M/S INDIAN OIL CORPORATION LIMITED

PRE-REQUISITE SLIP

RA Bill No.: RA BILL-10 Dtd. 13.02.2015

Name of the Department :

Name of the Work :

Name of the Contractor :

LOA No. and date

Percentage Engineer
checked by
Site Engineer

Engineer - In - Charge

Date of Commencement of the work :

Date of Completion as per LOA / Contract

Period of Bill :

Actual Date of completion :

Extension granted, if any :

Site Engineer
M/S INDIAN OIL CORPORATION LIMITED

PRE-REQUISITE SLIP

Paradip Raipur Ranchi Pipeline Project For


marketing top's group B- Khunti

COMBINED STATION WORKS (CSW) FOR


CONSTRUCTION OF MARKETING TAP OFF
POINTS GROUP-B-KHUNTI, JHARKHAND.

M/S Furnace Fabrica (I) Ltd.

24047898, DATE : 03/01/2014

100%

10%

2%

14.02.2014
(As per specific Notice)

13.02.2015
(12 months)

01.02.15 to 13.02.15

In progress

--

Engineer - In- Charge


LOKNATH APPARTMENT, B-BLOCK
ROOM NO: 403, HESAG INVOICE
HATIA, RANCHI-834003
EMAIL:ffil.ioclkhunti@gmail.com RA BILL-10
TO INVOICE NO: FFIL/IOCL-Khunti/MECHANICAL SUPPLY/10
DATE : 13.02.2015

INDIAN OIL CORPORATION LTD WORK ORDER NO: 24047898


DATE : 03/01/2014
PRRPL PROJECT PAN NO:AAACF0527E
SERVICE TAX NO: AAACF0527EST001
B BLOCK, GROUND FLOOR, SHAHDEO TOWER, SERVICE TAX CATEGORY: WORK CONTRACT
P.P COMPOUND, RANCHI - 834001
(JHARKHAND) TIN NO: 20610108951
CST NO: 20610108951-101

SL NO: ITEM DESCRIPTION AMOUNT (Rs)

1 MECHANICAL SUPPLY 740671.20

TOTAL BILL VALUE 740671.20

Amount in words: SEVEN LAKH FOURTY THOUSAND SIX HUNDRED SEVENTY ONE AND PAISE TWENTY ONLY

FURNACE FABRICA (INDIA) LTD.

(RESIDENT CONSTRUCTION MANAGER)


INVOICE NO: FFIL/IOCL-Khunti/MECHANICAL SUPPLY/10
DATE : 13.02.2015

WORK ORDER NO: 24047898


DATE : 03/01/2014
PAN NO:AAACF0527E
SERVICE TAX NO: AAACF0527EST001
SERVICE TAX CATEGORY: WORK CONTRACT
TIN NO: 20610108951
CST NO: 20610108951-101

AMOUNT (Rs)

740671.20

740671.20

THOUSAND SIX HUNDRED SEVENTY ONE AND PAISE TWENTY ONLY

FURNACE FABRICA (INDIA) LTD.

(RESIDENT CONSTRUCTION MANAGER)


LOKNATH APPARTMENT, B-BLOCK
ROOM NO: 403, HESAG
INVOICE
HATIA, RANCHI-834003
EMAIL:ffil.ioclkhunti@gmail.com RA BILL-10
TO INVOICE NO: FFIL/ IOCL - Khunti/ MECHANICAL SERVICE/ 10
DATE : 13.02.2015

INDIAN OIL CORPORATION LTD WORK ORDER NO: 24047898


DATE : 03/01/2014
PRRPL PROJECT PAN NO:AAACF0527E
SERVICE TAX NO: AAACF0527EST001
B BLOCK, GROUND FLOOR, SHAHDEO TOWER, SERVICE TAX CATEGORY: WORK CONTRACT
P.P COMPOUND, RANCHI - 834001
(JHARKHAND) TIN NO: 20610108951
CST NO: 20610108951-101

SL NO: ITEM DESCRIPTION AMOUNT (Rs)

1 MECHANICAL SERVICE WORKS 1640809.52

TOTAL 1640809.52
2 Add SERVICE TAX (12%) OF BILL VALUE 196897.14
3 EDUCATION CESS (2%) 3937.94
4 S&H CESS (1%) 1968.97
TOTAL BILL VALUE WITH TAXES 1843613.57
AMOUNT IN WORDS: EIGHTEEN LAKH FOURTY THREE THOUSAND SIX HUNDRED THIRTEEN AND PAISA FIFTY SEVEN
ONLY.

FURNACE FABRICA (INDIA) LTD.

(RESIDENT CONSTRUCTION MANAGER)


LOKNATH APPARTMENT, B-BLOCK
ROOM NO: 403, HESAG
INVOICE
HATIA, RANCHI-834003
EMAIL:ffil.ioclkhunti@gmail.com RA BILL-10
TO INVOICE NO: FFIL/IOCL-Khunti /CIVIL COMPOSITE/10
DATE : 13.02.2015

INDIAN OIL CORPORATION LTD WORK ORDER NO: 24047898


DATE : 03/01/2014
PRRPL PROJECT PAN NO:AAACF0527E
SERVICE TAX NO: AAACF0527EST001
B BLOCK, GROUND FLOOR, SHAHDEO TOWER, SERVICE TAX CATEGORY: WORK CONTRACT
P.P COMPOUND, RANCHI - 834001 (JHARKHAND) TIN NO: 20610108951
CST NO: 20610108951-101

SL NO: ITEM DESCRIPTION AMOUNT (Rs)

1 CIVIL COMPOSITE WORKS 6098639.22

TOTAL 6098639.22
2 Add SERVICE TAX (4.8%) OF BILL VALUE 292734.68
3 EDUCATION CESS (2%) 5854.69
4 S&H CESS (1%) 2927.35
TOTAL BILL VALUE WITH TAXES 6400155.94

AMOUNT IN WORDS: SIXTY FOUR LAKH ONE HUNDRED FIFTY FIVE AND PAISA NINETY FOUR ONLY.

FURNACE FABRICA (INDIA) LTD.

(RESIDENT CONSTRUCTION MANAGER)


LOKNATH APPARTMENT, B-BLOCK
ROOM NO: 403, HESAG
INVOICE
HATIA, RANCHI-834003
EMAIL:ffil.ioclkhunti@gmail.com RA BILL-10
TO INVOICE NO: FFIL/IOCL-Khunti /MECHANICAL
COMPOSITE/10 DATE : 13.02.2015

INDIAN OIL CORPORATION LTD WORK ORDER NO: 24047898


DATE : 03/01/2014
PRRPL PROJECT PAN NO:AAACF0527E
SERVICE TAX NO: AAACF0527EST001
B BLOCK, GROUND FLOOR, SHAHDEO TOWER, SERVICE TAX CATEGORY: WORK CONTRACT
P.P COMPOUND, RANCHI - 834001 (JHARKHAND) TIN NO: 20610108951
CST NO: 20610108951-101

SL NO: ITEM DESCRIPTION AMOUNT (Rs)

1 MECHANICAL COMPOSITE WORKS 449446.93

TOTAL 449446.93
2 Add SERVICE TAX (4.8%) OF BILL VALUE 21573.45
3 EDUCATION CESS (2%) 431.47
4 S&H CESS (1%) 215.73
TOTAL BILL VALUE WITH TAXES 471667.58
AMOUNT IN WORDS: FOUR LAKH SEVENTY ONE THOUSAND SIX HUNDRED SIXTY SEVEN AND PAISA FIFTY EIGHT
ONLY.

FURNACE FABRICA (INDIA) LTD.

(RESIDENT CONSTRUCTION MANAGER)


MECHANICAL
ATE : 13.02.2015

T001
CONTRACT

(Rs)

93

93
45
7
3
58
N AND PAISA FIFTY EIGHT

NACE FABRICA (INDIA) LTD.

ONSTRUCTION MANAGER)
CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/13

Work Description :- COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TAP O
WO NO.&DATE :24047898 Dated 03-01-2014 RA BILL NO : FFIL/CIVIL-MECH SER-MECH
CLIENT : INDIAN OIL CORPORATION LIMITED (PIPELINE DIVISION) DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA (INDIA) LTD MEASUREMENT PERIOD : 01.02.15 to 13.02.15
PART 1 & 2
MB DETAILS Upto Previous
SOR BREAK
S NO ITEM DESCRIPTION UOM UNIT RATE UP %
FROM TO QTY QUANTITY AMOUNT (RS.)

00020 CSW-COMPOSITE WORKS


1.0 MECHANICAL COMPOSITE WORKS
1.01 Supply & Erection of Structural Steel.
00010 Supply & Erection of Structural Steel. MT 45 97201 60 11.55 673602.93
1.03 Painting of A/G Piping(Product&Water)
00020 Zinc Ethyl Silicate Primer(1 coat of 65-75 micron ) SQM 11500 293 100 3012.70185 882721.641108214

00030
High build Epoxy MIO Intermediate Paint ( 1 coats of SQM 11500 293 100 1270.40957 372230.003348657
100 micron )
1.06 Supply & Installation of HOT Crane.

Supply of 5 Ton capacity HOT crane for the Fire fighting


00020 Pump House/Shed(36 M length, 8 M width&6.5 M EA 1 2332800 90 1 2099520
height)

00030
Supply of 5 Ton capacity HOT crane for the TLF Pump EA 1 4301100 90 1 3870990
House/Shed (88.5 M Length, 6 M width & 5.5 M height)

SUB TOTAL (INR) 7899064.57


MB DETAILS Upto Previous
SOR BREAK
S NO ITEM DESCRIPTION UOM UNIT RATE UP %
FROM TO QTY QUANTITY AMOUNT (RS.)

2.0 CIVIL COMPOSITE WORKS


00010 EARTH WORK
Site cleaning work of the ground in all kinds of soil
00020
including clearing the area
SQM 2500 13.00 100 0.000 0.00

00030 Excavation in all kinds of soil except


00040 a) Depth upto 1.5 m (measured from OGL) CUM 16000 138.00 100 2039.898 281505.96
00050 b) Depth between 1.5 m to 5 m CUM 3000 212.00 100 339.808 72039.33
Supplying and filling coarse sand under floors, in
00150
foundations and plinths etc. CUM 450 604.00 100 16.976 10253.20
00170 PILLING WORKS

00180 Boring single under reamed pile with RCC mix


(1:1.5:3)
00190 a) 300mm dia depth upto 6m M 3450 1793.00 100 6458.049 11579281.86
00230 LOAD TEST ON PILES
00250 A) TEST COLUMN
00260 a) Initial vertical static load test on single pile EA 9 54133.00 100 9.000 487197.00
00270 B) JOB COLUMN
00280 a) Initial vertical static load test on single pile EA 9 62052.00 100 9.000 558468.00
00290 Plain Concrete Works.
MB DETAILS Upto Previous
SOR BREAK
S NO ITEM DESCRIPTION UOM UNIT RATE UP %
FROM TO QTY QUANTITY AMOUNT (RS.)

00300 PCC mix (1:4:8) for foundation work cum 2000 3091.00 100 166.922 515955.84
00310 PCC with mix(1:3:6) cum 820 3462.00 100 18.500 64047.00
00320 PCC with mix(1:2:4) cum 30 3750.00 100 3.780 14175.00
00360 REINFORCED CEMENT CONCRETE
a)Laying RCC mix (1:1.5:3) in column, pedestal, beam,
00400 cum 4100 5514.00 100 1003.359 5532519.47
roof slab,chajja etc
00430 Reniforcement for RCC work TON 800 57933.00 100 192.487 11151354.12
00450 Supplying & using of plasticizer in RCC works. L 7800 107.00 100 128.000 13696.00
00470 Painting foundation concrete with hot bitumen SQM 5000 148.00 100 1308.212 193615.35
Supplying and laying flat brick soling in foundation
00490 SQM 2750 316.00 100 31400.92
trench, in floors,garages, sumps, etc. 99.370
00500
Brick work with burnt clay bricks of class
designation 50 in cement mortar 1:6.
00510 a)In foundation, plinth etc. CUM 750 3848.00 100 42.759 164535.19
00540 General Structural Steel Works
Supplying fabricating and fixing M.S structural steel
00550 TON 320 73438.00 100 90.932 6677872.07
work.

Supplying and providing chain link fencing with GI


00640 SQM 50 607.00 100 0.000 0.00
wire of 3 mm diaforming a mesh size of 50 x 50 mm

SUB TOTAL (INR) 37347916.30

00010 CSW- SERVICES


1.0 MECHANICAL SERVICE
1.08 ABOVE GROUND PIPING(PRODUCT LINES)
A) FABRICATION
MB DETAILS Upto Previous
SOR BREAK
S NO ITEM DESCRIPTION UOM UNIT RATE UP %
FROM TO QTY QUANTITY AMOUNT (RS.)

00010 Above ground piping for Product Process Lines


00020 24" OD x 0.375" WT APL 5L Gr. B Pipe M 825 5010 30 675.043 1014589.63
00030 20" OD x 0.375" WT APL 5L Gr. B Pipe M 1200 4801 30 654.269 942343.64
00040 18" ODx0.375" WT APL 5L Gr. B Pipe M 375 4320 30 224.043 290359.73
00050 14" OD x 0.375" WT APL 5L Gr. B Pipe M 1900 4124 30 1449.909 1793827.41
00060 12.75" OD x 0.375" WT APL 5L Gr.B Pipe M 1900 3519 30 1112.419 1174380.74
00070 10.75" OD x 0.365" WT APL 5L Gr.B Pipe M 950 3421 30 582.597 597919.30
00080 8.625" OD x 0.322" WT APL 5L Gr.B Pipe M 1100 2898 30 590.793 513635.43
00090 6.625" ODx0.280" WT APL 5L Gr.B Pipe M 750 2531 30 272.000 206529.60
00100 4.50" ODx0.237" WT ASTM A 106 Gr.B pipe M 1250 1789 30 755.240 405337.31
00120 2.375" ODx0.218" WT ASTM A 106 Gr.B pipe M 275 1001 30 0.000 0.00
B) ERECTION.
00020 24" OD x 0.375" WT APL 5L Gr. B Pipe M 825 5010 40 170.050 340780.20
00030 20" OD x 0.375" WT APL 5L Gr. B Pipe M 1200 4801 40 0.000 0.00
00050 14" OD x 0.375" WT APL 5L Gr. B Pipe M 1900 4124 40 520.575 858740.52
00060 12.75" OD x 0.375" WT APL 5L Gr.B Pipe M 1900 3519 40 137.100 192981.96
00070 10.75" OD x 0.365" WT APL 5L Gr.B Pipe M 950 3421 40 105.150 143887.26
00080 8.625" OD x 0.322" WT APL 5L Gr.B Pipe M 1100 2898 40 0.000 0.00
00120 2.375" ODx0.218" WT ASTM A 106 Gr.B pipe M 275 1001 40 0.000 0.00
1.09 UNDER GROUND PIPING(PRODUCT LINES-FAB)
00110 3.50" OD x 0.216" WT ASTM A 106 GR.B M 300 1317 40 196.585 103560.98
1.10 ABOVE GROUND PIPING FOR FUEL/ AIR LINES(FAB)
00030 3.50" ODx0.216" WT ASTM A 106 Gr.B pipe M 300 460 30 300.000 41400.00
00070 3.50" ODx0.216" WT ASTM A 106 Gr.B pipe M 600 460 30 501.685 69232.53
1.10 ABOVE GROUND PIPING FOR FUEL/ AIR LINES(ERE)
00070 3.50" ODx0.216" WT ASTM A 106 Gr.B pipe M 300 460 40 0.000 0.00
1.11 UNDER GROUND PIPING FOR FUEL/ AIR LINES(FAB)
00020 3.50" ODx0.216" WT ASTM A 106 Gr.B pipe M 450 538 40 59.020 12701.10
MB DETAILS Upto Previous
SOR BREAK
S NO ITEM DESCRIPTION UOM UNIT RATE UP %
FROM TO QTY QUANTITY AMOUNT (RS.)

1.12 ABOVE GROUND PIPING (FIRE WATER LINES)


00020 24" OD x 0.375" WT IS 3589 FE410 PIPE M 200 6033 30 106.518 192786.928
00030 16" ODx0.250 WT IS 3589 FE 410 PIPE M 2500 4022 30 1883.747 2272929.130
MB DETAILS Upto Previous
SOR BREAK
S NO ITEM DESCRIPTION UOM UNIT RATE UP %
FROM TO QTY QUANTITY AMOUNT (RS.)

00050 12" OD x 0.250" WT IS 3589 FE410 PIPE M 450 3205 30 164.696 158355.204
00060 10.75" ODx0.250 WT IS 3589 FE 410 PIPE M 975 2702 30 507.919 411719.141
00070 8.625" ODx0.250 WT IS 3589 FE 410 PIPE M 775 2162 30 70.000 45402.000
00080 6.625" OD x 0.250" WT IS3589 FE410 Pipe M 250 1621 30 21.000 10212.300
1.17 RADIOGRAPHIC INSPECTION
00020 24" NB Pipe Joints EA 35 3023 100 13 39299.00
00030 20" NB Pipe Joints EA 40 2571 100 10 25710.00
00040 18" NB Pipe Joints EA 20 1977 100 4 7908.00
00041 16" NB Pipe Joints EA 40 1887 100 8 15096.00
00060 14" NB Pipe Joints EA 70 1601 100 26 41626.00
00070 12" NB Pipe Joints EA 95 1521 100 28 42588.00
00080 10" NB Pipe Joints EA 55 1165 100 13 15145.00
00090 8" NB Pipe Joints EA 40 896 100 14 12544.00
00100 6" NB Pipe Joints EA 25 717 100 4 2868.00
00110 4" NB Pipe Joints EA 35 475 100 7 3325.00
00130 3" NB Pipe Joints EA 55 474 100 11 5214.00
SUB TOTAL (INR) 12004935.05

00030 CSW-SUPPLY
1.0 MECHANICAL SUPPLY
1.11 ASTM 106 GR.B SEAMLESS BARE STEEL PIPES
00010 ASTM A 106 GR.B PIPES (SEAMLESS PIPES)
00020 4.50" ODx0.237" WT M 1850 1326.00 90 1850 2207790.00
00030 3.50" ODx0.216" WT M 2400 933.00 90 2400 2015280.00
00040 2.375" ODx0.218" WT M 800 668.00 90 800 480960.00
00050 1.315" ODx0.179" WT M 1850 256.00 90 1850 426240.00
1.07 STEEL FLANGES (WNRF)
00010 STEEL FLANGES (WNRF)
MB DETAILS Upto Previous
SOR BREAK
S NO ITEM DESCRIPTION UOM UNIT RATE UP %
FROM TO QTY QUANTITY AMOUNT (RS.)

00020 3" X 300# (Pipe Size 3.500" OD x 0.216" WT) EA 22 1110.00 90 22 21978.00
00030 2" X 300# (Pipe Size 2.375" OD x 0.218" WT) EA 45 803.00 90 45 32521.50
00040 1" X 300# (Pipe Size 1.315" OD x 0.179" WT) EA 105 333.00 90 105 31468.50
00050 6" X 150# (Pipe Size 6.625" OD x 0.280" WT) EA 15 1671.00 90 15 22558.50
00060 4" X 150# (Pipe Size 4.500" OD x 0.237" WT) EA 220 1006.00 90 220 199188.00
00070 3" X 150# (Pipe Size 3.500" OD x 0.216" WT) EA 190 681.00 90 190 116451.00
00080 2" X 150# (Pipe Size 2.375" OD x 0.218" WT) EA 240 399.00 90 240 86184.00
00090 1" X 150# (Pipe Size 1.315" OD x 0.179" WT) EA 400 278.00 90 400 100080.00
00100 3/4" X 150# (Pipe Size 1.050" OD x 0.154" WT) EA 60 173.00 90 60 9342.00
1.08 STEEL FLANGES (BLRF)
00010 STEEL FLANGES (BLRF)
00020 3" X 300# (Pipe Size 3.500" OD x 0.216" WT) EA 4 1121 90 4 4035.60
00030 2" X 300# (Pipe Size 2.375" OD x 0.218" WT) EA 10 556 90 10 5004.00
00040 1" X 300# (Pipe Size 1.315" OD x 0.179" WT) EA 12 315 90 12 3402.00
00050 6" X 150# (Pipe Size 6.625" OD x 0.280" WT) EA 5 1316 90 5 5922.00
00060 4" X 150# (Pipe Size 4.500" OD x 0.237" WT) EA 50 1084 90 50 48780.00
00070 3" X 150# (Pipe Size 3.500" OD x 0.216" WT) EA 40 773 90 40 27828.00
00080 2" X 150# (Pipe Size 2.375" OD x 0.218" WT) EA 40 495 90 40 17820.00
00090 1" X 150# (Pipe Size 1.315" OD x 0.179" WT) EA 20 387 90 20 6966.00
00100 3/4" X 150# (Pipe Size 1.050" OD x 0.154" WT) EA 10 102 90 10 918.00
MB DETAILS Upto Previous
SOR BREAK
S NO ITEM DESCRIPTION UOM UNIT RATE UP %
FROM TO QTY QUANTITY AMOUNT (RS.)

1.13 STEEL FASTENERS


00010 STEEL FASTENERS
00020 0.750" Dia. X 5.00" Length (for 3" x 300# f) EA 202 104 90 202 18907.20
00030 0.625" Dia. X 4.00" Length (for 2" x 300# f) EA 414 57 90 414 21238.20
00040 0.625" Dia. X 3.50" Length (for 1" x 300# f) EA 966 54 90 966 46947.60
00050 1.125" Dia. X 7.75" Length (for 24" x 150# f) EA 368 334 90 368 110620.80
00060 1.125" Dia. X 7.00" Length (for 20" x 150# f) EA 368 282 90 368 93398.40
00070 1.125" Dia. X 6.50" Length (for 18" x 150# f) EA 184 216 90 184 35769.60
00080 1.000" Dia. X 6.00" Length (for 16" x 150# f) EA 2116 193 90 2116 367549.20
00090 1.000" Dia. X 6.00" Length (for 14" x 150# f) EA 1288 167 90 1288 193586.40
00100 0.875" Dia. X 5.50" Length (for 12" x 150# f) EA 2714 123 90 2714 300439.80
00110 0.875" Dia. X 5.25" Length (for 10" x 150# f) EA 2760 103 90 2760 255852.00
00120 0.750" Dia. X 4.75" Length (for 8" x 150# f) EA 1886 79 90 1886 134094.60
00130 0.750" Dia. X 4.50" Length (for 6" x 150# f) EA 1104 73 90 1104 72532.80
00140 0.625" Dia. X 4.00" Length (for 5" x 150# f) EA 276 53 90 276 13165.20
00150 0.625" Dia. X 4.00" Length (for 4" x 150# f) EA 2300 53 90 2300 109710.00
00160 0.625" Dia. X 4.00" Length (for 3" x 150# f) EA 1748 53 90 1748 83379.60
00170 0.625" Dia. X 3.75" Length (for 2" x 150# f) EA 2208 52 90 2208 103334.40
00180 0.500" Dia. X 3.00" Length (for 1" x 150# f) EA 3496 38 90 3496 119563.20
00190 0.500" Dia. X 3.00" Length (for 3/4" x 150# f) EA 552 38 90 552 18878.40
1.10 VALVES (HOV)
00010 : Supply and delivery of API 600/602 Gate valves,
BS5351 Ball valves, BS1865 Swing check valves etc
00020 API 600 Gate Valves (HOV)
00030 4"x150#, F/F, A/G EA 130 15523 90 130 1816191.00
00040 3"x150#, F/F, A/G EA 52 10783 90 52 504644.40
00050 2"x150#, F/F, A/G EA 116 7740 90 116 808056.00
00060 API 602 Gate Valves(HOV)
MB DETAILS Upto Previous
SOR BREAK
S NO ITEM DESCRIPTION UOM UNIT RATE UP %
FROM TO QTY QUANTITY AMOUNT (RS.)

00070 1"x 800#, W/W, A/G EA 239 1318 90 239 283501.80


00080 BS 5351 Ball Valves (HOV)
00090 4"x ANSI 150# F/F,A/G, BS 5351 Ball Valv EA 15 24672 90 15 333072.00
00100 3"x ANSI 300# F/F,A/G, BS 5351 Ball Valv EA 5 22126 90 5 99567.00
00110 3"x ANSI 150# F/F,A/G, BS 5351 Ball Valv EA 32 23862 90 32 687225.60
00120 2"x ANSI 300# F/F,A/G, BS 5351 Ball Valv EA 10 14419 90 10 129771.00
00130 2"x ANSI 150# F/F,A/G, BS 5351 Ball Valv EA 20 15620 90 20 281160.00
00140 1"x ANSI 300# F/F,A/G, BS 5351 Ball Valv EA 30 13362 90 30 360774.00
00150 1"x ANSI 150# F/F,A/G, BS 5351 Ball Valv EA 40 9893 90 40 356148.00
00160 BS 1868 Swing Check Valves
00170 4"x ANSI 150# F/F,A/G, BS 1868 Swing Che EA 20 23458 90 20 422244.00
00180 3"x ANSI 300# F/F,A/G, BS 1868 Swing Che EA 3 15072 90 3 40694.40
00190 3"x ANSI 150# F/F,A/G, BS 1868 Swing Che EA 25 11998 90 25 269955.00
00200 2"x ANSI 300# F/F,A/G, BS 1868 Swing Che EA 5 14148 90 5 63666.00
00210 2"x ANSI 150# F/F,A/G, BS 1868 Swing Che EA 26 14998 90 26 350953.20
00220 1"x ANSI 300# F/F,A/G, BS 1868 Swing Che EA 15 4054 90 15 54729.00
00230 1"x ANSI 150# F/F,A/G, BS 1868 Swing Che EA 95 3547 90 95 303268.50
1.04
00010Y-TYPE STRAINERS(10
Y-type MESH)
strainer (10 Mesh size) for fire water
services.
00020 12" x 12"-150#, Flow-616 CuM/Hr.(for F/F Pumps) EA 6 369037 90 6 1992799.80
MB DETAILS Upto Previous
SOR BREAK
S NO ITEM DESCRIPTION UOM UNIT RATE UP %
FROM TO QTY QUANTITY AMOUNT (RS.)

00030 8" x 8"-150#, Flow-105 CuM/Hr.(for Jockey Pumps) EA 2 199280 90 2 358704.00

00040 8" x 8"-150#, Flow-280 CuM/Hr.(for cooling water EA 4 199280 90 4 717408.00


risers of 2 nos. MS

00050 8" x 8"-150#, Flow-270 CuM/Hr.(for cooling water EA 6 199280 90 6 1076112.00


risers of 3 nos. HSD
6" x 6"-150#, Flow-120 CuM/Hr.(for cooling water
00060 risers of 1 no. MS Tank 16M Dia. X 15.0 M Ht.,each EA 2 149459 90 2 269026.20
tank)
6" x 6"-150#, Flow-50 CuM/Hr.(for cooling water risers
00070 of 1 no. MS Transmix Tank 10M Dia. X 9.0 M Ht.,2 nos. EA 2 149459 90 2 269026.20
for each tank)
1.09 PIPE FITTINGS.
00010 : Supply and delivery of Pipe fittings.
00020 Eccentric Reducers
00030 4" x 3"-150# EA 4 333 90 4 1198.80
00040 Concentric Reducers
00050 3" x 2"-300# EA 8 272 90 8 1958.40
00060 2" x 1"-300# EA 12 202 90 12 2181.60
00070 4" x 3"-150# EA 5 257 90 5 1156.50
00080 4" x 2"-150# EA 5 304 90 5 1368.00
00090 3" x 2"-150# EA 5 210 90 5 945.00
00100 2" x 1"-150# EA 5 202 90 5 909.00
00110 Equal Tee
00120 3"-300# EA 6 506 90 6 2732.40
00130 2"-300# EA 6 221 90 6 1193.40
00140 1"-300# EA 25 382 90 25 8595.00
00150 4"-150# EA 6 630 90 6 3402.00
MB DETAILS Upto Previous
SOR BREAK
S NO ITEM DESCRIPTION UOM UNIT RATE UP %
FROM TO QTY QUANTITY AMOUNT (RS.)

00160 3"-150# EA 15 372 90 15 5022.00


00170 2"-150# EA 12 221 90 12 2386.80
00180 1"-150# EA 10 177 90 10 1593.00
00190 Un Equal Tee
00200 3" x 2"-300 # EA 12 650 90 12 7020.00
00210 2" x1"-300# EA 15 464 90 15 6264.00
00220 4" x 3"-150# EA 5 852 90 5 3834.00
00230 4" x 2"-150# EA 6 864 90 6 4665.60
00240 4" x 1"-150# EA 10 1707 90 10 15363.00
00250 3" x 2"-150# EA 15 650 90 15 8775.00
00260 3" x 1"-150# EA 15 650 90 15 8775.00
00270 2" x 1"-150# EA 10 464 90 10 4176.00
00280 90 DEG. LR Bend
00290 3"-300# EA 25 1563 90 25 35167.50
00300 2"-300# EA 25 258 90 25 5805.00
00310 1"-300# EA 35 271 90 35 8536.50
00320 4"-150# EA 10 458 90 10 4122.00
00330 3"-150# EA 15 314 90 15 4239.00
00340 2"-150# EA 20 203 90 20 3654.00
00350 1"-150# EA 20 177 90 20 3186.00
00360 45 DEG. LR Bend
00370 4"-150# EA 5 313 90 5 1408.50
00380 3"-150# EA 5 269 90 5 1210.50
00390 Nipples & Half-Couplings (Mat.-ASTM A105)
00400 1" X 3/4" 3000# Red.Nipple 4"long EA 10 321 90 10 2889.00
00410 1" 3000# St. Nipple 4"long EA 10 114 90 10 1026.00
00420 1" 3000# CS A105 Half coupling EA 10 91 90 10 819.00
00430 Weld-O-Lets (Mat.-ASTM A105)
MB DETAILS Upto Previous
SOR BREAK
S NO ITEM DESCRIPTION UOM UNIT RATE UP %
FROM TO QTY QUANTITY AMOUNT (RS.)

00440 18" x 3"-150# EA 2 2428 90 2 4370.40


00450 12" x 3"-150# EA 2 1539 90 2 2770.20
00460 10" x 3"-150# EA 2 1539 90 2 2770.20
00470 14" x 2"-150# EA 3 1664 90 3 4492.80
00480 12" x 2"-150# EA 3 1664 90 3 4492.80
00490 10" x 2"-150# EA 3 1912 90 3 5162.40
1.01 20 KL FRP SLOP OIL TANK
00010 1.01 20 KL FRP SLOP OIL TANK EA 1 822968 90 0 0.00
SUB TOTAL (INR) 20008017.90
Total Valu
Less value
Net
ORBA-KHUNTI TOP/M/1308B

ONSTRUCTION OF MARKETING TAP OFF POINTS-KHUNTI,JHARKHAND.


: FFIL/CIVIL-MECH SER-MECH SUP-MECH COMP/RA BILL-10
: 13.02.2015
NT PERIOD : 01.02.15 to 13.02.15
ART 1 & 2
This Bill Cumilative
REMARKS
QUANTITY AMOUNT (RS.) QUANTITY AMOUNT (RS.)

1.11 65019.1874748 12.665 738622.12

938.91 275101.81 3951.616 1157823.46

373.13 109325.93 1643.536 481555.93

0 0 1.000 2099520.00

0 0 1.000 3870990.00

449446.93 8348511.50
This Bill Cumilative
REMARKS
QUANTITY AMOUNT (RS.) QUANTITY AMOUNT (RS.)

