DDR N°1 - Atk29 - TP180 - 08022017

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Page 1 sur 3

SONATRACH

Daily Drilling Report


WELL & SIDETRACK : DATE: DAY: DOP: DFS: TMD: TVD: FORMATION TOP: PROGRESS: ROT:
ATK-29 08/02/2017 1 47,10 1,00 35,00 m 35,00 m SENONIAN @ 12,0 m 23,00 m 19,50 hr
SUPERVISOR/SUPERINTENDENT: RIG NAME & No: FIELD: ACC. FREE: AFE (KD): DAILY (KD): CUM (KD): WELL OBJECTIVE:
S.DOUADI / A.ROUAIGUIA TP 180 AIT KHEIR 657 153 8 149 83 763 DEVELOPMENT
LAST CSG/LNR SHOE: LAST CSG/LNR TOP: LAST FM. TEST/EMW: L. BOP TEST: L.SAFETY MEETG: DAILY NPT: CUM NPT: I.SERVICE:
0,00 m 08/02/2017 3,00 hr 0,13 days NONE
ACCIDENT / INCIDENT TOPICS:
NILL
BIT DATA LAST BHA MUD CHECKS
BIT No./Re-Run(U) 1/N / NAME: DRILLING BHA TYPE 1: WBM TIME/LOC 00:01/
BIT RUN No. 1 OD TOOL JTS LENGTH TYPE 2: TIME/LOC /
BIT SIZE (in) 26,000 (in) TYPE No (m) DENSITY (sg) 1,05 ECD (sg)
BIT MANUFACTURE VAREL 5,000 HW 6 53,73 DEPTH (m) 35,0 SAND () 0,20
BIT TYPE ETR24JMRS 8,000 XO 1 1,00 FL TEMP (°C) 120 SOLIDS (%) 2,00
BIT IADC CODE 515 8,000 DC 12 110,20 FUN VIS (s/qt) 97 OIL (%)
BIT SERIAL No. 1511169 8,000 XO 1 1,23 PV (cp) 21 H2O (%) 98,00
BIT JETS (32nd") 1X16, 3X18 9,500 DC 1 9,05 YP (lbf/100ft²) 50 OIL/H2O / /
11,000 DC 1 9,39 GEL (10sec) (lbf/100ft²) 19,00 LGS (%) 0,10
BIT TFA (in²) 0,942 25,937 IBS 1 2,28 GEL (10m) (lbf/100ft²) 22,00 HGS (%) 1,56

BIT DEPTH IN 12,0 11,000 DC 2 18,90 E LIME (g/L)


(m) API FL (cc/30min)
BIT DEPTH OUT 35,0 11,000 SS 1 4,48 HPHT FL (cc/30min) CL-MUD (g/L) 1
(m)
CUM PROGRESS (m) 23,0 11,000 BS 1 0,94 pH 12,00 CL Brine (mg/L)

CUM HOURS 13,96 26,000 BIT 1 0,63 Pf (cc) 0,20 NaCL Brine (mg/L)

CUM ROP (WOC) (m/hr) 1,65 Mf (cc) 0,50 Ca+ (g/L) 0

WOB(Min/Max) (tonne) 3/6 / Pm (cc) 0,90 K+ (g/L)


RPM (Min/Max) 40/70 / KCL (ppm) CaCL2 (mg/L/mg/L)
BIT COND (IODL) -- ES (Volts) MBT (sg) 95,0000
BIT COND (BGOR) --- TOTAL BHA LENGTH (m) 211,83 DAILY GEOLOGY DATA
BIT HSI (hp/in²) 0,02 ITEM SINCE LAST INSPECT. HR FROM TO W.C W.O.C FORMATION

FUEL & WATER MUD LOSSES MOTOR&TURBINE (day/cum) SHOCK SUB 14,0 12,00 35,00 1,18 1,65 SENONIAN
FUEL: SURF: 41,0 m³ MOTOR: / JAR
WATER: 210,00 m³ HOLE: TURBINE: / BHA

