Download as pdf or txt
Download as pdf or txt
You are on page 1of 53

Content

1 Summary 3
2 Lifting technical property 3
2.1 lifting characteristics 4
2.technical property parameter list & matching 5
mechanism list
2.3 power supply parameter 7
3 Brief introduction of crane structure 8
3.1 overall layout 8
3.2 metal structure parts 9
3.3 working mechanism 18
3.4 safety protection devices 20
3.5 hydraulic jack-up device 21
3.6 electric control and operation system 22
4 Points for attention in electric installation 23

5 Installation and disassembly of the crane 24


5.1requirements and points for attention in 24
installation and disassembly
5.2 debugging instruction and order of installation 25
(foundation diagram attached)
5.3 safety regulation for operation 31

6 Service and maintenance of the crane 33


6.1 daily maintenance 33
6.2 regular maintenance 33
6.3 regular inspection 33
6.4service and maintenance of hydraulic jack-up 34
system
6.5 table of common faults and elimination methods 34
6.6 others 37

7 Attached diagrams and tables 37

7.1 concrete weight diagram 38


7.2 list of weight of tower crane components 39
7.3 list of lubricating of tower crane components 40
7.4 list of bearing configuration 41
7.5schematic diagram of pull rods of boom and 42
balance arm
7.6 concrete foundation diagram 43
7.7 diagram of electric principles 44

2
1.Summary

QTZ50 tower crane, a type of self-elevating tower crane, is designed by Potain and Liebherr. and

manufactured by Shandong Minglong construction machinery Co., Ltd. As the latest type of crane

transportation machinery, it is designed with “Tower Crane Computer-designing Platform” as the tool. In

the process of designing, group technology, combination design technology and finite element analysis

technology are made full use of in combination of international advanced tower crane technology and the

demand of domestic building market.

This machine is the crane with vertical arm support, trolley travel and up-rotary hydraulic jack-up system.

Its maximum effective amplitude is 48m and it is the only domestic tower crane type to reach this

amplitude. Its maximum lifting moment is 438kN·m. When used alone, its lifting height is 30 m and

attaching lifting height 120 m (α=2).

Each speed index of this machine has reached or exceeded national standard.

The weight of this machine (not including counterweight and attached devices) is 21.871 ton, and the

overall installed capacity is 20.9kW. With advanced parameters, reliable performance, handsome

appearance, excellent quality, simple and practical structure, advanced security devices, convenient

service, safety usage and reasonable price, this machine is an ideal type of construction machinery for

small and medium size construction enterprises.

2. Lifting technical property


2.1 lifting characteristics
characteristics::
table of lifting characteristics
(A)table characteristics((α=4)
Amplitude
3-12.5 13 14 15 16 17 18
m
Lifting
4 3.85 3.8 3.76 3.49 3.25 3.04
capacity t
Amplitude
19 20 21 22 23 24 25
m
Lifting
2.85 2.68 2.54 2.41 2.37 2.28 2.17
capacity t
Amplitude
26 27 28 29 30 31 32
m
Lifting
1.97 1.88 1.81 1.73 1.66 1.59 1.53
capacity t

3
Amplitude
33 34 35 36 37 38 39
m
Lifting
1.48 1.42 1.37 1.32 1.28 1.24 1.2
capacity t
Amplitude
40 41 42 43 44 45 46
m
Lifting
1.18 1.16 1.12 1.1 1.08 1.06 1.04
capacity t
Amplitude
47 48
m
Lifting
1.02 1
capacity t

table of lifting characteristics


characteristics((α=2)
Amplitude
3-25 26 27 28 29 30 31
m
capacity t 2 1.92 1.9 1.88 1.75 1.66 1.59
Amplitude
32 33 34 35 36 37 38
m
capacity t 1.53 1.48 1.42 1.37 1.32 1.28 1.24
Amplitude
39 40 41 42 43 44 45
m
capacity t 1.2 1.18 1.16 1.12 1.1 1.08 1.06
Amplitude
46 47 48
m
capacity t 1.04 1.02 1

Table Two

(B)curve of lifting characteristics


四倍率
(kg)
400
0
350
0
300
0
250
0
200
0
150
0

4
100
0
500

3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 (m)

lifting speed
Items
Unit
α=2 α=4

Rated lifting moment KN.m 400


Maximum lifting weight t 2 4

Operating amplitude 3 – 48
m

Maximum amplitude lifting weight 1


t
Independent type 30
Lifting height m
Attachment type 120/2 falls 60/4 falls

Under-frame 6.0×6.0
Height of Independent type 36
Outline
whole
dimension Attachment type 126
machine
s of the m
whole From boom end to rotary center 48.8
machine
From balance arm tail to rotary
11.2
center
Deadweight of Independent type t 21.871
whole machine Attachment type t 40.981

Counterweight 8.25
t
Motor total power kW 20.9
Others Max. installation height working level ≤6
wind scale
Allowed working temperature 0C -20~+40

Matching mechanism list

Hoisting mechanism M5

Mechanism load factor Slewing mechanism M4

Trolleying mechanism M4

5
type YZTD200L2-4/8/24

Electromotor Rotating speed r/min 1440 720 220

Power kW 15 15 4

Center
mm 450
distance
Reducer
Transmission
i 12.64
ratio

Diameter mm Φ330

Layer number
number 4
Drum of ropes

Rope capacity m 280

Rotating speed r/min 114 57 11.4


Hoisting
Type YW-300/45
mechanism
Brake Braking
N 630
force

Traction
N 10000
force
Wire rope
6×37-Φ11-1770-Ⅰmethyl plating
Specification
right cross

61.35/30. 30.67/15. 9.37/4.6


Hoisting speed m/min
67 34 9

Rated lifting weight t 0.8/1.6 2/4 2/4

Minimum stable lowering


m/min ≤7
speed

Total weight t 1.2

Type YZR132M-6

Slewing Rotating
Electromotor r/min 908
mechanism speed

Power kW 3.7

6
type XJL-100.180

Transmission
Reducer i 180
ratio

Output torque N·m 10000

Matching
Type QW. 1120.32A
slewing bearing

Modulus m 10

Tooth number z 13
Pinion
Modification
x +0.5
coefficient

Hydraulic
Type YOX280
coupling

Slewing speed r/min 0-0.6

Number of machine installed Number 1

Type YD100L2-4/6

Electromotor Rotating speed r/min 1440 960

Power kW 2.2 1.5

Type JM40

Reducer Transmission
Trolleying 38
ratio
mechanism
6×19-6.2-1550-methyl plating right
Specification
cross
Wire rope
Linear
m/min 38.4/25.6
velocity

Slewing speed m/min 38.4/25.6

Working
Hydraulic Hydraulic MPa 20
pressure
jacking pumping
Power kW 4
mechanism station
Pump type GB306

7
Rated pressure MPa 20

Cylinder
mm Φ125
diameter

Rod diameter mm Φ90

Jack-up stroke mm 1300

cylinder Installation
mm 1700
distance

Jack-up speed m/min 0.4

Maximum
t 24.6
jack-up force

2.3 power supply parameter


parameter::
2.3.1 total power of whole machine
machine::20.9kW
2.3.2 voltage of power supply
supply:
:~440V±10%
2.3.3 frequency of power supply
supply::60Hz
3. Brief introduction of crane structure
QTZ50 self-elevating tower crane consists of metal structure, component driving, hydraulic jack-up,
electric control and safety protection device. Here is brief introduction of each part and their
characteristics:
3.1 overall layout
layout::
The under-frame of whole machine is tightly fixed on special concrete foundation. Its upper part is
connected with tower body; the upper end of tower body is connected with jack-up set frame and lower
turn-table, and the surface of lower turn-table is connected with the outer ring of slewing bearing. The
rotating part fixed on the inner ring of slewing bearing includes rotary upper turn-table, tower cap,
balance arm, crane boom, trolley and hooks, counterweight, hoisting mechanism, slewing mechanism,
and cab. These components can all rotate fully to 540°around tower body axis line in their respective
horizontal plane.
The crane boom is connected with tower cap by two boom pull rods and its root is connected with upper
turn-table pin. The balance arm is connected tower cap by two boom pull rods and its root is connected
with upper turn-table pin. The hoisting mechanism is set at the rear of balance arm. The slewing
mechanism lies on the right of rotary upper turn-table and cab on the left. The trolley and hooks are
drawn by luffing mechanism close to the root of boom root, in vertical reciprocating motion along with
longitudinal axis of crane boom.

8
The height of tower body consists of heights of under-frame, standard joints, lower turn-table and upper
turn-table. Unattached height is composed of 13 standard joints(including 1 strengthened section).
When the maximum lifting height is 100 m, it is composed of 45 standard joints as well as five
attachment devices. Attached pre-burial device should be buried into the attached height position
planned beforehand so as to attach tower body to buildings by attached struts.
There are four dismountable ear plates above the standard joints of tower body in diagonal direction.
The upper parts of four slant beams are connected to ear plates and under-frame ear bases by pins. The
lift mechanism consists of two parts: jack-up set frame and hydraulic jack-up devices. The jack-up set
frame is framework spatial steel components, connected with lower turn-table by screws. At the back of it
there are jack-up cylinders and beams of hydraulic jack-up system installed. The hydraulic pumping
station lies on the set frame working platform. While jacking up, the jack-up beams act against footsteps.
With the function of cylinder, set frames together with parts above the lower turn-table elevate along axis
lines of tower body. Whenever the cylinder jacks up twice, one standard joint is introduced.