194.000 2522.00 194.000 2522.00

507.317 70009.73 2547.215 351515.68


57.286 12144.68 397.094 84184.01

6.924 4182.10 23.900 14435.30

0.000 0.00 6458.049 11579281.86

0.000 0.00 9.000 487197.00

0.000 0.00 9.000 558468.00


This Bill Cumilative
REMARKS
QUANTITY AMOUNT (RS.) QUANTITY AMOUNT (RS.)

32.227 99614.83 199.149 615570.67


2.900 10039.80 21.400 74086.80
9.254 34703.44 13.034 48878.44

257.497 1419837.13 1260.855 6952356.60

25.318 1466747.69 217.805 12618101.81


0.000 0.00 128.000 13696.00
487.271 72116.03 1795.482 265731.38
0.000
0.00 99.370 31400.92

7.353 28295.79 50.112 192830.98

33.423 2454497.20 124.355 9132369.27

698.400 423928.80 698.400 423928.80

6098639.22 43446555.52
This Bill Cumilative
REMARKS
QUANTITY AMOUNT (RS.) QUANTITY AMOUNT (RS.)

0.000 0.00 675.043 1014589.63


152.020 218954.41 806.289 1161298.05
0.000 0.00 224.043 290359.73
9.458 11701.44 1459.367 1805528.85
111.646 117864.68 1224.065 1292245.42
0.000 0.00 582.597 597919.30
155.200 134930.88 745.993 648566.31
0.000 0.00 272.000 206529.60
0.000 0.00 755.240 405337.31
126.000 37837.80 126.000 37837.80

0.000 0.00 170.050 340780.20


240.030 460953.61 240.030 460953.61
109.700 180961.12 630.275 1039701.64
122.810 172867.36 259.910 365849.32
0.000 0.00 105.150 143887.26
182.370 211403.30 182.370 211403.30
140.300 56176.12 140.300 56176.12

0.000 0.00 196.585 103560.98

0.000 0.00 300.000 41400.00


16.200 2235.60 517.885 71468.13

189.800 34923.20 189.800 34923.20

0.000 0.00 59.020 12701.10


This Bill Cumilative
REMARKS
QUANTITY AMOUNT (RS.) QUANTITY AMOUNT (RS.)

0.000 0.00 106.518 192786.93


0.000 0.00 1883.747 2272929.13
This Bill Cumilative
REMARKS
QUANTITY AMOUNT (RS.) QUANTITY AMOUNT (RS.)

0.000 0.00 164.696 158355.20


0.000 0.00 507.919 411719.14
0.000 0.00 70.000 45402.00
0.000 0.00 21.000 10212.30

0 0.00 13 39299.00
0 0.00 10 25710.00
0 0.00 4 7908.00
0 0.00 8 15096.00
0 0.00 26 41626.00
0 0.00 28 42588.00
0 0.00 13 15145.00
0 0.00 14 12544.00
0 0.00 4 2868.00
0 0.00 7 3325.00
0 0.00 11 5214.00
1640809.52 13645744.57

0 0 1850 2207790.00
0 0 2400 2015280.00
0 0 800 480960.00
0 0 1850 426240.00
This Bill Cumilative
REMARKS
QUANTITY AMOUNT (RS.) QUANTITY AMOUNT (RS.)

0 0.00 22 21978.00
0 0.00 45 32521.50
0 0.00 105 31468.50
0 0.00 15 22558.50
0 0.00 220 199188.00
0 0.00 190 116451.00
0 0.00 240 86184.00
0 0.00 400 100080.00
0 0.00 60 9342.00

0 0.00 4 4035.60
0 0.00 10 5004.00
0 0.00 12 3402.00
0 0.00 5 5922.00
0 0.00 50 48780.00
0 0.00 40 27828.00
0 0.00 40 17820.00
0 0.00 20 6966.00
0 0.00 10 918.00
This Bill Cumilative
REMARKS
QUANTITY AMOUNT (RS.) QUANTITY AMOUNT (RS.)

0 0.00 202 18907.20


0 0.00 414 21238.20
0 0.00 966 46947.60
0 0.00 368 110620.80
0 0.00 368 93398.40
0 0.00 184 35769.60
0 0.00 2116 367549.20
0 0.00 1288 193586.40
0 0.00 2714 300439.80
0 0.00 2760 255852.00
0 0.00 1886 134094.60
0 0.00 1104 72532.80
0 0.00 276 13165.20
0 0.00 2300 109710.00
0 0.00 1748 83379.60
0 0.00 2208 103334.40
0 0.00 3496 119563.20
0 0.00 552 18878.40

0 0.00 130 1816191.00


0 0.00 52 504644.40
0 0.00 116 808056.00
This Bill Cumilative
REMARKS
QUANTITY AMOUNT (RS.) QUANTITY AMOUNT (RS.)

0 0.00 239 283501.80

0 0.00 15 333072.00
0 0.00 5 99567.00
0 0.00 32 687225.60
0 0.00 10 129771.00
0 0.00 20 281160.00
0 0.00 30 360774.00
0 0.00 40 356148.00

0 0.00 20 422244.00
0 0.00 3 40694.40
0 0.00 25 269955.00
0 0.00 5 63666.00
0 0.00 26 350953.20
0 0.00 15 54729.00
0 0.00 95 303268.50

0 0.00 6 1992799.80
This Bill Cumilative
REMARKS
QUANTITY AMOUNT (RS.) QUANTITY AMOUNT (RS.)

0 0.00 2 358704.00

0 0.00 4 717408.00

0 0.00 6 1076112.00

0 0.00 2 269026.20

0 0.00 2 269026.20

0 0.00 4 1198.80

0 0.00 8 1958.40
0 0.00 12 2181.60
0 0.00 5 1156.50
0 0.00 5 1368.00
0 0.00 5 945.00
0 0.00 5 909.00

0 0.00 6 2732.40
0 0.00 6 1193.40
0 0.00 25 8595.00
0 0.00 6 3402.00
This Bill Cumilative
REMARKS
QUANTITY AMOUNT (RS.) QUANTITY AMOUNT (RS.)

0 0.00 15 5022.00
0 0.00 12 2386.80
0 0.00 10 1593.00

0 0.00 12 7020.00
0 0.00 15 6264.00
0 0.00 5 3834.00
0 0.00 6 4665.60
0 0.00 10 15363.00
0 0.00 15 8775.00
0 0.00 15 8775.00
0 0.00 10 4176.00

0 0.00 25 35167.50
0 0.00 25 5805.00
0 0.00 35 8536.50
0 0.00 10 4122.00
0 0.00 15 4239.00
0 0.00 20 3654.00
0 0.00 20 3186.00

0 0.00 5 1408.50
0 0.00 5 1210.50

0 0.00 10 2889.00
0 0.00 10 1026.00
0 0.00 10 819.00
This Bill Cumilative
REMARKS
QUANTITY AMOUNT (RS.) QUANTITY AMOUNT (RS.)

0 0.00 2 4370.40
0 0.00 2 2770.20
0 0.00 2 2770.20
0 0.00 3 4492.80
0 0.00 3 4492.80
0 0.00 3 5162.40

1 740671.20 1 740671.20
740671.20 20748689.10
Total Value of work done as per Part-I&II 86189500.69
Less value of work done upto previous Bill 77259933.83
Net Value of work done for this Bill 8929566.86
CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B

Work Description :- COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TAP OFF PO
WO NO.&DATE :24047898 Dated 03-01-2014 RA BILL NO : FFIL/CIVIL-MECH SER-MECH SUP
CLIENT : INDIAN OIL CORPORATION LIMITED (PIPELINE DIVISION) DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA (INDIA) LTD MEASUREMENT PERIOD : 01.02.15 to 13.02.15
ABSTRACT
MB DETAILS QUANTITY
SOR UNIT BREAK
ITEM NO ITEM DESCRIPTION UOM Upto
FROM TO QTY RATE UP % This Bill Cumilative
Previous
00020 CSW-COMPOSITE WORKS
1.0 MECHANICAL COMPOSITE WORKS
1.01 Supply & Erection of Structural Steel.
00010 Supply & Erection of Structural Steel. MT 45 97201 60 11.55 1.115 12.665
1.03 Painting of A/G Piping(Product&Water)
00020 Zinc Ethyl Silicate Primer(1 coat of 65-75 micron ) SQM 11500 293 100 3012.701847 938.914 3951.616
High build Epoxy MIO Intermediate Paint ( 1 coats of 100
00030 micron ) SQM 11500 293 100 1270.409568 373.126 1643.536

1.06 Supply & Installation of HOT Crane.


Supply of 5 Ton capacity HOT crane for the Fire fighting
00020 Pump House/Shed(36 M length, 8 M width&6.5 M EA 1 2332800 90 1 0.000 1.000
height)

Supply of 5 Ton capacity HOT crane for the TLF Pump


00030 House/Shed (88.5 M Length, 6 M width & 5.5 M height) EA 1 4301100 90 1 0.000 1.000

SUB TOTAL

2.0 CIVIL COMPOSITE WORKS


MB DETAILS QUANTITY
SOR UNIT BREAK
ITEM NO ITEM DESCRIPTION UOM Upto
FROM TO QTY RATE UP % This Bill Cumilative
Previous
00010 EARTH WORK
Site cleaning work of the ground in all kinds of soil
00020 SQM 2500 13.00 100 0 194.000 194.000
including clearing the area
00030 Excavation in all kinds of soil except
00040 a) Depth upto 1.5 m (measured from OGL) CUM 16000 138 100 2039.898232 507.317 2547.215
00050 b) Depth between 1.5 m to 5 m CUM 3000 212.00 100 339.80817 57.286 397.094
Supplying and filling coarse sand under floors, in
00150 CUM 450 604.00 100 16.9755 6.924 23.900
foundations and plinths etc.
00170 PILLING WORKS
00180 Boring single under reamed pile with RCC mix
(1:1.5:3)
00190 a) 300mm dia depth upto 6m M 3450 1793.00 100 6458.049 0.000 6458.049
00230 LOAD TEST ON PILES
00250 A) TEST COLUMN
00260 a) Initial vertical static load test on single pile EA 9 54133.00 100 9 0.000 9.000
00270 B) JOB COLUMN
00280 a) Initial vertical static load test on single pile EA 9 62052.00 100 9 0.000 9.000
00290 Plain Concrete Works.
00300 PCC mix (1:4:8) for foundation work CUM 2000 3091.00 100 166.92198 32.227 199.149
00310 PCC with mix(1:3:6) cum 820 3462.00 100 18.5 2.900 21.400
00320 PCC with mix(1:2:4) cum 30 3750.00 100 3.78 9.254 13.034
00360 REINFORCED CEMENT CONCRETE
a)Laying RCC mix (1:1.5:3) in column, pedestal,
00400
beam, roof slab,chajja etc CUM 4100 5514.00 100 1003.358627 257.497 1260.855

00430 Reniforcement for RCC work TON 800 57933.00 100 192.4870819 25.318 217.805
00450 Supplying & using of plasticizer in RCC works. L 7800 107.00 100 128 0.000 128.000
00470 Painting foundation concrete with hot bitumen SQM 5000 148.00 100 1308.2118 487.271 1795.482
MB DETAILS QUANTITY
SOR UNIT BREAK
ITEM NO ITEM DESCRIPTION UOM Upto
FROM TO QTY RATE UP % This Bill Cumilative
Previous

Supplying and laying flat brick soling in foundation


00490 SQM 2750 316.00 100 99.37 0.000 99.370
trench, in floors,garages, sumps, etc.

00500
Brick work with burnt clay bricks of class
designation 50 in cement mortar 1:6.
00510 a)In foundation, plinth etc. CUM 750 3848.00 100 42.758625 7.353 50.112
00540 General Structural Steel Works
Supplying fabricating and fixing M.S structural steel
00550
work. TON 320 73438.00 100 90.932107 33.423 124.355

Supplying and providing chain link fencing with GI


00640 SQM 50 607.00 100 0 698.400 698.400
wire of 3 mm diaforming a mesh size of 50 x 50 mm

SUB TOTAL

00010 CSW- SERVICES


1.0 MECHANICAL SERVICE (FABRICATION)
1.08 ABOVE GROUND PIPING(PRODUCT LINES)
A) FABRICATION
00010 Above ground piping for Product Process Lines
00020 24" OD x 0.375" WT APL 5L Gr. B Pipe M 825 5010 30 675.043 0.000 675.043
00030 20" OD x 0.375" WT APL 5L Gr. B Pipe M 1200 4801 30 654.269 152.020 806.289
00040 18" ODx0.375" WT APL 5L Gr. B Pipe M 375 4320 30 224.043 0.000 224.043
00050 14" OD x 0.375" WT APL 5L Gr. B Pipe M 1900 4124 30 1449.909 9.458 1459.367
00060 12.75" OD x 0.375" WT APL 5L Gr.B Pipe M 1900 3519 30 1112.419 111.646 1224.065
00070 10.75" OD x 0.365" WT APL 5L Gr.B Pipe M 950 3421 30 582.597 0.000 582.597
00080 8.625" OD x 0.322" WT APL 5L Gr.B Pipe M 1100 2898 30 590.793 155.200 745.993
00090 6.625" ODx0.280" WT APL 5L Gr.B Pipe M 750 2531 30 272 0.000 272
00100 4.50" ODx0.237" WT ASTM A 106 Gr.B pipe M 1250 1789 30 755.24 0.000 755.24
00120 2.375" ODx0.218" WT ASTM A 106 Gr.B pipe M 275 1001 30 0 126.000 126
MB DETAILS QUANTITY
SOR UNIT BREAK
ITEM NO ITEM DESCRIPTION UOM Upto
FROM TO QTY RATE UP % This Bill Cumilative
Previous
B) ERECTION.
00020 24" OD x 0.375" WT APL 5L Gr. B Pipe M 825 5010 40 170.05 0.000 170.05
00030 20" OD x 0.375" WT APL 5L Gr. B Pipe 1200 4801 40 0 240.030 240.03
00050 14" OD x 0.375" WT APL 5L Gr. B Pipe M 1900 4124 40 520.575 109.700 630.275
00060 12.75" OD x 0.375" WT APL 5L Gr.B Pipe M 1900 3519 40 137.1 122.810 259.91
00070 10.75" OD x 0.365" WT APL 5L Gr.B Pipe M 950 3421 40 105.15 0.000 105.15
00080 8.625" OD x 0.322" WT APL 5L Gr.B Pipe 1100 2898 40 0 182.370 182.37
00120 2.375" ODx0.218" WT ASTM A 106 Gr.B pipe 275 1001 40 0 140.300 140.3
1.09 UNDER GROUND PIPING(PRODUCT LINES-FAB)
00110 3.50" OD x 0.216" WT ASTM A 106 GR.B M 300 1317 40 196.585 0.000 196.585
1.10 ABOVE GROUND PIPING FOR FUEL/ AIR LINES(FAB)
00030 3.50" ODx0.216" WT ASTM A 106 Gr.B pipe M 300 460 30 300 0.000 300
70 3.50" ODx0.216" WT ASTM A 106 Gr.B pipe M 600 460 30 501.685 16.200 517.885
1.10 ABOVE GROUND PIPING FOR FUEL/ AIR LINES(ERE)
00070 3.50" ODx0.216" WT ASTM A 106 Gr.B pipe M 300 460 40 0.000 189.800 189.8
1.11 UNDER GROUND PIPING FOR FUEL/ AIR LINES(FAB)
00020 3.50" ODx0.216" WT ASTM A 106 Gr.B pipe M 450 538 40 59.02 0.000 59.02
1.12 ABOVE GROUND PIPING (FIRE WATER LINES-FAB)
00020 24" OD x 0.375" WT IS 3589 FE410 PIPE M 200 6033 30 106.518 0.000 106.518
00030 16" ODx0.250 WT IS 3589 FE 410 PIPE M 2500 4022 30 1883.747 0.000 1883.747
00050 12" OD x 0.250" WT IS 3589 FE410 PIPE M 450 3205 30 164.696 0.000 164.696
00060 10.75" ODx0.250 WT IS 3589 FE 410 PIPE M 975 2702 30 507.919 0.000 507.919
00070 8.625" ODx0.250 WT IS 3589 FE 410 PIPE M 775 2162 30 70 0.000 70.000
00080 6.625" OD x 0.250" WT IS3589 FE410 Pipe M 250 1621 30 21 0.000 21
1.17 RADIOGRAPHIC INSPECTION
00020 24" NB Pipe Joints EA 35 3023 100 13 0 13
00030 20" NB Pipe Joints EA 40 2571 100 10 0 10
00040 18" NB Pipe Joints EA 20 1977 100 4 0 4
MB DETAILS QUANTITY
SOR UNIT BREAK
ITEM NO ITEM DESCRIPTION UOM Upto
FROM TO QTY RATE UP % This Bill Cumilative
Previous
00050 16" NB Pipe Joints EA 40 1887 100 8 0 8
00060 14" NB Pipe Joints EA 70 1601 100 26 0 26
00070 12" NB Pipe Joints EA 95 1521 100 28 0 28
00080 10" NB Pipe Joints EA 55 1165 100 13 0 13
00090 8" NB Pipe Joints EA 40 896 100 14 0 14
00100 6" NB Pipe Joints EA 25 717 100 4 0 4
00110 4" NB Pipe Joints EA 35 475 100 7 0 7
00120 3" NB Pipe Joints EA 55 474 100 11 0 11
SUB TOTAL

00030 CSW-SUPPLY
1.0 MECHANICAL SUPPLY
1.11 ASTM 106 GR.B SEAMLESS BARE STEEL PIPES
ASTM A 106 GR.B STEEL PIPES (SEAMLESS BARE
00010
PIPES)
00020 4.50" ODx0.237" WT M 1850 1326.00 90 1850 0 1850
00030 3.50" ODx0.216" WT M 2400 933.00 90 2400 0 2400
00040 2.375" ODx0.218" WT M 800 668.00 90 800 0 800
00050 1.315" ODx0.179" WT M 1850 256.00 90 1850 0 1850
1.07 STEEL FLANGES (WNRF)
00010 STEEL FLANGES (WNRF)
00020 3" X 300# (Pipe Size 3.500" OD x 0.216" WT) EA 22 1110.00 90 22 0 22
00030 2" X 300# (Pipe Size 2.375" OD x 0.218" WT) EA 45 803.00 90 45 0 45
00040 1" X 300# (Pipe Size 1.315" OD x 0.179" WT) EA 105 333.00 90 105 0 105
00050 6" X 150# (Pipe Size 6.625" OD x 0.280" WT) EA 15 1671.00 90 15 0 15
00060 4" X 150# (Pipe Size 4.500" OD x 0.237" WT) EA 220 1006.00 90 220 0 220
00070 3" X 150# (Pipe Size 3.500" OD x 0.216" WT) EA 190 681.00 90 190 0 190
00080 2" X 150# (Pipe Size 2.375" OD x 0.218" WT) EA 240 399.00 90 240 0 240
MB DETAILS QUANTITY
SOR UNIT BREAK
ITEM NO ITEM DESCRIPTION UOM Upto
FROM TO QTY RATE UP % This Bill Cumilative
Previous
00090 1" X 150# (Pipe Size 1.315" OD x 0.179" WT) EA 400 278.00 90 400 0 400
00100 3/4" X 150# (Pipe Size 1.050" OD x 0.154" WT) EA 60 173.00 90 60 0 60
1.08 STEEL FLANGES (BLRF)
00010 STEEL FLANGES (BLRF)
00020 3" X 300# (Pipe Size 3.500" OD x 0.216" WT) EA 4 1121 90 4 0 4
00030 2" X 300# (Pipe Size 2.375" OD x 0.218" WT) EA 10 556 90 10 0 10
00040 1" X 300# (Pipe Size 1.315" OD x 0.179" WT) EA 12 315 90 12 0 12
00050 6" X 150# (Pipe Size 6.625" OD x 0.280" WT) EA 5 1316 90 5 0 5
00060 4" X 150# (Pipe Size 4.500" OD x 0.237" WT) EA 50 1084 90 50 0 50
00070 3" X 150# (Pipe Size 3.500" OD x 0.216" WT) EA 40 773 90 40 0 40
00080 2" X 150# (Pipe Size 2.375" OD x 0.218" WT) EA 40 495 90 40 0 40
00090 1" X 150# (Pipe Size 1.315" OD x 0.179" WT) EA 20 387 90 20 0 20
00100 3/4" X 150# (Pipe Size 1.050" OD x 0.154" WT) EA 10 102 90 10 0 10
1.13 STEEL FASTENERS
00010 STEEL FASTENERS
00020 0.750" Dia. X 5.00" Length (for 3" x 300# f) EA 202 104 90 202 0 202
00030 0.625" Dia. X 4.00" Length (for 2" x 300# f) EA 414 57 90 414 0 414
00040 0.625" Dia. X 3.50" Length (for 1" x 300# f) EA 966 54 90 966 0 966
00050 1.125" Dia. X 7.75" Length (for 24" x 150# f) EA 368 334 90 368 0 368
00060 1.125" Dia. X 7.00" Length (for 20" x 150# f) EA 368 282 90 368 0 368
00070 1.125" Dia. X 6.50" Length (for 18" x 150# f) EA 184 216 90 184 0 184
00080 1.000" Dia. X 6.00" Length (for 16" x 150# f) EA 2116 193 90 2116 0 2116
00090 1.000" Dia. X 6.00" Length (for 14" x 150# f) EA 1288 167 90 1288 0 1288
00100 0.875" Dia. X 5.50" Length (for 12" x 150# f) EA 2714 123 90 2714 0 2714
00110 0.875" Dia. X 5.25" Length (for 10" x 150# f) EA 2760 103 90 2760 0 2760
MB DETAILS QUANTITY
SOR UNIT BREAK
ITEM NO ITEM DESCRIPTION UOM Upto
FROM TO QTY RATE UP % This Bill Cumilative
Previous
00120 0.750" Dia. X 4.75" Length (for 8" x 150# f) EA 1886 79 90 1886 0 1886
00130 0.750" Dia. X 4.50" Length (for 6" x 150# f) EA 1104 73 90 1104 0 1104
00140 0.625" Dia. X 4.00" Length (for 5" x 150# f) EA 276 53 90 276 0 276
00150 0.625" Dia. X 4.00" Length (for 4" x 150# f) EA 2300 53 90 2300 0 2300
00160 0.625" Dia. X 4.00" Length (for 3" x 150# f) EA 1748 53 90 1748 0 1748
00170 0.625" Dia. X 3.75" Length (for 2" x 150# f) EA 2208 52 90 2208 0 2208
00180 0.500" Dia. X 3.00" Length (for 1" x 150# f) EA 3496 38 90 3496 0 3496
00190 0.500" Dia. X 3.00" Length (for 3/4" x 150# f) EA 552 38 90 552 0 552
MB DETAILS QUANTITY
SOR UNIT BREAK
ITEM NO ITEM DESCRIPTION UOM Upto
FROM TO QTY RATE UP % This Bill Cumilative
Previous

00010 : Supply and delivery of API 600/602 Gate valves,


BS5351 Ball valves, BS1865 Swing check valves etc
00020 API 600 Gate Valves (HOV)
00030 4"x150#, F/F, A/G EA 130 15523 90 130 0 130
00040 3"x150#, F/F, A/G EA 52 10783 90 52 0 52
00050 2"x150#, F/F, A/G EA 116 7740 90 116 0 116
00060 API 602 Gate Valves(HOV)
00070 1"x 800#, W/W, A/G EA 239 1318 90 239 0 239
00080 BS 5351 Ball Valves (HOV)
00090 4"x ANSI 150# F/F,A/G, BS 5351 Ball Valv EA 15 24672 90 15 0 15
00100 3"x ANSI 300# F/F,A/G, BS 5351 Ball Valv EA 5 22126 90 5 0 5
00110 3"x ANSI 150# F/F,A/G, BS 5351 Ball Valv EA 32 23862 90 32 0 32
00120 2"x ANSI 300# F/F,A/G, BS 5351 Ball Valv EA 10 14419 90 10 0 10
00130 2"x ANSI 150# F/F,A/G, BS 5351 Ball Valv EA 20 15620 90 20 0 20
00140 1"x ANSI 300# F/F,A/G, BS 5351 Ball Valv EA 30 13362 90 30 0 30
00150 1"x ANSI 150# F/F,A/G, BS 5351 Ball Valv EA 40 9893 90 40 0 40
00160 BS 1868 Swing Check Valves
00170 4"x ANSI 150# F/F,A/G, BS 1868 Swing Che EA 20 23458 90 20 0 20
00180 3"x ANSI 300# F/F,A/G, BS 1868 Swing Che EA 3 15072 90 3 0 3
00190 3"x ANSI 150# F/F,A/G, BS 1868 Swing Che EA 25 11998 90 25 0 25
00200 2"x ANSI 300# F/F,A/G, BS 1868 Swing Che EA 5 14148 90 5 0 5
00210 2"x ANSI 150# F/F,A/G, BS 1868 Swing Che EA 26 14998 90 26 0 26
00220 1"x ANSI 300# F/F,A/G, BS 1868 Swing Che EA 15 4054 90 15 0 15
00230 1"x ANSI 150# F/F,A/G, BS 1868 Swing Che EA 95 3547 90 95 0 95
1.04
00010Y-TYPE STRAINERS(10
Y-type MESH)
strainer (10 Mesh size) for fire water
services.
MB DETAILS QUANTITY
SOR UNIT BREAK
ITEM NO ITEM DESCRIPTION UOM Upto
FROM TO QTY RATE UP % This Bill Cumilative
Previous

00020 EA 6 369037 90 6 0 6
12" x 12"-150#, Flow-616 CuM/Hr.(for F/F Pumps)
00030 EA 2 199280 90 2 0 2
8" x 8"-150#, Flow-105 CuM/Hr.(for Jockey Pumps)
00040 8" x 8"-150#, Flow-280 CuM/Hr.(for cooling water EA 4 199280 90 4 0 4
risers of 2 nos. MS
00050 8" x 8"-150#, Flow-270 CuM/Hr.(for cooling water EA 6 199280 90 6 0 6
risers of 3 nos. HSD
6" x 6"-150#, Flow-120 CuM/Hr.(for cooling water
00060 risers of 1 no. MS Tank 16M Dia. X 15.0 M Ht.,each EA 2 149459 90 2 0 2
tank)
6" x 6"-150#, Flow-50 CuM/Hr.(for cooling water
00070 risers of 1 no. MS Transmix Tank 10M Dia. X 9.0 M EA 2 149459 90 2 0 2
Ht.,2 nos. for each tank)
MB DETAILS QUANTITY
SOR UNIT BREAK
ITEM NO ITEM DESCRIPTION UOM Upto
FROM TO QTY RATE UP % This Bill Cumilative
Previous
1.09 PIPE FITTINGS.
00010 : Supply and delivery of Pipe fittings.
00020 Eccentric Reducers
00030 4" x 3"-150# EA 4 333 90 4 0 4
00040 Concentric Reducers
00050 3" x 2"-300# EA 8 272 90 8 0 8
00060 2" x 1"-300# EA 12 202 90 12 0 12
00070 4" x 3"-150# EA 5 257 90 5 0 5
00080 4" x 2"-150# EA 5 304 90 5 0 5
00090 3" x 2"-150# EA 5 210 90 5 0 5
00100 2" x 1"-150# EA 5 202 90 5 0 5
00110 Equal Tee
00120 3"-300# EA 6 506 90 6 0 6
00130 2"-300# EA 6 221 90 6 0 6
00140 1"-300# EA 25 382 90 25 0 25
00150 4"-150# EA 6 630 90 6 0 6
00160 3"-150# EA 15 372 90 15 0 15
00170 2"-150# EA 12 221 90 12 0 12
00180 1"-150# EA 10 177 90 10 0 10
00190 Un Equal Tee
00200 3" x 2"-300 # EA 12 650 90 12 0 12
00210 2" x1"-300# EA 15 464 90 15 0 15
00220 4" x 3"-150# EA 5 852 90 5 0 5
00230 4" x 2"-150# EA 6 864 90 6 0 6
00240 4" x 1"-150# EA 10 1707 90 10 0 10
MB DETAILS QUANTITY
SOR UNIT BREAK
ITEM NO ITEM DESCRIPTION UOM Upto
FROM TO QTY RATE UP % This Bill Cumilative
Previous
00250 3" x 2"-150# EA 15 650 90 15 0 15
00260 3" x 1"-150# EA 15 650 90 15 0 15
00270 2" x 1"-150# EA 10 464 90 10 0 10
00280 90 DEG. LR Bend
00290 3"-300# EA 25 1563 90 25 0 25
00300 2"-300# EA 25 258 90 25 0 25
00310 1"-300# EA 35 271 90 35 0 35
00320 4"-150# EA 10 458 90 10 0 10
00330 3"-150# EA 15 314 90 15 0 15
00340 2"-150# EA 20 203 90 20 0 20
00350 1"-150# EA 20 177 90 20 0 20
00360 45 DEG. LR Bend
00370 4"-150# EA 5 313 90 5 0 5
00380 3"-150# EA 5 269 90 5 0 5
00390 Nipples & Half-Couplings (Mat.-ASTM A105)
00400 1" X 3/4" 3000# Red.Nipple 4"long EA 10 321 90 10 0 10
00410 1" 3000# St. Nipple 4"long EA 10 114 90 10 0 10
00420 1" 3000# CS A105 Half coupling EA 10 91 90 10 0 10
00430 Weld-O-Lets (Mat.-ASTM A105)
00440 18" x 3"-150# EA 2 2428 90 2 0 2
00450 12" x 3"-150# EA 2 1539 90 2 0 2
00460 10" x 3"-150# EA 2 1539 90 2 0 2
00470 14" x 2"-150# EA 3 1664 90 3 0 3
00480 12" x 2"-150# EA 3 1664 90 3 0 3
00490 10" x 2"-150# EA 3 1912 90 3 0 3
MB DETAILS QUANTITY
SOR UNIT BREAK
ITEM NO ITEM DESCRIPTION UOM Upto
FROM TO QTY RATE UP % This Bill Cumilative
Previous
1.01 20 KL FRP SLOP OIL TANK
00010 1.01 20 KL FRP SLOP OIL TANK EA 1 822968 90 0 1 1

Total Value of work d


Less value of work do
Net Value of w
/KORBA-KHUNTI TOP/M/1308B

CONSTRUCTION OF MARKETING TAP OFF POINTS-KHUNTI,JHARKHAND.


