: PT.

KALTIM CIPTAYASA
: EXTENTION MAINTENANCE BUILDING

Week Ending: 07-Apr-13


Report No. 25

WEEKLY ACTIVITIES REPORT


1.ACTIVITIES PERFORMED WITHIN LAST WEEK
WHEN STATUS/
WHAT
START FINISH PROGRESS
1 ENGINEERING (Revisi Gambar dan Calculation Sheet) 21-Mar-13 31-Mar-13 1.00
2 PEKERJAAN TANAH 21-Mar-13 31-Mar-13 100
3 PEKERJAAN STRUKTUR
Pondasi 21-Mar-13 31-Mar-13 100
Lantai Bawah
Pekerjaan lantai Beton K 250 21-Mar-13 31-Mar-13 -
Kolom H Beam 200x200x8x12 21-Mar-13 31-Mar-13 90
Base Plate 21-Mar-13 31-Mar-13 100
Lantai Atas
Kolom H Beam 200x200x8x12 21-Mar-13 31-Mar-13 90
Balok Baja I Beam 300x150x6,5x9 21-Mar-13 31-Mar-13 90
Rink Balk 250x125x6x9 21-Mar-13 31-Mar-13 90
Joint 21-Mar-13 31-Mar-13 50
Metal Deck 21-Mar-13 31-Mar-13 50
Beton lantai Beton K225 21-Mar-13 31-Mar-13 27.77
Pekerjaan Atap
Rangka Baja Atap 21-Mar-13 31-Mar-13 39.29
Penutup Atap 21-Mar-13 31-Mar-13 -
Plat Steel listplank thk 2mm 21-Mar-13 31-Mar-13 -
4 PEKERJAAN SEPTIC TANK
Septic Tank 21-Mar-13 31-Mar-13 -
Resapan 21-Mar-13 31-Mar-13 100
2.ACTIVITIES TOBE PERPORMED THIS WEEK
WHEN STATUS/
WHAT
START FINISH PROGRESS
1 ENGINEERING 31-Mar-13 07-Apr-13 100
2 PEKERJAAN TANAH 31-Mar-13 07-Apr-13 100
3 PEKERJAAN STRUKTUR
Pondasi 31-Mar-13 07-Apr-13 100
Lantai Bawah
Pekerjaan lantai Beton K 250 31-Mar-13 07-Apr-13 80
Kolom H Beam 200x200x8x12 31-Mar-13 07-Apr-13 90
Base Plate 31-Mar-13 07-Apr-13 100
Lantai Atas
Kolom H Beam 200x200x8x12 31-Mar-13 07-Apr-13 90
Balok Baja I Beam 300x150x6,5x9 31-Mar-13 07-Apr-13 90
Rink Balk 250x125x6x9 31-Mar-13 07-Apr-13 90
Joint 31-Mar-13 07-Apr-13 50
Metal Deck 31-Mar-13 07-Apr-13 100
Beton lantai Beton K225 31-Mar-13 07-Apr-13 60
Pekerjaan Atap
Rangka Baja Atap 31-Mar-13 07-Apr-13 50
Penutup Atap 31-Mar-13 07-Apr-13 -
Plat Steel listplank thk 2mm 31-Mar-13 07-Apr-13 -
4 PEKERJAAN SEPTIC TANK 31-Mar-13 07-Apr-13
Septic Tank 31-Mar-13 07-Apr-13 -
Resapan 31-Mar-13 07-Apr-13 100

Page 1 of 2
: PT.KALTIM CIPTAYASA
: EXTENTION MAINTENANCE BUILDING

Week Ending: 07-Apr-13


Report No. 25

WEEKLY ACTIVITIES REPORT


3.ACTIVITIES TO BE PERFORMED NEXT WEEK
WHEN STATUS/
WHAT
START FINISH PROGRESS
1 ENGINEERING 07-Apr-12 14-Apr-12 100
2 PEKERJAAN TANAH 07-Apr-12 14-Apr-12 100
3 PEKERJAAN STRUKTUR
Pondasi 07-Apr-12 14-Apr-12 100
Lantai Bawah
Pekerjaan lantai Beton K 250 07-Apr-12 14-Apr-12 100
Kolom Baja I Profil 200x100x22 07-Apr-12 14-Apr-12 100
Base Plate 07-Apr-12 14-Apr-12 100
Lantai Atas
Kolom Baja I 200x100x22 07-Apr-12 14-Apr-12 100
Balok Baja I 200x100x22 07-Apr-12 14-Apr-12 100
Rink Balk 250x125x6x9 07-Apr-12 14-Apr-12 100
Joint 07-Apr-12 14-Apr-12 100
Metal Deck 07-Apr-12 14-Apr-12 100
Beton lantai Beton K225 07-Apr-12 14-Apr-12 100
Pekerjaan Atap
Rangka Baja Atap 07-Apr-12 14-Apr-12 90
Penutup Atap 07-Apr-12 14-Apr-12 90
Plat Steel listplank thk 2mm 07-Apr-12 14-Apr-12 -
4 PEKERJAAN SEPTIC TANK
Septic Tank 07-Apr-12 14-Apr-12 -
Resapan 07-Apr-12 14-Apr-12 100
4.AREA OF CONCERN
REQUIRED
WHAT
DATE
- Erection Purlin Rangka Atap

Bontang, 07-Apr-13 Checked


PT. KALTIM CIPTAYASA PT.KALTIM PASIFIK AMONIAK

Burhanudin Sayyid Hasan Al Hamid, ST.


Supervisor

Page 2 of 2