When the lifting height is no more than 30 meters, adopt the independent style; when it is more than 30

meters, adopt the attached style. While attaching, under no circumstances should the length upper

cantilever parts exceed 20 meters. In case of independent height, the standard joint number should be

13; in case of attached style, more standard joints and attached devices could be used according to the

need.

Usage height of tower crane and attached device arrangements are illustrated in Diagram One.

9
Diagram 1

3.2 metal structure parts

The metal structure parts mainly include under-frame, tower body standard joints, attached devices,

slewing bearing, lower turn-table, upper turn-table, tower cap, cab, balance arm, crane boom, boom pull

rod, trolley, jack-up set frame, etc.

3.2.1 under-frame and slant beams


beams::(see Diagram 2)

The under-frame is a crossbeam consisting of one whole beam and two half-beams. The slant beam is a

square tube with two connection plates welded at two ends. High-strength bolts or pins joint crossbeam

and four slant beams together so as to facilitate handling and transportation. The upper parts of four

slant beams are connected with four main limbs of standard joints by clamp connections. (While

10
installing the tower crane, before the jack-up set frame exceeds the height of hinge supports of standard

joint slant beams, hinge supports and slant beams are not installed to connect standard joints so as to

facilitate the installation of jack-up set frames and lower the height of whole machine installation. If the

lifting height of equipment installation is sufficient, install quadric-hinge supports and quadric-struts first

and then go on adding more joints.)

Diagram 2

3.2.2 tower body joints


joints:
:(see Diagram 3)
Tower body is composed of standard joints which are formed by group welded of angel steels with the
structure of long square space trusses. Every two standard joints of tower body are connected firmly by
Level 10.9 M27 high-strength bolts and screws. Inside each standard joint there is a ladder with the
same length so as to facilitate manipulation and maintenance personnel getting on and off tower crane.
There is one rest platform every three joints. All standard joints have interchangeability. By changing the
number of tower body standard joints installed, the crane will reach different lifting heights. Two groovy
footsteps are welded respectively on two main chords on the same side of standard joints. This position
of main chords has been strengthened. While doing jack-up work, with the expansion of jack-up cylinder,
shaft heads at two ends of jack-up beams and climbing claws of jack-up set frame fall into the footstep

11
groove successively according to the procedure, so as to make jack-up set frame elevate vertically along
with tower body. When two cycles of motion are completed, the jack-up set frame will elevate one
standard joint height. Accordingly, at this time, one standard joint could be added. Repeat motion like this
to make tower body achieve required height. When disassembling the tower crane, the reversed
procedure is adopted to lower the height of tower body step by step.

套 架

标 准 节

加 强 节

标 准 节

Diagram 3
3.2.3 crane boom
boom(see Diagram 4):The cross section of crane boom is isosceles triangle. Top chord,
tilted belly poles and horizontal tilted belly poles are all seamless steel tubes. Two bottom chords are
made of steel bars. Make sure the surface and side of bottom chords smooth and mutually vertical so
that they can also be used as operation track of trolley. The crane boom consists of eight joints and there
is no interchangeability between each joint. According to its structure features and joint method of top
chord, installation position of each boom could be located. Top chords of each joint are connected by
flanges and four M22 high-strength bolts and bottom chords by plugged pins. With little gap, the joint is
smooth so as to reduce vibration when small wheels pass.

Diagram 4
3.2.4 turret
urret((see Diagram 5): The turret consists of three parts: upper turn-table, lower turn-table and
slewing tower body. The upper part of upper turn-table is welded with rectangle rotary tower body of
angle steels. The top four corners are connected to tower cap with ear plate pins. Beams at two sides
are made of channel steels, and their lower parts are fixed firmly by 28 pieces M22 high-strength bolts
and slewing bearing inner ring. The front is connected with crane boom root by pins, and the back with

12
balance arm root by pins. At the left front there is cab as well as working platform. Slewing mechanism is
installed on the two side of upper turn-table. The pinions of slewing mechanism mesh with the large gear
ring of slewing bearing. Because slewing bearing is fixed on the lower bearing, when the slewing
mechanism is started, the upper-table of tower crane and above can do slewing movement along with
tower body axis.

1.lower turn-table 2. slewing bearing 3.Upper turn-table 4.Cab 5.slewing mechanism 6.slewing

tower body

The lower part of slewing bearing is lower turn-table. The outer ring of slewing bearing and lower

turn-table are connected tightly together by twenty-eight pieces M22 high-strength bolts. The whole load

on the top of tower crane is transmitted to lower turn-table by slewing bearing. Four corners of lower

turn-table are welded respectively with two standard joint connection sleeves, connected to tower body

standard joint by eight M27 high-strength bolts.


3.2.5 tower cap
cap(see Diagram 6): Tower cap is space truss structure group welded with angle steels.
Its bottom connected to rotary tower body and its top is designed with hinge supports, hinged
respectively with crane boom pull rod and balance arm pull rod. There is a platform on the upper part of
tower cap and installation personnel can install and disassembly tower body and reeve lifting wire ropes

13
on this platform. On the top of tower there is an anemometer sensor installed.

Diagram 6
3.2.6 balance arm
arm(see Diagram 7):Balance arm is truss structural welded with angle steel and channel
steel. Hoisting mechanism is installed in the middle close to rear. At the tail of balance arm there are six
counterweights. There are walking platforms on the boom surface and at two sides of counterweights so
as to facilitate maintenance and installation.

Diagram 7

3.2.7 Cab
Cab::Cab is frame structure with insulation material filled around. The whole cab is located at the
right front of rotary frame. At the right front is crane boom and at the left back is balance arm. The cab is
spacious and bright with broad horizons. The front windows can be open to facilitate ventilation. Inside
the cab there is manipulation seat and at its sides there is manipulation platform. Switch box is located at
the rear of manipulation seat so as to facilitate the switching on/off of power supply of electricity control

14
cabinet. Electricity control cabinet and resistance box are located at the root of balance arm and hence
convenient maintenance. Apart from lamps, there is plug inside power switch box for the purpose of
connecting power supply in case of night maintenance or lowering or raising the temperature of cab.
3.2.8 trolley
trolley:: Trolley is steel structure component that propels hooks and lifting goods in reciprocating
motion along with crane boom longitudinal axis. It has four road wheels, two at each side. The operation
track of road wheels is the bottom chord of boom. On one side of the trolley lies maintenance hanging
basket which motions together with trolley and can safely transport operation personnel to any position
of crane boom for installation or maintenance. There are regulation screws at two ends of trolley which
are used to tighten amplitude wire ropes. Meanwhile, there is rope-breaking protector to prevent trolley
out of control once its amplitude rope is broken. Also, there are anti-collapse devices at both sides of the
trolley.
3.2.9 jack-up set frame
frame::(see Diagram 8)

The jack-up set frame consists of set frame, working platform, guidance roller, climbing pedal,

introducing platform of tower body standard joint, etc. Jack-up beams of hydraulic jack-up device is hung

on the beam at the back of set frame, and the pumping station lies on the working platform. All these

make up hydraulic jack-up mechanism.

Diagram8

Jack-up frame set lies outside tower body and is connected with four flanges of lower turn-table by
high-strength bolts via four flanges on the top. Jack-up set frame is square section space truss welded
by angle iron so as to facilitate transportation. With the function of jack-up cylinder, jack-up set frame
makes vertical motion dependent on eight guide rollers. The hinge support on the beam in the middle of
set frame is connected with cylinder by single-ear hinge so as to bear the jack-up load of cylinder. In the
middle of set frame there are two climbing pedals. When the cylinder takes back piston rod, the climbing
pedals bear the whole load on the top of tower crane.
Introducing platform is installed at the front of middle and upper part of jack-up frame. Steel plate web is
welded on the introducing platform so that introducing rollers can be inserted into standard joint
connection sleeve. When the standard joints are elevated to the height of introducing platform, put the
standard on the introducing platform so as to pull in standard joints. There are two layers of removable
working platform in the middle of set frame surrounded by guardrails so as to ensure the safety of

15
operation personnel.

3.2.10 attached devices


devices:
:(see Diagram 9)

This crane has six sets of attached devices. Each set includes a set of connection frame and three struts

of adjustable length and its function is to fix tower body onto the building so as to maintain the stability of

tower body.

The attached connection frame fixes the main chord of standard joint. And adjust struts at two corners of

tower body with one adjustment rod. Then the struts connect with building attachment points. The

horizontal load of tower body is supported by building, and hence the force condition of tower crane is

improved.

While installing the tower crane, notice the location of attachment and plan the height position of

attachment point on tower body (the attachment height could be adjusted appropriately). Because the

length of each wall-attached struts could be adjusted within some range, the distance from the center of

tower crane to building walls changes within some range. The attached frame should be installed at

places of horizontal abdomen rods of standard joints.

Diagram 10

One end of struts is connected to the building by one double-ear. Double-ear and its fixing method on the

16
building are decided by the customer, but it must satisfy the bearing requirements. (See Diagram 10).

3.2.11 bearing capacity of foundation and attachment points


points:: When installing the tower crane,

calculate the bearing capacity of attachment points and tower crane foundation of the building. Their

bearing capacity should be no less than the data listed in Table Four and Table Five.

Table 4 foundation load list


Load Name unit value
Vertical load of foundation kN 280
Horizontal load of foundation kN 60.5
Tilting moment of foundation kN.m 611
Torque of foundation kN.m 98.6
Table Five List of Attachment Point Load
Attachment Point
Point I PointⅡ PointⅢ PointⅣ PointⅤ PointⅥ unit
Load
Horizontal pressure
40 52 64 76 88 100 kN
(puling)force

In the process of installing attached devices, examine lateral verticality of tower body axis by theodolite.