LL NO : FFIL/CIVIL-MECH SER-MECH SUP-MECH COMP/RA BILL-10
: 13.02.2015
UREMENT PERIOD : 01.02.15 to 13.02.15
ABSTRACT
AMOUNT (RS.)
REMARKS
Upto Previous This Bill Cumilative

673602.93 65019.19 738622.12

882721.64 275101.81 1157823.46


372230.00 109325.93 481555.93

2099520.00 0.00 2099520.00

3870990.00 0.00 3870990.00

7899064.57 449446.93 8348511.50


AMOUNT (RS.)
REMARKS
Upto Previous This Bill Cumilative

0.00 2522.00 2522.00

281505.96 70009.73 351515.68


72039.33 12144.68 84184.01

10253.20 4182.10 14435.30

11579281.86 0.00 11579281.86

487197.00 0.00 487197.00

558468.00 0.00 558468.00

515955.84 99614.83 615570.67


64047.00 10039.80 74086.80
14175.00 34703.44 48878.44

5532519.47 1419837.13 6952356.60

11151354.12 1466747.69 12618101.81


13696.00 0.00 13696.00
193615.35 72116.03 265731.38
AMOUNT (RS.)
REMARKS
Upto Previous This Bill Cumilative

31400.92 0.00 31400.92

164535.19 28295.79 192830.98

6677872.07 2454497.20 9132369.27

0.00 423928.80 423928.80

37347916.30 6098639.22 43446555.52

1014589.63 0.00 1014589.63


942343.64 218954.41 1161298.05
290359.73 0.00 290359.73
1793827.41 11701.44 1805528.85
1174380.74 117864.68 1292245.42
597919.30 0.00 597919.30
513635.43 134930.88 648566.31
206529.60 0.00 206529.60
405337.31 0.00 405337.31
0.00 37837.80 37837.80
AMOUNT (RS.)
REMARKS
Upto Previous This Bill Cumilative

340780.20 0.00 340780.20


0.00 460953.61 460953.61
858740.52 180961.12 1039701.64
192981.96 172867.36 365849.32
143887.26 0.00 143887.26
0.00 211403.30 211403.30
0.00 56176.12 56176.12

103560.98 0.00 103560.98

41400.00 0.00 41400.00


69232.53 2235.60 71468.13

0.00 34923.20 34923.20

12701.10 0.00 12701.10

192786.93 0.00 192786.93


2272929.13 0.00 2272929.13
158355.20 0.00 158355.20
411719.14 0.00 411719.14
45402.00 0.00 45402.00
10212.30 0.00 10212.30

39299.00 0.00 39299.00


25710.00 0.00 25710.00
7908.00 0.00 7908.00
AMOUNT (RS.)
REMARKS
Upto Previous This Bill Cumilative

15096.00 0.00 15096.00


41626.00 0.00 41626.00
42588.00 0.00 42588.00
15145.00 0.00 15145.00
12544.00 0.00 12544.00
2868.00 0.00 2868.00
3325.00 0.00 3325.00
5214.00 0.00 5214.00
12004935.05 1640809.52 13645744.57

2207790.00 0.00 2207790.00


2015280.00 0.00 2015280.00
480960.00 0.00 480960.00
426240.00 0.00 426240.00

21978.00 0.00 21978.00


32521.50 0.00 32521.50
31468.50 0.00 31468.50
22558.50 0.00 22558.50
199188.00 0.00 199188.00
116451.00 0.00 116451.00
86184.00 0.00 86184.00
AMOUNT (RS.)
REMARKS
Upto Previous This Bill Cumilative

100080.00 0.00 100080.00


9342.00 0.00 9342.00

4035.60 0.00 4035.60


5004.00 0.00 5004.00
3402.00 0.00 3402.00
5922.00 0.00 5922.00
48780.00 0.00 48780.00
27828.00 0.00 27828.00
17820.00 0.00 17820.00
6966.00 0.00 6966.00
918.00 0.00 918.00

18907.20 0.00 18907.20


21238.20 0.00 21238.20
46947.60 0.00 46947.60
110620.80 0.00 110620.80
93398.40 0.00 93398.40
35769.60 0.00 35769.60
367549.20 0.00 367549.20
193586.40 0.00 193586.40
300439.80 0.00 300439.80
255852.00 0.00 255852.00
AMOUNT (RS.)
REMARKS
Upto Previous This Bill Cumilative

134094.60 0.00 134094.60


72532.80 0.00 72532.80
13165.20 0.00 13165.20
109710.00 0.00 109710.00
83379.60 0.00 83379.60
103334.40 0.00 103334.40
119563.20 0.00 119563.20
18878.40 0.00 18878.40
AMOUNT (RS.)
REMARKS
Upto Previous This Bill Cumilative

1816191.00 0.00 1816191.00


504644.40 0.00 504644.40
808056.00 0.00 808056.00

283501.80 0.00 283501.80

333072.00 0.00 333072.00


99567.00 0.00 99567.00
687225.60 0.00 687225.60
129771.00 0.00 129771.00
281160.00 0.00 281160.00
360774.00 0.00 360774.00
356148.00 0.00 356148.00

422244.00 0.00 422244.00


40694.40 0.00 40694.40
269955.00 0.00 269955.00
63666.00 0.00 63666.00
350953.20 0.00 350953.20
54729.00 0.00 54729.00
303268.50 0.00 303268.50
AMOUNT (RS.)
REMARKS
Upto Previous This Bill Cumilative

1992799.80 0.00 1992799.80

358704.00 0.00 358704.00

717408.00 0.00 717408.00

1076112.00 0.00 1076112.00

269026.20 0.00 269026.20

269026.20 0.00 269026.20


AMOUNT (RS.)
REMARKS
Upto Previous This Bill Cumilative

1198.80 0.00 1198.80

1958.40 0.00 1958.40


2181.60 0.00 2181.60
1156.50 0.00 1156.50
1368.00 0.00 1368.00
945.00 0.00 945.00
909.00 0.00 909.00

2732.40 0.00 2732.40


1193.40 0.00 1193.40
8595.00 0.00 8595.00
3402.00 0.00 3402.00
5022.00 0.00 5022.00
2386.80 0.00 2386.80
1593.00 0.00 1593.00

7020.00 0.00 7020.00


6264.00 0.00 6264.00
3834.00 0.00 3834.00
4665.60 0.00 4665.60
15363.00 0.00 15363.00
AMOUNT (RS.)
REMARKS
Upto Previous This Bill Cumilative

8775.00 0.00 8775.00


8775.00 0.00 8775.00
4176.00 0.00 4176.00

35167.50 0.00 35167.50


5805.00 0.00 5805.00
8536.50 0.00 8536.50
4122.00 0.00 4122.00
4239.00 0.00 4239.00
3654.00 0.00 3654.00
3186.00 0.00 3186.00

1408.50 0.00 1408.50


1210.50 0.00 1210.50

2889.00 0.00 2889.00


1026.00 0.00 1026.00
819.00 0.00 819.00

4370.40 0.00 4370.40


2770.20 0.00 2770.20
2770.20 0.00 2770.20
4492.80 0.00 4492.80
4492.80 0.00 4492.80
5162.40 0.00 5162.40
AMOUNT (RS.)
REMARKS
Upto Previous This Bill Cumilative

0.00 740671.20 740671.20


20008017.90 740671.20 20748689.10
Total Value of work done as per Part-I&II 86189500.69
Less value of work done upto previous Bill 77259933.83
Net Value of work done for this Bill 8929566.86
INDIAN OIL CORPORATION LIMITED
(PIPELINES DIVISION)

WORK DESCRIPTION :-COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF


MARKETING TAP OFF POINTS-KHUNTI,JHARKHANDKHUNTI,JHARKHAND.KHUNTI,JHARKHAND.

PART-III
RA Bill No. : FFIL/KHUNTI/RA BILL-10, Dtd:-13.02.2015

Sl. DESCRIPTION AMOUNT


a) Civil Composite.
Total value of composite civil work done as per
1 Rs. 6,098,639.22
the present bill (Excluding taxes)
2.1 Add SERVICE TAX (4.8%) OF BILL VALUE Rs. 292734.68
2.2 EDUCATION CESS (2%) Rs. 5854.69
2.3 S&H CESS (1%) Rs. 2927.35
Total Value of Work done for this Bill including
3 Rs. 6,400,155.94
Service Tax
4 Deductions

BG No. 0607014BG0000608 for


4.1 Security Deposit @10% Rs. an amount of 38358452.00 has
been submitted against SD

4.2 Income tax @ 2% Rs. 121,972.78


4.3 Building Cess @1% Rs. 60,986.39
4.4 WCT @ 4% for Jharkhand State Rs. 243,945.57
5 Net amount Payable after Deduction(A) Rs. 5,973,251.19
b) Mechanical Service
Total value of Mechanical Service work done as
1 Rs. 1,640,809.52
per the present bill (Excluding taxes)
2 Add SERVICE TAX (12.36%) OF BILL VALUE Rs. 202,804.06
Total Value of Work done for this Bill including
3 Rs. 1,843,613.57
Service Tax
4 Deductions
4.1 Security Deposit @10% Rs. _
4.2 Income tax @ 2% Rs. 32,816.19
4.3 Building Cess @1% Rs. 16,408.10
4.4 WCT @ 4% for Jharkhand State Rs. 65,632.38
5 Net amount Payable after Deduction (B) Rs. 1,728,756.91
c) Mechanical Supply
Total value of Mechanical Supply done as per the
1 Rs. 740,671.20
present bill
2 Deductions
2.1 Security Deposit @10% Rs. _
2.2 Income tax @ 2% Rs. 14,813.42
2.3 Building Cess @1% Rs. 7,406.71
2.4 WCT @ 4% for Jharkhand State Supply Portion Rs. 29,626.85
3 Net amount Payable after Deduction Rs. 688824.22
d) Mechanical Composite.
INDIAN OIL CORPORATION LIMITED
(PIPELINES DIVISION)

WORK DESCRIPTION :-COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF


MARKETING TAP OFF POINTS-KHUNTI,JHARKHANDKHUNTI,JHARKHAND.KHUNTI,JHARKHAND.

PART-III
RA Bill No. : FFIL/KHUNTI/RA BILL-10, Dtd:-13.02.2015
Total value of composite Mechanical work done
1 Rs. 449,446.93
as per the present bill (Excluding taxes)
2.1 Add SERVICE TAX (4.8%) OF BILL VALUE Rs. 21573.45
2.2 EDUCATION CESS (2%) Rs. 431.47
2.3 S&H CESS (1%) Rs. 215.73
Total Value of Work done for this Bill including
3 Rs. 471,667.58
Service Tax
INDIAN OIL CORPORATION LIMITED
(PIPELINES DIVISION)

WORK DESCRIPTION :-COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF


MARKETING TAP OFF POINTS-KHUNTI,JHARKHANDKHUNTI,JHARKHAND.KHUNTI,JHARKHAND.

PART-III
RA Bill No. : FFIL/KHUNTI/RA BILL-10, Dtd:-13.02.2015
4 Deductions
4.1 Security Deposit @10% Rs. _
4.2 Income tax @ 2% Rs. 8,988.94
4.3 Building Cess @1% Rs. 4,494.47
4.4 WCT @ 4% for Jharkhand State Rs. 17,977.88
5 Net amount Payable after Deduction(C) Rs. 440,206.30
Total amount Payable after Deductions(A+B+C) Rs. 8,142,214.40
RUPEES EIGHTY ONE LAKH FOURTY TWO THOUSAND TWO HUNDRED FOURTEEN AND PAISE
FOURTY ONLY.

Certified that work has been completed as per specification and as per contract documents
1 verified and certified for paymnt of Rs. 8142214.4 /-for the work carried out from 01.02.15 to
13.02.15
Certified that the measurement recorded in this bill have been taken by me/officers working under
2 me and recorded at page No 01 to 64 in MB No. FFIL/10
Certified that all quantities of work as shown in the bill have actually been executed and are in no
3 case less than the final account payment charged in this bill.
Certified that all Recoveries on account of Supply of material, equipments service facilities etc.
4 advance, retention money and rebates as per terms of the contract have been made.

5 There is nothing due from the contractor.

Site Engineer Engineer-in-Charge

FOR USE IN FINANCE DEPT.

Passed For Payment of Rs_________________ (Rupees_____________ _________________ _______


_ _ _ _ __ ____________ _____________ ________________ ___________ only)
AO/ DFM/ FM/ SFM / CFM

CERTIFICATE

1) Certified that we have taken separate PF establishment code No and covered under the EPF Act 1952
andthe PF is deducted and deposited alongwith Employee's contribution in respect of all eligible
employees as per PF Rules

2) Certified that the wages paid to our employees and sub contractors employees are not lesser than the
minimum wages provided under the minimum wages Act applicable to the concerned state Government.
INDIAN OIL CORPORATION LIMITED
(PIPELINES DIVISION)

WORK DESCRIPTION :-COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF


MARKETING TAP OFF POINTS-KHUNTI,JHARKHANDKHUNTI,JHARKHAND.KHUNTI,JHARKHAND.

PART-III
RA Bill No. : FFIL/KHUNTI/RA BILL-10, Dtd:-13.02.2015
For Furnace Fabrica India Limited

Authorized Signatory
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B

MEASUREMENT SHEET MB NO. :


MEASUREMENT PERIOD: 01.02.15 to 13.02.15 RA BILL NO: FFIL/SERVICE/RA BILL-10
W.O NO & DATE:WORK ORDER NO: 24047898, DATE : 03/01/2014 DATE:13.02.2015
Activity Description : Pipe fabrication ….. As per direction of EIC
ITEM NO./ Description: MECHANICAL WORKS - SERVICE (FAB)
SL. NO. SOR ITEM SOR. ITEM NO. DESCRIPTION UOM (M) QTY REMARKS
1 00030 20" OD x 0.375" WT APL 5L Gr. B Pipe M 152.020
3 1.08 ABOVE 00050 14" OD x 0.375" WT APL 5L Gr. B Pipe
GROUND
M 9.458
4 PIPING(PRODUCT 00060 12.75" OD x 0.375" WT APL 5L Gr.B Pipe M 111.646
LINES) 30% PAYMENT AGAINIST
5 FABRICATION 00080 8.625" OD x 0.365" WT APL 5L Gr.B Pipe M 155.200 FABRICATION
6 00120 2.375"OD x 0.218" WT ASTM 106 A Gr. B M 126.000
Total Quantity (M) 554.324

Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME:

DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B

MEASUREMENT SHEET MB NO. :


MEASUREMENT PERIOD: RA BILL NO: FFIL/SERVICE/RA BILL-10
W.O NO & DATE:WORK ORDER NO: 24047898, DATE : 03/01/2014 DATE:13.02.2015
Activity Description : Pipe fabrication ….. As per direction of EIC
ITEM NO./ Description: MECHANICAL WORKS - SERVICE (ERECTION)
SL. NO. SOR ITEM SOR. ITEM NO. DESCRIPTION UOM (M) QTY REMARKS
1 00030 20" OD x 0.375" WT APL 5L Gr. B Pipe M 240.030
3 1.08 ABOVE 00050 14" OD x 0.375" WT APL 5L Gr. B Pipe M 109.700
4 GROUND 00060 12.75" OD x 0.375" WT APL 5L Gr.B Pipe M 122.810
PIPING(PRODUCT 40% PAYMENT AGAINIST
5 LINES) ERECTION 00080 8.625" OD x 0.365" WT APL 5L Gr.B Pipe M 182.370 ERECTION
6 00120 2.375"OD x 0.218" WT ASTM 106 A Gr. B M 140.300
Total Quantity (M) 795.210

Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME:

DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B

MEASUREMENT SHEET MB NO. :


MEASUREMENT PERIOD: 01.02.15 to 13.02.15 RA BILL NO: FFIL/SERVICE/RA BILL-10
W.O NO & DATE:WORK ORDER NO: 24047898, DATE : 03/01/2014 DATE:13.02.2015
.
SL. NO. SOR ITEM SOR. ITEM NO. DESCRIPTION UOM (M) QTY REMARKS

1.10 ABOVE
GROUND PIPING 30% PAYMENT AGAINIST
1 00070 3.50" OD x 0.216" WT ASTM A 106 GR.B M 16.2
FOR FUEL/AIR FABRICATION
LINES (FAB)
Total Quantity (M) 16.200

Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME:

DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B

MEASUREMENT SHEET MB NO. :


MEASUREMENT PERIOD: 01.02.15 to 13.02.15 RA BILL NO: FFIL/SERVICE/RA BILL-10
W.O NO & DATE:WORK ORDER NO: 24047898, DATE : 03/01/2014 DATE:13.02.2015
.
SL. NO. SOR ITEM SOR. ITEM NO. DESCRIPTION UOM (M) QTY REMARKS

1.10 ABOVE
GROUND PIPING 40% PAYMENT AGAINIST
1 00070 3.50" OD x 0.216" WT ASTM A 106 GR.B M 189.8
FOR FUEL/AIR FABRICATION
LINES (ERE)
Total Quantity (M) 189.800

Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME:
DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B

MEASUREMENT SHEET MB NO. :


MEASUREMENT PERIOD: 01.02.15 to 13.02.15 RA BILL NO: FFIL/SERVICE/RA BILL-10
W.O NO & DATE:WORK ORDER NO: 24047898, DATE : 03/01/2014 DATE:13.02.2015
.
SL. NO. SOR ITEM SOR. ITEM NO. DESCRIPTION UOM (M) QTY REMARKS

1.12 ABOVE
GROUND PIPING 30% PAYMENT AGAINIST
1 00050 12.75" OD x 0.250" WT IS 3589 FE410 PIPE M 0
(FIRE WATER FABRICATION
LINES-FAB.)
Total Quantity (M) 0.000

Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME:

DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B

MEASUREMENT SHEET MB NO. :


MEASUREMENT PERIOD: 01.02.15 to 13.02.15 RA BILL NO: FFIL/SERVICE/RA BILL-10
W.O NO & DATE:WORK ORDER NO: 24047898, DATE : 03/01/2014 DATE:13.02.2015
Activity Description : Pipe fabrication ….. As per direction of EIC
SL. NO. SOR ITEM SOR. ITEM NO. DESCRIPTION UOM (M) QTY REMARKS
1 00020 24" NB Pipe Joint EA 0
2 00040 18" NB Pipe Joint EA 0
3 00060 14" NB Pipe Joint EA 0
4 1.17 00070 12" NB Pipe Joint EA 0
5 RADIOGRAPHIC 00080 10" NB Pipe Joint EA 0
6 INSPECTION 00090 8" NB Pipe Joint EA 0
7 00100 6" NB Pipe Joint EA 0
8 00120 4" NB Pipe Joint EA 0
9 00130 3" NB Pipe Joint EA 0
Total Quantity (Nos.) 0.000

Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME:
DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR THE ERECTION OF PROCESS PIPING
MEASUREMENT PERIOD: 01/02/2015 to 13/02/2015 INSPECTION SHEET OF STATION PIPING
CALCULATION SHEET
Activity Description : Above ground piping ….. As per direction of EIC
SOR Item No: 1.08 ABOVE GROUND PIPING- 00030 20" OD x 0.375" WT APL 5L Gr. B Pipe
JOINT NO: BILLING QTY
SL. NO. LINE NO. REMARKS
FROM TO This Bill Previous Cumilative
J:4 J:8 54.41 Sheet no: 5 of 11,
20"-P-5015-11 0 114.31
1 J:24 J:32 59.9 Sheet no: 7 of 11,
J:4 J:8 54.46 Sheet no: 5 of 11,
20"-P-5014-11 69.61
2 J:25 J:27 15.15 0 Sheet no: 7 of 11,
3 20"-P-5013-11 J:4 J:8 56.11 0 56.11 Sheet no: 5 of 11,
TOTAL LENGTH (IN METER) 240.03 0 240.03
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME: VISHNU P P J K BHAGAT

DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR THE ERECTION OF PROCESS PIPING
MEASUREMENT PERIOD: 01/02/2015 to 13/02/2015 INSPECTION SHEET OF STATION PIPING
CALCULATION SHEET
Activity Description : Above ground piping….. As per direction of EIC
SOR Item No: 1.08 ABOVE GROUND PIPING- 00050 14" OD x 0.375" WT APL 5L Gr. B Pipe
JOINT NO: BILLING QTY
SL. NO. LINE NO. REMARKS
FROM TO This Bill Previous Cumilative
2 14-P-5036-11 J No:1 J No:14 60.85 137.325 198.175 Sheet no: 1 of 11
3 14-P-5037-11 J No:1 J No:8 35.3 137.25 172.55 Sheet no: 1 of 11
4 14-P-5038-11 J No:1 J No:3 13.55 139.1 152.65 Sheet no: 1 of 11
TOTAL LENGTH (IN METER) 109.7 413.675 523.375
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME: VISHNU P P J K BHAGAT


DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR THE ERECTION OF PROCESS PIPING
MEASUREMENT PERIOD: 01/02/2015 to 13/02/2015 INSPECTION SHEET OF STATION PIPING
CALCULATION SHEET
Activity Description : Above ground piping ….. As per direction of EIC
SOR Item No: 1.08 ABOVE GROUND PIPING- 00060 12.75" OD x 0.375" WT APL 5L Gr. B Pipe
JOINT NO: BILLING QTY
SL. NO. LINE NO. REMARKS
FROM TO This Bill Previous Cumilative
1 12-P-5002-11 J No:1 J No:10 63.5 137.1 200.6 Sheet no:1 of 11
2 12-P-5001-11 J No:3 J No:7 59.31 0 59.31 Sheet no: 5 of 11
TOTAL LENGTH (IN METER) 122.81 137.1 259.91
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME: VISHNU P P J K BHAGAT


DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR THE ERECTION OF PROCESS PIPING
MEASUREMENT PERIOD: 01/02/2015 to 13/02/2015 INSPECTION SHEET OF STATION PIPING
CALCULATION SHEET
Activity Description : Above ground piping ….. As per direction of EIC
SOR Item No: 1.08 ABOVE GROUND PIPING- 00060 8" OD x 0.375" WT APL 5L Gr. B Pipe
JOINT NO: BILLING QTY
SL. NO. LINE NO. REMARKS
FROM TO This Bill Previous Cumilative
J No:03 J No:07 58.71 Sheet no:5 of 11
1 8"-P-5016-11 0 122.46
J No:22 J No:29 63.75 Sheet no:7 of 11
2 8"-P-5087-11 J No:03 J No:07 59.91 0 59.91 Sheet no:5 of 11
TOTAL LENGTH (IN METER) 182.37 0 182.37
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME: VISHNU P P J K BHAGAT


DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR THE ERECTION OF PROCESS PIPING
MEASUREMENT PERIOD: 01/02/2015 to 13/02/2015 INSPECTION SHEET OF STATION PIPING
CALCULATION SHEET
Activity Description : Above ground piping ….. As per direction of EIC
SOR Item No: 1.10 ABOVE GROUND PIPING- 00070 3.50" OD x 0.216" WT ASTM A 106 GR.B
JOINT NO: BILLING QTY
SL. NO. LINE NO. REMARKS
FROM TO This Bill Previous Cumilative
1 3" COMPRESSED AIR LINE J No:01 J No:12 61.1 0 Sheet no:1 of 11
2 3" COMPRESSED AIR LINE J No:48 J No:60 41.35 0 189.8 Sheet no:3 of 11
3 3" COMPRESSED AIR LINE J No:61 J No:78 87.35 0 Sheet no:4 of 11
TOTAL LENGTH (IN METER) 189.8 0 189.8
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME: VISHNU P P J K BHAGAT


DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR THE ERECTION OF PROCESS PIPING
MEASUREMENT PERIOD: 01/02/2015 to 13/02/2015 INSPECTION SHEET OF STATION PIPING
CALCULATION SHEET
Activity Description : Above ground piping ….. As per direction of EIC
SOR Item No: 1.08 ABOVE GROUND PIPING- 00120 2.375" OD x 0.218"WT ASTM A 106 GR .B
JOINT NO: BILLING QTY
SL. NO. LINE NO. REMARKS
FROM TO This Bill Previous Cumilative
1 2"-P-5024-11 J No:01 J No:11 70.1 0 70.1 Sheet no:1 of 11
2 2"-P-5021-11 J No:01 J No:11 70.2 0 70.2 Sheet no:1 of 11
TOTAL LENGTH (IN METER) 140.3 0 140.3
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME: VISHNU P P J K BHAGAT


DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR THE FABRICATION OF PROCESS PIPING
MEASUREMENT PERIOD: 01/02/2015 to 13/02/2015 INSPECTION SHEET OF STATION PIPING
CALCULATION SHEET
Activity Description : Above ground piping ….. As per direction of EIC
SOR Item No: 1.08 ABOVE GROUND PIPING- 00030 20" OD x 0.375" WT APL 5L Gr. B Pipe
TOTAL LENGTH
SL. NO. LINE NO. FROM TO JOINT NOS. LENGTH (M) REMARKS
(M)
1 5 OF 11 20-P-5013-11 P P FJ-5 11.870 F(W)-188
2 5 OF 11 20-P-5013-11 P P FJ-7 23.900 F(W)-188
3 5 OF 11 20-P-5013-11 P P FJ-8 6.000 F(W)-195
4 5 OF 11 20-P-5014-11 P P FJ-5 12.000 F(W)-188
5 5 OF 11 20-P-5014-11 P P FJ-7 23.900 F(W)-188
6 5 OF 11 20-P-5014-11 P P FJ-8 6.000 F(W)-195
7 5 OF 11 20-P-5015-11 P P FJ-5 11.850 152.020 F(W)-188
8 5 OF 11 20-P-5015-11 P P FJ-7 23.900 F(W)-188
9 5 OF 11 20-P-5015-11 P P FJ-8 6.000 F(W)-195
10 7 OF 11 20-P-5015-11 P P FJ-29 18.700 F(W)-190
11 7 OF 11 20-P-5015-11 P E45 FJ-25 1.100 F(W)-197
12 7 OF 11 20-P-5015-11 P P 27 A 6.800 F(W)-197
Total Quantity (m) 152.020
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME: VISHNU P P J K BHAGAT


DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR THE FABRICATION OF PROCESS PIPING
MEASUREMENT PERIOD: 01/02/2015 to 13/02/2015 INSPECTION SHEET OF STATION PIPING
CALCULATION SHEET
Activity Description : Above ground piping ….. As per direction of EIC
SOR Item No: 1.08 ABOVE GROUND PIPING- 00050 14" OD x 0.375" WT APL 5L Gr. B Pipe
LINE TOTAL LENGTH
SL. NO. FROM TO JOINT NOS. LENGTH (M) REMARKS
NO. (M)
1 2 OF 11 14-P-5036-11 P E45 FJ-7 0.700 F(W)-187
2 2 OF 11 14-P-5036-11 P E45 FJ-12 0.800 F(W)-189
3 2 OF 11 14-P-5037-11 P E45 FJ-12 0.800 F(W)-189
4 9 OF 11 24-P-5026-11 E90 F 39 1.193 F(W)-184
5 9 OF 11 24-P-5026-11 E90 F 58 1.193 F(W)-185
9.458
6 9 OF 11 24-P-5026-11 E90 F 68 1.193 F(W)-184
7 9 OF 11 24-P-5026-11 E90 F 73 1.193 F(W)-184
8 9 OF 11 24-P-5026-11 E90 F 78 1.193 F(W)-184
9 9 OF 11 24-P-5026-11 E90 F 83 1.193 F(W)-186
Total Quantity (m) 9.458
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME: VISHNU P P J K BHAGAT


DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR THE FABRICATION OF PROCESS PIPING
MEASUREMENT PERIOD: 01/02/2015 to 13/02/2015 INSPECTION SHEET OF STATION PIPING
CALCULATION SHEET
Activity Description : Above ground piping ….. As per direction of EIC
SOR Item No: 1.08 ABOVE GROUND PIPING- 00060 12.75" OD x 0.375" WT APL 5L Gr. B Pipe
TOTAL LENGTH
SL. NO. LINE NO. FROM TO JOINT NOS. LENGTH (M) REMARKS
(M)
1 5 OF 11 12-P-5001-11 P P FJ-6 23.900 F(W)-190
2 7 OF 11 12-P-5001-11 P P FJ-24 23.800 F(W)-191
3 2 OF 11 12-P-5002-11 P P FJ-8 12.430 F(W)-189
4 9 OF 11 14-P-5038-11 E90 F 76 1.029 F(W)-186
5 9 OF 11 14-P-5038-11 E90 F 86 1.029 F(W)-185
6 9 OF 11 14-P-5038-11 E90 F 96 1.029 111.646 F(W)-185
7 9 OF 11 14-P-5038-11 E90 F 101 1.029 F(W)-186
8 10 OF 11 12-P-5085-11 P P FJ-110 24.000 F(W)-192
9 5 OF 11 12-P-5001-11 P P FJ-4 11.500 F(W)-196
10 5 OF 11 12-P-5001-11 P P FJ-7 11.900 F(W)-198
Total Quantity (m) 111.646
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME: VISHNU P P J K BHAGAT


DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR THE FABRICATION OF PROCESS PIPING
MEASUREMENT PERIOD: 01/02/2015 to 13/02/2015 INSPECTION SHEET OF STATION PIPING
CALCULATION SHEET
Activity Description : Above ground piping ….. As per direction of EIC
SOR Item No: 1.08 ABOVE GROUND PIPING- 00080 8.625" OD x 0.322 WT APL 5L Gr. B Pipe
TOTAL LENGTH
SL. NO. LINE NO. FROM TO JOINT NOS. LENGTH (M) REMARKS
(M)
1 5 OF 11 8-P-5016-11 P P FJ-6 23.910 F(W)-190
2 7 OF 11 8-P-5016-11 P P FJ-24 23.840 F(W)-191
3 7 OF 11 8-P-5016-11 P P FJ-26 11.900 F(W)-191
4 5 OF 11 8-P-5087-11 P P FJ-6 23.900 F(W)-190
5 10 OF 11 8-P-5087-11 P P FJ-86 24.000 F(W)-192
155.200
6 5 OF 11 8-P-5016-11 P P FJ-4 11.900 F(W)-196
7 5 OF 11 8-P-5087-11 P P FJ-4 11.950 F(W)-196
8 5 OF 11 8-P-5016-11 P P FJ-7 11.900 F(W)-198
9 5 OF 11 8-P-5087-11 P P FJ-7 11.900 F(W)-198
Total Quantity (m) 155.200
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME: VISHNU P P J K BHAGAT


DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR THE FABRICATION OF PROCESS PIPING
MEASUREMENT PERIOD: 01/02/2015 to 13/02/2015 INSPECTION SHEET OF STATION PIPING
CALCULATION SHEET
Activity Description : Above ground piping ….. As per direction of EIC
SOR Item No: 1.08 ABOVE GROUND PIPING- 00120 2.375" OD x 0.218"WT ASTM A 106 GR .B
TOTAL LENGTH
SL. NO. LINE NO. FROM TO JOINT NOS. LENGTH (M) REMARKS
(M)
1 1 OF 11 2-P-1521-11 P P FJ-2 6.000 F(W)-194
2 1 OF 11 2-P-1521-11 P P FJ-3 6.000 F(W)-194
3 1 OF 11 2-P-1521-11 P P FJ-4 6.000 F(W)-194
4 1 OF 11 2-P-1521-11 P P FJ-5 6.000 F(W)-194
5 1 OF 11 2-P-1521-11 P P FJ-6 6.000 F(W)-194
6 1 OF 11 2-P-1521-11 P P FJ-7 6.000 F(W)-194
7 2 OF 11 2-P-1521-11 P P FJ-8 6.000 F(W)-194
8 2 OF 11 2-P-1521-11 P P FJ-9 6.000 F(W)-194
9 2 OF 11 2-P-1521-11 P P FJ-10 6.000 F(W)-194
10 2 OF 11 2-P-1521-11 P P FJ-11 12.000 F(W)-194
11 1 OF 11 2-P-1524-11 P P FJ-2 6.000 126.000 F(W)-193
12 1 OF 11 2-P-1524-11 P P FJ-3 6.000 F(W)-193
13 1 OF 11 2-P-1524-11 P P FJ-4 6.000 F(W)-193
14 1 OF 11 2-P-1524-11 P P FJ-5 6.000 F(W)-193
15 1 OF 11 2-P-1524-11 P P FJ-6 6.000 F(W)-193
16 1 OF 11 2-P-1524-11 P P FJ-7 6.000 F(W)-193
17 1 OF 11 2-P-1524-11 P P FJ-8 6.000 F(W)-193
18 1 OF 11 2-P-1524-11 P P FJ-9 6.000 F(W)-193
19 1 OF 11 2-P-1524-11 P P FJ-10 6.000 F(W)-193
20 1 OF 11 2-P-1524-11 P P FJ-11 6.000 F(W)-193
Total Quantity (m) 126.000
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:
NAME: VISHNU P P J K BHAGAT
DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR THE FABRICATION OF AIR LINES
MEASUREMENT PERIOD: 01/02/2015 to 13/02/2015 INSPECTION SHEET OF STATION PIPING
CALCULATION SHEET
Activity Description : Above ground piping ….. As per direction of EIC
SOR Item No: 1.10 ABOVE GROUND PIPING- 00070 3.50" OD x 0.216" WT ASTM A 106 G
TOTAL LENGTH
SL. NO. LINE NO. FROM TO JOINT NOS. LENGTH (M) REMARKS
(M)
1 3 OF 11 3-Compressed air line P P FJ-49 6.750 F(W)-180
2 3 OF 11 3-Compressed air line P E45 FJ-54 6.750 F(W)-180
3 4 OF 11 3-Compressed air line P E45 FJ-67 1.350 16.200 F(W)-180
4 4 OF 11 3-Compressed air line P E45 FJ-75 1.350 F(W)-180
Total Quantity (m) 16.200
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME: VISHNU P P J K BHAGAT


DATE:
CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B
WORK DESCRIPTION :-COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TAP OFF
KHUNTI,JHARKHANDKHUNTI,JHARKHAND.KHUNTI,JHARKHAND.
CIVIL MEASUREMENT SHEET No RA-10

WO NO & DATE :24047898 Dated 14-02-2014


CLIENT : INDIAN OIL CORPORATION LIMITED
CONTRACTOR : M/S FURNACE FABRICA(INDIA) Ltd.
SOR Item
S.NO Description UOM
No.
1 00010 EARTH WORK

2 00030 Excavation in all kinds of soil except

Site cleaning work of the ground in all kinds of soil


3 00020 SQM
including clearing the area
4 00040 a) Depth upto 1.5 m(measured from OGL) CUM
5 00050 b) Depth between 1.5 m to 5 m CUM
Supplying and filling coarse sand under floors, in
6 00150 CUM
foundations and plinth

7 00290 PLAIN CONCRETE WORK

8 00300 PCC with mix(1:4:8) CUM

9 00310 PCC with mix(1:3:6) CUM

10 00320 PCC with mix(1:2:4) CUM

11 00360 REINFORCED CEMENT CONCRETE

12 00390 RCC with mix (1:1.5:3)

13 00400 a)In foundation,plinth, ramps etc. CUM

14 00430 Reinforcement for RCC Work TON

15 00470 Painting foundation concrete with hot bitumen SQM

16 00480 BRICK WORK

Brick work with burnt clay bricks of class designation


17 00500 50 in cement mortor 1:6

18 00510 a) In foundation, plinth etc. CUM

19 00540 GENERAL STRUCTURAL STEEL WORK


Supplying,fabricating,erecting,placing and fixing in
20 TON
position M.S. structural works-Foundation Bolts
00550
Supplying,fabricating,erecting,placing and fixing in
21 TON
position M.S. structural works

Supplying and providing chain link fencing with GI wire


22 00640 SQM
of 3 mm diaforming a mesh size of 50 x 50 mm

Certified that the work is done as per drawings, specifications and instructions. Quantities mentioned above are checked and verified
FOR FFIL FOR IOC

SIGNATURE SIGNATURE

NAME NAME
DATE DATE
/M/1308B
ION OF MARKETING TAP OFF POINTS-
,JHARKHAND.
No RA-10

RA BILL NO. : FFIL/ CIVIL RA-10


Bill date: 13.02.2015
Billing Period : 01.02.15 – 13.02.15

TOTAL QTY REMARKS

194.00
13
507.317 138
57.286 212

6.924
604

32.227
3091
2.900
3462
9.254
3750

257.497
5514

25.31800
57933

487.271
148

7.353
3848
2.006
73438

34.908
73438

698.400
607
cked and verified
FOR IOCL

25.318
194
70009.72709
12144.67991

4182.096

99614.83158

10039.8

34703.4375

1419837.132

1466747.694

72116.034

28295.787
147280.2028

2307216.995

423928.8
6096311.22
CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B

WORK DESCRIPTION :-COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TOP OFF POINTS-KHUNTI,JHARKHAND.