PUMP DATA WELL & LOCATION SLOW PUMP MATERIAL TRANSPORT


PUMP 1 3 2 AREA AIT KHEIR PUMP ITEM UNIT REC'D USED ON LOC

MAKE OILWELL OILWELL OILWELL BLOCK No. DEPTH 1


MODEL A1700-PT 12-P-160 A1700-PT DIRECTION NORD SPM 1
LINER (in) BASSIN GHARDAIA PRESS 1
STROKE (in) 12,000 12,000 12,000 FM TARGET TRIAS DEPTH 2
EFF (%) DEVIATED NO SPM 2
PRESS (psi) PERM.DATUM KELLY BUSHING PRESS 2
SPM ELEVATION 413,75 STRING WEIGHT(ton) & TORQUE(ft/lbf)

LPM KB to GL 7,62 ACT.HKLD: PICK UP:


ANNULAR VELOCITY (m/min) MUD VOLUME(m³) SLACK OFF: ROTATING:

AV DP: DP/CSG: STRING: 0,0 ANNULUS: 12,0 TQ.on BTM: TQ.off BTM:

AV DC: Jets Vel ( m/s): PITS: 397,0 TOTAL 409,0 BELOW JAR: ABV. JAR:

MUD CHEMICAL USAGE


ITEM UNITS REC'D USED ON LOC ITEM UNITS REC'D USED ON LOC
BARYTE LOCAL 1,5 250,500 250,500 Bentonite (Local 1,250 85,000 47,500 37,500

CARBONATE DE SOUDE 0,025 1,250 0,400 0,850 SOUDE CAUSTIQUE 0,025 1,200 0,550 0,650

CMC LVT 0,025 1,000 1,000 AVADETER 0,165 1,320 0,330 0,990

ECOULUBE 0,170 0,680 0,170 0,510 GRANULAR C 0,025 2,000 2,000

GRANULAR F 0,025 2,000 2,000 GRANULAR M 0,025 1,375 1,375

AVAMICA C 0,025 2,000 2,000 AVAMICA F 0,025 2,000 2,000

AVATENSIO LT 0,165 0,660 0,660 AVABENTOIL HY 0,025 3,000 3,000

AVABENTOIL SA 0,025 1,500 1,500 CHLORURE DE SODIUM 1 22,000 22,000

AVOILPE 0,9 2,700 2,700 AVOIL SE 0,9 2,700 2,700

AVOIL FR/HT 0,025 0,900 0,900 AVOIL TN 0,19 0,330 0,330

OpenWells Printed: février 09, 2017 at 6:33 am SHDDR v5.0_22/Nov/2014


Page 2 sur 3
SONATRACH

Daily Drilling Report


WELL & SIDETRACK : DATE: DAY: DOP: DFS: TMD: TVD: FORMATION TOP: PROGRESS: ROT:
ATK-29 08/02/2017 1 47,10 1,00 35,00 m 35,00 m SENONIAN @ 12,0 m 23,00 m 19,50 hr
SUPERVISOR/SUPERINTENDENT: RIG NAME & No: FIELD: ACC. FREE: AFE (KD): DAILY (KD): CUM (KD): WELL OBJECTIVE:
S.DOUADI / A.ROUAIGUIA TP 180 AIT KHEIR 657 153 8 149 83 763 DEVELOPMENT
LAST CSG/LNR SHOE: LAST CSG/LNR TOP: LAST FM. TEST/EMW: L. BOP TEST: L.SAFETY MEETG: DAILY NPT: CUM NPT: I.SERVICE:
0,00 m 08/02/2017 3,00 hr 0,13 days NONE
ACCIDENT / INCIDENT TOPICS:
NILL