The overall height should be no more than 4 / 1000, which could be achieved by adjustment of the

length of attached struts. The three struts of each set of attachment device should be kept within the

same horizontal plane. The height of building attachment points should be the same as that of

corresponding attached hinge seat of standard joints, with error of no more than 200mm. The hinge

connection between attachment struts, attachment joints and building attachment points should be

reliable and fixed tightly by bolts. After the adjustment of strut length, tighten the adjustment screws.

Examine frequently whether those screws are loose or not in the working process. If anything abnormal

occurs, stop the machine immediately and take measures to solve the problem. The hinge seat on the

building must be double-eared. Apart from the earring assembly illustrated in Diagram 4, it must also

have the bearing capacity illustrated in Table Five.


The attachment devices of this tower crane are designed within 3.5 to 4 meters from the crane center to
building external wall. Exceed this range, special attachment should be equipped in communication with
manufacturer.
3.3 working mechanism
mechanism:: Working mechanism includes such components as hoisting mechanism,
slewing mechanism, and luffing mechanism.
3.3.1 hoisting mechanism
mechanism:(see Diagram 11)

17
The hoisting mechanism mainly consists of motor, brake wheel, reducer, drum, height limiter, etc. It is
installed at the back of balance arm and driven by three-speed motor. The hoisting mechanism changes
its speed via switch of control console. Thus, ideal hoisting speed and accuracy of slow emplacement
are achieved. Its high-speed lifting weight should be no more than 1.6t and medium and slow speed
lifting weight no more than 4t, controlled automatically by electrical system of FKDX multifunctional
limiter.
3.3.2 slewing mechanism
mechanism:(see Diagram 12)

1 motor 2 upper lag

3 hydraulic coupling 4 lower lag


5 electromagnetic break 6 end cover
7 planetary reducer 8 pinions
9 pedestal 10 slewing frame beams

11 large slew gear ring

Diagram 12 Principle Schematic Diagram of Slewing Mechanism


The slewing mechanism mainly consists of wound-rotor motor, starting variable resistance box, hydraulic
coupling, electromagnetic brake, rotary limiter, planetary reducer, pinion and pedestal. It has compact
structure, large transmission ratio and stable starting and braking. In the working process, this
mechanism will not be influenced by bigger wind-power. Make use of the brake to keep crane boom at
accurate position. The brake has the function of location but not the function of deceleration braking.
However, in non-working state the crane boom can rotate following wind directions.
3.3.3 Trolley ing mechanism
Trolleying mechanism:(see Diagram 13)

18
This mechanism is used to drive trolley to motion reciprocally along with crane boom longitudinal axis
so as to achieve the amplitude movement of hooks and lifting goods. This mechanism is installed in the
first crane boom, mainly including two-speed motor, reducer, drum and FKDX multifunctional limiter.

1. motor 2. reducer
3. rum
4. multifunctional limiter

Diagram 13 Principle Schematic Diagram of Luffing Mechanism


3.3.4 hoisting wire rope system
system:(see Diagram 14)

This system is let out by drum of hoisting mechanism and directed to pulley through tower cap and crane
boom root. Then it passes through trolley and hook pulley block and then fixes wire ropes at the front of
crane boom. The lifting speed of hoisting wire rope is 2.

1. drums of hoisting mechanism

2. tower cap guide pulley

3. crane boom root guide pulley

4. hook pulley block

5. amplitude pulley block


6. the end of the boom
Diagram 14 Puncturing Schematic Diagram of Hoisting Wire Rope
When hooks with lifting speed as 4 are needed, just let loose pulley device at the upper part of hook

19
group into hook grooves and lock it.
3.3.5 amplitude wire rope system
system::(see Diagram 15)
One amplitude wire rope gets respectively out of either end of amplitude wire rope drum. One passes
through crane boom root guide pulley and gets fixed at the rear of trolley. The other passes through
guide pulleys at the middle and end of crane boom and gets fixed at the front of the trolley. Wire-rope
tension adjusting devices are installed at the front and back of trolley.

1. Oriented pulley at the root of crane boom

2. Luffing mechanism drum

3. Guide pulleys at the middle of crane boom

4. Trolley

5. Guide pulley at the end of boom

3.4 safety protection devices


devices:This machine is mounted with different kinds of safety protection devices

essential to tower crane, mainly including FKDX multifunctional limitator with such functions as lifting

weight, lifting moment and amplitude constraint, FKDX-G lifting height limitator, FKDX-H rotary limitator

and anemometer.

3.4.1 Structure and function of FKDX multifunctional limit er


limiter

(1)ffunction of limiting lifting weight


weight::

Slow and medium speed lifting weight should be limited to no more than maximum lifting weight allowed

by tower crane. High speed is the descending speed of hooks without goods. The lifting weight should

be no more than 40% of maximum lifting weight, i.e. 1.6 t. It is automatically changed into medium speed

if more than 1.6 t.

function of limiting lifting moment


(2)function moment::

Moment generated by protecting lifting goods (weight×amplitude) should be no more than lifting moment

20
allowed by tower crane. Its function is to send out alarm at 90% of rated moment and when moment

respectively arrives at rated moment but less than 110% adjusted according to lifting weight and

amplitude. Meanwhile, cut off power supply of lifting mechanism and outward amplitude of slewing

mechanism so that lifting goods can only descend but not elevate. Thus, the trolley can only operate

toward the direction of low amplitude but not the direction of high amplitude.

function of limiting amplitude displacement


(3)function displacement::

Cut off power supply at corresponding direction of slewing mechanism so as to ensure its safe operation,

when the trolley drives to minimum or maximum amplitude,

3.4.2 FKDX-G lifting height limit


limiteer:

The function of this limiter is to make sure lifting height no more than maximum lifting height allowed by

tower crane so as to ensure the safe operation of tower crane. Installed at the end of lifting mechanism

drum axis, it is driven by drum axis. Cut off lifting power supply of lifting motor and brake when hooks

exceed the height. At this time the lifting mechanism can only descend. Each time the lifting height of

tower crane is changed, readjust the limiter.

3.4.3 FKDX-H rotary limiter


limiter::

The function of this limiter is to make sure the rotary angles on the left and right on the top are no more

than 540°so that power cable will not be cut off.

This mechanism consists of gears, scaffold, stroke switch, etc. Located at the right front of upper

turn-table frame, its gears mesh with large gear ring of slewing bearing. When the upper part is rotating,

gears drive input axis of limiter to rotate. When slewing mechanism rotate 540°(left or right),contact

points touch with contact heads inside the limiter so that the power supply of operating direction of rotary

motor is cut off. Therefore, it can only rotate at the opposite direction but not go on rotating at the same

direction.

In the process of transporting, in order to avoid getting knocked in the process of transportation, remove

this mechanism for safekeeping in preparation for usage while installation.

3.4.4 anemometer: When the boom root is higher than 50m, anemometer should be installed on top of

tower cap. Alarming system should be installed in the cab and sent out alarm when in working state

wind level is more than six and in jack-up working more than four. At this time any working should be

stopped. (Customers can set all by themselves) The above lifting weight, lifting moment, limiting function

of working amplitude, its working principles and debug method is illustrated in detail in operation

21
instruction of FKDX multifunctional limiter.

3.5 hydraulic jack-up device


device:: This device consists of hydraulic cylinder, jack-up beams and hydraulic
pumping station.(see Diagram 16)
In the process of jack-up working, first transport standard joints for installation to introducing
platform by hooks of this tower crane and then adjust balance with trolley. Drive the trolley to
balance point, remove the bolts that connect lower turn-table and standard joints and then put
axis heads at both ends of jack-up beam into the hemicycle groove. Start the pumping station to
stick out piston rod. Drive lower turn-table and parts above by set frame to lift the height of half a
standard joint, and then put climbing pedal on the footstep of standard joint. Pull back piston rod
and jack-up beam, and then put axis heads at both ends of jack-up beam into the previous
footstep groove. Lift the height of half a standard joint again. Two lifting will add one standard
joint. The tower crane removal principles are the same but the process is opposite. In the whole
process of jack-up, pay close attention to components in relative motion.

1 cylinder 2 balance valve

3 reversing valve 4 relief valve 5

pump 6 tank

7 oil filter 8 motor

9 switch of pressure gauge

10 pressure gauge

Diagram 16 Hydraulic Principle Diagram

Find out whether there is resistance in between them. If there is abnormal noise or oil pressure suddenly
rises or exceeds 20Mpa, immediately stop working. Find out the problem and then proceed working after
getting rid of it.
While jacking up, connect to the power on the electricity in the process of hydraulic power transmission.

The motor drives the gear pump to rotate and pressure oil enters manual reversing valve of three unit

four passage. The oil enters hydraulic cylinder via balance valve and pushed piston rod. Pointer

pressure gauge and relief valve are installed along the oil passage so as to avoid overpressure of the

system. Once the relief valve is tightened, no random variation is allowed. Manual reversing valve is

used to change the direction of oil intake and return. Balance valve lies on the side with high pressure of

cylinder to avoid sudden shrinkage of piston rod under dead weight of upper parts when the system

suddenly stops oil supply, or automatic extension under dead weight of piston rod and jack-up beam.