SECTION/SPREAD :-
WO NO & DATE : 24047898 Dated 14-02-2014 RA BILL No : FFIL/ CIVIL RA-10
CLIENT : INDIAN OIL CORPORATION LIMITED DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA(INDIA) Ltd. MEASUREMENT PERIOD : 01.02.15 – 13.02.15
CALCULATION SHEET

SOR Dimensions
SR. No. Item Description UOM Height Quantity
No. NOS Length(L) Breadth (B) (H) /Depth
(D)
1 00010 EARTH WORK

6 00030 Excavation in all kinds of soil except

7 00040 a)Depth upto 1.5 m(measured from OGL)

8 PIPE BRIDGE
9 CUM 4 2.300 0.750 0.825 5.693
PC1 (11,12,13,14)
10 CUM 4 1.550 1.349 0.825 6.900
11 CULVERT

12 CULVERT-4 CUM 3 6.470 2.300 0.717 32.009

13 CULVERT-11 CUM 2 6.470 2.300 1.500 44.643

14 SURPRISE TT CHECKING PLATFORM

15 " CUM 10 2.250 2.250 1.500 75.938


16 SLEEPER FOUNDATION (SHEET 5 OF 11)

17 PS (18) CUM 1 2.100 1.200 1.500 3.780

18 PS (20) CUM 1 9.100 1.200 1.500 16.380

19 PS (25) CUM 1 1.600 1.600 1.500 3.840

20 SLEEPER FOUNDATION (SHEET 6 OF 11)

21 PS (5) CUM 1 4.750 1.200 0.893 5.090

22 PS (6) CUM 1 3.900 1.200 1.016 4.755

23 PS (6A) CUM 1 1.050 1.600 1.500 2.520

24 PS (7) CUM 1 2.300 1.200 1.028 2.837

25 PS (8) CUM 1 1.600 1.600 1.500 3.840

26 PS (9) CUM 1 1.600 1.600 1.500 3.840


27 PS (10) CUM 1 1.950 1.600 1.500 4.680

28 PS (11) CUM 1 5.300 1.200 1.500 9.540

29 PS (12) CUM 1 1.600 1.600 1.500 3.840

30 PS (19) CUM 1 1.600 1.600 1.500 3.840

31 PS (20) CUM 1 1.600 1.600 1.500 3.840

32 PS (21) CUM 1 1.250 1.600 1.500 3.000

33 PSG (22) CUM 1 1.250 1.600 1.500 3.000

34 PS (23) CUM 1 1.250 1.600 1.500 3.000

35 PS (24) CUM 1 1.250 1.600 1.500 3.000

36 PS (25) CUM 1 1.250 1.600 1.500 3.000

37 PS (26) CUM 1 1.250 1.600 1.500 3.000

38 SLEEPER FOUNDATION (SHEET 8 OF 11)


39 PS (1) CUM 1 1.250 1.600 1.500 3.000

40 PS (2) CUM 1 1.250 1.600 1.500 3.000

41 PS (3) CUM 1 1.250 1.600 1.500 3.000

42 SLEEPER FOUNDATION (SHEET 9 OF 11)

43 PS (1) CUM 1 11.500 1.200 1.500 20.700

44 PS (9) CUM 1 2.600 1.200 1.500 4.680

45 PS (10) CUM 1 2.600 1.200 1.500 4.680

46 FIRE WATER NETWORK

47 FL-PS-205 CUM 1 1.450 1.350 1.170 2.290

48 FL-PS-206 CUM 1 1.450 1.350 1.070 2.095

49 FL-PS-207 CUM 1 1.450 1.350 1.020 1.997

50 FL-PS-208 CUM 1 1.450 1.350 0.990 1.938


51 FL-PS-209 CUM 1 1.450 1.350 0.710 1.390

52 FL-PS-210 CUM 1 1.450 1.350 0.830 1.625

53 FL-PS-211 CUM 1 1.450 1.350 0.840 1.644

54 FL-PS-212 CUM 1 1.450 1.350 0.770 1.507

55 FL-PS-213 CUM 1 1.450 1.350 0.660 1.292

56 FL-PS-214 CUM 1 1.450 1.350 0.650 1.272

57 FL-PS-215 CUM 1 1.450 1.350 0.500 0.979

58 FL-PS-216 CUM 1 1.450 1.350 0.550 1.077

59 FL-PS-217 CUM 1 1.450 1.350 0.480 0.940

60 FL-PS-218 CUM 1 1.450 1.350 0.500 0.979

61 FL-PS-219 CUM 1 1.450 1.350 0.510 0.998


62 FL-PS-220 CUM 1 1.450 1.350 0.370 0.724

63 FL-PS-221 CUM 1 1.450 1.350 0.440 0.861

64 FL-PS-222 CUM 1 1.450 1.350 0.500 0.979

65 FL-PS-223 CUM 1 1.450 1.350 0.410 0.803

66 FL-PS-224 CUM 1 1.450 1.350 0.430 0.842

67 FL-PS-225 CUM 1 1.450 1.350 0.460 0.900

68 FL-PS-226 CUM 1 1.450 1.350 0.355 0.695

69 FL-PS-227 CUM 1 1.450 1.350 0.300 0.587

70 FL-PS-232 CUM 1 1.450 1.350 0.610 1.194

71 FL-PS-233 CUM 1 1.450 1.350 0.630 1.233

72 FL-PS-234 CUM 1 1.450 1.350 0.730 1.429


73 FL-PS-235 CUM 1 1.450 1.350 0.770 1.507

74 FL-PS-238 CUM 1 1.450 1.350 0.770 1.507

75 FL-PS-239 CUM 1 1.450 1.350 0.900 1.762

76 FL-PS-240 CUM 1 1.450 1.350 0.580 1.135

77 FL-PS-241 CUM 1 1.450 1.350 0.600 1.175

78 FL-PS-242 CUM 1 1.450 1.350 0.750 1.468

79 CHAIN LINK FENCING


80 ( SKO Tank East side Road Center to manifold area) CUM 1 58.000 0.500 0.300 8.700

81 PIPE SLEEPER SHEET 5 OF 11 AREA GRADING

82 PS (1 TO 17) CUM 1 68.700 4.600 0.279 88.170


83 Pedestal deduction CUM -1 65.550 1.200 0.279 -21.946
84 PIPE SLEEPER SHEET 6 OF 11 AREA GRADING
85 PS (16 TO 20) CUM 1 21.184 1.500 0.381 12.107
86 PS (21 TO 26) CUM 1 20.390 1.150 0.381 8.934
87 Pedestal deduction CUM -1 15.500 1.600 0.381 -9.449
88 PIPE SLEEPER SHEET 9 OF 11 AREA GRADING
89 PS (1 TO 5) CUM 1 24.000 11.400 0.416 113.818
90 Pedestal deduction CUM -5 11.500 1.200 0.416 -28.704
91 TOTAL QTY (CUM) 507.317

92 00050 b) Depth between 1.5 m to 5 m

93 CULVERT
94 CULVERT-11 CUM 2 6.470 2.300 0.123 3.661
95 SURPRISE TT CHECKING PLATFORM
96 " CUM 10 2.250 2.250 0.100 5.062
97 SLEEPER FOUNDATION (SHEET 5 OF 11)

98 PS (18) CUM 1 2.100 1.200 0.830 2.092

99 PS (20) CUM 1 9.100 1.200 0.610 6.661

100 PS (25) CUM 1 1.600 1.600 0.665 1.702

101 SLEEPER FOUNDATION (SHEET 6 OF 11)

102 PS (8) CUM 1 1.600 1.600 0.376 0.963

103 PS (9) CUM 1 1.600 1.600 0.376 0.963

104 PS (10) CUM 1 1.950 1.600 0.078 0.243

105 PS (11) CUM 1 5.300 1.200 0.028 0.178

106 PS (12) CUM 1 1.600 1.600 0.406 1.039

107 PS (19) CUM 1 1.600 1.600 0.628 1.608

108 PS (20) CUM 1 1.600 1.600 0.788 2.017

109 PS (21) CUM 1 1.250 1.600 1.150 2.300


110 PSG (22) CUM 1 1.250 1.600 1.105 2.210

111 PS (23) CUM 1 1.250 1.600 1.200 2.400

112 PS (24) CUM 1 1.250 1.600 1.185 2.370

113 PS (25) CUM 1 1.250 1.600 1.255 2.510

114 PS (26) CUM 1 1.250 1.600 1.300 2.600

115 SLEEPER FOUNDATION (SHEET 8 OF 11)

116 PS (1) CUM 1 1.250 1.600 1.260 2.520

117 PS (2) CUM 1 1.250 1.600 1.180 2.360

118 PS (3) CUM 1 1.250 1.600 0.850 1.700

119 SLEEPER FOUNDATION (SHEET 9 OF 11)

120 PS (1) CUM 1 11.500 1.200 0.633 8.735

121 PS (9) CUM 1 2.600 1.200 0.258 0.805

122 PS (10) CUM 1 2.600 1.200 0.188 0.587

TOTAL QTY (CUM) 57.286


Certified that the work is done as per drawings, specifications and instructions. Quantities mentioned above are checked and verified
FOR FFIL FOR IOCL

SIGNATURE SIGNATURE
NAME NAME
DATE DATE

CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B

WORK DESCRIPTION :-COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TOP OFF POINTS-KHUNTI,JHARKHAND.

SECTION/SPREAD :-
WO NO & DATE : 24047898 Dated 14-02-2014 RA BILL No : FFIL/ CIVIL RA-10
CLIENT : INDIAN OIL CORPORATION LIMITED DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA(INDIA) Ltd. MEASUREMENT PERIOD : 01.02.15 – 13.02.15
CALCULATION SHEET

SOR Dimensions
SR. No. Item Description UOM Height Quantity
No. NOS Length(L) Breadth (B) (H) /Depth
(D)
1 00290 PLAIN CONCRETE WORK
2 00300 PCC with mix(1:4:8)
3 PIPE BRIDGE
4 CUM 4 2.300 0.750 0.100 0.690
PC3 (11,12,13,14)
5 CUM 4 1.550 1.349 0.100 0.836

6 SURPRISE TT CHECKING PLATFORM

7 " CUM 10 2.250 2.250 0.100 5.062

8 CULVERT

9 CULVERT-4,11 CUM 5 6.470 2.300 0.100 7.441


10 PIPE SLEEPER (SHEET 5 OF 11)

11 PS (18) CUM 1 2.100 1.200 0.100 0.252

12 PS (20) CUM 1 9.100 1.200 0.100 1.092

13 PS (25) CUM 1 1.600 1.600 0.100 0.256

14 PIPE SLEEPER FOUNDATION (RAFT) (SHEET 6 OF 11)

15 PS (5) CUM 1 4.750 1.200 0.100 0.570

16 PS (6) CUM 1 3.900 1.200 0.100 0.468

17 PS (6A) CUM 1 1.050 1.600 0.100 0.168

18 PS (7) CUM 1 2.300 1.200 0.100 0.276

19 PS (8,9,12,19,20) CUM 5 1.600 1.600 0.100 1.280

20 PS (10) CUM 1 1.950 1.600 0.100 0.312

21 PS (11) CUM 1 5.300 1.200 0.100 0.636

22 PS (21,22,23,24,25,26) CUM 6 1.250 1.600 0.100 1.200

23 PIPE SLEEPER FOUNDATION (PEDESTAL) (SHEET 8 OF 11)

24 PS (1,2,3) CUM 3 1.250 1.600 0.100 0.600

25 PIPE SLEEPER (SHEET 9 OF 11)

26 PS (1) CUM 1 11.500 1.200 0.100 1.380

27 PS(9,10) CUM 2 2.600 1.200 0.100 0.312


28 FIRE WATER NETWORK

29 FL-PS (205 TO 227,232 TO 235,238 TO 242) CUM 32 1.450 1.350 0.150 9.396

30 TOTAL QTY (CUM) 32.227


31 00310 PCC with mix(1:3:6)
32 ( SKO Tank East side Road Center to manifold area) CUM 1 58.000 0.500 0.100 2.900
33
34 TOTAL QTY (CUM) 2.900
35 00320 PCC with mix(1:2:4)
36 VERTICAL ANGLE POSTS FIXING CUM 89 0.450 0.350 0.600 8.411
37 INTERMEDIATE ANGLE FIXING CUM 50 0.45 0.25 0.15 0.844
TOTAL QTY (CUM) 9.254
Certified that the work is done as per drawings, specifications and instructions. Quantities mentioned above are checked and verified
FOR FFIL FOR IOCL

SIGNATURE SIGNATURE

NAME NAME

DATE DATE

CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B

WORK DESCRIPTION :-COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TOP OFF POINTS-KHUNTI,JHARKHAND.
SECTION/SPREAD :-
WO NO & DATE : 24047898 Dated 14-02-2014 RA BILL No : FFIL/ CIVIL RA-10
CLIENT : INDIAN OIL CORPORATION LIMITED DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA(INDIA) Ltd. MEASUREMENT PERIOD : 01.02.15 – 13.02.15
CALCULATION SHEET
SOR Dimensions
SR. No. Item Description UOM Height Quantity
No. NOS Length(L) Breadth (B) (H) /Depth
(D)
1 00360 REINFORCED CEMENT CONCRETE

2 00390 RCC with mix (1:1.5:3)

3 00400 a)In foundation,plinth, ramps etc.


4 PIPE BRIDGE

5 PC1 (15,16) CUM 2 4.700 2.200 0.650 13.442

6 CUM 4 2.200 0.700 0.450 2.772


PC3 (11,12,13,14)
7 CUM 4 1.450 1.299 0.450 3.390
8 PEDESTAL (PIPE BRIDGE)
9 P2- 11,12,13,14 CUM 4 0.750 0.450 1.375 1.856

10 P1- 15,15A,16,16A,17,18,19,20 CUM 8 0.750 0.650 1.375 5.363

11 CULVERT

12 CULVERT-11,4 (RAFT) CUM 5 6.370 2.200 0.500 35.035

13 CULVERT-4 (PEDESTAL) CUM 3 6.370 0.350 1.256 8.401

14 CULVERT-5 (PEDESTAL) CUM 3 6.370 0.350 1.206 8.066


15 CULVERT-6 (PEDESTAL) CUM 2 6.370 0.350 1.710 7.625

16 CULVERT-10 & 11 (PEDESTAL) CUM 4 6.370 0.350 1.110 9.899

17 SURPRISE TT CHECKING PLATFORM

18 " CUM 10 2.100 2.100 0.500 22.050

19 PIPE SLEEPER FOUNDATION (RAFT) (SHEET 5 OF 11)

PS (8) CUM 1 4.600 1.100 0.450 2.277

20 PS (18) CUM 1 2.000 1.100 0.450 0.990

21 PS (20) CUM 1 9.000 1.100 0.450 4.455

22 PS (25) CUM 1 1.500 1.500 0.400 0.900

23 PIPE SLEEPER FOUNDATION (PEDESTAL) (SHEET 5 OF 11)

24 PS (8) CUM 1 4.600 0.350 1.340 2.157

25 PS (12) CUM 1 2.700 0.350 1.340 1.266

26 PS (13) CUM 1 1.800 0.350 1.940 1.222

27 PS (14) CUM 1 2.150 0.350 1.340 1.008

28 PS (15) CUM 1 1.650 0.350 1.940 1.120

29 PS (17) CUM 1 0.400 0.350 1.940 0.272

30 PS (18) CUM 1 2.000 0.350 0.465 0.326


31 PS (20) CUM 1 9.000 0.350 0.465 1.465

32 PS (21,22) CUM 2 0.900 0.350 1.940 1.222

33 PS (25) CUM 1 1.500 0.350 0.565 0.297

34 PIPE SLEEPER FOUNDATION (RAFT) (SHEET 6 OF 11)

35 PS (5) CUM 1 4.650 1.100 0.450 2.302

36 PS (6) CUM 1 3.800 1.100 0.450 1.881

37 PS (6A) CUM 1 0.950 1.500 0.400 0.570

38 PS (7) CUM 1 2.200 1.100 0.450 1.089

39 PS (8,9,12,19,20) CUM 5 1.500 1.500 0.400 4.500

40 PS (10) CUM 1 1.850 1.500 0.400 1.110

41 PS (11) CUM 1 5.200 1.100 0.450 2.574

42 PS (21,22,23,24,25,26) CUM 6 1.150 1.500 0.400 4.140

43 PIPE SLEEPER FOUNDATION (PEDESTAL) (SHEET 6 OF 11)

44 PS (5) CUM 1 4.650 0.350 1.265 2.059

45 PS (6) CUM 1 3.800 0.350 1.265 1.682

46 PS (6A) CUM 1 0.950 0.350 1.865 0.620

47 PS (7) CUM 1 2.200 0.350 1.265 0.974

48 PS (8,9,12,19,20) CUM 5 1.500 0.350 1.865 4.896


49 PS (10) CUM 1 1.850 0.350 1.865 1.208

50 PS (11) CUM 1 5.200 0.350 1.265 2.302

51 PS (21,22,23,24,25,26) CUM 6 1.150 0.350 1.865 4.504

52 PIPE SLEEPER FOUNDATION (PEDESTAL) (SHEET 7 OF 11)

53 PS (1,2,3,4,15) CUM 5 4.000 0.350 1.265 8.855

54 PS (5) CUM 1 2.100 0.350 1.265 0.930

55 PS (6,7,8,9,10,11,12,13,14) CUM 9 3.200 0.350 1.265 12.751

56 PIPE SLEEPER FOUNDATION (RAFT) (SHEET 8 OF 11)

57 PS (1,2,3) CUM 3 1.150 1.500 0.400 2.070

58 PIPE SLEEPER FOUNDATION (PEDESTAL) (SHEET 8 OF 11)

59 PS (1,2,3) CUM 3 1.150 0.350 1.865 2.252

60 PIPE SLEEPER FOUNDATION (RAFT) (SHEET 9 OF 11)

61 PS (1) CUM 1 11.400 1.100 0.450 5.643

62 PS (9,10) CUM 2 2.500 1.100 0.450 2.475

63 PIPE SLEEPER FOUNDATION (PEDESTAL) (SHEET 9 OF 11)

64 PS (1,2) CUM 2 11.400 0.350 1.265 10.095

65 PS (9) CUM 1 2.500 0.350 0.590 0.516

66 PS (10) CUM 1 2.500 0.350 1.265 1.107

67 PS (12) CUM 1 3.850 0.350 1.965 2.648

68 FIRE WATER NETWORK


69 RAFT FL-PS (205 TO 227,232 TO 235,238 TO 242) CUM 32 1.300 1.200 0.300 14.976

PEDESTAL FL-PS (232 TO 242, 273 TO 280,312 TO 318,322 TO


70 CUM 37 0.850 0.500 1.265 19.892
332 )
TOTAL QTY (CUM) 257.497
Certified that the work is done as per drawings, specifications and instructions. Quantities mentioned above are checked and verified
FOR FFIL FOR IOCL

SIGNATURE SIGNATURE

NAME NAME

DATE DATE

CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B

WORK DESCRIPTION :-COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TOP OFF POINTS-KHUNTI,JHARKHAND.

SECTION/SPREAD :-
WO NO & DATE : 24047898 Dated 14-02-2014 RA BILL No : FFIL/ CIVIL RA-10
CLIENT : INDIAN OIL CORPORATION LIMITED DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA(INDIA) Ltd. MEASUREMENT PERIOD : 01.02.15 – 13.02.15
CALCULATION SHEET
SOR Dimensions
SR. No. Item Description UOM Height Quantity
No. NOS Length(L) Breadth (B) (H) /Depth
(D)
1 00470 Painting foundation concrete with hot bitumen

2 TLF PUMP HOUSE


3 SQM 88 0.500 1.350 59.400
PEDESTAL (A/1 to 22, B/1 to 22)
4 SQM 88 0.650 1.350 77.220
5 P. BEAM DEDUCTION SQM -88 0.300 0.500 -13.200

6 PLINTH BEAM SQM 4 88.5 0.500 177.000


7 PEDESTAL DEDUCTION SQM -42 0.500 0.500 -10.500

8 PIPE BRIDGE
9 SQM 10 7.300 0.450 32.850
10 PC3 (3,4,5,6,9,10,11,12,13,14) SQM 10 2.200 0.700 15.400
11 SQM 10 1.450 1.299 18.836
12 PEDESTAL DEDUCTION SQM -10 0.750 0.450 -3.375
13 SQM 4 4.700 0.650 12.220
14 PC2 (15,16) SQM 4 2.200 0.650 5.720
15 SQM 2 4.700 2.200 20.680
16 PEDESTAL DEDUCTION SQM -4 -1.950
0.750 0.650
17 SQM 16 2.200 0.550 19.360
PC1 (17,18,19,20)
18 SQM 4 2.200 2.200 19.360
19 PEDESTAL DEDUCTION SQM -4 0.750 0.650 -1.950

20 PEDESTAL

21 SQM 28 0.750 1.075 22.575


P2 (1,2,3,4,5,6,7,8,9,10,11,12,13,14)
22 SQM 28 0.450 1.075 13.545
23 SQM 16 0.750 1.075 12.900
P1 (15,15A,16,16A,17,18,19,20))
24 SQM 16 0.650 1.075 11.180
TOTAL QTY (SQM) 487.271
Certified that the work is done as per drawings, specifications and instructions. Quantities mentioned above are checked and verified
FOR FFIL FOR IOCL
SIGNATURE SIGNATURE

NAME NAME

DATE DATE

CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B

WORK DESCRIPTION :-COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TOP OFF POINTS-KHUNTI,JHARKHAND.

SECTION/SPREAD :-
WO NO & DATE : 24047898 Dated 14-02-2014 RA BILL No : FFIL/ CIVIL RA-10
CLIENT : INDIAN OIL CORPORATION LIMITED DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA(INDIA) Ltd. MEASUREMENT PERIOD : 01.02.15 – 13.02.15
CALCULATION SHEET
Dimensions
SOR
SR. No. Item Description UOM Height Quantity
No. NOS Length(L) Breadth (B) (H) /Depth
(D)
1 00480 BRICK WORK

Brick work with burnt clay bricks of class designation 50 in


6 00500 cement mortor 1:6
7 00510 a) In foundation, plinth etc.
8 CUM 1 58.000 0.375 0.300 6.525
(From SKO Tank East side Road Center to manifold area)
9 CUM 1 58.000 0.250 0.150 2.175
10 DEDUCTION VERTICAL ANGLE POST CUM -19 0.450 0.350 0.450 -1.347

TOTAL QTY (CUM) 7.353


Certified that the work is done as per drawings, specifications and instructions. Quantities mentioned above are checked and verified
FOR FFIL FOR IOCL
SIGNATURE SIGNATURE

NAME NAME

DATE DATE

CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B

WORK DESCRIPTION :-COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TOP OFF POINTS-KHUNTI,JHARKHAND.

SECTION/SPREAD :-
WO NO & DATE : 24047898 Dated 14-02-2014 RA BILL No : FFIL/ CIVIL RA-10
CLIENT : INDIAN OIL CORPORATION LIMITED DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA(INDIA) Ltd. MEASUREMENT PERIOD : 01.02.15 – 13.02.15
CALCULATION SHEET
SOR Dimensions
SR. No. Item Description UOM Height Quantity
No. NOS Length(L) Breadth (B) (H) /Depth
(D)
Supplying and filling coarse sand under floors, in
1 00150
foundations and plinth
2 Pipe sleeper sheet 5 of 11 PS(20) CUM 1 9.100 1.200 0.150 1.638
3 Pipe sleeper sheet 9 of 11 PS(9,10) CUM 2 2.600 1.200 0.150 0.936

4 Chain link fencing CUM 1 58.000 0.500 0.150 4.350


5 TOTAL QTY (CUM) 6.924
6 Supplying and providing chain link fencing with GI wire
00640 of 3 mm diaforming a mesh size of 50 x 50 mm
7 Chain link fencing SQM 1 388.00 1.800 698.400

TOTAL QTY (SQM) 698.400


Certified that the work is done as per drawings, specifications and instructions. Quantities mentioned above are checked and verified
FOR FFIL FOR IOCL

SIGNATURE SIGNATURE

NAME NAME

DATE DATE

CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B

WORK DESCRIPTION :-COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TOP OFF POINTS-KHUNTI,JHARKHAND.

