees, regarding
more general topics of the Project HSE Policy; in example lesson learned, near miss
reports, implementation of the requirements and message from the management or
Engineer’s HSE Officers.

7. Environmental Issues

7.1 Introduction
● As part of the development of the Organization’s Environmental Management System(s)
the significant issues that are faced both on site and within offices or other facilities
should be addressed. This approach subsequently allows for a systematic focus upon
the important environmental aspects to be adopted which in turn facilitates prioritization
of limited resources.

7.2 Definitions
● An environmental aspect can be defined as an element of an organizations activities,
products and/or services that can interact with the environment.

● In general environmental issues arising from the construction activities covered in the
scope of this Method Statement are mainly

● Dust generation impact

● Mud generation

● General housekeeping rules for all operatives shall be observed.

8. Quality Control Requirements

● Pipe deliveries shall be recorded on a separate form, which shall be prepared and
maintained by the Q.C. Inspector / Q.C. Engineer (Main contractor). Each UPVC pipe
delivery ticket must be reviewed by the Q.C. Inspector / Q.C. Engineer prior to
Installation.

Method Statement ​for Installation of UPVC Pipes


Page no. 8

You might also like