22
All hydraulic components of this mechanism are installed on one bottom plate inside the tank with
compact structure. All the technical parameters of the hydraulic system are as follows:
Working pressure 20 Mpa Jack-up speed 0.4 m/min
Effective distance 1300 Flow 7.5 L/min
Jack-up force 24.6 t Cylinder diameter 125 mm(inside diameter)
Motor power 4 kW Piston rod diameter φ90 mm
Installation space 1700

Table 6
3.6 electric control and manipulation system
system::
This crane employs power supply of three-phase five-line. The power connects to electric control box in
the cab by iron-covered switch under the tower via cables. The coupled control platform in the cab sends
out signals of host order to control the operation of all mechanisms of tower crane.
3.6.1 system introduction
introduction::The electric system consists of four parts: hoisting system, slewing system,
luffing system and hydraulic jack-up system.

3.6.1.1 hoisting system : Hoisting system is pulled by YZTD200 L2-4/8/24-15/15/4KW three-phase

motor and takes control of different contractors respectively by operating the coupled platform so as to

change motor connection method and achieve high or low speed. When stopped, make use of hydraulic

thruster brake and the procedure of hydraulic thruster is to brake by cut off electricity.
3.6.1.2 slewing system
system:: Slewing mechanism is driven by YZR132M-6/3.7KW wound-rotor motor with
steady start-up and harmonious gear shift. Control circuit by operating switch on coupling platform so as
to achieve left and right rotation. There is an electromagnetic brake of constant open type installed in
slewing mechanism. It is used for location only when the rotation is fully stopped. Electromagnet and
slewing mechanism are controlled by electric interlocking switch so as to avoid working simultaneously.
The operating procedure of this electromagnet is electrifying brake.
3.6.1.3 trolley amplitude system : The trolley is driven by YD100L2-4/6 2.2/1.5KW motor via

worm-gear and worm-rod reducer. Control circuit by operating switch on coupling platform to achieve

inward and outward amplitude or stop working.

3.6.1.4 hydraulic jack-up system


system:: Three-phase socket of hydraulic pumping station motor power is

prepared on the installation plate of electric box. In the process of hydraulic jack-up, connect to pumping

station power (the principles and procedures are illustrated in Item 3.5 an Diagram 16). After the

completion of jack-up, cut off the electricity in time.

3.6.2 safety devices


devices::

3.6.2.1 There is upper limit switch on lifting height limiter. Limit maximum lifting height of tower crane by

bump block of limiter triggering stroke switch.

3.6.2.2 There are limit switches of left and right rotation on rotary limiter, so as to effectively limit tower

23
crane to rotate within 540°left and right. Hence, the cables are protected from damage.

3.6.2.3 FKDX multifunctional limit


limiteer : This limiter has three functions: limit amplitude, weight and
moment.
There are maximum and minimum limit switches in amplitude limiter to make sure the trolley is operation
within maximum and minimum amplitude.
There are maximum and high-speed lifting weight limit switches on lifting weight limiter. When the weight
exceeds correspond lifting weight, use the switches to cut off the power of lifting motor and send out
alarm by ringing. Thus, it can only descend but not elevate. Or automatically change into
medium-speed operation from high-speed operation.

There are three switches on lifting moment limiter to control lifting motor and amplitude motor

simultaneously, i.e. 90 % maximum moment limit switch k1 and super moment limit switch k2 and k3

respectively adjusted by lifting weight and amplitude. When the lifting moment exceeds rated lifting

moment but within 110%, trigger limit switches and send out alarm by ringing so that the hooks can only

operate toward the direction of small amplitude and downward, but not toward the direction of large

amplitude and upward.

3.6.3 electric protection and signal devices


devices::

3.6.3.1 over-current protection


protection::There is auto-release in auto-power air switch DZ5-50. Electricity will

be cut off automatically when the current in the circuit is too strong.
3.6.3.2 zero position protection
protection::When the tower crane starts to work, the operating handle of each
mechanism must be positioned at zero and press start button to pull in overall contactor, and then start
up each mechanism. Otherwise, the overall contactor will get in so as to avoid mis operation of the tower
crane.
3.6.3.3 thermal relay protection : Heat protection devices are installed in hoisting, slewing and luffing

mechanisms to avoid overload, short circuit and other abnormal phenomena.

3.6.3.4 fuse protection


protection:: Fuses are installed in control circuit, lighting circuit and signal lamp circuit so

as to achieve short circuit and overload protection.

3.6.3.5 electric bell


bell:: In preparation of driving, notify the personnel on the site by electric bell. The electric bell

lies below the left side of cab controlled by the button on the platform. In case of overload of the crane (maximum

lifting weight, maximum lifting moment), automatically connect to the circuit and sent out alarm by ring.

3.6.3.6 There are obstruction lights respectively on top of tower crane and at the end of boom and

balance arm. According to the requirements of clients, one more search light could be installed at the

front of cab. All the switches are installed on the installation plate of electric box outside at the back of

24
cab. (According to requirements, obstruction lights and illumination lights will be installed by clients on

their own.)

4. points for attention in electric installation


installation::

4.1 This crane employs power supply of three-phase five-line. Zero line is not connected with tower body.

The tower crane should be connected to the ground reliably by special grounding lines. Grounding

resistance should be no more than 4Ω.(Clients bury grounding lines by themselves.)

4.2 No high-low pressure wire poles and overhead wires should exist 10 meters away from the range of
the length of crane boom.

4.3 In the process of tower crane installation, measure the resistance of each main circuit and land

insulation resistance of control circuit before power on some components or power on each part of the

whole crane after the completion of installation. Make sure they are no less than 0.5MΩ. The resistance

of main crane structure, motor pedestal, metal shell of all electric equipment and grounding resistance of

conductor should be no more than 4Ω.

4.4 The main cable section of crane power should be no less than 10mm2.
4.5 When something goes wrong with electric circuits, cut off grounding power and repair according to
Electric Principle Diagram.

4.6 Periodical maintenance should be done to such electric components as contactors and air switches.

Clean the fouling at core pulling-in surface. Check whether the electric contactors are well-functioned

and whether wire-tightening bolts are loose.

4.7 In the operation process, if anything abnormal is detected, adjust and repair in time. Go on working

only when it returns to normal. Operation with faults of the machine is strictly forbidden

4.8 When the hoisting motor is functioning at a low speed, the time of full-loaded continuous

operation in each ten minutes should be no longer than two minutes.

5. installation and disassembly of the crane


crane::

5.1 requirements and points for attention in installation and disassembly


disassembly::

5.1.1 The company in charge of installation and disassembly should have corresponding qualifications

issued by provincial security inspection department. The installation and disassembly of crane should be

conducted according to requirements and order in this operation instruction. Technicians make process

procedures and regulations of installation or disassembly in written form and submit to operation

personnel.

5.1.2 In the process of installation or disassembly, working personnel should wear safety helmet. In case

25
of high-altitude work, enter the site with anti-skid rubber shoes and safety belt.

5.1.3 In the process of installation, according to regulations, split pins at ends of assembled pins must be

kept open. Baffle bolts at axis ends, wire rope bolts and other connection bolts must be firm and reliable

in accordance with relevant regulations.

5.1.4 Standard components such connection ropes, bolts, screws, cotter pins that connect each

component of this crane, as well as baffle at axis end, and pins, etc. must be qualified products or

qualified components made according to design drawing. Random substitute is not allowed.

5.1.5 The crane should be installed on special foundation in accordance with design requirements with

the weight of no less than 50t. The connection between foundation, pre-burial components of building

attachment points and concrete should be firm and reliable with bearing capacity no less than that

regulated in this operation instruction.

5.1.6 The size of installation and foundation position of relative building are illustrated in Diagram 17.

The site should be flat and tidy without sundries and obstructions. No overhead wires exist above the

site.

3000
3000

12000 53000

Explanation:

1 The site within the marked range of two dots should be

flat and tidy without sundries and obstructions.

2 Installation site may lie to the left of the building.


3 The distance between the center of tower crane and
outer walls of building is 4000mm.

Diagram 17 Planar Diagram of Installation Site

5.2 order and explanation of installation and disassembly


disassembly::
It is suggested that the installation (or disassembly) of the whole crane is conducted by an automobile

26
more than 12t.
5.2.1 Install cross beam of under-frame

Put the assembled cross beam on the foundation. After making choice of the location, press the casting

die and pressboard and fix ground anchor bolts tightly. The horizontal flatness of four bearings is no

more than 1.5 mm.

5.2.2 When connect two well-connected standard joints with four bearings of cross beam by M27

high-strength bolts, pay attention that one side with footsteps should be vertical with the building. (Below

the side with footsteps is the back, and the opposite is the front.)

Diagram 18 Schematic Diagram of Set Frame Installation


5.2.3 Assemble the jack-up set frame and put it around the assembled two joints of tower body. Put the

climbing pins carefully on the footsteps of standard joints. Locate the hydraulic system to one side at the

back of tower body and connect temporary wires.

5.2.4 Assemble the lower turn-table, slewing bearing, upper turn-table, slewing mechanism and tower

cap and lift them onto the half-joint. Then connect them with tower body bolts. (Slewing mechanism and

tower cap can be lifted and assembled alone.) (Diagram 20) Before lifting and install tower cap,

respectively install front and back pull rod of the boom, one pull rod and one pulling rod of balance arm to

the tower cap.

27
Diagram 19 Jacking frame

5.2.5 Connect cab with working platform and install onto the upper turn-table. Tighten the top screws and
set up the support so as to make the installation firm.

Diagram 20 Schematic Diagram of Parts above the Half-joint

5.2.6 Install the balance arm, hoisting mechanism, power-distribution cabinet and pull rod of balance

arm. Connect the wires of each part required and then lift the balance arm horizontally (at this time, mark

the lifting point for disassembly) and connect it with balance arm hinge joint at the back of rotary tower

body on the upper turn-table by pins. Go on lifting so that the back end of balance arm will rise to form an

angle. Then connect two pull rods of balance arm and two pull rods installed beforehand onto tower cap

by pins. Flatten the balance arm so that pull rods will bear forces.