SECTION/SPREAD :-
WO NO & DATE : 24047898 Dated 14-02-2014 RA BILL No : FFIL/ CIVIL RA-10
CLIENT : INDIAN OIL CORPORATION LIMITED DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA(INDIA) Ltd. MEASUREMENT PERIOD : 01.02.15 – 13.02.15
CALCULATION SHEET

SOR Dimensions
SR. No. Item Description UOM Height Quantity
No. NOS Length(L) Breadth (B) (H) /Depth
(D)
1 00010 EARTH WORK
Site cleaning work of the ground in all kinds of soil
2 00020
including clearing the area

3 CHAIN LINK FENCING SQM 1 388.000 0.500 194.000

TOTAL QTY (SQM) 194.000


Certified that the work is done as per drawings, specifications and instructions. Quantities mentioned above are checked and verified
FOR FFIL FOR IOCL

SIGNATURE SIGNATURE

NAME NAME

DATE DATE
Remarks

FGL= 95.875
EGL=95.700
Bottom of PCC= 94.875

FGL= 94.000
EGL= 92.917
Bottom of
PCC= 92.200
FGL= 93.500
EGL= 93.323 UPTO(1.5
m)-91.823
Bottom of
PCC= 91.700
TOP OF ISLAND= 98.00
EGL= 97.559
UPTO(1.5 m)-96.059

Bottom of PCC= 95.959


FGL-93.500 EGL-94.280
UPTO(1.5 m)-92.780
BOPCC-91.950

FGL-93.500 EGL-94.060
UPTO(1.5 m)-92.56
BOPCC-91.950

FGL-94.000 EGL-94.065
UPTO(1.5 m)-92.565
BOPCC-91.900

FGL-94.00
EGL-93.343
BOPCC-92.450

FGL-94.00
EGL-93.466
BOPCC-92.450

FGL-94.00
EGL-93.400
BOPCC-91.900

FGL-94.00
EGL-93.478
BOPCC-92.450

FGL-94.00 EGL-93.776
UPTO(1.5 m)-92.276
BOPCC-91.900

FGL-94.00 EGL-93.776
UPTO(1.5 m)-92.276
BOPCC-91.900
FGL-94.00 EGL-93.478
UPTO(1.5 m)-91.978
BOPCC-91.900

FGL-94.00 EGL-93.978
UPTO(1.5 m)-92.478
BOPCC-92.450

FGL-94.00 EGL-93.806
UPTO(1.5 m)-92.306
BOPCC-91.900

FGL-94.00 EGL-94.028
UPTO(1.5 m)-92.528
BOPCC-91.900

FGL-94.00 EGL-94.188
UPTO(1.5 m)-92.688
BOPCC-91.900

FGL-94.00 EGL-94.550
UPTO(1.5 m)-93.050
BOPCC-91.900

FGL-94.00 EGL-94.505
UPTO(1.5 m)-93.005
BOPCC-91.900

FGL-94.00 EGL-94.600
UPTO(1.5 m)-93.100
BOPCC-91.900

FGL-94.00 EGL-94.585
UPTO(1.5 m)-93.085
BOPCC-91.900

FGL-94.00 EGL-94.655
UPTO(1.5 m)-93.155
BOPCC-91.900

FGL-94.00 EGL-94.700
UPTO(1.5 m)-93.200
BOPCC-91.900
FGL-94.00 EGL-94.660
UPTO(1.5 m)-93.160
BOPCC-91.900

FGL-94.00 EGL-94.580
UPTO(1.5 m)-93.080
BOPCC-91.900

FGL-94.00 EGL-94.250
UPTO(1.5 m)-92.750
BOPCC-91.900

FGL-93.500 EGL-94.083
UPTO(1.5 m)-92.583
BOPCC-91.950

FGL-93.500 EGL-93.708
UPTO(1.5 m)-92.208
BOPCC-91.950

FGL-93.500 EGL-93.638
UPTO(1.5 m)-92.138
BOPCC-91.950

FGL-94.000
EGL-94.020
BOPCC-92.850 92.85

FGL-94.000
EGL-93.920
BOPCC-92.850

FGL-94.000
EGL-93.870
BOPCC-92.850

FGL-94.000
EGL-93.840
BOPCC-92.850
FGL-94.000
EGL-93.560
BOPCC-92.850

FGL-94.000
EGL-93.680
BOPCC-92.850

FGL-94.000
EGL-93.690
BOPCC-92.850

FGL-94.000
EGL-93.620
BOPCC-92.850

FGL-94.000
EGL-93.510
BOPCC-92.850

FGL-94.000
EGL-93.500
BOPCC-92.850

FGL-94.000
EGL-93.350
BOPCC-92.850

FGL-94.000
EGL-93.400
BOPCC-92.850

FGL-94.000
EGL-93.330
BOPCC-92.850

FGL-94.000
EGL-93.350
BOPCC-92.850

FGL-94.000
EGL-93.360
BOPCC-92.850
FGL-94.000
EGL-93.220
BOPCC-92.850

FGL-94.000
EGL-93.290
BOPCC-92.850

FGL-94.000
EGL-93.350
BOPCC-92.850

FGL-94.000
EGL-93.260
BOPCC-92.850

FGL-94.000
EGL-93.280
BOPCC-92.850

FGL-94.000
EGL-93.310
BOPCC-92.850

FGL-94.000
EGL-93.205
BOPCC-92.850

FGL-94.000
EGL-93.150
BOPCC-92.850

FGL-94.000
EGL-93.460
BOPCC-92.850

FGL-94.000
EGL-93.480
BOPCC-92.850

FGL-94.000
EGL-93.580
BOPCC-92.850
FGL-94.000
EGL-93.620
BOPCC-92.850

FGL-94.000
EGL-93.620
BOPCC-92.850

FGL-94.000
EGL-93.750
BOPCC-92.850

FGL-94.000
EGL-93.430
BOPCC-92.850

FGL-94.000
EGL-93.450
BOPCC-92.850

FGL-94.000
EGL-93.600
BOPCC-92.850

FGL-94.000
AVG. EGL-94.279

FGL-94.000
AVG. EGL-94.381 1038.187
94.381

FGL-93.500
AVG. EGL-93.916
UPTO(1.5 m)-91.823

Bottom of PCC= 91.700


UPTO(1.5 m)-96.059

Bottom of PCC= 95.959

UPTO(1.5 m)-92.780
BOPCC-91.950
UPTO(1.5 m)-92.56
BOPCC-91.950
UPTO(1.5 m)-92.565
BOPCC-91.900

UPTO(1.5 m)-92.276
BOPCC-91.900
UPTO(1.5 m)-92.276
BOPCC-91.900
UPTO(1.5 m)-91.978
BOPCC-91.900
UPTO(1.5 m)-92.478
BOPCC-92.450
UPTO(1.5 m)-92.306
BOPCC-91.900
UPTO(1.5 m)-92.528
BOPCC-91.900
UPTO(1.5 m)-92.688
BOPCC-91.900
UPTO(1.5 m)-93.050
BOPCC-91.900
UPTO(1.5 m)-93.005
BOPCC-91.900
UPTO(1.5 m)-93.100
BOPCC-91.900
UPTO(1.5 m)-93.085
BOPCC-91.900
UPTO(1.5 m)-93.155
BOPCC-91.900
UPTO(1.5 m)-93.200
BOPCC-91.900

UPTO(1.5 m)-93.160
BOPCC-91.900

UPTO(1.5 m)-93.080
BOPCC-91.900

UPTO(1.5 m)-92.750
BOPCC-91.900

UPTO(1.5 m)-92.583
BOPCC-91.950

UPTO(1.5 m)-92.208
BOPCC-91.950
UPTO(1.5 m)-92.138
BOPCC-91.950
Remarks

TOPCC= 94.975
BOPCC= 94.875

TOPCC= 96.059
BOPCC= 95.959

TOPCC= 91.800
BOPCC= 91.700
TOPCC= 92.050
BOPCC= 91.950
TOPCC= 92.050
BOPCC= 91.950
TOPCC= 92.000
BOPCC= 91.900

TOC=92.550
BOC=92.450
TOC=92.550
BOC=92.450
TOC=92.000
BOC=91.900
TOC=92.550
BOC=92.450
TOC=92.000
BOC=91.900
TOC=92.000
BOC=91.900
TOC=92.550
BOC=92.450
TOC=92.000
BOC=91.900

TOC=92.000
BOC=91.900

TOC=92.050
BOC=91.950
TOPCC= 92.050
BOPCC= 91.950
TOPCC= 93.000
BOPCC= 92.850
Remarks

TOC=92.725
BOC=92.075

TOC=95.425
BOC=94.975

TOC=96.800
BOC=95.425

TOC=96.800
BOC=95.425

TOC=92.300
BOC=91.800

TOC=94.056
BOC=92.800

TOC=93.506
BOC=92.300
TOC=93.010
BOC=91.300

TOC=93.410
BOC=92.300

TOPCC= 96.559
BOPCC= 96.059

TOC=93.000
BOC=92.550
TOC=93.000
BOC=92.050
TOC=93.000
BOC=92.050
TOC=92.4000
BOC=93.000

TOC=94.340
BOC=93.000
TOC=94.340
BOC=93.000
TOC=94.340
BOC=92.400
TOC=94.340
BOC=93.000
TOC=94.340
BOC=92.400
TOC=94.340
BOC=92.400
TOC=92.965
BOC=92.500
TOC=92.965
BOC=92.500
TOC=94.340
BOC=92.400
TOC=92.965
BOC=92.400

TOC=93.000
BOC=92.550
TOC=93.000
BOC=92.550
TOC=92.400
BOC=92.000
TOC=93.000
BOC=92.550
TOC=92.400
BOC=92.000
TOC=92.400
BOC=92.000
TOC=93.000
BOC=92.550
TOC=92.400
BOC=92.000

TOC=94.265
BOC=93.000
TOC=94.265
BOC=93.000
TOC=94.265
BOC=92.400
TOC=94.265
BOC=93.000
TOC=94.265
BOC=92.400
TOC=94.265
BOC=92.400
TOC=94.265
BOC=93.000
TOC=94.265
BOC=92.400

TOC=94.265
BOC=93.000
TOC=94.265
BOC=93.000
TOC=94.265
BOC=93.000

TOC=92.400
BOC=92.000

TOC=94.265
BOC=92.400

TOC=92.500
BOC=92.050
TOC=92.500
BOC=92.050

TOC=93.765
BOC=92.500
TOC=93.090
BOC=92.500
TOC=93.765
BOC=92.500
TOC=94.465
BOC=92.500
Remarks
Remarks
Remarks

Due to slushy area


Remarks
CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B
WORK DESCRIPTION :- COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TAP OFF POINTS-
KHUNTI,JHARKHANDKHUNTI,JHARKHAND.

SECTION/SPREAD :-
WO NO & DATE : 24047898 Dated 14-02-2014 RA BILL No : FFIL/ CIVIL RA-10
CLIENT : INDIAN OIL CORPORATION LIMITED DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA (INDIA) Ltd. MEASUREMENT PERIOD : 01.02.15 – 13.02.15

CALCULATION SHEET

SOR Dimensions
SR. No. Item Description UOM Quantity
Cutting Total Weight of
No. Dia nos
Length(M) Length(M) Tor/m

1 00360 REINFORCED CEMENT CONCRETE

2 00430 Reinforcement for RCC Work

3 PIPE BRIDGE
4 PC2 (15,16)
5 Top Main bar TON 20 mm 62 2.650 164.300 2.469 0.406
6 Top Dist-bar " 20 mm 30 5.150 154.500 2.469 0.381
7 Bottom Main bar " 20 mm 94 2.650 249.100 2.469 0.615
8 Bottom Dist-bar " 20 mm 44 5.150 226.600 2.469 0.559
9 Pile binder " 12 mm 6 12.182 73.092 0.888 0.065
10 Stirrups " 10 mm 264 2.020 533.280 0.617 0.329
11 Links " 10 mm 22 0.700 15.400 0.617 0.010
12 Extra bar chair " 12 mm 16 1.506 24.096 0.888 0.021
13 Lap length " 12 mm 6 0.684 4.104 0.888 0.004
14 PC3 (11,12,13,14)
15 Bottom bar (main) " 20 mm 16 2.450 39.200 2.469 0.097
16 varies " 20 mm 4 2.352 9.408 2.469 0.023
17 " " 20 mm 4 2.054 8.216 2.469 0.020
18 " " 20 mm 4 1.756 7.024 2.469 0.017
19 " " 20 mm 4 1.458 5.832 2.469 0.014
20 " " 20 mm 4 1.160 4.640 2.469 0.011
21 " " 20 mm 4 1.130 4.520 2.469 0.011
22 Top bar (main) " 16 mm 16 2.466 39.456 1.580 0.062
23 varies " 16 mm 4 2.368 9.472 1.580 0.015
24 " " 16 mm 4 2.030 8.120 1.580 0.013
25 " " 16 mm 4 1.772 7.088 1.580 0.011
26 " " 16 mm 4 1.474 5.896 1.580 0.009
27 " " 16 mm 4 1.176 4.704 1.580 0.007
28 " " 16 mm 4 1.146 4.584 1.580 0.007
29 stirrups " 10 mm 48 1.950 93.600 0.617 0.058
30 stirrups " 10 mm 48 1.244 59.712 0.617 0.037
31 Bottom bar(dist) " 20 mm 16 2.249 35.984 2.469 0.089
32 varies " 20 mm 8 1.925 15.400 2.469 0.038
33 " " 20 mm 8 1.601 12.808 2.469 0.032
34 " " 20 mm 8 1.188 9.504 2.469 0.023
35 " " 20 mm 8 1.061 8.488 2.469 0.021
36 Bottom bar(dist) " 16 mm 16 2.265 36.240 1.580 0.057
37 varies " 16 mm 8 1.941 15.528 1.580 0.025
38 " " 16 mm 8 1.617 12.936 1.580 0.020
39 ' " 16 mm 8 1.204 9.632 1.580 0.015
40 ' " 16 mm 8 1.077 8.616 1.580 0.014
41 stirrups " 10 mm 40 1.950 78.000 0.617 0.048
42 stirrups " 10 mm 40 1.244 49.760 0.617 0.031
43 pile binder " 12 mm 12 7.728 92.736 0.888 0.082
44 Extra bar chair " 12 mm 24 1.506 36.144 0.888 0.032
45 PEDESTAL (PIPE BRIDGE)
46 P2- 11,12,13,14
47 Vertical " 20 mm 48 2.362 113.376 2.469 0.280
48 stirrups " 10 mm 36 2.200 79.200 0.617 0.049
49 stirrups " 10 mm 36 1.570 56.520 0.617 0.035
50 stirrups " 10 mm 36 0.850 30.600 0.617 0.019
51 stirrups " 10 mm 36 0.550 19.800 0.617 0.012
52 P1- 15,15A,16,16A
53 Vertical " 20 mm 64 2.630 168.320 2.649 0.446
54 stirrups " 10 mm 40 2.600 104.000 0.617 0.064
55 stirrups " 10 mm 40 1.970 78.800 0.617 0.049
56 stirrups " 10 mm 40 2.070 82.800 0.617 0.051
57 CULVERT
58 culvert-4
59 Top main bar " 16 mm 96 2.486 238.656 1.58 0.377
60 Top dis. Bar " 16 mm 33 6.656 219.648 1.58 0.347
61 Bottom main bar " 20 mm 126 2.470 311.220 2.469 0.768
62 Bottom dis. bar " 20 mm 45 6.640 298.800 2.469 0.738
63 vertical " 16 mm 204 2.877 586.908 1.58 0.927
64 vertical " 16 mm 102 3.059 312.018 1.58 0.493
65 Binder " 12 mm 96 6.590 632.640 0.888 0.562
66 Binder " 12 mm 10 6.238 62.380 0.888 0.055
67 Binder " 16 mm 128 2.266 290.048 1.58 0.458
68 Binder " 16 mm 128 3.042 389.376 1.58 0.615
69 Binder " 12 mm 8 6.270 50.160 0.888 0.045
70 Extra bar chair " 12 mm 24 1.800 43.200 0.888 0.038
71 Extra Spacer bar 12 mm 18 1.700 30.600 0.888 0.027
72 culvert-11
73 Top main bar " 16 mm 64 2.486 159.104 1.58 0.251
74 Top dis. Bar " 16 mm 22 6.656 146.432 1.58 0.231
75 Bottom main bar " 20 mm 84 2.470 207.480 2.469 0.512
76 Bottom dis. bar " 20 mm 30 6.640 199.200 2.469 0.492
77 vertical " 16 mm 102 2.731 278.562 1.58 0.440
78 vertical " 16 mm 102 2.913 297.126 1.58 0.469
79 Binder " 12 mm 60 6.590 395.400 0.888 0.351
80 Binder " 12 mm 10 6.238 62.380 0.888 0.055
81 Binder " 16 mm 128 2.266 290.048 1.58 0.458
82 Binder " 12 mm 4 6.270 25.080 0.888 0.022
83 Extra bar chair " 12 mm 16 1.700 27.200 0.888 0.024
84 Extra Spacer bar 12 mm 12 1.700 20.400 0.888 0.018
85 culvert-5
86 Binder " 16 mm 128 2.266 290.048 1.58 0.458
87 Binder " 16 mm 128 3.042 389.376 1.58 0.615
88 Binder " 12 mm 8 6.270 50.160 0.888 0.045
89 culvert-6
90 Binder " 16 mm 128 2.266 290.048 1.58 0.458
91 Binder " 12 mm 4 6.270 25.080 0.888 0.022
92 culvert-10
93 Binder " 16 mm 128 2.266 290.048 1.58 0.458
94 Binder " 12 mm 4 6.270 25.080 0.888 0.022

95 SURPRISE TT CHECKING PLATFORM

96 Bottom (Both ways) " 12 mm 420 2.502 1050.840 0.888 0.933


97 Top (Both ways) " 10 mm 176 2.510 441.760 0.617 0.273
98 vertical " 20 mm 120 2.997 359.640 2.469 0.888
99 strriups " 8 mm 100 1.960 196.000 0.395 0.077
100 strriups " 8 mm 200 1.400 280.000 0.395 0.111
TOTAL QTY (T) 17.474
Certified that the work is done as per drawings, specifications and instructions. Quantities mentioned above are checked and verified
FOR FFIL FOR IOCL

SIGNATURE SIGNATURE

NAME NAME

DATE DATE
CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B

WORK DESCRIPTION :- COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TAP OFF POINTS-
KHUNTI,JHARKHANDKHUNTI,JHARKHAND.

SECTION/SPREAD :-
WO NO & DATE : 24047898 Dated 14-02-2014 RA BILL No : FFIL/ CIVIL RA-10
CLIENT : INDIAN OIL CORPORATION LIMITED DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA (INDIA) Ltd. MEASUREMENT PERIOD : 01.02.15 – 13.02.15
CALCULATION SHEET

SOR Dimensions
SR. No. Item Description UOM Cutting Total Weight of Quantity
No. Dia nos
Length(M) Length(M) Tor/m
1 00360 REINFORCED CEMENT CONCRETE
2 00430 Reinforcement for RCC Work
PIPE SLEEPER FOUNDATION (SHEET 5
3 OF 11)
4 PS (8) (L= 4.6 m)
5 Top bar (main) TON 12 mm 23 1.352 31.096 0.888 0.028
6 Top bar (dist) " 12 mm 6 4.852 29.112 0.888 0.026
7 Bottom bar (main) " 16 mm 23 1.336 30.728 1.58 0.049
8 Bottom bar (dist) " 16 mm 6 4.836 29.016 1.58 0.046
9 vertical " 16 mm 48 2.339 112.272 1.58 0.177
10 binder " 10 mm 7 9.572 67.004 0.617 0.041
11 Extra bar chair " 12 mm 4 1.800 7.200 0.888 0.006
12 Extra Spacer bar " 12 mm 4 1.700 6.800 0.888 0.006
13 Extra anchor bar welded to IP " 10 mm 26 0.600 15.600 0.617 0.010
14 Extra U-bar IP Fixing " 12 mm 8 0.550 4.400 0.888 0.004
15 PS (18) (L= 2.00 m)
16 Top bar (main) " 12 mm 10 1.352 13.520 0.888 0.012
17 Top bar (dist) " 12 mm 6 2.252 13.512 0.888 0.012
18 Bottom bar (main) " 16 mm 10 1.336 13.360 1.58 0.021
19 Bottom bar (dist) " 16 mm 6 2.236 13.416 1.58 0.021
20 vertical " 16 mm 22 1.464 32.208 1.58 0.051
21 binder " 10 mm 3 4.372 13.116 0.617 0.008
22 Extra anchor bar welded to IP " 10 mm 11 0.600 6.600 0.617 0.004
23 Extra U-bar IP Fixing " 12 mm 3 0.550 1.650 0.888 0.001
24 PS (20) (L= 9.00 m)
25 Top bar (main) " 12 mm 45 1.352 60.840 0.888 0.054
26 Top bar (dist) " 12 mm 6 9.252 55.512 0.888 0.049
27 Bottom bar (main) " 16 mm 45 1.336 60.120 1.58 0.095
28 Bottom bar (dist) " 16 mm 6 9.236 55.416 1.58 0.088
29 vertical " 16 mm 92 1.464 134.688 1.58 0.213
30 binder " 10 mm 3 18.372 55.116 0.617 0.034
31 Extra bar chair " 12 mm 9 1.800 16.200 0.888 0.014
32 Extra anchor bar welded to IP " 10 mm 50 0.600 30.000 0.617 0.019
Extra U-bar IP Fixing
33 12 mm 14
" 0.550 7.700 0.888 0.007
34 PS (25) (L= 1.5 m)
35 Top bar (main) " 10 mm 10 1.710 17.100 0.617 0.011
36 Top bar (dist) " 10mm 10 1.710 17.100 0.617 0.011
37 Bottom bar (main) " 12mm 10 1.702 17.020 0.888 0.015
38 Bottom bar (dist) " 12 mm 10 1.702 17.020 0.888 0.015
39 vertical " 16 mm 18 1.702 30.636 1.58 0.048
40 binder " 10 mm 3 3.372 10.116 0.617 0.006
41 Extra anchor bar welded to IP " 10 mm 8 0.600 4.800 0.617 0.003
42 Extra U-bar IP Fixing " 12 mm 2 0.550 1.100 0.888 0.001
PIPE SLEEPER FOUNDATION (SHEET 6
43 OF 11)
44 PS (5) (L= 4.65 m)
45 Top bar (main) " 12 mm 24 1.352 32.448 0.888 0.029
46 Top bar (dist) " 12 mm 6 4.902 29.412 0.888 0.026
47 Bottom bar (main) " 16 mm 24 1.336 32.064 1.58 0.051
48 Bottom bar (dist) " 16 mm 6 4.886 29.316 1.58 0.046
49 vertical " 16 mm 50 2.264 113.200 1.58 0.179
50 binder " 10 mm 7 9.672 67.704 0.617 0.042
51 Extra bar chair " 12 mm 4 1.800 7.200 0.888 0.006
52 Extra Spacer bar " 12 mm 4 1.700 6.800 0.888 0.006
53 Extra anchor bar welded to IP " 10 mm 26 0.600 15.600 0.617 0.010
54 Extra U-bar IP Fixing " 12 mm 8 0.550 4.400 0.888 0.004
55 PS (6) (L= 3.8 m)
56 Top bar (main) " 12 mm 19 1.352 25.688 0.888 0.023
57 Top bar (dist) " 12 mm 6 4.052 24.312 0.888 0.022
58 Bottom bar (main) " 16 mm 19 1.336 25.384 1.58 0.040
59 Bottom bar (dist) " 16 mm 6 4.036 24.216 1.58 0.038
60 vertical " 16 mm 40 2.264 90.560 1.58 0.143
61 binder " 10 mm 7 7.972 55.804 0.617 0.034
62 Extra bar chair " 12 mm 3 1.800 5.400 0.888 0.005
63 Extra Spacer bar " 12 mm 3 1.700 5.100 0.888 0.005
64 Extra anchor bar welded to IP " 10 mm 21 0.600 12.600 0.617 0.008
65 Extra U-bar IP Fixing " 12 mm 5 0.550 2.750 0.888 0.002
66 PS (6A) (L= .95 m)
67 Top bar (main) " 10 mm 10 1.160 11.600 0.617 0.007
68 Top bar (dist) " 10 mm 6 1.710 10.260 0.617 0.006
69 Bottom bar (main) " 12 mm 10 1.152 11.520 0.888 0.010
70 Bottom bar (dist) " 12 mm 6 1.702 10.212 0.888 0.009
71 vertical " 16 mm 12 3.002 36.024 1.58 0.057
72 binder " 10 mm 10 2.272 22.720 0.617 0.014
73 Extra anchor bar welded to IP " 10 mm 5 0.600 3.000 0.617 0.002
74 Extra U-bar IP Fixing " 12 mm 2 0.550 1.100 0.888 0.001
75 PS (7) (L= 2.2 m)
76 Top bar (main) " 12 mm 11 1.352 14.872 0.888 0.013
77 Top bar (dist) " 12 mm 6 2.452 14.712 0.888 0.013
78 Bottom bar (main) " 16 mm 11 1.336 14.696 1.58 0.023
79 Bottom bar (dist) " 16 mm 6 2.436 14.616 1.58 0.023
80 vertical " 16 mm 24 2.264 54.336 1.58 0.086
81 binder " 10 mm 7 4.772 33.404 0.617 0.021
82 Extra anchor bar welded to IP " 10 mm 12 0.600 7.200 0.617 0.004
83 Extra U-bar IP Fixing " 12 mm 3 0.550 1.650 0.888 0.001
84 PS (8,9,12,19,20) (L=1.5 m)
85 Top bar (main) " 10 mm 50 1.710 85.500 0.617 0.053
86 Top bar (dist) " 10 mm 50 1.710 85.500 0.617 0.053
87 Bottom bar (main) " 12 mm 50 1.702 85.100 0.888 0.076
88 Bottom bar (dist) " 12 mm 50 1.702 85.100 0.888 0.076
89 vertical " 16 mm 90 3.002 270.180 1.58 0.427
90 binder " 10 mm 50 3.372 168.600 0.617 0.104
91 Extra anchor bar welded to IP " 10 mm 8 0.600 4.800 0.617 0.003
92 Extra U-bar IP Fixing " 12 mm 2 0.550 1.100 0.888 0.001
93 PS (10) (L= 1.85 m)
94 Top bar (main) " 10 mm 12 1.710 20.520 0.617 0.013
95 Top bar (dist) " 10 mm 10 2.060 20.600 0.617 0.013
96 Bottom bar (main) " 12 mm 12 1.702 20.424 0.888 0.018
97 Bottom bar (dist) " 12 mm 10 2.052 20.520 0.888 0.018
98 vertical " 16 mm 26 2.202 57.252 1.58 0.090
99 binder " 10 mm 6 4.072 24.432 0.617 0.015
100 Extra anchor bar welded to IP " 10 mm 10 0.600 6.000 0.617 0.004
101 Extra U-bar IP Fixing " 12 mm 3 0.550 1.650 0.888 0.001
102 PS (11) (L= 5.2 m)
103 Top bar (main) " 12 mm 26 1.352 35.152 0.888 0.031
104 Top bar (dist) " 12 mm 6 5.452 32.712 0.888 0.029
105 Bottom bar (main) " 16 mm 26 1.336 34.736 1.58 0.055
106 Bottom bar (dist) " 16 mm 6 5.436 32.616 1.58 0.052
107 vertical " 16 mm 54 1.464 79.056 1.58 0.125
108 binder " 10 mm 3 10.772 32.316 0.617 0.020
109 Extra bar chair " 12 mm 5 1.800 9.000 0.888 0.008
110 Extra anchor bar welded to IP " 10 mm 18 0.600 10.800 0.617 0.007
111 Extra U-bar IP Fixing " 12 mm 5 0.550 2.750 0.888 0.002
112 PS (21,22,23,24,25,26) (L= 1.15 m)
113 Top bar (main) " 10 mm 48 1.710 82.080 0.617 0.051
114 Top bar (dist) " 10 mm 60 1.360 81.600 0.617 0.050
115 Bottom bar (main) " 12 mm 48 1.702 81.696 0.888 0.073
116 Bottom bar (dist) " 12 mm 60 1.352 81.120 0.888 0.072
117 vertical " 16 mm 84 3.002 252.168 1.58 0.398
118 binder " 10 mm 60 2.672 160.320 0.617 0.099
119 Extra anchor bar welded to IP " 10 mm 36 0.600 21.600 0.617 0.013
120 Extra U-bar IP Fixing " 12 mm 12 0.550 6.600 0.888 0.006
PIPE SLEEPER FOUNDATION (SHEET 8
121 OF 11)
122 PS (1,2,3) (L= 1.15 m)
123 Top bar (main) " 10 mm 24 1.710 41.040 0.617 0.025
124 Top bar (dist) " 10 mm 30 1.360 40.800 0.617 0.025
125 Bottom bar (main) " 12 mm 24 1.702 40.848 0.888 0.036
126 Bottom bar (dist) " 12 mm 30 1.352 40.560 0.888 0.036
127 vertical " 16 mm 42 3.002 126.084 1.58 0.199
128 binder " 10 mm 21 2.672 56.112 0.617 0.035
129 Extra anchor bar welded to IP " 10 mm 18 0.600 10.800 0.617 0.007
130 Extra U-bar IP Fixing " 12 mm 6 0.550 3.300 0.888 0.003
PIPE SLEEPER FOUNDATION (SHEET 9
131 OF 11)
132 PS (1) (L= 11.4 m)
133 Top bar (main) " 12 mm 57 1.352 77.064 0.888 0.068
134 Top bar (dist) " 12 mm 6 11.652 69.912 0.888 0.062
135 Bottom bar (main) " 16 mm 57 1.336 76.152 1.58 0.120
136 Bottom bar (dist) " 16 mm 6 11.636 69.816 1.58 0.110
137 vertical " 16 mm 116 2.264 262.624 1.58 0.415
138 binder " 10 mm 7 23.172 162.204 0.617 0.100
139 Extra bar chair " 12 mm 11 1.800 19.800 0.888 0.018
140 Extra Spacer bar " 12 mm 11 1.700 18.700 0.888 0.017
141 Extra anchor bar welded to IP " 10 mm 63 0.600 37.800 0.617 0.023
142 Extra U-bar IP Fixing " 12 mm 17 0.550 9.350 0.888 0.008
143 PS (9,10) (L= 2.5 m)
144 Top bar (main) " 12 mm 26 1.352 35.152 0.888 0.031
145 Top bar (dist) " 12 mm 12 2.752 33.024 0.888 0.029
146 Bottom bar (main) " 16 mm 26 1.336 34.736 1.58 0.055
147 Bottom bar (dist) " 16 mm 12 2.736 32.832 1.58 0.052
148 vertical " 16 mm 56 1.589 88.984 1.58 0.141
149 binder " 10 mm 14 5.372 75.208 0.617 0.046
150 Extra bar chair " 12 mm 2 1.800 3.600 0.888 0.003
151 Extra anchor bar welded to IP " 10 mm 26 0.600 15.600 0.617 0.010
152 Extra U-bar IP Fixing " 12 mm 6 0.550 3.300 0.888 0.003
153 FIRE WATER NETWORK
154 Bottom bar (main) " 10 mm 224 1.310 293.440 0.617 0.181
155 Bottom bar (Dis.) " 10 mm 192 1.410 270.720 0.617 0.167
156 vertical " 16 mm 128 1.641 210.048 1.58 0.332
157 vertical " 12 mm 128 1.657 212.096 0.888 0.188
158 Stirrups " 8 mm 549 2.460 1350.540 0.395 0.533
159 Stirrups " 8 mm 549 1.740 955.260 0.395 0.377
160 Extra anchor bar welded to IP " 8 mm 185 0.600 111.000 0.395 0.044
161 Extra U-bar IP Fixing " 12 mm 74 1.100 81.400 0.888 0.072
TOTAL QTY (T) 7.844
Certified that the work is done as per drawings, specifications and instructions. Quantities mentioned above are checked and verified
FOR FFIL FOR IOCL
SIGNATURE SIGNATURE

NAME NAME

DATE DATE

CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B

WORK DESCRIPTION :- COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TAP OFF POINTS-
KHUNTI,JHARKHANDKHUNTI,JHARKHAND.

SECTION/SPREAD :-
WO NO & DATE : 24047898 Dated 14-02-2014 RA BILL No : FFIL/ CIVIL RA-10
CLIENT : INDIAN OIL CORPORATION LIMITED DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA (INDIA) Ltd. MEASUREMENT PERIOD : 01.02.15 – 13.02.15
CALCULATION SHEET

SOR Dimensions
SR. No. Item Description UOM Quantity
No.
SOR
SR. No. Item Description UOM (Thicknes Cutting Total Unit Quantity
No. nos
s/Dia) Length(M) Length(M) Weight/M

1 00540 GENERAL STRUCTURAL STEEL WORK


Supplying,fabricating,erecting,placin
2 00550 g and fixing in position M.S.
structural works.
3 PIPE BRIDGE
4 Bolts TON 32 mm 208 0.875 182.000 5.978 1.243
5 TLF PUMP HOUSE
6 Bolts TON 20 mm 352 0.675 237.600 2.165 0.762
7 CHAIN LINK FENCING
8 Angle posts ISA (50x50x6) TON 6 mm 89 2.600 231.400 4.50 1.041
Intermediate condition ISA (50X50X6)
9 6 mm 50
TON 2.100 105.000 4.50 0.473
10 ISA 45X45X5 TON 5 mm 2 388.00 776.000 3.40 2.638
TOTAL QTY (T) 6.158
Certified that the work is done as per drawings, specifications and instructions. Quantities mentioned above are checked and verified
FOR FFIL FOR IOCL

SIGNATURE SIGNATURE

NAME NAME

DATE DATE

CONTRACT NO-PLCC/KORBA-KHUNTI TOP/M/1308B


WORK DESCRIPTION :- COMBINED STATION WORKS (CSW) FOR CONSTRUCTION OF MARKETING TAP OFF POINTS-
KHUNTI,JHARKHANDKHUNTI,JHARKHAND.

