Arabian Bemco Contracting Co. KSA Power Plant Project-10 Risk Assessment
Arabian Bemco Contracting Co. KSA Power Plant Project-10 Risk Assessment
KSA
Power Plant Project-10
RISK ASSESSMENT
Risk Risk
Hazard Persons at Risk Rating Proposed Control Measures Rating
S L R S L R
Power Tools • Lead Man 5 5 25 • Flushing Crew Shall Be Trained & Competent. 5 1 5
• Rotating Parts • Flushing Crew • Work Crews Will Use Appropriate PPE.( Safety Goggles,
• Electrocution From Damage Cables • Supervisor Face Shields, Dust Mask )
• Inhalation (Dust) • General Helpers • STARRT Talks For All Crews by Supervisor/Foreman.
• Dust/Objects In Eye • Power Tools Training As Tool Box Talks Topic.
• Power Tools And Cables Shall Be Inspected Daily And
Color Coded Prior To Start Of Work.
• Damage or Defective Power Tools Shall Be Tagged Out Of
Service And Immediately Returned To The Tool Room for
Repair.
• Grounding/Earthling Will Be Provided On All Mobile
Generators.
Noise (Equipment) • Lead Man 5 4 20 • Work Crews Will Use Appropriate PPE (Ear Muff, Ear 4 1 4
• Ear Damage • Flushing Crew Plug).
• General Helpers • STARRT Talks For Crews Working In Noisy Environment.
• Supervisor • Noise (Ear Protection) As Training In Tool Box Talks Topic.
• Inspector • Ensure Appropriate Barricades (Tape) & Sign Boards “Ear
Protectors Must Be Worn In This Area” Placed Around In
The Equipment.
• All Silencers Must Be Inspected For Maintenance To Ensure
The Proper Condition Of Equipment Prior To Start Of Work.
• All Equipment On Site Must Utilize Silencer.
of 1 Page 6
Arabian Bemco Contracting Co. KSA
Power Plant Project-10
RISK ASSESSMENT
Risk Risk
Rating Rating
Manual Handling • Supervisor 5 5 25 • STARRT Talks For Crews. 5 1 5
• Lead Man • Manual Handling As Tool Box Talks Topic.
• Flushing Crew • Work Crews Will Use Appropriate PPE. ( Safety Goggles,
• General Helpers Welder Gloves, Argon Gloves)
Hazard Persons at Risk Proposed
• Plan The Route Control
Before You Lift. Measures
• Keep Work Area & Walkways Clear.
• Allow Rest Periods.
• Workers Are Trained To Move Feet Instead Of Twisting
Body.
of 2 Page 6
Arabian Bemco Contracting Co. KSA
Power Plant Project-10
RISK ASSESSMENT
Risk Risk
Rating Rating
Hazard Persons at Risk • Work Crews Proposed ControlPPE.
Will Use Appropriate Measures
• Sufficient Water Available For Eye And Skin Wash.
Compressed Air • Supervisor 5 4 20 • Pressure Testing Crew Shall Be Trained And Competent. 4 1 4
• Air Impact • Lead Man • Work Crews Will Use Appropriate PPE
• Eyes • Flushing Crew • STARRT Talks For All Crews.
• Skin • Inspector • Compressed Air Training As Tool Box Talks Topic.
• Hose Whip Check • General Helpers • Provide Adequate Fire Protection (Provision Of Sand, Fire
Blanket, and Fire Watchman & Fire Extinguisher).
• Air Hose Must Be Keeping Free Of Grease And Oil.
• Hose Ends Must Be Secured To Prevent Whipping.
• Compressed Air Shall Be Identified the Maximum Working
Pressure.
• Proper Training Prior To Start Of Work.
• Compressed Air System Shall Be Inspected Regularly.
• Proper Communication During Operation
• First Aid Kit Will Be Available.
Working At Heights • Supervisor 5 5 25 • Working At Heights Training As Tool Box Talks Topic. 5 1 5
• Fall Person • Lead Man • STARRT Talks for Crews Working At Heights.
• Fall Material • Flushing Crew • Scaffold Erection by Competent Person.
• General Helpers • Scaftag Inspection Approval before Use.
• Inspector • Safety Full Body Harness Required (Fall Protection).
of 3 Page 6
Arabian Bemco Contracting Co. KSA
Power Plant Project-10
RISK ASSESSMENT
Risk Risk
Rating Rating
Electrical Works • Supervisor 5 5 25 • Electricians Shall Be Trained & Competent. 5 1 5
• Fire & Explosion • General Helpers • Helper Shall Be Trained & Competent.
• Electrocution • Flushing Crew • Work Crews Will Use Appropriate PPE.
• Lead Man • Safe Insulated Tools Will Be Used In Order To Carry Out
Hazard Persons at Risk Proposed Control Measures
Electrical Work.
• STARRT Talks For All Crews Involve In Site Electricity.
• Site Electricity Training as Tool Box Talks Topic.
• Lock Out/Tag out System.
• First Aid Kit Will Be Available.
Risk Risk
Rating Rating
Hazard Persons at Risk Proposed Control Measures
• Always Check The Area Free From Unnecessary Materials.
• Work Place Shall Be Maintained In A Good Condition That
Is Clean And Tidy.
Fluid Spills From Vehicles Equipment • Environment 5 4 20 • Daily Inspection of Equipment for Leaks. 4 1 4
• Ground Contamination • Routine Preventive Maintenance Program.
• Water Contamination • Maintenance Performed By Competent Persons.
• Drip Pans Sheets Used during Service and all joint point of
hoses.
• Spills Kit (Sand) Available In Service Area.
• Impervious Material under Fuel Tanks (Bounded) Fuelling
Area, Service Area.
• Impervious Material under Waste Oil Storage Area.
• Proper drainage system.
• Barricade the area and sign board posted (Danger Flushing in
progress) all around the area.
of 5 Page 6
Arabian Bemco Contracting Co. KSA
Power Plant Project-10
RISK ASSESSMENT
Risk Risk
Rating Rating
Hazard Persons at Risk Proposed Control Measures
Originator Signature: Sajid Ali Date: 18-09-2015
of 6 Page 6
Arabian Bemco Contracting Co. KSA
Power Plant Project-10
RISK ASSESSMENT
Risk Risk
Rating Rating
Hazard Persons at Risk Proposed Control Measures
Originator Signature: Sajid Ali Date: 18-09-2015