5.2.7 Lift two counterweights, put them at the side near the hoisting mechanism, and connect the
hoisting mechanism with temporary lines. (See figure 21.)

28
Figure 21 Installation Instruction of Balance Arm
5.2.8 Assemble and install the boom, luffing mechanism and trolley. The pull rod of the boom is installed
in the upper chord of the boom with the end fixed by iron wires.

Notice: Check carefully whether the pins of fasteners are properly used and tightly connected, and

whether the cotter pins and baffles are correctly installed in place. When approved, conduct integral

lifting horizontally, finding and marking the equilibrium position carefully for the teardown of the tower.

When being in place, link the pivot points of the boom in front of the slewing tower in the upper turntable

with pins. Then, go on lifting until the front end of the boom is up with an elevation angle of 10°~20°.

Untie the wires that has fixed the pull rod, separately connect the front and back pull rods in the boom

and the front and back pull rods installed in the tower cap in advance with pins, and then gradually set

the boom level and make the pull rods weighted. (See Figure 22.)

Figure 22 Installation Instruction of Boom


5.2.10 Lift counterweights, one piece at a time, and six pieces in total (including the two pieces have
been installed) with a total weight of 8.25 t.

5.2.11 Cut down the main power supply to complete the wiring connection of the whole machine. During

29
wiring connection, refer to the electrical schematic diagram, the electrical layout drawing and the wiring

connection drawing. After wiring connection, detect the insulation resistance of each component against

the ground according to the requirements in 4.1 and 4.3. When approved, wire up the main power supply

on the ground, install the lifting hook (with a magnification of 4) as showed in Figure 14 hoisting rope

reeving, and the rope end is tightly fixed in the arm end and the 3 rope clamps is fixed as required.

5.2.12 Lift up two standard sections and install diagonal stay (Figure 23)

a. Adjust the boom to be right ahead (with the same direction as the inlet beam) and line required

standard sections in this direction. Lift a standard section on the inlet platform and dismount the eight

M27 high strength bolts between the under turntable and the standard section. Put the shaft heads at

both ends of the lifting beam into the marching tank and upright them. Make the lifting beam close to the

tower as much as possible, and it would be better for it to be in the same plane with the longitudinal axis

of the oil tank. Start the hydraulic system and extend the piston rod for 20-30mm, making the under

turntable just separate from the standard section, then stretch the lifting hook outward from the arm heel.

The trolley stops when the clearance (about 2mm) between the four guide wheels in front of and behind

the set frame and the tower body is even more or less (The drive shall remember the equilibrium

position). Meanwhile, make the rotary electromagnetic brake work prevent the boom from swinging.

Figure 23 Lift up Two Standard Sections and Install Diagonal Stay

b. Open the climbing pedal and operate the hydraulic system, to make the piston rod continue to be

extended. When the shaft heads at both ends of the lifting beam can afford more than one step, put the

climbing pedal reliably on the step and operate the reversing valve to stop lifting up and turn it into the

pulling back of the piston rod, until the shaft heads at both ends of the lifting beam can be put into the

tank of above step. Stretch the oil tank outward again (open the climbing pedal as soon as the shaft

30
head leaves the step) until the space in the upper part of the tower body is just OK for a standard section.

Then pull the standard section at the upper end of the inlet platform into the set frame in alignment with

the eight bolt holes, and draw it back to the oil tank to make the joint faces of upper and under standard

sections touch each other, connect the two standard sections tightly with the eight M27 high strength

bolts (retightening force 250KN, and retightening force moment 1.35KN·m). Pull the inlet lifting hook to

the most outward end and to draw the oil tank back, making the under turntable fall on the newly added

standard section. Connect firmly with 4 bolts along the diagonals.

c. Start the trolley and hang the second standard section on the inlet lifting hook and repeat above

process. Tighten the eight connecting bolts between the under turntable and the tower body when the

second section is added. Then install four movable brace rods transverse upper lug at under part of the

third section. Link the four transverse brace rods to the diagonal direction between the set frame and the

tower body with upper and down pins.

So far, the tower crane has been installed and can enter operating state after debugging. Follow the

above method in case that any section needs to be added. After lifting up, lower the lifting frame to the

bottom of the tower body or the top attachment device and fix it incase of season or area of strong cloud.

During lifting up, a special person shall be sent to support the lifting beam, and both ends of the lifting

beam shall be positioned correctly in the step tank. And attention shall also be paid to the working

condition of the beam in the lifting process, stop working in case of any uncommon conditions and

handle properly for safety.

5.2.13 Debugging of Crane

a. Debugging of rotary limiter: Start the rotary mechanism and prevent the cable conductor of power

supply from knotting. Rotate the boom to the left for 180°. Adjust one contact terminal of the limiter’s

contact to make it cut down the motor circuit rotating to the left and can only rotate to the right. Then

rotate to the right for 540°. Adjust the other contact of the limiter to make it cut down the motor circuit

rotating to the right and the boom can only rotate to the left. After adjustment, repeat testing for three

times to achieve a sensitive and reliable rotating spacing to both sides, and go on adjusting until the

requirement is met.

b. Adjustment of lifting altitude limiter: Start the lifting mechanism until the minimum distance between

the top of the lifting hook and the trolley is 1m. Adjust both contact terminals of the limiter to make it cut

down the lifting motor’s upward circuits at various speed and can only go down. Lower the lifting hook for

31
3~5m and then raise again until it stops automatically. Check the minimum distance between the top of

the lifting hook and the trolley to make it ≥0.7m±10%. Repeat above operation for three times to meet

the requirements.

c. Adjustment of FKDX multi-function limiter

Adjustment of amplitude: Start the luffing mechanism, making the trolley run from the arm heel to the

arm head at high speed and then turn into low-speed running when the trolley is 5m away from the arm

head, go on running to achieve maximum rating amplitude. Adjust both contact terminals of the limiter to

cut down the forward motor circuit and can only run backward. Start the car backward for 10m and then

forward at low speed, checking whether it will stop automatically within the maximum amplitude with an

error of 2%. Repeat above operation until approved. Then debug the minimum amplitude spacing in the

same way with an error of 10%. During debugging, make sure that the distance between the front (rear)

of the trolley and the bumper block shall ≥200m when the trolley stops automatically.

Adjustment of lifting capacity limitation: Medium and high speed and a micro-motion lowering speed are

provided for the lifting mechanism. The lifting capacity at low and medium speed is the maximum rating

lifting capacity. The high speed is the falling speed with load. The lifting capacity is 40% of the maximum

rating lifting capacity. The method of fixed-yard variable-range is adopted in adjustment. Firstly, lift

maximum rating lifting capacity 4t at medium speed from 10m away, and normal lifting shall be done.

Then put the load down to the ground and add 400kg, and lifting shall not be done because of automatic

outage. Adjust the lifting capacity at high speed after the low and medium speed has been finished. Lift

1.6t at high speed and normal lifting shall be done. Then put the load down to the ground and add 160kg,

and lifting shall not be done because of automatic outage. Repeat inspecting and verifying for three

times after adjustment. Approval shall be achieved when all the requirements are met, or adjustment

shall be conducted again.

Adjustment of force moment limitation: Three limit switches and three adjustable contact terminals. Limit

switch k1 is the alarm limit switch when the force moment reaches 90% of the rating force moment. Limit

switch 2 and limit switch 3 are the limit switch when the force moments separately adjusted according to

lifting capacity and amplitude are between the rating lifting force moment and 110% of it, controlling the

lifting mechanism and luffing mechanism and making the lifting mechanism not rise but fall and the

luffing mechanism not go outward but inward. Details are listed in the operation instruction of FKDX

multi-function limiter.

32
5.2.14 Commissioning of Crane
Commissioning shall be conducted when the crane has been installed and debugged. The method and
process are as the following:

a. No-load operation: Check whether every mechanism runs normally, whether every limit switch is

sensitive and reliable (rotary limit, height limit and amplitude limit) and whether the movement of every

electrical original is correct.

b. Rating load testing: ① When α=4, and the amplitude is 48.0m, lift 0.765t; when the amplitude is

3-10.96m, lift 4t; ② Lift 4t, ring alarm when the outward amplitude is between 10.96m and 12.06m, the

trolley stops and the lifting hook can not raise. ③ When the amplitude is 48.0m, lift 0.84t, ring alarm, and

the lifting hook can not raise; ④ Lift 4t, the amplitude is less than 7m, the lifting hook raise for 5m, raise

and fall for three times to do wheels-locked testing; ⑤ Lift 4t, rotate to both sides for 3 times when the

amplitude is about 10.96m, make the trolley go back and forth for one round with the amplitude from

10.96m to 3m; ⑥ Lift 0.765t, rotate to both sides when the amplitude is about 48.0m, and make the

trolley go back and forth for one round with the amplitude from 48.0 to 3m; ⑦ Lift 0.765t, carry out the

operation of both lifting and rotating, and then the multiple operation of luffing and rotating.

5.2.15 Demounting of Tower Crane

The demounting sequence of the tower is the inverse process of installation, that is, first demount those

installed early and then demount those installed late. As the demounting is usually carried out when

construction is completed and even after long-term redundancy, problems may exist in the condition of

equipments. Hence attention shall be paid before and during demounting. Only after careful inspection

and taking measures can disassembly be conducted.