SECTION/SPREAD :-
WO NO & DATE : 24047898 Dated 14-02-2014 RA BILL No : FFIL/ CIVIL RA-10
CLIENT : INDIAN OIL CORPORATION LIMITED DATE : 13.02.2015
CONTRACTOR : M/S FURNACE FABRICA (INDIA) Ltd. MEASUREMENT PERIOD : 01.02.15 – 13.02.15
CALCULATION SHEET
Dimensions
SOR
SR. No. Item Description UOM No of Bolts Per Bolt Quantity
No. Size (mm) Unit Weight
Foundations Foundations Length

1 00540 GENERAL STRUCTURAL STEEL WORK


2 00550 Foundation Bolts
3 PIPE BRIDGE
4 Bolts in P1 Pedestal MT 32 14 8.000 0.875 5.978 0.670
Bolts in P2 Pedestal 32 8 12.000 0.875 5.978 0.574
5 TLF PUMP HOUSE
6 Bolts in Pedestals (P) 20 44 8.000 0.675 2.165 0.762
TOTAL QTY (T) 2.006
Certified that the work is done as per drawings, specifications and instructions. Quantities mentioned above are checked and verified
FOR FFIL FOR IOCL

SIGNATURE SIGNATURE

NAME NAME
DATE DATE
Remarks
Remarks
Remarks
Remarks
Remarks
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
INSPECTION SHEET FOR STRUCTURE ERECTION.
MEASUREMENT PERIOD: 01.02.15 to 13.02.15 AREA : TLF BAYS 1
CALCULATION SHEET
Activity Description : 2 Civil Composite works/00550 Structural Works ….. As per direction of EIC
SOR Item No: 2. CIVIL COMPOSITE WORKS/ 00550
TLF BAYS 1
Total
Eraction Unit weight Quantity
SL NO Drawing no Item Weight Report No
Mark
(Kg) Nos. (Kg)
1 02104-201402 BEAM 02104B2 99.47 1 99.47 22
2 02104-201402 BEAM 02104B3 92.19 1 92.19 22
3 02102-201402 BEAM 02102B3 80.95 1 80.95 22
4 02102-201402 BEAM 02102B4 73.66 1 73.66 22
5 02154-201402 VERTICAL BRACING 02154VB2 91.26 1 91.26 22
6 02156-201402 VERTICAL BRACING 02156VB4 35.94 2 71.88 22
7 02155-201402 VERTICAL BRACING 02155VB1 59.18 1 59.18 22
8 02151-201402 SITE RAFTER 02151SR1 271.36 1 271.36 22
9 02131-201402 HORZINTAL BRACING 02131HB1 26.75 2 53.5 22
10 02132-201402 HORZINTAL BRACING 02132HB2 18.4 1 18.4 22
11 02133-201402 HORZINTAL BRACING 02133HB2 18.57 1 18.57 22
12 02102-201402 BEAM 02102B3 80.95 1 80.95 23
13 02102-201402 BEAM 02102B4 73.66 1 73.66 23
14 02150-201402 BEAM 02102B5 70.61 1 70.61 23
15 02104-201402 BEAM 02104B2 99.47 1 99.47 23
16 02104-201402 BEAM 02104B3 92.19 1 92.19 23
17 02104-201402 BEAM 02104B4 89.15 1 89.15 23
18 02107-201402 BEAM 02107B4 95.98 1 95.98 23
19 02107-201402 BEAM 02107B1 139.1 1 139.1 23
20 02147-201402 RAFTER 02147RA1 854.12 2 1708.24 23
21 02108-201402 FRAME 02108FR1 711.07 1 711.07 23
22 02107-201402 BEAM 02107B6 140.72 1 140.72 23
23 02150-201402 SITE RAFTER 02150SR2 272.38 1 272.38 23
24 02107-201402 BEAM 02107B4 95.98 1 95.98 24
25 02107-201402 BEAM 02107B1 139.1 1 139.1 24
26 02108-201402 FRAME 02108FR1 711.07 1 711.07 24
27 02109-201402 FRAME 02109FR1 715.08 2 1430.16 24
28 02131-201402 HORZINTAL BRACING 02131HB2 26.75 2 53.5 24
29 02130-201402 HORZINTAL BRACING 02130HB2 27.65 4 110.6 24
30 02130-201402 HORZINTAL BRACING 02130HB4 29.21 4 116.84 24
31 02131-201402 HORZINTAL BRACING 02131HB6 28.28 2 56.56 24
32 02131-201402 HORZINTAL BRACING 02131HB4 27.67 2 55.34 24
33 02133-201402 HORZINTAL BRACING 02133HB3 19.59 2 39.18 24
34 02133-201402 HORZINTAL BRACING 02133HB2 18.57 1 18.57 24
35 02131-201402 HORZINTAL BRACING 02131HB1 26.75 1 26.75 24
36 02130-201402 HORZINTAL BRACING 02130HB6 26.75 2 53.5 24
37 02130-201402 HORZINTAL BRACING 02130HB2 27.65 4 110.6 24
38 02130-201402 HORZINTAL BRACING 02130HB4 29.21 4 116.84 24
39 02131-201402 HORZINTAL BRACING 02131HB6 28.28 2 56.56 24A
40 02132-201402 HORZINTAL BRACING 02132HB4 19.42 2 38.84 24A
41 02131-201402 HORZINTAL BRACING 02131HB4 27.67 2 55.34 24A
42 02132-201402 HORZINTAL BRACING 02132HB2 18.40 1 18.4 24A
43 02131-201402 HORZINTAL BRACING 02131HB1 26.75 1 26.75 24A
44 02108-201402 FRAME 02108FR1 711.07 1 711.07 25
45 02109-201402 FRAME 02109FR1 715.08 1 715.08 25
46 02107-201402 BEAM 02107B2 86.43 1 86.43 25
47 02105-201402 BEAM 02105B2 128.84 1 128.84 25
48 02131-201402 HORZINTAL BRACING 02131HB6 28.28 1 28.28 25
49 02132-201402 BEAM 02132HB4 19.42 1 19.42 25
50 02131-201402 HORZINTAL BRACING 02131HB4 27.67 1 27.67 25
51 02130-201402 HORZINTAL BRACING 02130HB3 29.21 3 87.63 25
52 02130-201402 HORZINTAL BRACING 02130HB4 29.21 1 29.21 25
53 02130-201402 HORZINTAL BRACING 02130HB2 27.65 3 82.95 25
54 02131-201402 HORZINTAL BRACING 02131HB1 26.75 2 53.5 25
55 02132-201402 HORZINTAL BRACING 02132HB2 18.40 1 18.4 25
56 02130-201402 HORZINTAL BRACING 02130HB6 26.75 1 26.75 25
57 02133-201402 HORZINTAL BRACING 02133HB1 18.57 1 18.57 25
58 02130-201402 HORZINTAL BRACING 02130HB2 27.65 1 27.65 25A
59 02131-201402 HORZINTAL BRACING 02131HB2 26.75 1 26.75 25A
60 02104-201402 BEAM 02104B2 99.47 3 298.41 26
61 02104-201402 BEAM 02104B3 92.19 3 276.57 26
62 02104-201402 BEAM 02104B4 89.15 3 267.45 26
63 02102-201402 BEAM 02102B3 80.95 3 242.85 26
64 02102-201402 BEAM 02102B4 73.66 3 220.98 26
65 02102-201402 BEAM 02102B5 70.61 3 211.83 26
66 02131-201402 SITE RAFTER 02151SR1 271.36 2 542.72 26
67 02131-201402 HORZINTAL BRACING 02131HB5 28.28 1 28.28 27
68 02131-201402 HORZINTAL BRACING 02133HB3 19.59 1 19.59 27
69 02131-201402 HORZINTAL BRACING 02131HB3 27.67 1 27.67 27
70 02131-201402 HORZINTAL BRACING 02131HB6 28.28 2 56.56 27
71 02133-201402 HORZINTAL BRACING 02133HB3 19.59 1 19.59 27
72 02131-201402 HORZINTAL BRACING 02131HB4 27.67 2 55.34 27
73 02130-201402 HORZINTAL BRACING 02130HB4 29.21 4 116.84 27
74 02130-201402 HORZINTAL BRACING 02130HB2 27.65 4 110.6 27
75 02131-201402 HORZINTAL BRACING 02131HB1 26.75 2 53.5 27
76 02133-201402 HORZINTAL BRACING 02133HB2 18.57 1 18.57 27
77 02131-201402 HORZINTAL BRACING 02131HB2 26.75 1 26.75 27
78 02132-201402 HORZINTAL BRACING 02132HB4 19.42 1 19.42 27
79 02132-201402 HORZINTAL BRACING 02132HB2 18.4 1 18.4 27
80 02130-201402 HORZINTAL BRACING 02130HB6 26.75 1 26.75 27
81 02151-201402 SITE RAFTER 02151SR1 271.36 1 271.36 27
82 02131-201402 HORZINTAL BRACING 02131HB5 28.28 1 28.28 28
83 02132-201402 HORZINTAL BRACING 02132HB3 19.42 1 19.42 28
84 02131-201402 HORZINTAL BRACING 02131HB4 27.67 3 83.01 28
85 02130-201402 HORZINTAL BRACING 02130HB4 29.21 6 175.26 28
86 02130-201402 HORZINTAL BRACING 02130HB3 29.21 2 58.42 28
87 02130-201402 HORZINTAL BRACING 02130HB2 27.65 6 165.9 28
88 02130-201402 HORZINTAL BRACING 02130HB1 27.65 2 55.3 28
89 02130-201402 HORZINTAL BRACING 02130HB5 26.75 1 26.75 28
90 02132-201402 HORZINTAL BRACING 02132HB1 18.4 1 18.4 28
91 02130-201402 HORZINTAL BRACING 02130HB6 26.75 2 53.5 28
92 02131-201402 HORZINTAL BRACING 02131HB6 28.28 3 84.84 28
93 02132-201402 HORZINTAL BRACING 02132HB4 19.42 1 19.42 28
94 02131-201402 HORZINTAL BRACING 02131HB1 26.75 3 80.25 28
95 02132-201402 HORZINTAL BRACING 02132HB2 18.4 1 18.4 28
96 02131-201402 HORZINTAL BRACING 02131HB2 26.75 2 53.5 28
97 02131-201402 HORZINTAL BRACING 02131HB3 27.67 1 27.67 28
98 02133-201402 HORZINTAL BRACING 02133HB3 19.59 2 39.18 28A
99 02133-201402 HORZINTAL BRACING 02133HB2 18.57 2 37.14 28A
100 02131-201402 HORZINTAL BRACING 02131HB6 28.28 1 28.28 29
101 02132-201402 HORZINTAL BRACING 02132HB4 19.42 1 19.42 29
102 02131-201402 HORZINTAL BRACING 02131HB4 27.67 1 27.67 29
103 02130-201402 HORZINTAL BRACING 02130HB4 29.21 2 58.42 29
104 02132-201402 HORZINTAL BRACING 02132HB2 18.4 2 36.8 29
105 02131-201402 HORZINTAL BRACING 02131HB1 26.75 1 26.75 29
106 02132-201402 HORZINTAL BRACING 02132HB2 18.4 1 18.4 29
107 02130-201402 HORZINTAL BRACING 02130HB6 26.75 1 26.75 29
108 02131-201402 HORZINTAL BRACING 02131HB6 28.28 1 28.28 29
109 02133-201402 HORZINTAL BRACING 02133HB3 19.59 1 19.59 29
110 02131-201402 HORZINTAL BRACING 02131HB4 27.67 1 27.67 29
111 02130-201402 HORZINTAL BRACING 02130HB4 29.21 2 58.42 29
112 02130-201402 HORZINTAL BRACING 02130HB2 27.65 2 55.3 29
113 02131-201402 HORZINTAL BRACING 02131HB1 26.75 1 26.75 29
114 02133-201402 HORZINTAL BRACING 02133HB2 18.57 1 18.57 29
115 02131-201402 HORZINTAL BRACING 02131HB2 26.75 1 26.75 29
116 02131-201402 HORZINTAL BRACING 02131HB5 28.28 1 28.28 30
117 02133-201402 HORZINTAL BRACING 02133HB3 19.59 1 19.59 30
118 02131-201402 HORZINTAL BRACING 02131HB3 27.67 1 27.67 30
119 02130-201402 HORZINTAL BRACING 02130HB3 29.21 2 58.42 30
120 02130-201402 HORZINTAL BRACING 02130HB1 27.65 2 55.3 30
121 02130-201402 HORZINTAL BRACING 02130HB5 26.75 1 26.75 30
122 02133-201402 HORZINTAL BRACING 02133HB1 18.57 1 18.57 30
123 02130-201402 HORZINTAL BRACING 02130HB6 26.75 1 26.75 30
124 02131-201402 HORZINTAL BRACING 02131HB5 28.28 1 28.28 30
125 02132-201402 HORZINTAL BRACING 02132HB3 19.42 1 19.42 30
126 02131-201402 HORZINTAL BRACING 02131HB3 27.67 1 27.67 30
127 02130-201402 HORZINTAL BRACING 02130HB3 29.21 2 58.42 30
128 02130-201402 HORZINTAL BRACING 02130HB1 27.65 2 55.3 30
129 02130-201402 HORZINTAL BRACING 02130HB5 26.75 1 26.75 30
130 02132-201402 HORZINTAL BRACING 02132HB1 18.4 1 18.4 30
131 02130-201402 HORZINTAL BRACING 02130HB6 26.75 1 26.75 30
132 02156-201402 VERTICAL BRACING 02156VB4 35.94 2 71.88 31
133 02154-201402 VERTICAL BRACING 02154VB2 91.26 1 91.26 31
134 02155-201402 VERTICAL BRACING 02155VB1 59.18 1 59.18 31
135 02156-201402 VERTICAL BRACING 02156VB4 35.94 2 71.88 31
136 02154-201402 VERTICAL BRACING 02154VB2 91.26 1 91.26 31
137 02155-201402 VERTICAL BRACING 02155VB1 59.18 1 59.18 31
138 02156-201402 VERTICAL BRACING 02156VB4 35.94 2 71.88 31
139 02154-201402 VERTICAL BRACING 02154VB2 91.26 1 91.26 31
140 02155-201402 VERTICAL BRACING 02155VB1 59.18 1 59.18 31
141 02156-201402 VERTICAL BRACING 02156VB4 35.94 2 71.88 31
142 02154-201402 VERTICAL BRACING 02154VB2 91.26 1 91.26 31
143 02155-201402 VERTICAL BRACING 02155VB1 59.18 1 59.18 31
144 02111-201402 COLUMN 02111C1 592.75 2 1185.5 31
145 02117-201402 COLUMN 02117C1 231.45 2 462.9 31
146 02144-201402 PURLIN 02144PU6 106.99 3 320.97 31
147 02107-201402 SITE RAFTER 02107B6 140.72 3 422.16 31A
148 02150-201402 RAFTER 02150SR2 272.38 3 817.14 31A
149 02147-201402 RAFTER 02147RA1 854.12 1 854.12 31A
150 02145-201402 RAFTER 02145RA1 1402.34 1 1402.34 31A
151 02148-201402 RAFTER 02148RA1 905.1 1 905.1 31A
TOTAL WEIGHT (IN MT) 22.183
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME:
DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
CALCULATION SHEET FOR STRUCTURE ERECTION.
MEASUREMENT PERIOD 01.02.15 to 13.02.15 AREA : TLF BAYS 2
CALCULATION SHEET
Activity Description : 2 Civil Composite works/00550 Structural Works ….. As per direction of EIC
SOR Item No: 2. CIVIL COMPOSITE WORKS/ 00550
TLF BAYS 2
Total
Eraction Unit weight Quantity
SL NO Drawing no Item Weight Report No
Mark
(Kg) Nos. (Kg)
1 02131-201402 HORIZONTAL BRACING 02131HB5 28.28 1 28.28 FS-41
2 02133-201402 HORIZONTAL BRACING 02133HB3 19.59 1 19.59 FS-41
3 02131-201402 HORIZONTAL BRACING 02131HB3 27.67 1 27.67 FS-41
4 02130-201402 HORIZONTAL BRACING 02130HB3 29.21 2 58.42 FS-41
5 02130-201402 HORIZONTAL BRACING 02130HB2 27.65 2 55.3 FS-41
6 02131-201402 HORIZONTAL BRACING 02131HB1 26.75 1 26.75 FS-41
7 02133-201402 HORIZONTAL BRACING 02133HB1 18.57 1 18.57 FS-41
8 02131-201402 HORIZONTAL BRACING 02131HB2 26.75 1 26.75 FS-41
9 02131-201402 HORIZONTAL BRACING 02131HB6 28.28 1 28.28 FS-41
10 02133-201402 HORIZONTAL BRACING 02133HB3 19.59 1 19.59 FS-41
11 02131-201402 HORIZONTAL BRACING 02131HB4 27.67 1 27.67 FS-41
12 02130-201402 HORIZONTAL BRACING 02130HB4 29.21 2 58.42 FS-41
13 02131-201402 HORIZONTAL BRACING 02131HB6 28.28 1 28.28 FS-41
14 02132-201402 HORIZONTAL BRACING 02132HB4 19.42 1 19.42 FS-41
15 02131-201402 HORIZONTAL BRACING 02131HB4 27.67 1 27.67 FS-41
16 02130-201402 HORIZONTAL BRACING 02130HB3 29.21 1 29.21 FS-41
17 02130-201402 HORIZONTAL BRACING 02130HB4 29.21 1 29.21 FS-41A
18 02130-201402 HORIZONTAL BRACING 02130HB2 27.65 2 55.3 FS-41A
19 02131-201402 HORIZONTAL BRACING 02131HB1 26.75 1 26.75 FS-41A
20 02132-201402 HORIZONTAL BRACING 02132HB2 18.4 1 18.4 FS-41A
21 02130-201402 HORIZONTAL BRACING 02130HB6 26.75 1 26.75 FS-41A
22 02131-201402 HORIZONTAL BRACING 02131HB6 28.28 1 28.28 FS-41A
23 02132-201402 HORIZONTAL BRACING 02132HB4 19.42 1 19.42 FS-41A
24 02131-201402 HORIZONTAL BRACING 02131HB4 27.67 1 27.67 FS-41A
25 02130-201402 HORIZONTAL BRACING 02130HB4 29.21 1 29.21 FS-41A
26 02130-201402 HORIZONTAL BRACING 02130HB4 29.21 1 29.21 FS-41A
27 02130-201402 HORIZONTAL BRACING 02130HB2 27.65 2 55.3 FS-42
28 02131-201402 HORIZONTAL BRACING 02131HB1 26.75 1 26.75 FS-42
29 02133-201402 HORIZONTAL BRACING 02133HB2 18.57 1 18.57 FS-42
30 02131-201402 HORIZONTAL BRACING 02131HB2 26.75 1 26.75 FS-42
31 02131-201402 HORIZONTAL BRACING 02131HB6 28.28 1 28.28 FS-42
32 02133-201402 HORIZONTAL BRACING 02133HB3 19.59 1 19.59 FS-42
33 02131-201402 HORIZONTAL BRACING 02131HB4 27.67 1 27.67 FS-42
34 02130-201402 HORIZONTAL BRACING 02130HB4 29.21 2 58.42 FS-42
35 02130-201402 HORIZONTAL BRACING 02130HB2 27.65 2 55.3 FS-42
36 02131-201402 HORIZONTAL BRACING 02131HB1 26.75 1 26.75 FS-42
37 02133-201402 HORIZONTAL BRACING 02133HB2 18.57 1 18.57 FS-42
38 02131-201402 HORIZONTAL BRACING 02131HB2 26.75 1 26.75 FS-42
39 02130-201402 HORIZONTAL BRACING 02130HB2 27.65 2 55.3 FS-42
40 02131-201402 HORIZONTAL BRACING 02131HB1 26.75 1 26.75 FS-42
41 02132-201402 HORIZONTAL BRACING 02132HB2 18.4 1 18.4 FS-42
42 02130-201402 HORIZONTAL BRACING 02130HB6 26.75 1 26.75 FS-42 A
43 02131-201402 HORIZONTAL BRACING 02131HB6 28.28 1 28.28 FS-42 A
44 02132-201402 HORIZONTAL BRACING 02132HB4 19.42 1 19.42 FS-42 A
45 02131-201402 HORIZONTAL BRACING 02131HB4 27.67 1 27.67 FS-42 A
46 02130-201402 HORIZONTAL BRACING 02130HB4 29.21 2 58.42 FS-42 A
47 02130-201402 HORIZONTAL BRACING 02130HB2 27.65 2 55.3 FS-42 A
48 02131-201402 HORIZONTAL BRACING 02131HB1 26.75 1 26.75 FS-42 A
49 02132-201402 HORIZONTAL BRACING 02132HB2 18.4 1 18.4 FS-42 A
50 02130-201402 HORIZONTAL BRACING 02130HB6 26.75 1 26.75 FS-42 A
51 02111-201402 COLUMN 02111C1 592.75 1 592.75 FS-43
52 02150-201402 SIDE RUNNER 02150SR2 272.38 1 272.38 FS-43
53 02145-201402 RAFTER 02145RA1 1402.34 1 1402.34 FS-43
54 02148-201402 RAFTER 02148RA1 905.1 1 905.1 FS-43
55 02150-201402 SIDE RUNNER 02150SR2 272.38 1 272.38 FS-43
56 02107-201402 BEAM 02107B6 140.72 1 140.72 FS-43
57 02144-201402 PURLIN 02144PU6 106.99 10 1069.9 FS-43
58 02143-201402 PURLIN 02143PU2 104.83 1 104.83 FS-44
59 02143-201402 PURLIN 02143PU5 108.33 2 216.66 FS-44
60 02144-201402 PURLIN 02144PU2 103.49 1 103.49 FS-44
61 02144-201402 PURLIN 02144PU3 106.99 2 213.98 FS-44
62 02144-201402 PURLIN 02144PU6 106.99 6 641.94 FS-44
63 02144-201402 PURLIN 02144PU1 103.49 1 103.49 FS-44
64 02144-201402 PURLIN 02144PU6 106.99 2 213.98 FS-44
65 02132-201402 HORIZONTAL BRACING 02132HB8 54.06 1 54.06 FS-44
66 02132-201403 HORIZONTAL BRACING 02132HB5 53.64 4 214.56 FS-44
67 02144-201402 PURLIN 02144PU4 108.33 3 324.99 FS-44
68 02143-201402 PURLIN 02143PU1 104.83 1 104.83 FS-44
69 02133-201402 HORIZONTAL BRACING 02133HB5 53.53 1 53.53 FS-44

TOTAL WEIGHT (IN MT) 8.573


Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL
SIGN:

NAME:
DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B

MEASUREMENT SHEET
MEASUREMENT PERIOD: 01/02/2015 TO 13/02/2015 RA BILL NO: FFIL/MECHANICAL COMPOSITE/RA-10
W.O NO & DATE:WORK ORDER NO: 24047898, DATE : 03/01/2014 DATE:13/02/2015
Activity Description :WO item 00020 Khunti Marketing TOP-Piping CSW-Composite Works.
SL. NO. ITEM NO: SOR. NO. DESCRIPTION UOM QTY REMARKS
00010 1.03 Painting of A/G Piping(Product&Water)
MECHANICAL
1 COMPOSITE/1.03 00020 Zinc Ethyl Silicate Primer(1 coat of 65-75 SQM 938.91
Painting of A/G micron )
Piping(Product&W
2 ater) 00030
High build Epoxy MIO Intermediate Paint SQM 373.13
( 1 coats of 100 micron )
Total Quantity (SQM) 1312.04
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME:

DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B

MEASUREMENT SHEET
MEASUREMENT PERIOD: 01/02/2015 TO 13/02/2015 RA BILL NO: FFIL/MECHANICAL COMPOSITE/RA-10
W.O NO & DATE:WORK ORDER NO: 24047898, DATE : 03/01/2014 DATE:13/02/2015
Activity Description :WO item 00020 Khunti Marketing TOP-Piping CSW-Composite Works.
SL. NO. ITEM NO: SOR. NO. DESCRIPTION UOM QTY REMARKS
MECHANICAL
COMPOSITE/1.01
1 00010 Supply & Erection of Structural Steel. MT 1.115
Supply & Erection
of Structural Steel.
Total Quantity (MT) 1.115
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME:

DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
CALCULATION SHEET OF PRIMER PAINTING
MEASUREMENT PERIOD: 01.02.15 to 13.02.15
CALCULATION SHEET
Activity Description : Above ground piping….. As per direction of EIC
SOR Item No: 1.03 Painting of A/G Piping(Product&Water)-00020
SPOOL LENGTH
SL. NO. LINE NO.(SPOOL NO) SIZE AREA (SQ MTR) REMARKS
(M)
1 24-P-5026-11(SP-16) 24 7.400 14.178 F/P/33
2 24-P-5028-11(SP-9) 24 6.040 11.572 F/P/33
3 20-P-5013-11(SP-13) 20 12.579 20.083 F/P/33
4 20-P-5014-11(SP-22) 20 7.800 12.453 F/P/33
5 3-BARE PIPE 3.5 5.930 1.657 F/P/33
6 3-BARE PIPE 3.5 5.870 1.640 F/P/33
7 3-BARE PIPE 3.5 6.250 1.746 F/P/33
8 3-BARE PIPE 3.5 6.120 1.710 F/P/33
9 20-P-5014-11(SP-20) 20 4.500 7.185 F/P/34
10 20-P-5014-11(SP-2) 20 13.424 21.432 F/P/34
11 20-P-5015-11(SP-23) 20 7.000 11.176 F/P/34
12 24-P-5027-11(SP-13) 24 7.240 13.871 F/P/34
13 18-BARE-PIPE 18 11.900 17.099 F/P/34
14 18-BARE-PIPE 18 11.950 17.171 F/P/34
15 12-P-5001-11(SP-17) 12.75 12.398 12.619 F/P/35
16 12-P-5002-11(SP-1) 12.75 4.003 4.074 F/P/35
17 12-P-5002-11(SP-2) 12.75 12.190 12.407 F/P/35
18 20-P-5013-11(SP-8) 20 13.469 21.504 F/P/35
19 20-P-5013-11(SP-14) 20 5.600 8.941 F/P/35
20 20-P-5015-11(SP-21) 20 2.700 4.311 F/P/35
21 4-P-5021-11(SP-41) 4.5 12.000 4.311 F/P/35
22 4-P-5021-11(SP-42) 4.5 12.000 4.311 F/P/35
23 8-BARE PIPE 8.625 11.970 8.242 F/P/35
24 8-BARE PIPE 8.625 11.960 8.235 F/P/35
25 12-BARE PIPE 12.75 11.900 12.112 F/P/35
26 12-BARE PIPE 12.75 12.400 12.621 F/P/35
27 20-P-5013-11(SP-7) 20 12.504 19.964 F/P/36
28 20-P-5013-11(SP-9) 20 12.790 20.420 F/P/36
29 20-P-5014-11(SP-17) 20 13.364 21.337 F/P/36
30 20-P-5015-11(SP-7) 20 12.514 19.979 F/P/36
31 20-P-5015-11(SP-15) 20 12.650 20.197 F/P/36
32 12-P-5002-11(SP31) 12.75 12.270 12.489 F/P/36
33 12-P-5085-11(SP-38) 12.75 12.000 12.214 F/P/36
34 20-P-5010-11(SP-1) 20 6.713 10.718 F/P/37
35 20-P-5012-11(SP-1) 20 6.713 10.718 F/P/37
36 20-P-5013-11(SP-10) 20 2.767 4.418 F/P/37
37 20-P-5014-11(SP-14) 20 2.525 4.031 F/P/37
38 8-P-5016-11(SP-13) 8.625 12.270 8.448 F/P/37
39 8-P-5016-11(SP-17) 8.625 12.280 8.455 F/P/37
40 12-P-5002-11(SP-35) 12.75 12.355 12.575 F/P/37
41 3-DRAIN (HSD)(SP-4) 3.5 13.700 3.828 F/P/37
42 3-P-5133-11(SP-37) 3.5 11.800 3.297 F/P/37
43 3-P-5133-11(SP-43) 3.5 11.790 3.294 F/P/37
44 3-P-5133-11(SP-44) 3.5 11.850 3.311 F/P/37
45 20-BARE-PIPE 20 11.850 18.919 F/P/37
46 20-BARE-PIPE 20 11.860 18.935 F/P/37
47 20-P-5014-11(SP-42) 20 13.374 21.353 F/P/38
48 20-P-5015-11(SP-17) 20 10.840 17.307 F/P/38
49 20-P-5014-11(SP-21) 20 12.040 19.223 F/P/38
50 20-P-5013-11(SP-2) 20 13.399 21.392 F/P/38
51 20-P-5013-11(SP-15) 20 12.680 20.245 F/P/38
52 20-P-5014-11(SP-10) 20 12.474 19.916 F/P/39
53 20-P-5014-11(SP-13) 20 12.560 20.053 F/P/39
54 20-P-5015-11(SP-2) 20 13.404 21.400 F/P/39
55 24-P-5028-11(SP-7) 24 12.522 23.991 F/P/39
56 20-P-5014-11(SP-19) 20 12.484 19.932 F/P/39
57 20-P-5015-11(SP-20) 20 12.434 19.852 F/P/39
58 8-P-5016-11(SP-2) 8.625 12.540 8.634 F/P/40
59 8-P-5087-11(SP-9) 8.625 12.510 8.613 F/P/40
60 12-P-5066-11(SP-4) 12.75 11.218 11.418 F/P/41
61 3-Compressed air line(SP-1) 3.5 11.540 3.224 F/P/41
62 3-Compressed air line(SP-2) 3.5 12.290 3.434 F/P/41
63 3-Compressed air line(SP-3) 3.5 12.310 3.439 F/P/41
64 3-Compressed air line(SP-4) 3.5 12.370 3.456 F/P/41
65 3-Compressed air line(SP-5) 3.5 12.240 3.420 F/P/41
66 3-Compressed air line(SP-7) 3.5 11.950 3.339 F/P/41
67 3-Compressed air line(SP-18) 3.5 12.000 3.353 F/P/41
68 3-Compressed air line(SP-19) 3.5 11.940 3.336 F/P/41
69 3-Compressed air line(SP-20) 3.5 11.800 3.297 F/P/41
70 3-Compressed air line(SP-24) 3.5 11.330 3.166 F/P/41
71 3-Compressed air line(SP-37) 3.5 12.250 3.423 F/P/41
72 4 LINE TO VRS(SP-12) 4.5 11.680 4.196 F/P/41
73 4 LINE TO VRS(SP-13) 4.5 12.890 4.630 F/P/41
74 4 LINE TO VRS(SP-19) 4.5 12.270 4.408 F/P/41
75 4 LINE TO VRS(SP-20) 4.5 12.210 4.386 F/P/41
76 4 LINE TO VRS(SP-28) 4.5 12.210 4.386 F/P/41
77 4 LINE TO VRS(SP-29) 4.5 12.440 4.469 F/P/41
78 4 LINE TO VRS(SP-30) 4.5 12.200 4.383 F/P/41
79 12-P-5085-11(SP-6) 12.75 12.550 12.774 F/P/41
80 20-P-5014-11(SP-7) 20 12.574 20.075 F/P/42
81 12-BARE PIPE 12.75 11.730 11.939 F/P/42
82 12-BARE PIPE 12.75 11.800 12.010 F/P/42
83 12-BARE PIPE 12.75 11.780 11.990 F/P/42
84 12-BARE PIPE 12.75 11.870 12.081 F/P/42
85 8-BARE PIPE 8.625 11.900 8.193 F/P/42
86 8-BARE PIPE 8.625 11.890 8.187 F/P/42
87 8-BARE PIPE 8.625 11.900 8.193 F/P/42
88 8-BARE PIPE 8.625 11.900 8.193 F/P/42
Total Quantity (SQ MTR) 938.914
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified

