Professional Documents
Culture Documents
Bab 8 MS Project-Tutorial
Bab 8 MS Project-Tutorial
Bab 8 MS Project-Tutorial
siswoyo@polban.ac.id 1
2
Time, Cost, and Scope: Managing Project Constraints
• Project management gets most interesting when you must balance
the Project Triangle: time, cost, and scope constraints of your
projects.
• The project triangle illustrates the process of balancing constraints
because the three sides of the triangle are connected, and changing
one side of a triangle affects at least one other side.
siswoyo@polban.ac.id 3
siswoyo@polban.ac.id 4
Impacts of Cost Cutting
siswoyo@polban.ac.id 6
MS Project 2010 Setup
• Select File, Options, click on “Schedule” tab
• For Calendar options for this project: “Select “All
New Projects”
• For Scheduling options for this project: select “All
New Projects”
• For New Tasks Created: select “Auto Scheduled”
• For Duration is entered in: select “weeks”
• For default task type: select “fixed duration”
• make sure New tasks are effort driven is NOT checked
• Click OK when finished
7
8
Creating a Project
Creating a Project
10
Example Project
• Task, Duration, and Immediate Predecessor Information for Construction Project
• IMMEDIATE DURATION
• TASK DESCRIPTION PREDECESSORS (WEEKS)
• 1 START -- 0
• 2 Excavate and Pour Footers 1 3
• 3 Pour Concrete Foundation 2 1
• 4 Erect Rough Wall & Roof 3 4
• 5 Install Siding 4 6
• 6 Install Plumbing 4 3
• 7 Install Electrical 4 4
• 8 Install Wallboard 6,7 5
• 9 Lay Flooring 8 6
• 10 Do Interior Painting 8 3
• 11 Install Interior Fixtures 9,10 3
• 12 Install Gutters & Downspouts 5 2
• 13 Do Grading & Landscaping 12 3
• 14 FINISH 11,13 0
11
siswoyo@polban.ac.id 13
siswoyo@polban.ac.id 14
Entering Task Information
15
Task Information
Double-clicking on a task name opens the Task Information” screen
16
Project Charts
• The Gantt Chart view shows task linkages
• Since START and FINISH are dummy activities with 0
duration, they are milestones in MS Project (black
diamonds)
– Right-click on dates in the chart and then “zoom” as
desired
• Change view to Network Diagram by clicking on “View”
in the menu and then select “Network Diagram” (zoom as
desired)
17
Gantt Chart
18
Network Diagram
19
20
Project Critical Path Length
21
22
Schedule Table & Detail Gantt
23
24
Critical Path Analysis
• Notice that tasks 12 and 13 both have 7 weeks of total
slack
• However, if task 12 uses this slack, it is not available to
task 13, so its slack is not free
• Tasks 12 and 13 are linked, so delaying the start of 12
delays the start of 13 by the same amount
•
25
Summary Tasks
• Summary tasks can be used to better organize a project (see
constructionS.mpp)
• We add three summary tasks: Structure, Interior, and
Exterior
• Structure includes current tasks 2 – 4, Interior includes 6 –
11, Exterior includes 5, 12, 13
• Example: highlight “Excavate and Pour Footers,” click on
“Tasks”, click on” Summary,” enter “Structure”
• Indent first three tasks under “Structure” by highlighting them
and selecting “indent” (thick green arrow going to the right)
26
Creating a Summary Task
27