(1) Before demounting, check carefully whether every mechanism runs normally, especially the hydraulic

jack-up mechanism, whether bolts at every fastening position are complete and sound, whether pin

baffles are complete and sound, and whether main stressed members are sound. Demounting shall be

conducted only when everything is normal.

(2) Rotate the boom to the direction of the inlet beam of the standard section, making the rotary

electromagnetic brake positioned.

(3) Demount the eight bolts connecting the top standard section with the under turntable, start the

pumping station and stretch the piston rod of the oil tank. The shaft head of the lifting beam falls on the

corresponding step of the second standard section and jacks up slightly to separate the under turntable

33
from the first section. At this time, the lifting hook is running outward from the arm heel. Observe the

clearance between front and back set frame guide wheels and the tower body. The trolley stops when

the clearance is even (about 1.5-2mm). Remember the equilibrium position.

(4) Hang the inlet roller wheel in the diagonal web member of the end plane of the standard section to be

demounted, and then demount the eight connecting bolts between the first and the second sections. Go

on starting the pumping station and stretch the piston rod of the oil tank, making the interfaces of the first

and the second section separate for about 50mm, then insert the inlet roller wheel to the connecting

trepanning and regulate the position. Push the first section out of the set frame along the inlet beam and

put it on the inlet platform.

(5) Operate the reversing valve to draw the piston rod of the oil tank back, carefully open the raising

pedal and make it fall to corresponding step slowly with the set frame. Then take the lifting beam out of

the step tank and operate the reversing valve to stretch the piston rod of the oil tank outward until the

shaft heads at both ends of the lifting beam are put into next step tank and jack up for 50-100mm. Lift the

raising pedal to make the set frame continue to fall.

(6) Operate the reversing valve to draw back the piston rod of the oil tank, until the under plane of the

under turntable touches the upper plane of the second section. Penetrate and tighten one bolt of tower

body connecting at each opposite angle when the two planes meet.

(7) Put the standard section hung by the hook down to the ground, and then lift the standard section lying

on the inlet platform and drive the trolley to the equilibrium position.

(8) Demount the four connecting bolts on the lower plane of the lower turntable. Repeat the procedures

(4)-(7) to demount the standard sections one by one. Notice that when any attachment device is installed,

it shall be demounted when the demounting frame hits the standard section of the attachment device,

and it shall not be demounted earlier.

(9) When the lifting set frame falls to the place of the four diagonal stays at the bottom, first demount the

diagonal stays to lower the demounting height (also the installation height).

(10) Demount the hoisting rope and the lifting hook set, and demount the cable conductor on the boom

and the balance arm. Then disassemble the counterweight set in the counterweight chamber and

demount all the counterweights in the front counterweight chamber and one counterweight in the back

counterweight chamber. Prepare to demount the boom.

(11) Keep the hoisting point in boom installation (marked). Lift the boom with an elevation angle of

34
100-200°with a 12t vehicle. Demount the pins between the first and section sections of the front and

back pull rods separately and fix the pull rod on the boom tightly. Set level the boom slowly and demount

the arm heel pin. Put the boom to the supporting frame on the ground slowly.

(12) Lift the two counterweights remained on the balance arm. With the hoisting point in the boom

installation as the hoisting point (marked), lift the balance arm with an elevation angle of 100-200°.

Demount the pins between the first and section sections of the two pull rods separately and fix the pull

rod on the balance arm tightly. Set level the balance arm slowly and demount the arm heel pin. Put the

balance arm to the ground slowly.

(13) Demount the cable conductor connecting the driver’s cab with that of the outside. Demount the

driver’s cab, the tower cap, upper and lower turntables separately.

(14) Demount the 16 flange bolts in the lifting frame and the lower turntable. Demount the bolts in the

lower turntable and one connected standard section, then withdraw the set frame, and then demount the

strengthening section, base section, under pressure plate and under frame one by one.

5.3 Safety Operation Specification

5.3.1 The crane shall be taken care of by special person. The driver shall get professional training and

receive work license issued by provincial security department. Driving without license is forbidden.

Anyone other than installation, repair and driving stuff shall not climb the tower crane. After the main

power supply on the ground is cut down, inspection must be done to make sure whether there is

electricity in the metal structure of the crane with a test pencil. Take the escalator when safety is assured.

5.3.2 Before operation, daily and regular maintenance must be done according to the instruction, and the

safety protection device shall be examined. Working shall be conducted only when the requirements are

met.

5.3.3 Working without meeting the requirements of voltage and electric current is strictly forbidden.

5.3.4 During working, persons without permission shall not enter the working range of the crane.

Anybody shall not stand under the boom.

5.3.5 During working, special person shall be arranged to communicate with the driver and direct lifting

and installation. (The user shall prepare interphones)

5.3.6 The driver shall ring alarm when lifting or load is passing above people, and concentrate on

working deeply.

5.3.7 The working of the crane shall be conducted according to lifting characteristics in the instruction

35
strictly. Over-load and over-moment working is forbidden. It is also forbidden to work against regulations

after demounting relevant safety device. During lifting and section-adding, lifting and rotating working

shall not be done unless the connecting bolts are tightened.

5.3.8 The crane shall not pull or lift load diagonally, pull piles or anything else, lift material with unknown

weight or lift materials frozen on the ground in winter.


5.3.9 In case of mechanism in which positive and negative rotating are provided, when negative rotating
is required, negative switch shall not be turned on before the mass force disappears and the motor stops.
Sudden starting the reversing switch is forbidden.
5.3.10 For operation of mechanism with fast and slow shift, must do it from slow shift to fast shift or vice

versa, mustn’t get over shift, and assure the period for every shift transition is at least 2-4 seconds.

5.3.11 Mustn’t use slewing brake before the turning motion of the crane boom stops.

5.3.12 mustn’t use the crane hook to lift personnel.

5.3.13 The maintenance hanging basket on trolley mustn’t bear a load over 100 kg; during operation and

maintenance there mustn’t be more than 2 persons in it.

5.3.14 When the crane is working, prohibit people from standing on the arm ladder and the platform of

crane, and mustn’t debug and maintain devices.

5.3.15 Mustn’t relax crane ropes after the hook falls to ground.

5.3.16 Drivers must finish the following work before off duty:

a. Raise up the hook and make it higher than the height of every workpiece within the scope for crane

slewing; and place the dolly 15 - 18m away from the centre of the crane body.

b. Dial every operation switch to zero position, cut off the general power supply indoor, lock the door, and

cut off the general ground power supply after coming down the tower crane.

5.3.17 When lift mechanism hoists heavy things with slow speed shift, the time of running with full load

can’t be too long, and the successive running time can’t be over 2 minutes every 10 minutes in order not

to burn out the motor.

5.3.18 If wind power exceeds grade 4, prohibit removing work; if it exceeds grade 6, prohibit the tower

crane working.

5.3.19 The crane must have good measure of grounding, the electric resistance for grounding can’t

exceed 10Ω.In case of thunder storm, prohibit walking around the tower reel.

5.3.20 Plenty photometric brightness must be supplied when working at night.

5.3.21 Prohibit storing inflammable and explosive materials in the drivers’ cab. Pay attention to fire

36
protection when making warm in winter.

5.3.22 Prohibit the tower crane from running in spite of illness, two professionals should be present for

solving electrical faults.

5.3.23 The tower crane’s normal working temperature range is: -20℃~40℃

5.3.24 Every time the tower crane is reinstalled, only after being redebugged according to 5.2 of this

instruction, can it be put into use.

5.3.25 If the brake of the tower crane fails during working, drivers should be calm, send out a warning

signal, transfer the heavy thing to an open and void place, and control it to fall to ground by electromotor.

Prohibit down by deadweight.

5.3.26 In case of sudden power failure when the tower crane is working, ascertain the reason first, if the

period without electricity is too long, take measures, and let the heavy thing down to ground

slowly(control the electromagnet of the arrester).

6. Service and Maintenance of the Crane

6.1 Daily maintenance: before the work, check and maintain the crane and keep a record of it.

6.1.1 Check the oil volume of each reducer. If it is below the specified amount, add new oil immediately

which should be clean, without corrosive or unclean oil. While replenishing, a filter screen should be

used,

Oil tab of each reducer: hoisting mechanism reducer: 70# industrial gear oil

Slewing mechanism reducer: 90# gear oil

Luffing mechanism reducer: 70# industrial gear oil

Notes: if there is no industrial gear oil, 40# or 30# mechanical oil can be used,

6.1.2 Check the lubricating of the drum bearing of the hoisting mechanism and the drum bearings on the

two ends of the luffing mechanism. When it is necessary, add No.2 calcium base grease to guarantee

there is oil in the oil cup.

37
6.1.3 Smear and add grease to the slewing mechanism, the big and small gear and the rotating and

rolling bearing.

6.1.4 Check whether there is damage in the cable line of the power supply and whether there are

loosening and wearing in the junction. Clear the dust of the electrical equipment.

6.1.5 Check the contact and corrosion condition of the contactor and controller.

6.1.6 Check each connecting bolts to see if they loosen or fall off. If they are, they should be fastened or

added to immediately,

6.1.7 Check the hoisting and luffing wire ropes. If the broken ones surpass 5% or the nominal diameter

wear surpass 5%, the wire ropes should be renewed. Check whether the fixing end of the wire rope is

firm and the bolts of the rope checking is loose. If there are problems, deal with them immediately.

6.1.8 Check each safety devise. If they do not work, they should be changed and repaired without delay,

especially the limitations of the moment and weight of the uplifting whose reliability should be

guaranteed.