AGENCY: FFIL IOCL

SIGN:

NAME:
DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B
CALCULATION SHEET OF MIO PAINTING.
MEASUREMENT PERIOD: 01.02.15 to 13.02.15
CALCULATION SHEET
Activity Description : Above ground piping ….. As per direction of EIC
SOR Item No: 1.03 Painting of A/G Piping(Product&Water)-00030
SPOOL LENGTH
SL. NO. LINE NO. SPOOL NO: SIZE AREA (SQ MTR) REMARKS
(M)
1 10-P-5083-11(SP-44) 10.75 12.000 10.298 F/M/09
2 10-P-5083-11(SP-45) 10.75 6.000 5.149 F/M/09
3 10-P-5083-11(SP-47) 10.75 6.000 5.149 F/M/09
4 8-P-5087-11(SP-34) 8.625 12.000 8.262 F/M/09
5 8-P-5087-11(SP-39) 8.625 6.000 4.131 F/M/09
6 8-P-5087-11(SP-40) 8.625 6.000 4.131 F/M/09
7 8-P-5087-11(SP-42) 8.625 12.000 8.262 F/M/09
8 8-P-5087-11(SP-47) 8.625 12.000 8.262 F/M/09
9 18-P-5084-11(SP-48) 18 12.000 17.243 F/M/09
10 18-P-5084-11(SP-49) 18 10.000 14.369 F/M/09
11 18-P-5084-11(SP-53) 18 6.000 8.621 F/M/09
12 12-P-5085-11(SP-39) 12.75 6.000 6.107 F/M/09
13 12-P-5085-11(SP-40) 12.75 6.000 6.107 F/M/09
14 12-P-5085-11(SP-41) 12.75 6.000 6.107 F/M/09
15 12-P-5085-11(SP-46) 12.75 12.000 12.214 F/M/09
16 12-P-5085-11(SP-51) 12.75 12.000 12.214 F/M/09
17 20-BARE-PIPE 20 11.900 18.999 F/M/09
18 20-BARE-PIPE 20 11.800 18.840 F/M/09
19 12-BARE PIPE(2NOS) 12.75 23.460 23.878 F/M/09
20 14-BARE PIPE(2NOS) 14 23.810 26.610 F/M/09
21 20-P-5013-11(SP-8) 20 13.469 21.504 F/M/10
22 20-P-5013-11(SP-9) 20 12.790 20.420 F/M/10
23 24-P-5026-11(SP-16) 24 7.400 14.178 F/M/10
24 24-P-5028-11(SP-9) 24 6.040 11.572 F/M/10
25 20-P-5013-11(SP-13) 20 12.579 20.083 F/M/10
26 20-P-5014-11(SP-22) 20 7.800 12.453 F/M/10
27 3-BARE PIPE 3.5 5.930 1.657 F/M/10
28 3-BARE PIPE 3.5 5.870 1.640 F/M/10
29 3-BARE PIPE 3.5 6.250 1.746 F/M/10
30 3-BARE PIPE 3.5 6.120 1.710 F/M/10
31 8-BARE PIPE 8.625 11.970 8.242 F/M/10
32 8-BARE PIPE 8.625 11.960 8.235 F/M/10
33 12-BARE PIPE 12.75 11.900 12.112 F/M/10
34 12-BARE PIPE 12.75 12.400 12.621 F/M/10
Total Quantity (m) 373.126
Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified

AGENCY: FFIL IOCL

SIGN:

NAME:
DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B

MEASUREMENT SHEET
MEASUREMENT PERIOD: 01.02.15 to 13.02.15 RA BILL NO: FFIL/MECHANICAL SUPPLY/RA BILL-10
W.O NO & DATE:WORK ORDER NO: 24047898, DATE : 03/01/2014 DATE:13.02.2015
Activity Description :WO item 00030 Khunti Marketing TOP-Piping CSW Supply
SL. NO. ITEM NO: SOR. NO. DESCRIPTION UOM QTY REMARKS

00010 SUPPLY OF 20 KL FRP SLOP OIL TANK.


1. MECHANICAL 90% PAYMENT AGAINIST
SUPPLY/ 1.01 FRP SUPPLY
SLOP OIL TANK.
1 00020 20 KL FRP SLOP OIL TANK EA 1

Total Quantity (Nos) 1.000


Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME:
DATE:
FURNACE FABRICA (INDIA) LTD.
CLIENT:M/S IOCL
COMBINED STATION WORKS FOR CONSTRUCTION OF MARKETING TOP - GROUP-B

CALCULATION SHEET
MEASUREMENT PERIOD: 01.02.15 to 13.02.15 RA BILL NO: FFIL/MECHANICAL SUPPLY/RA BILL-10
W.O NO & DATE:WORK ORDER NO: 24047898, DATE : 03/01/2014 DATE:13.02.2015
Activity Description :WO item 00030 Khunti Marketing TOP-Piping CSW Supply
SL. NO. ITEM NO: SOR. NO. DESCRIPTION UOM QTY REMARKS

00010 SUPPLY OF 20 KL FRP SLOP OIL TANK.


1. MECHANICAL 90% PAYMENT AGAINIST
SUPPLY/ 1.01 FRP SUPPLY
SLOP OIL TANK.
1 00020 20 KL FRP SLOP OIL TANK EA 1

Total Quantity (Nos) 1.000


Certified that the work done as per drawing, specification & instruction, Quantity mentioned above are checked and verified
AGENCY: FFIL IOCL

SIGN:

NAME: VISHNU P P J K BHAGAT


DATE:
M
COMBINED STATION WORKS (CSW) FOR CONSTRUCTION
Name of Work B-KHUNTI, JHARKHAND.
Name of Contractor M/S Furnace Fabrica (I) Ltd.
LOA No. 24047898, DATE : 03/01/2014
Attachment of Bill No. & Date RA Bill No – 09 Dated – 31.01.2015
Issue detail
Sr.
Particulars of materials GIV No. & Date UOM
No.

1 PIPE,CS,ERW,API5L,GRB,BE,6IN,7.1 PRRPL-GROUP-B/GIV FF-1 27/05/15 M


2 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 PRRPL-GROUP-B/GIV FF-1 27/05/15 M
3 ELBO,45,LR,BW,CS,A234,WPB,24IN,150 PRRPL-GROUP-B/GIV FF-10, 17/07/14 EA
4 ELBO,90,LR,BW,CS,A234,WPB,18IN,150 PRRPL-GROUP-B/GIV FF-10, 17/07/14 EA
5 ELBO,45,LR,BW,A234,WPB,18IN,STD PRRPL-GROUP-B/GIV FF-10, 17/07/14 EA
6 FL,WN,RF,CS,A105,150,18IN,STD PRRPL-GROUP-B/GIV FF-10, 17/07/14 EA
7 ELBO,90,LR,BW,CS,A234,WPB, 8IN, 150 PRRPL-GROUP-B/GIV FF-10, 17/07/14 EA
8 ELB,45,LR,BW,CS,A234,WPB, 8,STD PRRPL-GROUP-B/GIV FF-10, 17/07/14 EA
9 TEE,EQ,BW,CS,A234,WPB,10IN,STD PRRPL-GROUP-B/GIV FF-10, 17/07/14 EA
10 PIPE,CS,ERW,API5L,GRB,BE,8IN,8.2 PRRPL-GROUP-B/GIV FF-11, 6/08/14 M
11 PIPE,CS,ERW,API5L,GRB,BE,18IN,9.5 PRRPL-GROUP-B/GIV FF-11, 6/08/14 M
12 PIPE,CS,ERW,API5L,GRB,BE,10IN,9.3 PRRPL-GROUP-B/GIV FF-11, 6/08/14 M
13 PIPE,CS,ERW,API5L,GRB,BE,6IN,7.1 PRRPL-GROUP-B/GIV FF-11, 6/08/14 M
14 TEE,EQ,BW,CS,A234,WPB,8IN,150 PRRPL-GROUP-B/GIV FF-11, 6/08/14 EA
15 TEE,EQ,BW,CS,A234,WPB,6IN,STD PRRPL-GROUP-B/GIV FF-11, 6/08/14 EA
16 FL,WN,RF,CS,A105,150,6IN,40 PRRPL-GROUP-B/GIV FF-11, 6/08/14 EA
17 ELBO,45,LR,BW,CS,A234,WPB,6IN,150 PRRPL-GROUP-B/GIV FF-11, 6/08/14 EA
18 TEE,EQ,BW,CS,A234,WPB,12IN,STD PRRPL-GROUP-B/GIV FF-11, 6/08/14 EA
19 PIPE,MS,ERW,IS3589,GR410,BE,6IN 6.35TH PRRPL-GROUP-B/GIV FF-11, 6/08/14 M
20 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 PRRPL-GROUP-B/GIV FF-11, 6/08/14 M
21 PIPE,MS,ERW,IS3589,GR410,BE,16IN,6.35TH PRRPL-GROUP-B/GIV FF-12, 16/08/14 M
22 FL,SO,RF,CS,A105,150,16IN PRRPL-GROUP-B/GIV FF-12, 16/08/14 EA
23 FL,WN,RF,CS,A105,150,6IN,40 PRRPL-GROUP-B/GIV FF-13, 22/08/14 EA
24 FL,WN,RF,CS,A105,150,8IN,STD PRRPL-GROUP-B/GIV FF-13, 22/08/14 EA
25 FL,WN,RF,CS,A105,150,10IN,40 PRRPL-GROUP-B/GIV FF-13, 22/08/14 EA
26 FL,WN,RF,CS,A105,150,12IN,STD PRRPL-GROUP-B/GIV FF-13, 22/08/14 EA
27 ELBOW 90 LR BW CS WPH Y65 12IN 150 PRRPL-GROUP-B/GIV FF-13, 22/08/14 EA
28 ELBO,90,LR,BW,CS,A234,WPB, 6IN, 150 PRRPL-GROUP-B/GIV FF-13, 22/08/14 EA
29 ELBO,90,LR,BW,CS,A234,WPB, 8IN, 150 PRRPL-GROUP-B/GIV FF-13, 22/08/14 EA
30 ELBO,90,LR,BW,CS,A234,WPB, 10IN, 150 PRRPL-GROUP-B/GIV FF-13, 22/08/14 EA
31 TEE,EQ,BW,CS,A234,WPB,8IN,150 PRRPL-GROUP-B/GIV FF-13, 22/08/14 EA
32 TEE,EQ,BW,CS,A234,WPB,10IN,STD PRRPL-GROUP-B/GIV FF-13, 22/08/14 EA
33 TEE,EQ,BW,CS,A234,WPB,12IN,STD PRRPL-GROUP-B/GIV FF-13, 22/08/14 EA
34 ELB,45,LR,BW,CS,A234,WPB,10,STD PRRPL-GROUP-B/GIV FF-14, 22/08/14 EA
35 ELB,45,LR,BW,CS,A234,WPB,12,STD PRRPL-GROUP-B/GIV FF-14, 22/08/14 EA
36 TEE,UNEQ,BW,CS,A234,WPB,10X6 IN,150 PRRPL-GROUP-B/GIV FF-14, 22/08/14 EA
37 TEE,UNEQ,BW,CS,A234,WPB,12X6IN,150 PRRPL-GROUP-B/GIV FF-14, 22/08/14 EA
38 TEE,UNEQ,BW,CS,A234,WPB,12X10IN,150 PRRPL-GROUP-B/GIV FF-14, 22/08/14 EA
39 TEE,UNEQ,BW,CS,A234,WPB,12X8IN,150 PRRPL-GROUP-B/GIV FF-14, 22/08/14 EA
40 RED,CONC,BW,CS,A234,WPB,12x8IN,STD PRRPL-GROUP-B/GIV FF-14, 22/08/14 EA
41 ELBO,45,LR,BW,CS,A234,WPB,6IN,150 PRRPL-GROUP-B/GIV FF-14, 22/08/14 EA
42 ELBO,90,LR,BW,CS,A234,WPB, 16IN, 150 PRRPL-GROUP-B/GIV FF-15, 13/08/14 EA
43 TEE,EQ,BW,CS,A234,WPB,16IN,STD PRRPL-GROUP-B/GIV FF-15, 13/08/14 EA
44 RED,CONC,BW,CS,A234,WPB,16x12IN,STD PRRPL-GROUP-B/GIV FF-15, 13/08/14 EA
45 RED,CONC,BW,CS,A234,WPB,16x10IN,STD PRRPL-GROUP-B/GIV FF-15, 13/08/14 EA
46 PIPE,CS,ERW,API5L,GRB,BE,6IN,7.1 PRRPL-GROUP-B/GIV FF-16, 02/09/14 M
47 PIPE,CS,ERW,API5L,GRB,BE,8IN ,8.2 PRRPL-GROUP-B/GIV FF-16, 02/09/14 M
48 PIPE,CS,ERW,API5L,GRB,BE,10IN,9.3 PRRPL-GROUP-B/GIV FF-16, 02/09/14 M
49 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 PRRPL-GROUP-B/GIV FF-16, 02/09/14 M
50 PIPE,MS,ERW,IS3589,GR410,BE,16IN,6.35TH PRRPL-GROUP-B/GIV FF-16, 02/09/14 M
51 ELBO,45,LR,BW,CS,A234,WPB,24IN,150 PRRPL-GROUP-B/GIV FF-17, 03/09/14 EA
52 TEE,EQ,BW,CS,A234,WPB,24IN,20 PRRPL-GROUP-B/GIV FF-17, 03/09/14 EA
53 UNEQUALTEE,EQ,BW,CS,A234,WPB, 24X14 PRRPL-GROUP-B/GIV FF-17, 03/09/14 EA
54 UNEQUALTEE,EQ,BW,CS,A234,WPB,24X12 PRRPL-GROUP-B/GIV FF-17, 03/09/14 EA
55 UNEQUALTEE,EQ,BW,CS,A234,WPB, 24X8 PRRPL-GROUP-B/GIV FF-17, 03/09/14 EA
56 ELB,45,LR,BW,CS,A234,WPB,10,STD PRRPL-GROUP-B/GIV FF-18, 22/09/14 EA
57 ELBO,90,LR,BW,CS,A234,WPB, 10IN, 150 PRRPL-GROUP-B/GIV FF-18, 22/09/14 EA
58 ELBOW 90 LR BW CS WPH Y65 12IN 150 PRRPL-GROUP-B/GIV FF-18, 22/09/14 EA
59 FL,SO,RF,CS,A105,150,16IN PRRPL-GROUP-B/GIV FF-18, 22/09/14 EA
60 FL,WN,RF,CS,A105,150,24IN,20 PRRPL-GROUP-B/GIV FF-18, 22/09/14 EA
61 FL,WN,RF,CS,A105,150,12IN,STD PRRPL-GROUP-B/GIV FF-18, 22/09/14 EA
62 ELBOW 90 LR BW CS WPH Y65 14IN 150 PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
63 ELBOW 90 LR BW CS WPH Y65 12IN 150 PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
64 ELBO,45,LR,BW,CS,A234,WPB,14IN,150 PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
65 ELB,45,LR,BW,CS,A234,WPB,12,STD PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
66 ELBO,45,LR,BW,CS,A234,WPB,20IN,150 PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
67 ELB,45,LR,BW,CS,A234,WPB,10,STD PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
68 TEE,EQ,BW,CS,A234,WPB,10IN,STD PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
69 TEE,EQ,BW,CS,A234,WPB,12IN,STD PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
70 FL,WN,RF,CS,A105,150,14IN,30/STD PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
71 FL,WN,RF,CS,A105,150,12IN,STD PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
72 FL,WN,RF,CS,A105,150,24IN,20 PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
73 FL,WN,RF,CS,A105,150,20IN,20 PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
74 ELBO,90,LR,BW,CS,A234,WPB, 10IN, 150 PRRPL-GROUP-B/GIV FF-2, 31/05/14 EA
75 ELBO,90,LR,BW,CS,A234,WPB, 8IN, 150 PRRPL-GROUP-B/GIV FF-3, 31/05/14 EA
76 ELB,45,LR,BW,CS,A234,WPB, 8,STD PRRPL-GROUP-B/GIV FF-3, 31/05/14 EA
77 TEE,EQ,BW,CS,A234,WPB,8IN,150 PRRPL-GROUP-B/GIV FF-3, 31/05/14 EA
78 FL,WN,RF,CS,A105,150,8IN,STD PRRPL-GROUP-B/GIV FF-3, 31/05/14 EA
79 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 PRRPL-GROUP-B/GIV FF-4, 06/06/14 M
80 PIPE,CS,ERW,API5L,GRB,BE,8IN ,8.2 PRRPL-GROUP-B/GIV FF-4, 06/06/14 M
81 PIPE,CS,ERW,API5L,GRB,BE,10IN,9.3 PRRPL-GROUP-B/GIV FF-4, 06/06/14 M
82 PIPE,CS,ERW,API5L,GRB,BE,14IN,9.5 PRRPL-GROUP-B/GIV FF-4, 06/06/14 M
83 ELBO,90,LR,BW,CS,A234,WPB, 14IN, 150 PRRPL-GROUP-B/GIV FF-5, 15/06/14 EA
84 ELBO,45,LR,BW,CS,A234,WPB,14IN,150 PRRPL-GROUP-B/GIV FF-5, 15/06/14 EA
85 FL,WN,RF,CS,A105,150,14IN PRRPL-GROUP-B/GIV FF-5, 15/06/14 EA
86 ELBOW 90 LR BW CS WPH Y65 12IN 150 PRRPL-GROUP-B/GIV FF-5, 15/06/14 EA
87 ELB,45,LR,BW,CS,A234,WPB,12,STD PRRPL-GROUP-B/GIV FF-5, 15/06/14 EA
88 FL,WN,RF,CS,A105,150,12IN,STD PRRPL-GROUP-B/GIV FF-5, 15/06/14 EA
89 ELBO,45,LR,BW,CS,A234,WPB,24IN,150 PRRPL-GROUP-B/GIV FF-5, 15/06/14 EA
90 TEE,EQ,BW,CS,A234,WPB,24IN,20 PRRPL-GROUP-B/GIV FF-5, 15/06/14 EA
91 FL,WN,RF,CS,A105,150,24IN,20 PRRPL-GROUP-B/GIV FF-6, 15/06/14 EA
92 ELBO,90,LR,BW,CS,A234,WPB,20IN,150 PRRPL-GROUP-B/GIV FF-6, 15/06/14 EA
93 ELBO,45,LR,BW,CS,A234,WPB,20IN,150 PRRPL-GROUP-B/GIV FF-6, 15/06/14 EA
94 FL,WN,RF,CS,A105,150,20IN,20 PRRPL-GROUP-B/GIV FF-6, 15/06/14 EA
95 ELBO,90,LR,BW,CS,A234,WPB, 10IN, 150 PRRPL-GROUP-B/GIV FF-6, 15/06/14 EA
96 ELB,45,LR,BW,CS,A234,WPB,10,STD PRRPL-GROUP-B/GIV FF-6, 15/06/14 EA
97 TEE,EQ,BW,CS,A234,WPB,10IN,STD PRRPL-GROUP-B/GIV FF-6, 15/06/14 EA
98 FL,WN,RF,CS,A105,150,10IN,20 PRRPL-GROUP-B/GIV FF-6, 15/06/14 EA
99 ELBO,90,LR,BW,CS,A234,WPB, 8IN, 150 PRRPL-GROUP-B/GIV FF-6, 15/06/14 EA
100 ELB,45,LR,BW,CS,A234,WPB, 8,STD PRRPL-GROUP-B/GIV FF-7, 25/06/14 EA
101 FL,WN,RF,CS,A105,150,8IN,STD PRRPL-GROUP-B/GIV FF-7, 25/06/14 EA
102 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 PRRPL-GROUP-B/GIV FF-7, 25/06/14 M
103 PIPE,CS,ERW,API5L,GRB,BE,24IN,9.5 PRRPL-GROUP-B/GIV FF-7, 25/06/14 M
104 ELBO,90,LR,BW,CS,A234,WPB,20IN,150 PRRPL-GROUP-B/GIV FF-7, 25/06/14 EA
105 ELBO,45,LR,BW,CS,A234,WPB,20IN,150 PRRPL-GROUP-B/GIV FF-7, 25/06/14 EA
106 FL,WN,RF,CS,A105,150,20IN,20 PRRPL-GROUP-B/GIV FF-7, 25/06/14 EA
107 PIPE,CS,ERW,API5L,GRB,BE,20IN,9.5 PRRPL-GROUP-B/GIV FF-7, 25/06/14 M
108 PIPE,CS,ERW,API5L,GRB,BE,14IN,9.5 PRRPL-GROUP-B/GIV FF-7, 25/06/14 M
109 PIPE,MS,ERW,IS3589,GR410,BE, 24IN,9.5 PRRPL-GROUP-B/GIV FF-7, 25/06/14 M
110 PIPE,CS,ERW,API5L,GRB,BE,20IN,9.5 PRRPL-GROUP-B/GIV FF-8, 17/07/14 M
111 PIPE,CS,ERW,API5L,GRB,BE,24IN,9.5 PRRPL-GROUP-B/GIV FF-8, 17/07/14 M
112 PIPE,CS,ERW,API5L,GRB,BE,14IN,9.5 PRRPL-GROUP-B/GIV FF-8, 17/07/14 M
113 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 PRRPL-GROUP-B/GIV FF-8, 17/07/14 M
114 ELBO,45,LR,BW,CS,A234,WPB,24IN,150 PRRPL-GROUP-B/GIV FF-8, 17/07/14 EA
115 ELBO,90,LR,BW,CS,A234,WPB,24IN,150 PRRPL-GROUP-B/GIV FF-9, 17/07/14 EA
116 TEE,EQ,BW,CS,A234,WPB,20IN,STD PRRPL-GROUP-B/GIV FF-9, 17/07/14 EA
117 TEE,EQ,BW,CS,A234,WPB,18IN,STD PRRPL-GROUP-B/GIV FF-9, 17/07/14 EA
118 TEE,EQ,BW,CS,A234,WPB,14IN,STD PRRPL-GROUP-B/GIV FF-9, 17/07/14 EA
119 UNEQUALTEE,EQ,BW,CS,A234,WPB,20/14IN,STD PRRPL-GROUP-B/GIV FF-9, 17/07/14 EA
120 UNEQUALTEE,EQ,BW,CS,A234,WPB,20/12IN,STD PRRPL-GROUP-B/GIV FF-9, 17/07/14 EA
121 UNEQUALTEE,EQ,BW,CS,A234,WPB,20/8IN,STD PRRPL-GROUP-B/GIV FF-9, 17/07/14 EA
122 UNEQUALTEE,EQ,BW,CS,A234,WPB,18/12IN,STD PRRPL-GROUP-B/GIV FF-9, 17/07/14 EA
123 UNEQUALTEE,EQ,BW,CS,A234,WPB,18/4IN,STD PRRPL-GROUP-B/GIV FF-9, 17/07/14 EA
124 UNEQUALTEE,EQ,BW,CS,A234,WPB,18/3IN,STD PRRPL-GROUP-B/GIV FF-9, 17/07/14 EA
125 UNEQUALTEE,EQ,BW,CS,A234,WPB,14/12IN,STD PRRPL-GROUP-B/GIV FF-9, 17/07/14 EA
126 PIPE,MS,ERW,IS3589,GR410,BE, 8" IN PRRPL-GROUP-B/GIV FF-19, 21.10.14 M
127 PIPE,MS,ERW,IS3589,GR410,BE, 10" IN PRRPL-GROUP-B/GIV FF-19, 21.10.14 M
128 PIPE,MS,ERW,IS3589,GR410,BE,16IN,6.35TH PRRPL-GROUP-B/GIV FF-19, 21.10.14 M
129 PIPE,CS,ERW,API5L,GRB,BE,14IN,9.5 PRRPL-GROUP-B/GIV FF-19, 21.10.14 M
130 UNEQUALTEE,EQ,BW,CS,A234,WPB,14/6IN,STD PRRPL-GROUP-B/GIV FF-20, 10.10.14 EA
131 UNEQUALTEE,EQ,BW,CS,A234,WPB,14/8IN,STD PRRPL-GROUP-B/GIV FF-20, 10.10.14 EA
132 ELBOW 90 LR BW CS WPH Y65 14IN 150 PRRPL-GROUP-B/GIV FF-20, 10.10.14 EA
133 FL,WN,RF,CS,A105,150,14IN PRRPL-GROUP-B/GIV FF-20, 10.10.14 EA
134 FL,SO,RF,CS,A105,150,8 IN PRRPL-GROUP-B/GIV FF-20, 10.10.14 EA
135 FL,SO,RF,CS,A105,150,10 IN PRRPL-GROUP-B/GIV FF-20, 10.10.14 EA
136 ELB,45,LR,BW,CS,A234,WPB,12,STD PRRPL-GROUP-B/GIV FF-21, 15.10.14 EA
137 ELBOW 45LR BW CS WPH Y65 14IN 150 PRRPL-GROUP-B/GIV FF-21, 15.10.14 EA
138 ELBOW 90 LR BW CS WPH Y65 14IN 150 PRRPL-GROUP-B/GIV FF-21, 15.10.14 EA
139 ELBO,90,LR,BW,CS,A234,WPB,18IN,150 PRRPL-GROUP-B/GIV FF-21, 15.10.14 EA
140 ELBO,45,LR,BW,CS,A234,WPB,18IN,150 PRRPL-GROUP-B/GIV FF-21, 15.10.14 EA
141 FL,WN,RF,CS,A105,150,10IN,40 PRRPL-GROUP-B/GIV FF-21, 15.10.14 EA
142 RED,CONC,BW,CS,A234,WPB 10x8IN,STD PRRPL-GROUP-B/GIV FF-21, 15.10.14 EA
143 FL,SO,RF,CS,A105,150,16IN PRRPL-GROUP-B/GIV FF-21, 15.10.14 EA
144 FL,WN,RF,CS,A105,150,18IN,STD PRRPL-GROUP-B/GIV FF-21, 15.10.14 EA
145 FL,SO,RF,CS,A105,150,16IN PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
146 FL,SO,RF,CS,A105,150,10 IN PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
147 FL,WN,RF,CS,A105,150,12IN,STD PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
148 FL,WN,RF,CS,A105,150,14IN PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
149 FL,WN,RF,CS,A105,150,10IN,40 PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
150 FL,WN,RF,CS,A105,150,6IN,40 PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
151 FL,WN,RF,CS,A105,150,8IN,STD PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
152 TEE,EQ,BW,CS,A234,WPB,24IN,20 PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
153 TEE,EQ,BW,CS,A234,WPB,10IN,STD PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
154 UNEQUALTEE,EQ,BW,CS,A234,WPB,10/4IN,STD PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
155 ELB,45,LR,BW,CS,A234,WPB,12,STD PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
156 ELBO,90,LR,BW,CS,A234,WPB, 10IN, 150 PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
157 ELBO,90,LR,BW,CS,A234,WPB, 6IN, 150 PRRPL-GROUP-B/GIV FF-22, 27.10.14 EA
158 PIPE,CS,ERW,API5L,GRB,BE,6IN,7.1 PRRPL-GROUP-B/GIV FF-26, 19.11.14 M
159 PIPE,CS,ERW,API5L,GRB,BE,8IN ,8.2 PRRPL-GROUP-B/GIV FF-26, 19.11.14 M
160 PIPE,CS,ERW,API5L,GRB,BE,10IN,9.3 PRRPL-GROUP-B/GIV FF-26, 19.11.14 M
161 PIPE,MS,ERW,IS3589,GR410,BE, 10" IN PRRPL-GROUP-B/GIV FF-26, 19.11.14 M

162 PIPE,CS,ERW,API5L,GRB,BE,12IN,.235 PRRPL-GROUP-B/GIV FF-26, 19.11.14 M

163 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 PRRPL-GROUP-B/GIV FF-26, 19.11.14 M


164 PIPE,CS,ERW,API5L,GRB,BE,14IN,9.5 PRRPL-GROUP-B/GIV FF-26, 19.11.14 M
165 PIPE,MS,ERW,IS3589,GR410,BE,16IN,6.35TH PRRPL-GROUP-B/GIV FF-26, 19.11.14 M
166 PIPE,CS,ERW,API5L,GRB,BE,18IN,9.5 PRRPL-GROUP-B/GIV FF-26, 19.11.14 M
167 PIPE,CS,ERW,API5L,GRB,BE,20IN,9.5 PRRPL-GROUP-B/GIV FF-26, 19.11.14 M
168 PIPE,CS,ERW,API5L,GRB,BE,24IN,9.5 PRRPL-GROUP-B/GIV FF-26, 19.11.14 M
169 PIPE,MS,ERW,IS3589,GR410,BE,24IN,9.65TH PRRPL-GROUP-B/GIV FF-26, 19.11.14 M
170 PIPE,MS,ERW,IS3589,GR410,BE,14IN,6.35TH PRRPL-GROUP-B/GIV FF-26, 19.11.14 M
171 ELBO,90,LR,BW,CS,A234,WPB, 6IN, 150 PRRPL-GROUP-B/GIV FF-25, 14.11.14 EA
172 ELBO,45,LR,BW,CS,A234,WPB, 6IN, 150 PRRPL-GROUP-B/GIV FF-25, 14.11.15 EA
173 ELBO,90,LR,BW,CS,A234,WPB, 10IN, 150 PRRPL-GROUP-B/GIV FF-25, 14.11.16 EA
174 ELBO,45,LR,BW,CS,A234,WPB, 12IN, 150 PRRPL-GROUP-B/GIV FF-25, 14.11.17 EA
175 ELBO,45,LR,BW,CS,A234,WPB, 14IN, 150 PRRPL-GROUP-B/GIV FF-25, 14.11.18 EA
176 ELBO,45,LR,BW,CS,A234,WPB, 20IN, 150 PRRPL-GROUP-B/GIV FF-25, 14.11.19 EA
177 FL,SO,RF,CS,A105,150,24 IN PRRPL-GROUP-B/GIV FF-24, 14.11.19 EA
178 FL,SO,RF,CS,A105,150,12 IN PRRPL-GROUP-B/GIV FF-24, 14.11.19 EA
179 FL,WN,RF,CS,A105,150,8IN PRRPL-GROUP-B/GIV FF-25, 14.11.19 EA
180 FL,WN,RF,CS,A105,150,12IN,STD PRRPL-GROUP-B/GIV FF-25, 14.11.19 EA
181 FL,WN,RF,CS,A105,150,14IN PRRPL-GROUP-B/GIV FF-25, 14.11.19 EA
182 FL,WN,RF,CS,A105,150,24IN PRRPL-GROUP-B/GIV FF-25, 14.11.19 EA
183 FL,SO,RF,CS,A105,150,16 IN PRRPL-GROUP-B/GIV FF-25, 14.11.19 EA
184 FL,SO,RF,CS,A105,150,10 IN PRRPL-GROUP-B/GIV FF-25, 14.11.19 EA