6.1.9 Check the braking efficiency of the hoisting and the slewing mechanism. If they are not sensitive

and reliable, they should be changed in time.

6.2 Maintain regularly: once every half month and keep a record of the checking and maintaining.

6.2.1 Carry out daily maintenance.

6.2.2 Add No.4 calcium base grease to the guide pulley and the conjunction of the pull rod and the

bearing, trolley pulley, the pulley of the subassembly of hanger and the slewing bearing of the crane.

6.2.3 Because the hoisting and luffing wire ropes are prolonged after being used for a period of time, the

wire ropes as well as the limiter of the hoisting height and luffing should be re-adjusted,

6.2.4 Fasten once the connecting bolts of other components and the bolts and nuts of the wire rope

platen and rope checking. Change them when necessary.

6.2.5 The insulating properties of various electricity-consuming and electricity transmitting equipment

should be reliable without electric leakage.

6.3 Check regularly: check every half year and keep a record of problem dealing.

6.3.1 During the process of transportation and storage, the damage of metal structural components and

the deformation of structural components are not allowed. If there is damaged and wholly distorted or

deformed, the components should not be used before restoration.

6.3.2 Check every metal structures and components to see whether there are crackles in the welding

38
area and the material and whether there is corrosion in the structural components. If there are, they

should be handled timely and can not be used before repairing.

6.3.3 Replace the connecting bolts and pin rolls if they are over worn or deformed.

6.3.4 Clean each reducer and replenish them with lubricant. Dismantle and clean each rolling bearing

and clean the sliding bearings. Wnen assemble them, lubricating grease should be injected or smeared.

6.3.5 Smear lubricating grease to the slewing open gear pair.

6.3.6 Check and adjust every brake and safety devise.

6.3.7 Check, repair and change some components with relatively bigger serious wear such as small

carriers moving wheels, every pulley and covers of sliding axles and slewing mechanical small gears.

6.3.8 Check, repair and change lift and luffing wire ropes.

6.3.9 Check each controller of the electric operation, lubricate the rotating parts and polish the arc crater

of the moving and fixed contacts. Clean the grime and dust on the drill keys of each contactor and check

insulated condition of winding.

6.3.10 Check and repair various electric wires and cable lines.

6.3.11 After each project, spray and lacquer paint on every parts to avoid the corrosion of regularly used

cranes which should be painted semiannually or annually.

6.4 Service and maintenance of the hydraulic jack-up system.

6.4.1 The hydraulic oil used in the hydraulic power pack should be infused and changed according to the

specifications of the hydraulic system; the oil tanker should be cleaned regularly.

6.4.2 The pressure of the overflow valve cannot be changed at will after being adjusted. Every time

before jacking-up, the oil pressure gauge should be used to check whether the pressure is normal.

6.4.3 Regularly check whether the pipe conjunctions are tight. Oil leakage is not allowed.

6.4.4 Oil filer should be regularly checked to make sure there is no blockage wherein and no change of

the adjusted value of the pressure relief valve.

6.4.5 Once leaking of the oil pump, oil tanker and controlling valve is detected, repairing should be

promptly carried out.

6.4.6 In winter when starting the machine, it should be started and stopped repeatedly to make the oil

temperature rise and the maneuver of the controlling valve nimble before formal operation.

6.4.7 every time when starting the oil pump after the assembly and overhaul, need to check whether the

inlet and out let are connected reversely, whether the revolving direction of the electric motor is correct

39
and whether the oil suction pipe is leaking. After that, use the hand to try to revolve it. Finally, start and

try the machine according the regulations.

6.5 Common failures and methods of elimination


number Symptoms of failures Causes of failures Methods of elimination

The break moment is too Adjust the spring pressure of


The drop hanger slides and the
small. .There is grime on the the break. Clean the grime.
1 trolley moves backward after brake
brake wheel. The break time Adjust the gap width of the
because of the slippage of the
is too long. small brake scotch.
arrester.
Adjust the gap width of the
The load of the arrester lashes too The brake is too quick. The
brake scotch or increase the
2 violently gap between both sides of the
push of the hydraulic
valve scotch is not even.
handspike.
The brake heats up and sends out The gap of the brake scotch is Widen the gap of the brake
3
smoke while braking. too small. scotch.
Properly increase or decrease
The temperature of the reducer is The lubricant is too little or too
4 the oil volume.
too high, much.

Mainly it is because the


lubricating grease is too little Change the lubricating grease
The temperature of the bearing of or too much, the quality of according to the standard.
5
the reducer is too high. lubricating grease is low, the Properly readjust the bearing
axial gap of the bearing is not gap or change the bearing.
up to the standard or the
bearing is broken.
The closeness of the abutted
surfaces of the connecting
6 The reducer leaks. part is not good. The seal ring Change the seal ring.
at the ends of the axle is
damaged due to wearing.
Mainly check whether there is
extraneous matter stuck in the
The slewing mechanism cannot Clear up the extraneous
7 gear or whether the oil volume
be started. matter and add oil reasonably.
of the hydrodynamic coupling
is two low.
The slewing mechanism jolts Maybe the oil volume of the
8
serious hydrodynamic coupling is too Reduce the oil volume to the

40
high. right amount.
a. the oil pump is wearing and
its efficiency is declining.
b. there is not enough oil in
the tanker or the oil filter is
stuck. Repair or replace the
9 The motion jacking-up is two slow. The rod of the hand-operated damaged parts. Add enough
direction valve and valve oil or clean the oil filter.
opening are severely worn.
d. The seal of the cylinder
piston rod is damaged, which
causes inner linkage.
a. Inner oil leakage of oil
pump is serious
b. The adjusted pressure of
overflow valve is too low. Repair, change and adjust
Jacking-up is powerless or cannot
10 c. The valve core according to the contents in
be realized.
hand-operated direction valve 6.4.
is excessive worn.
d. The overflow valve is struck
tightly.
When jacking-up, vibration noises
11 The oil filter is blocked. Clean the oil filter.
appears.
The jacking-up system does not
work.
The rotating direction of the
Change the rotating direction
12 electric motor and that of the
of the electric motor.
oil pump is different.

a. The air in the oil cylinder


piston rod of the tanker is not Stretch repeatedly without
When jacking-up, vibrating crawl
13 all drew out completely. load to discharge the air.
happens.
b. There is hindrance in the
guide mechanism.
a. There is something wrong
with the direction- locking
Jacking-up with load drops valve on the top of the Eliminate the fault and replace
14
automatically. cylinder the sealing component.
b. The seal of the oil cylinder
piston rod of is damaged.

41
1. The controlling connection
1. Check the connecting
is wrong.
graph.
2. The fuse is burned.
2. Check the fuse capacity, if
3. The motor winding is
too small, change a larger
short-circuited, grounded or
one.
open circuited.
3. Measure the voltage of the
4. The voltage of the electric
power network.
The luffing mechanism does not motor is too low.
15 4. Supply electricity at various
work. 5. The connection of the
speeds to find the short-circuit
winding is wrong.
parts and open-circuit parts,
6. The sluice of the
and repair them.
electromagnetic brake is not
5. check the voltage and
loosened.
voltage winding of the brake
7. the load is too heavy or
to see whether there is
there is something wrong with
open-circuit or sticking
the conveying mechanism.
1. There is friction between
1. Check whether the gaps of
the stator and rotor.
the stator and rotor are even.
2. The electric motor and the
2. Readjust the coaxiality of
reducer box do not on the
the electric motor and the
same axle.
There are unusual noise and over- reducer box.
3. The bearing is severely in
16 violent Vibration with the luffing 3. Clean the bearing and add
need of oil or is damaged.
mechanism. new lubricant. Change the
4. The gears have a lot of
bearing.
wear and tear.
4. Replace the gear box.
5. There is two phase
5. Cut off power supply to
operation with a whistling
check and repair.
sound.
1. The load is too heavy. 1. If the stator current is bigger
2. The load is continuous and than the specified value, the
the work is not in compliance load should be reduced.
with the regulations. 2. Make the load in
3. There is two phase compliance with the
The temperature of luffing
operation. regulations.
17 mechanism motor too high or
4. The voltage of the 3. Measure the three phase
smoking.
electricity supply is too high or current and eliminate the fault.
too low. 4. Check the input voltage and
5. The electric machine correct it.
winding is grounded or there 5. Find out the reason and
is short-circuiting between the repair.

42
brakes. 6. Adjust the air gaps
6. The gap between the according to regulations.
friction plates is wrong. 7. Check the brake voltage
7. The time of brake and and delay the operating time
release is wrong. of the breaker to eliminate the
8 The ventilation of the fault.
electric motor is blocked and 8. Keep ventilation.
heats up over high.

1. The bearing is burnt out. 1. Replace the bearing.


The bearing of the luffing
18 2. The lubricating grease is 2. Add the lubricating grease
mechanism is over-heated.
too much or too little. according to the regulations.
1. The supply cord and the
earth wire are wrongly
connected.
1. Find out and correct.
2. The earth wire is not well
19 The luffing mechanism is electrified. 2. The earth wire should be
connected.
well connected.
3. The wire of the electric
motor is scuffed and
connected to the ground.
1. The brake spring which is
1. The brake moment is too
broken up or out of service
small.
The brake of the luffing mechanism should be replaced.
20 2. The friction plates are worn
is out of control. 2. The electric brush is broken
and the air gaps become
and the voltage is not
bigger.
sufficient.
1. The handle knob is not
cleared.
1. Clear the handle knob.
The machine does not work when 2. The fuse is burnt out.
21 2. Change the fuse.
being started. 3. The starting and stopping
3. Fix or change the button.
buttons have poor contact.

Check whether the jacking-up


There is tripping operation while brake is open and whether the
22
jacking-up. calibration values are
changed.
1. The handle has poor 1. Fix the contact or the
The luffing has the second speed contact. handle knot.
23
but not the first speed. 2. The spot of contactor has 2. Repair or replace the
poor contact. contractor.

43
3. The electric motor is 3. Repair or replace the
damaged. electric motor.
1. The limit switch or the 1. Fix or replace the limit
The luffing has the first speed but touch spot has poor contact. switch.
24
not the second speed. 2. The electric motor is 2. Fix or replace the electric
damaged. motor.
1. The break switch has poor
contact. 1. Fix or replace the break
2. The rectifier bridge is burnt switch.
25 The slewing brake does not work.
out. 2. Replace or fix the damaged
3. The delay relay has poor components.
contact.
Adjust the sequence of wire
An incorrect wire connection
Amplitude indicator is reversed or connecting or clean the
26 of the amplitude indicator or a
inaccurate potentiometer, and fasten the
poor contact in the sensor.
bolts.
1. Check working voltage and
1. Input voltage below level
Hoisting power is less and the motor make sure that the input
27 2. Broken wire in AC
does not work. voltage is not below 360V.
contactor.
2. Connect the circuit.
1. Operating is too frequent.
1. Reduce operating
The temperature of motor is too 2. Too long operation at low
28 frequency properly.
high. speed or brake in lifting is not
2. Check starting brake.
started.
First check the external
Fault of external components
component and then check
29 Movement after lifting starts. or internal electric
the internal electric
components of the console.
component when necessary.

Table 7

6.6 Others

6.6.1 Change working oil for the hydraulic coupling every two years. When oiling, it is better not fill too

much, and remaining 80~90% of the capacity is the usual oil quantity. The working oil is No. 22 turbine

oil (alternative by No. 6 hydraulic transmission oil). Do not demount the part unless any fault exists.

6.6.2 The maintenance of every motor and lifting brake is provided in the operating instruction.

7. Attached drawings and tables

7.1 Schedule of the weight of tower crane components

44
Weight
Code Name Name
(kg) Code Weight (kg)

Equilibrium pull
1 QTZ400.1 Under frame 658 15 QTZ400.12 208
rod

2 QTZ400.2 Diagonal stay 133


16 QTZ400.13 Balanced jib 1653.5
3 QTZ400.3 / /

Strength
4 QTZ400.4 657x1 Multi-function
section 17 QTZ400.14 5
limiter
5 QTZ400.5 Mast section 568x12

Hydraulic
6 FDS400 200 18 QTZ400.15 Tower cap 1033
system

7 QTZ400.6 Outer frame 2565 19 QTZ400.16 Slewing limiter 1.5

Pull rod of
20 QTZ400.17 670
boom
8 QTZ400.7 Under turntable 608

21 QTZ400.18 Inlet beam 58

Rotating
9 HSW.30.1220 400 22 QTZ400.19 Boom 2965
support

Slewing trolleying
10 FHZH.400 215 23 FBF.400 180
mechanism mechanism

11 QTZ400.8 Upper turntable 928 24 QTZ400.20 Lifting hook set 136

12 QTZ400.9 Driver’s cab 266 25 QTZ400.21 trolley 165

Electrical
13 QTZ400.10 150 26 QTZ400.22 Wall ties 618
system

Hoisting
14 QTZ400.12 Counterweight 1067 27 FQS.400 1200
mechnanism

Table 8

7.2 List of lubrication of tower crane components


7.2

45
Name of Quantity of
No. Lubricant Lubricating Category of Lubricant Lubricating Method Note
Housing Points
Brake of lifting Lubricating Engine oil Oil with an oil can every 56
1
mechanism pivot point hours working
Gearbox of In winter: 20 machine Oil properly every 240
2 lifting 3 oil hours working, and change
mechanism In summer: machine oil the oil every 1500 hours.
All the rolling Oil properly every 160
bearings ZGⅢ calcium base hours and clean away twice
3
(excluding grease a year.
motor bearings)
In winter: ZG-Ⅱ Refer to
All the motor calcium base grease Change the oil every 1500 the
4
bearings In summer: HJ-Ⅴ hours working. instruction
calcium base grease s for motor

All the steel Boil in oil in every heavy


5
wires Graphite grease and medium repair
In winter: ZG-Ⅱ
calcium base grease Oil every 240 hours
6
All the pulleys In summer: HJ-Ⅴ working
calcium base grease
Speed of Oil every 240 hours
Slewing working, and change the oil
mechanism of every 1500 hours.
7 luffing 3 No. 40 machine oil
mechanism of
trolley reduces.

Track of upper Coat and pressure-inject


and under In winter: Ⅱ calcium every 56 hours working.
seats of the base grease
8 open gear ring 15
of the rotary In summer: Ⅴ calcium
mechanism base grease

In winter: No. 10
Hydraulic oil
9 1 machine oil Change the oil twice a year
tank
In summer: No. 30

46
machine oil
Hydraulic oil and No. 22 Change the oil every 1500 Refer to
turbine oil hours working the
Hydraulic
instruction
coupling of
10 s for
rotary
purchased
mechanism
componen
ts
In winter: N.25 Refer to
transformer oil the
Hydraulic
In summer: No. 10 instruction
pushing rod of
11 2 transformer oil Change the oil twice a year s for
lifting
purchased
mechanism
componen
ts

Table 9

7.3 Bearing allocation list

qua
No. Type of Bearing Code of Bearing Standard No. Installation Position
ntity

1 180308 GB279-88 Pulley block of tower cap 2

Rolling wheel of inlet beam


2 800205 GB278-89 2

3 180308 GB279-88 Lifting guide wheel of boom 2

4 60206 GB278-89 Luffing guide wheel of boom 4

5 60206 GB278-89 Suspension pulley block of boom 6

6 8308 GB301-84 Lifting hook 1

7 180308 GB279-88 Lifting hook 6

47
8 180308 GB279-88 Pulley of trolley 6

9 180206 GB279-88 Rolling wheel of trolley 8

10

11

12

7.5 Drawing of Concrete Foundation

Technical requirements:

1. The earth bearing strength under foundation should be more than 200 KN/m2.
2. Allowance of foundation surface should be ≤2mm, higher 100mm than the ground.
3. Volume is 20.81m3, weight is more than 50t.
4. Strength classes of concrete is C35 (GB50164-92). Strength grade of ordinary Portland cement
should be more than 42.5R (GB175-1999), reinforced concealed project should meet the requirement of
GB50204-2002, concreting should be firm and stable, loosen isn't allowed.

48
5. The surroundings of foundation should have smooth drainage, avoid long time ponding.
6. The customer should prepare base plates, poles and reinforcing bars.
7. Pay attention to foundation arranging direction before digging the foundation pit.

Spare parts

No. Item Name Quantity Material Note


1 GB6174-86 Hexagon thin nuts M27-ZnD 16 pcs
2 GB6170-86 Hexagon nutsM27-ZnD 16 pcs
3 Foundation bolts 16 pcs Q235B This drawing
4 Longitudinal Deformed steel barΦ16-6000 24 pcs HRB335 Without drawing
bars
5 Poles Deformed steel barΦ25-600 8 pcs HRB335
6 Steel frame Deformed steel barΦ12-4400 56 pcs HRB335 This drawing

件 3 地脚螺栓:Item3 foundation bolts (1:10); 件 6 框筋:item 6 steel frame(1:50)

7.6 Diagram of balanced weight

49
Quantity of balanced weight is 6 pieces; Per weight is more than 1.375t; Item 6, 7, 8, materials should be
prepared by the customer.

50
Materials

No. Item Name Quantity Material


1 Angle steel 30x3-1040 4 Q235B
2 Angle steel 30x3-640 4 Q235B
3 Angle steel 30x3-1650 4 Q235B
4 Angle steel 30x3-870 4 Q235B
5 Round steel Φ25-1900 1 Q235B
6 Reinforcement Φ10-874 6 Q235B
7 Reinforcement Φ10-1034 2 Q235B
8 Reinforcement Φ10-240 10 Q235B
9 Angle steel 30x3-270 8 Q235B
10 Angle steel 30x3-220 2 Q235B
11 Angle steel 30x3-820 2 Q235B
12 Reinforcement Φ10-2290 6 Q235B

7.7 Electrical Schematic Diagram

51
Electrical diagrams (hoisting control return circuit parts)

52
7.8 Assembly of pulling rod

1000
3150
6150
6150
6150

800
0
6150

599
6150

0
615
800
800

60
46

50
61

0
80

7.9 Instructions of changing jibs

53
1300
1040 1040

900
2300
1650

880 280

880 280
Table 1 Table 2
7.9.1 a. From 48m jib to 42m jib, disassembly the seventh section, use the eighth section to connect
the sixth section, the size of pulling rod keeps the same.
b. Decrease one piece balanced weight, from six pieces (table 1) to five pieces, and take some
measures to fix the balanced five pieces balanced weight in order that they shake and move.
(the weight of balanced weight is : 6850±15)
7.9.2 a. From 48m jib to 36m jib, disassembly the sixth and seventh sections, use the eighth section
to connect with the fifth section, pulling rod keeps the same.
b. Decrease two pieces balanced weights, that are away from the mechanism, changed to four
pieces (table 1), added one small piece balanced weight (table 2), put it on the empty space,
fix it in order that it shakes and moves. (the weight of balanced weight is : 6850±15)

seller’’s drawing.
Note: small balanced weight need to be made by seller

54

You might also like