185 FL,WN,RF,CS,A105,150,8IN PRRPL-GROUP-B/GIV FF-27, 14.11.19


EA

186 FL,WN,RF,CS,A105,150,10IN PRRPL-GROUP-B/GIV FF-27, 14.11.19


EA

187 FL,WN,RF,CS,A105,150,12IN,STD PRRPL-GROUP-B/GIV FF-27, 14.11.19


EA

188 FL,WN,RF,CS,A105,150,14IN PRRPL-GROUP-B/GIV FF-27, 14.11.19


EA

189 TEE,EQ,BW,CS,A234,WPB,24IN,STD PRRPL-GROUP-B/GIV FF-28, 27.11.14


EA

190 UNEQUALTEE,EQ,BW,CS,A234,WPB,24X16 PRRPL-GROUP-B/GIV FF-28, 27.11.15


EA

191 UNEQUALTEE,EQ,BW,CS,A234,WPB,24X12 PRRPL-GROUP-B/GIV FF-28, 27.11.16


EA

192 UNEQUALTEE,EQ,BW,CS,A234,WPB,24X10 PRRPL-GROUP-B/GIV FF-28, 27.11.17


EA

193 UNEQUALTEE,EQ,BW,CS,A234,WPB,24X8 PRRPL-GROUP-B/GIV FF-28, 27.11.18


EA

194 UNEQUALTEE,EQ,BW,CS,A234,WPB,18X4 PRRPL-GROUP-B/GIV FF-29, 27.11.18


EA

195 UNEQUALTEE,EQ,BW,CS,A234,WPB,12X4 PRRPL-GROUP-B/GIV FF-29, 27.11.19


EA

196 UNEQUALTEE,EQ,BW,CS,A234,WPB,10X4 PRRPL-GROUP-B/GIV FF-29, 27.11.20


EA

197 UNEQUALTEE,EQ,BW,CS,A234,WPB,8X4 PRRPL-GROUP-B/GIV FF-29, 27.11.21


EA

198 UNEQUALTEE,EQ,BW,CS,A234,WPB,12X6 PRRPL-GROUP-B/GIV FF-29, 27.11.22


EA
199 UNEQUALTEE,EQ,BW,CS,A234,WPB,12X8 PRRPL-GROUP-B/GIV FF-29, 27.11.23
EA

200 TEE,EQ,BW,CS,A234,WPB,12IN,STD PRRPL-GROUP-B/GIV FF-29, 27.11.24


EA

201 PRRPL-GROUP-B/GIV FF-29, 27.11.25


FL,SO,RF,CS,A105,150,6 IN EA

202 PRRPL-GROUP-B/GIV FF-29, 27.11.26


FL,SO,RF,CS,A105,150,8 IN EA

203 PIPE,MS,ERW,IS3589,GR410,BE,6IN 6.35TH PRRPL-GROUP-B/GIV FF-29, 27.11.27 M

204 PRRPL-GROUP-B/GIV FF-29, 27.11.28 M


PIPE,MS,ERW,IS3589,GR410,BE, 8" IN

205 UNEQUALTEE,EQ,BW,CS,A234,WPB,12X6 PRRPL-GROUP-B/GIV FF-29, 27.11.29


EA

Contractors Signature
M/S INDIAN OIL CORPORATION LIMITED
MATERIAL ISSUE STATEMENT
W) FOR CONSTRUCTION OF MARKETING TAP OFF POINTS GROUP-

il Return detail Previous Bills RAB- 8


Actual Actual
Qty. in Qty. in Net Issue Actual
GRV No. & Date Consump. Consump.
M /NOS M Qty. Consump. M
Nos. M
11.760 - - 11.760 0.000 0
11.880 - - 11.880 11.880 0
4 - - 4.000 0 4
2 - - 2.000 0 2
1 - - 1.000 0 1
1 - - 1.000 0 1
5 - - 5.000 0 5
5 - - 5.000 0 4
11 - - 11.000 0 11
297.55 - - 297.550 283.700 0 13.850
117.91 - - 117.910 16.500 0 101.410
178.38 - - 178.380 178.380 0
235.68 - - 235.680 223.000 0 12.680
6 - - 6.000 0 6
3 - - 3.000 0 3
3 - - 3.000 0 3
3 - - 3.000 0 3
5 - - 5.000 0 5
5.95 - - 5.950 0.000 0
118.79 - - 118.790 118.790 0
564.38 - - 564.380 564.38 0
100.000 - - 100.000 0 100
3 - - 3.000 0 3
19 - - 19.000 0 19
14 - - 14.000 0 14
49 - - 49.000 0 49
3 - - 3.000 0 3
13 - - 13.000 0 13
17 - - 17.000 0 8
6 - - 6.000 0 6
15 - - 15.000 0 3
10 - - 10.000 0 10
30 - - 30.000 0 30
2 - - 2.000 0 2
3 - - 3.000 0 3
3 - - 3.000 0 3
3 - - 3.000 0 3
5 - - 5.000 0 3
4 - - 4.000 0 2
9 - - 9.000 0 9
5 - - 5.000 0 0
41 - - 41.000 0 0
18 - - 18.000 0 13
15 - - 15.000 0 0
10 - - 10.000 0 0
118.06 - - 118.060 0.000 0
119.02 - - 119.020 30.000 0 49.800
238.12 - - 238.120 134 0 30.900
358.06 - - 358.060 264.640 0 93.420
637.49 - - 637.490 637.49 0
11 - - 11.000 0 11
2 - - 2.000 0 2
18 - - 18.000 0 18
7 - - 7.000 0 7
3 - - 3.000 0 3
3 - - 3.000 0 3
3 - - 3.000 0 3
9 - - 9.000 0 7
50 - - 50.000 0 50
5 - - 5.000 0 4
10 - - 10.000 0 10
13.000 - - 13.000 0 13
21.000 - - 21.000 0 21
37.000 - - 37.000 0 37
20.000 - - 20.000 0 20
6.000 - - 6.000 0 6
7.000 - - 7.000 0 7
2.000 - - 2.000 0 2
6.000 - - 6.000 0 6
3.000 - - 3.000 0 3
2.000 - - 2.000 0 2
3.000 - - 3.000 0 3
2.000 - - 2.000 0 2
6.000 - - 6.000 0 6
13.000 - - 13.000 0 13
7.000 - - 7.000 0 7
3.000 - - 3.000 0 3
1.000 - - 1.000 0 1
178.540 - - 178.540 178.540 0
178.600 - - 178.600 178.600 0
178.300 - - 178.300 178.3 0
179.140 - - 179.140 179.140 0
7.000 - - 7.000 0 7
7.000 - - 7.000 0 7
15.000 - - 15.000 0 15
1.000 - - 1.000 0 1
3.000 - - 3.000 0 3
45.000 - - 45.000 0 44
3.000 - - 3.000 0 3
3.000 - - 3.000 0 3
15.000 - - 15.000 0 14
3.000 - - 3.000 0 3
3.000 - - 3.000 0 3
16.000 - - 16.000 0 6
1.000 - - 1.000 0 1
1.000 - - 1.000 0 1
1.000 - - 1.000 0 1
16.000 - - 16.000 0 16
5.000 - - 5.000 0 5
5.000 - - 5.000 0 5
17.000 - - 17.000 0 17
178.590 - - 178.590 178.590 0
69.900 - - 69.900 69.900 0
15.000 - - 15.000 0 12
15.000 - - 15.000 0 15
16.000 - - 16.000 0 13
118.820 - - 118.820 118.820 0
298.750 - - 298.750 298.750 0
71.500 - - 71.500 0.000 0
1,044.130 - - 1,044.130 498.414 0
485.520 - - 485.520 424.900 0 60.620
59.540 - - 59.540 59.540 0
119.260 - - 119.260 119.260 0
3.000 - - 3.000 0 3
20.000 - - 20.000 0 12
12.000 - - 12.000 0 7
1.000 - - 1.000 0 0
37.000 - - 37.000 0 33
15.000 - - 15.000 0 15
6.000 - - 6.000 0 6
4.000 - - 4.000 0 3
7.000 - - 7.000 0 6
15.000 - - 15.000 0 2
1.000 - - 1.000 0 1
13.000 - - 13.000 0 12
60.38 - - 60.380 60.38 0
419.65 - - 419.650 419.65 0
477.96 - - 477.960 477.96 0
721.61 - - 721.610 498.5 0 147.200

4 - - 4.000 0 3

8 - - 8.000 0 6

5 - - 5.000 0 5

25 - - 25.000 0 25

12 - - 12.000 0 5

30 - - 30.000 0 30

3 - - 3.000 0 3
4 - - 4.000 0 3

10 - - 10.000 0 9

1 - - 1.000 0 1

1 - - 1.000 0 0

9 - - 9.000 0 9

3 - - 3.000 0 0

17 - - 17.000 0 17

7 - - 7.000 0 5

15 - - 15.000 0 15

25 - - 25.000 0 25
18 - - 18.000 0 0
23 - - 23.000 0 23
21 - - 21.000 0 3
7 - - 7.000 0 1
5 - - 5.000 0 5
1 - - 1.000 0 0
2 - - 2.000 0 2
2 - - 2.000 0 0
1 - - 1.000 0 1
2 - - 2.000 0 2
5 - - 5.000 0 0
436.04 - - 436.040 0 0
511.15 - - 511.150 0 0
413.84 - - 413.840 0 0
829.39 - - 829.390 0 41
PRRPL-GROUP-B/GRV
650 94.21 555.790 0 0 31.2
FF/R-01, 14.1.15
1342.48 - - 1,342.480 0 129 31.2
648.5 - - 648.500 0 0
790.66 - - 790.660 0 70 56.791
283.73 - - 283.730 0 0 10.4
190.17 - - 190.170 0 0
506.14 - - 506.140 0 0 9.755
225.155 - - 225.155 0 65 38.1
54.95 - - 54.950 0 0
6 - - 6.000 0 0
1 - - 1.000 0 0
3 - - 3.000 0 3
1 - - 1.000 0 1
6 - - 6.000 0 6
3 - - 3.000 0 0
15 - - 15.000 0 7
40 - - 40.000 0 26
5 - - 5.000 0 0
3 - - 3.000 0 0
10 - - 10.000 0 0
3 - - 3.000 0 0
5 - - 5.000 0 0
10 - - 10.000 0 0

- - 20.000 0 0
20

- - 16.000 0 0
16

- - 49.000 0 0
49

- - 60.000 0 1
60

- - 5.000 0 0
5

- - 3.000 0 0
3

- - 14.000 0 0
14

- - 4.000 0 0
4

- - 3.000 0 0
3

- - 3.000 0 0
3

- - 8.000 0 0
8

- - 4.000 0 0
4

- - 6.000 0 0
6

- - 2.000 0 0
2
- - 1.000 0 0
1

- - 2.000 0 0
2

- - 6.000 0 0
6

- - 2.000 0 0
2
35.65 - - 35.650 21

12.04 - - 12.040 10

- - 4.000 0 0
4
6402.004 1456.000 687.326
Site Eng
RAB- 8 RAB- 9 RAB- 10
Actual Actual Actual
Actual Actual
Consump. Consump. Consump. Balance Qty. Remarks
Consump. M Consump. M
Nos. Nos. Nos.
11.760
0.000
0.000
0.000
0.000
0.000
0.000
1.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
5.950
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
6 3.000
0.000
12.000
0.000
0.000
0.000
0.000
0.000
0.000
2.000
2.000
0.000
5.000
41.000
5.000
15.000
10.000
118.060
39.220
32 41.085
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
1 1 0.000
0.000
1.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0 0.000
0.000
0.000
0.000
0.000
1 0.000
0.000
0.000
1.000
0.000
0.000
10.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
3.000
0.000
3.000
0.000
0.000
71.500
152 393.696
0.000
0.000
0.000
0.000
8.000
5.000
1.000
4.000
0.000
0.000
1.000
1.000
13 0.000
0.000
1.000
0.000
0.000
0.000
75.910 0.000
1.000
2.000
0.000
0.000
7.000
0.000
0.000
1 0.000
1 0.000
0.000
1.000
0.000
3.000
0.000
1 1.000
0.000
0.000
12 6 0.000
0.000
7 11.000
6.000
0.000
1 0.000
0.000
2.000
0.000
0.000
5 0.000
436.040
155 355.950
413.840
829.390

46 478.510

112 1199.634
59.520 9 579.522
733.869
273.330
190.170
55.365 441.020
187.055
54.950
2 4.000
1.000
0.000
0.000
0.000
3.000
8.000
14.000
5 0.000
3 0.000
10 0.000
3.000
5 0.000
10.000

20.000

16.000

3 46.000

7 9 4 39.000

5.000

2 1.000

14 0.000

2 2.000

2 1.000

3 0.000

8 0.000

4 0.000

6 0.000

2 0.000
1.000

2.000

6 0.000

2 0.000

14.650

2.040

4 0.000

77.000 269.010 17.000 7216.241


Site Engineer / Engineer-In-Charge
M/S INDIAN OIL CORPORATIO
MATERIAL RECOVERY STAT
COMBINED STATION WORKS (CSW) FOR CONSTRUC
Name of Work
JHARKHAND.
Name of Contractor M/S Furnace Fabrica (I) Ltd.
LOA No. 24047898, DATE : 03/01/2014
Attachment of Bill No. & Date RA Bill No – 09 Dated –31.01.2015

Sr. Recovery
Particulars of materials UOM Issued Qty.
No. Rate
1 PIPE,CS,ERW,API5L,GRB,BE,6IN,7.1 M 11.76 -
2 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 M 11.88 -
3 ELBO,45,LR,BW,CS,A234,WPB,24IN,150 EA 4 -
4 ELBO,90,LR,BW,CS,A234,WPB,18IN,150 EA 2 -
5 ELBO,45,LR,BW,A234,WPB,18IN,STD EA 1 -
6 FL,WN,RF,CS,A105,150,18IN,STD EA 1 -
7 ELBO,90,LR,BW,CS,A234,WPB, 8IN, 150 EA 5 -
8 ELB,45,LR,BW,CS,A234,WPB, 8,STD EA 5 -
9 TEE,EQ,BW,CS,A234,WPB,10IN,STD EA 11 -
10 PIPE,CS,ERW,API5L,GRB,BE,8IN,8.2 M 297.55 -
11 PIPE,CS,ERW,API5L,GRB,BE,18IN,9.5 M 117.91 -
12 PIPE,CS,ERW,API5L,GRB,BE,10IN,9.3 M 178.38 -
13 PIPE,CS,ERW,API5L,GRB,BE,6IN,7.1 M 235.68 -
14 TEE,EQ,BW,CS,A234,WPB,8IN,150 EA 6 -
15 TEE,EQ,BW,CS,A234,WPB,6IN,STD EA 3 -
16 FL,WN,RF,CS,A105,150,6IN,40 EA 3 -
17 ELBO,45,LR,BW,CS,A234,WPB,6IN,150 EA 3 -
18 TEE,EQ,BW,CS,A234,WPB,12IN,STD EA 5 -
19 PIPE,MS,ERW,IS3589,GR410,BE,6IN 6.35TH M 5.95 -
20 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 M 118.79 -
21 PIPE,MS,ERW,IS3589,GR410,BE,16IN,6.35TH M 564.38 -
22 FL,SO,RF,CS,A105,150,16IN EA 100 -
23 FL,WN,RF,CS,A105,150,6IN,40 EA 3 -
24 FL,WN,RF,CS,A105,150,8IN,STD EA 19 -
25 FL,WN,RF,CS,A105,150,10IN,40 EA 14 -
26 FL,WN,RF,CS,A105,150,12IN,STD EA 49 -
27 ELBOW 90 LR BW CS WPH Y65 12IN 150 EA 3 -
28 ELBO,90,LR,BW,CS,A234,WPB, 6IN, 150 EA 13 -
29 ELBO,90,LR,BW,CS,A234,WPB, 8IN, 150 EA 17 -
30 ELBO,90,LR,BW,CS,A234,WPB, 10IN, 150 EA 6 -
31 TEE,EQ,BW,CS,A234,WPB,8IN,150 EA 15 -
32 TEE,EQ,BW,CS,A234,WPB,10IN,STD EA 10 -
33 TEE,EQ,BW,CS,A234,WPB,12IN,STD EA 30 -
34 ELB,45,LR,BW,CS,A234,WPB,10,STD EA 2 -
35 ELB,45,LR,BW,CS,A234,WPB,12,STD EA 3 -
36 TEE,UNEQ,BW,CS,A234,WPB,10X6 IN,150 EA 3 -
37 TEE,UNEQ,BW,CS,A234,WPB,12X6IN,150 EA 3 -
38 TEE,UNEQ,BW,CS,A234,WPB,12X10IN,150 EA 5 -
39 TEE,UNEQ,BW,CS,A234,WPB,12X8IN,150 EA 4 -
40 RED,CONC,BW,CS,A234,WPB,12x8IN,STD EA 9 -
41 ELBO,45,LR,BW,CS,A234,WPB,6IN,150 EA 5 -
42 ELBO,90,LR,BW,CS,A234,WPB, 16IN, 150 EA 41 -
43 TEE,EQ,BW,CS,A234,WPB,16IN,STD EA 18 -
44 RED,CONC,BW,CS,A234,WPB,16x12IN,STD EA 15 -
45 RED,CONC,BW,CS,A234,WPB,16x10IN,STD EA 10 -
46 PIPE,CS,ERW,API5L,GRB,BE,6IN,7.1 M 118.06 -
47 PIPE,CS,ERW,API5L,GRB,BE,8IN ,8.2 M 119.02 -
48 PIPE,CS,ERW,API5L,GRB,BE,10IN,9.3 M 238.12 -
49 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 M 358.06 -
50 PIPE,MS,ERW,IS3589,GR410,BE,16IN,6.35TH M 637.49 -
51 ELBO,45,LR,BW,CS,A234,WPB,24IN,150 EA 11 -
52 TEE,EQ,BW,CS,A234,WPB,24IN,20 EA 2 -
53 UNEQUALTEE,EQ,BW,CS,A234,WPB, 24X14 EA 18 -
54 UNEQUALTEE,EQ,BW,CS,A234,WPB,24X12 EA 7 -
55 UNEQUALTEE,EQ,BW,CS,A234,WPB, 24X8 EA 3 -
56 ELB,45,LR,BW,CS,A234,WPB,10,STD EA 3 -
57 ELBO,90,LR,BW,CS,A234,WPB, 10IN, 150 EA 3 -
58 ELBOW 90 LR BW CS WPH Y65 12IN 150 EA 9 -
59 FL,SO,RF,CS,A105,150,16IN EA 50 -
60 FL,WN,RF,CS,A105,150,24IN,20 EA 5 -
61 FL,WN,RF,CS,A105,150,12IN,STD EA 10 -
62 ELBOW 90 LR BW CS WPH Y65 14IN 150 EA 13 -
63 ELBOW 90 LR BW CS WPH Y65 12IN 150 EA 21 -
64 ELBO,45,LR,BW,CS,A234,WPB,14IN,150 EA 37 -
65 ELB,45,LR,BW,CS,A234,WPB,12,STD EA 20 -
66 ELBO,45,LR,BW,CS,A234,WPB,20IN,150 EA 6 -
67 ELB,45,LR,BW,CS,A234,WPB,10,STD EA 7 -
68 TEE,EQ,BW,CS,A234,WPB,10IN,STD EA 2 -
69 TEE,EQ,BW,CS,A234,WPB,12IN,STD EA 6 -
70 FL,WN,RF,CS,A105,150,14IN,30/STD EA 3 -
71 FL,WN,RF,CS,A105,150,12IN,STD EA 2 -
72 FL,WN,RF,CS,A105,150,24IN,20 EA 3 -
73 FL,WN,RF,CS,A105,150,20IN,20 EA 2 -
74 ELBO,90,LR,BW,CS,A234,WPB, 10IN, 150 EA 6 -
75 ELBO,90,LR,BW,CS,A234,WPB, 8IN, 150 EA 13 -
76 ELB,45,LR,BW,CS,A234,WPB, 8,STD EA 7 -
77 TEE,EQ,BW,CS,A234,WPB,8IN,150 EA 3 -
78 FL,WN,RF,CS,A105,150,8IN,STD EA 1 -
79 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 M 178.54 -
80 PIPE,CS,ERW,API5L,GRB,BE,8IN ,8.2 M 178.6 -
81 PIPE,CS,ERW,API5L,GRB,BE,10IN,9.3 M 178.3 -
82 PIPE,CS,ERW,API5L,GRB,BE,14IN,9.5 M 179.14 -
83 ELBO,90,LR,BW,CS,A234,WPB, 14IN, 150 EA 7 -
84 ELBO,45,LR,BW,CS,A234,WPB,14IN,150 EA 7 -
85 FL,WN,RF,CS,A105,150,14IN EA 15 -
86 ELBOW 90 LR BW CS WPH Y65 12IN 150 EA 1 -
87 ELB,45,LR,BW,CS,A234,WPB,12,STD EA 3 -
88 FL,WN,RF,CS,A105,150,12IN,STD EA 45 -
89 ELBO,45,LR,BW,CS,A234,WPB,24IN,150 EA 3 -
90 TEE,EQ,BW,CS,A234,WPB,24IN,20 EA 3 -
91 FL,WN,RF,CS,A105,150,24IN,20 EA 15 -
92 ELBO,90,LR,BW,CS,A234,WPB,20IN,150 EA 3 -
93 ELBO,45,LR,BW,CS,A234,WPB,20IN,150 EA 3 -
94 FL,WN,RF,CS,A105,150,20IN,20 EA 16 -
95 ELBO,90,LR,BW,CS,A234,WPB, 10IN, 150 EA 1 -
96 ELB,45,LR,BW,CS,A234,WPB,10,STD EA 1 -
97 TEE,EQ,BW,CS,A234,WPB,10IN,STD EA 1 -
98 FL,WN,RF,CS,A105,150,10IN,20 EA 16 -
99 ELBO,90,LR,BW,CS,A234,WPB, 8IN, 150 EA 5 -
100 ELB,45,LR,BW,CS,A234,WPB, 8,STD EA 5 -
101 FL,WN,RF,CS,A105,150,8IN,STD EA 17 -
102 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 M 178.59 -
103 PIPE,CS,ERW,API5L,GRB,BE,24IN,9.5 M 69.9 -
104 ELBO,90,LR,BW,CS,A234,WPB,20IN,150 EA 15 -
105 ELBO,45,LR,BW,CS,A234,WPB,20IN,150 EA 15 -
106 FL,WN,RF,CS,A105,150,20IN,20 EA 16 -
107 PIPE,CS,ERW,API5L,GRB,BE,20IN,9.5 M 118.82 -
108 PIPE,CS,ERW,API5L,GRB,BE,14IN,9.5 M 298.75 -
109 PIPE,MS,ERW,IS3589,GR410,BE, 24IN,9.5 M 71.5 -
110 PIPE,CS,ERW,API5L,GRB,BE,20IN,9.5 M 1044.13 -
111 PIPE,CS,ERW,API5L,GRB,BE,24IN,9.5 M 485.52 -
112 PIPE,CS,ERW,API5L,GRB,BE,14IN,9.5 M 59.54 -
113 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 M 119.26 -
114 ELBO,45,LR,BW,CS,A234,WPB,24IN,150 EA 3 -
115 ELBO,90,LR,BW,CS,A234,WPB,24IN,150 EA 20 -
116 TEE,EQ,BW,CS,A234,WPB,20IN,STD EA 12 -
117 TEE,EQ,BW,CS,A234,WPB,18IN,STD EA 1 -
118 TEE,EQ,BW,CS,A234,WPB,14IN,STD EA 37 -
119 UNEQUALTEE,EQ,BW,CS,A234,WPB,20/14IN,STD EA 15 -
120 UNEQUALTEE,EQ,BW,CS,A234,WPB,20/12IN,STD EA 6 -
121 UNEQUALTEE,EQ,BW,CS,A234,WPB,20/8IN,STD EA 4 -
122 UNEQUALTEE,EQ,BW,CS,A234,WPB,18/12IN,STD EA 7 -
123 UNEQUALTEE,EQ,BW,CS,A234,WPB,18/4IN,STD EA 15 -
124 UNEQUALTEE,EQ,BW,CS,A234,WPB,18/3IN,STD EA 1 -
125 UNEQUALTEE,EQ,BW,CS,A234,WPB,14/12IN,STD EA 13 -
126 PIPE,MS,ERW,IS3589,GR410,BE, 8" IN EA 60.38 -
127 PIPE,MS,ERW,IS3589,GR410,BE, 10" IN EA 419.65 -
128 PIPE,MS,ERW,IS3589,GR410,BE,16IN,6.35TH EA 477.96 -
129 PIPE,CS,ERW,API5L,GRB,BE,14IN,9.5 EA 721.61 -
130 UNEQUALTEE,EQ,BW,CS,A234,WPB,14/6IN,STD EA 4 -
131 UNEQUALTEE,EQ,BW,CS,A234,WPB,14/8IN,STD EA 8 -
132 ELBOW 90 LR BW CS WPH Y65 14IN 150 EA 5 -
133 FL,WN,RF,CS,A105,150,14IN EA 25 -
134 FL,SO,RF,CS,A105,150,8 IN EA 12 -
135 FL,SO,RF,CS,A105,150,10 IN EA 30 -
136 ELB,45,LR,BW,CS,A234,WPB,12,STD EA 3 -
137 ELBOW 45LR BW CS WPH Y65 14IN 150 EA 4 -
138 ELBOW 90 LR BW CS WPH Y65 14IN 150 EA 10 -
139 ELBO,90,LR,BW,CS,A234,WPB,18IN,150 EA 1 -
140 ELBO,45,LR,BW,CS,A234,WPB,18IN,150 EA 1 -
141 FL,WN,RF,CS,A105,150,10IN,40 EA 9 -
142 RED,CONC,BW,CS,A234,WPB 10x8IN,STD EA 3 -
143 FL,SO,RF,CS,A105,150,16IN EA 17 -
144 FL,WN,RF,CS,A105,150,18IN,STD EA 7 -
145 FL,SO,RF,CS,A105,150,16IN EA 15 -
146 FL,SO,RF,CS,A105,150,10 IN EA 25 -
147 FL,WN,RF,CS,A105,150,12IN,STD EA 18 -
148 FL,WN,RF,CS,A105,150,14IN EA 23 -
149 FL,WN,RF,CS,A105,150,10IN,40 EA 21 -
150 FL,WN,RF,CS,A105,150,6IN,40 EA 7 -
151 FL,WN,RF,CS,A105,150,8IN,STD EA 5 -
152 TEE,EQ,BW,CS,A234,WPB,24IN,20 EA 1 -
153 TEE,EQ,BW,CS,A234,WPB,10IN,STD EA 2 -
154 UNEQUALTEE,EQ,BW,CS,A234,WPB,10/4IN,STD EA 2 -
155 ELB,45,LR,BW,CS,A234,WPB,12,STD EA 1 -
156 ELBO,90,LR,BW,CS,A234,WPB, 10IN, 150 EA 2 -
157 ELBO,90,LR,BW,CS,A234,WPB, 6IN, 150 EA 5 -
158 PIPE,CS,ERW,API5L,GRB,BE,6IN,7.1 M 436.04 -
159 PIPE,CS,ERW,API5L,GRB,BE,8IN ,8.2 M 511.15 -
160 PIPE,CS,ERW,API5L,GRB,BE,10IN,9.3 M 413.84 -
161 PIPE,MS,ERW,IS3589,GR410,BE, 10" IN M 829.39 -
162 PIPE,CS,ERW,API5L,GRB,BE,12IN,9.5 M 555.79 -
163 PIPE,CS,ERW,API5L,GRB,BE,12IN,.235 M 1342.48 -
164 PIPE,CS,ERW,API5L,GRB,BE,14IN,9.5 M 648.5 -
165 PIPE,MS,ERW,IS3589,GR410,BE,16IN,6.35TH M 790.66 -
166 PIPE,CS,ERW,API5L,GRB,BE,18IN,9.5 M 283.73 -
167 PIPE,CS,ERW,API5L,GRB,BE,20IN,9.5 M 190.17 -
168 PIPE,CS,ERW,API5L,GRB,BE,24IN,9.5 M 506.14 -
169 PIPE,MS,ERW,IS3589,GR410,BE,24IN,9.65TH M 225.155 -
170 PIPE,MS,ERW,IS3589,GR410,BE,14IN,6.35TH M 54.95 -
171 ELBO,90,LR,BW,CS,A234,WPB, 6IN, 150 EA 6 -
172 ELBO,45,LR,BW,CS,A234,WPB, 6IN, 150 EA 1 -
173 ELBO,90,LR,BW,CS,A234,WPB, 10IN, 150 EA 3 -
174 ELBO,45,LR,BW,CS,A234,WPB, 12IN, 150 EA 1 -
175 ELBO,45,LR,BW,CS,A234,WPB, 14IN, 150 EA 6 -
176 ELBO,45,LR,BW,CS,A234,WPB, 20IN, 150 EA 3 -
177 FL,SO,RF,CS,A105,150,24 IN EA 15 -
178 FL,SO,RF,CS,A105,150,12 IN EA 40 -
179 FL,WN,RF,CS,A105,150,8IN EA 5 -
180 FL,WN,RF,CS,A105,150,12IN EA 3 -
181 FL,WN,RF,CS,A105,150,14IN EA 10 -
182 FL,WN,RF,CS,A105,150,24IN EA 3 -
183 FL,SO,RF,CS,A105,150,16 IN EA 5 -
184 FL,SO,RF,CS,A105,150,10 IN EA 10 -
185 FL,WN,RF,CS,A105,150,8IN EA 20 -
186 FL,WN,RF,CS,A105,150,10IN EA 16 -
187 FL,WN,RF,CS,A105,150,12IN EA 49 -
188 FL,WN,RF,CS,A105,150,14IN EA 60 -
189 TEE,EQ,BW,CS,A234,WPB,24IN,STD EA 5 -
190 UNEQUALTEE,EQ,BW,CS,A234,WPB,24X16 EA 3 -
191 UNEQUALTEE,EQ,BW,CS,A234,WPB,24X12 EA 14 -
192 UNEQUALTEE,EQ,BW,CS,A234,WPB,24X10 EA 4 -
193 UNEQUALTEE,EQ,BW,CS,A234,WPB,24X8 EA 3 -
194 UNEQUALTEE,EQ,BW,CS,A234,WPB,18X4 EA 3 -
195 UNEQUALTEE,EQ,BW,CS,A234,WPB,12X4 EA 8 -
196 UNEQUALTEE,EQ,BW,CS,A234,WPB,10X4 EA 4 -
197 UNEQUALTEE,EQ,BW,CS,A234,WPB,8X4 EA 6 -
198 UNEQUALTEE,EQ,BW,CS,A234,WPB,12X6 EA 2 -
199 UNEQUALTEE,EQ,BW,CS,A234,WPB,12X8 EA 1 -
200 TEE,EQ,BW,CS,A234,WPB,12IN,STD EA 2 -
201 FL,SO,RF,CS,A105,150,6 IN EA 6 -
202 FL,SO,RF,CS,A105,150,8 IN EA 2 -
203 PIPE,MS,ERW,IS3589,GR410,BE,6IN 6.35TH M 35.65 -
204 PIPE,MS,ERW,IS3589,GR410,BE, 8" IN M 12.04 -
205 UNEQUALTEE,EQ,BW,CS,A234,WPB,12X6 EA 4 -
Total 0.000 0.000

Contractors Signature
L CORPORATION LIMITED
L RECOVERY STATEMENT
(CSW) FOR CONSTRUCTION OF MARKETING TAP OFF POINTS GROUP-B-KHUNTI,

4
.2015
Recovery Qty. Recovery Amount
Upto
This Bill Cummulative Upto Previous This Bill Cummulative
Previous
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - ` - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
- - - - - -
0.000 0.000 0.000 0.000 0.000 0.000

Site Engineer / Engineer-In-Charge