MUD CHEMICAL USAGE


ITEM UNITS REC'D USED ON LOC ITEM UNITS REC'D USED ON LOC
DIESEL 54,000 54,000

SURVEY DATA
MD INC AZI TVD N/S (-) E/W (-) VS DLS MD INC AZI TVD N/S (-) E/W (-) VS DLS
(m) (°) (°) (m) (m) (m) (m) (°/30m) (m) (°) (°) (m) (m) (m) (m) (°/30m)
PERSONNEL DATA
COMPANY NO HOURS NAMES COMPANY NO HOURS NAMES
SH-DDO 2 0,00 S,BENSEMCHA+S,DOUADI SARL BECHIRI / WATER TRUCK 1 0,00 F,BENGASMI
DML MUD LOGGING 3 0,00 A,BELABBAS AVA MUD 2 0,00 M,AMROUNE
SLB/COPS 3 0,00 H,KARA SH/ MEC 1 0,00 A.SAOUD
ENTP 40 0,00 L.BENACHI SARL LAOUINIE / WATER TRUCK 13 0,00 A,YOUSFI
SH RIG ASSISTANT 1 0,00 K,MESSAOUD AVA WAST MANAGEMENT 2 0,00 H,SALEM
LIGABUE CATRING 18 0,00 N,ABBASSEN HIMAYA PLUS 31 0,00 S,MIKAOUSSI
SH MECANIQUE TRAINEE 1 0,00 A,KIRECHE

OPERATIONS SUMMARY
FROM-TO HRS PHASE CODE SUB DESCRIPTION FROM-TO NPT NPT DETAIL NPT Co Op Co BILL
00:00-21:00 21,00 26" 02 P E START DRILLING 26" HOLE SECTION 12,0-34,0 ENTP T1
* M/U BIT 26 "+ BIT SUB + SHOCK SUB +02 DC 11"
* Pre-spud meeting with all crews
* Start Drilling with reduced parameters (no mud losses)
* WOB= 2-5T RPM 40-70 rpm Q= 500-1300 lpm Pr= 40 psi
* ROP Daily/Cummul : WOC= 1,38 // 1,38 m/hr WC= 1,17 // 1,17m/hr
21:00-23:30 2,50 26" 06 N I POOH 26"BHA HOLE SECTION 34,0-0,0 DPRB STAB SH/FOR ENTP T1
**Communication on surface
**L/D BIT 26 "+ BIT SUB + SHOCK SUB +02 DC 11"
23:30-00:00 0,50 26" 12 N J RIG UP ENTP & COPS SURFACE EQUIPMENT 0,0-0,0 DPRB STAB SH/FOR ENTP T1

AFTER MIDNIGHT OPERATIONS:


SET CEMENT PLUG 12 m3 (d=1.9)- get cement on surface + WAIT ON CEMENT HARDNESS
CURRENT OPERATION:
WAIT ON CEMENT HARDNESS
24 Hrs SUMMARY OPERATIONS:
START DRILLING 26" HOLE SECTION + POOH 26"BHA HOLE SECTION + SET CEMENT PLUG
PLAN OPERATIONS:
DRILLING 26" HOLE SECTION TO CSG POINT +/- 338m
REQUIREMENTS / RENTAL EQUIPMENT:
NEED CARTOUCHE IMPRIMANTE HP LASER JET P3005 PCL6 (51A)
REMARKS:
************************************* DRILLING WITH TOP DRIVE ****************************************************
NPT: DAILY: 3.0 hrs // Cumul: 0.125 Days (ENTP: 0.0 hrs) (DOWN HOLE PROBLEMS: 03.00 hrs) ENTP;(T3/NR monthly=00/00 hrs,T3/NR cumul=0.0/00 hrs)
Planned days = Actual days= 1
ROP : (m/h) WOC WC
* DAILY/CUMUL: 1.65/1.65 1.18/1.18
* SENONIEN: 1.65 1.18
** ON RIG:
** (SARL LAOUINI): 13TRUCKS OF 32m3
** (SARL BECHIRI): 01 TRUCK OF 29m3

Distance between water well and rig location (km): 20 km DP OUED NOUMER
** ON SITE:
** CRD MUD LOGGING CABINE
** AVA CABINE+SOLID CONTROL MATERIALS +MUD PRODUCT. .
** SH MATERIALS PROGRAM
** cementing unit & crew + Water tank +Silos
* 46 JTS 18"5/8 87.5# K55 BTC + 200 JTS 13"3/8 68# N80 BTC + 04 JTS 7" 32# P 110 BTC
* 02 PUP JOINT 13"3/8 +02 PUP JOINT 9"5/8 + 02 PUP JOINT 7"
* 02 X-O FULL JOINT 7" 32# P110 N.VAM BOX * BTC PIN
* 30" CONDUCTOR PIPE
* SHOCK SUB 11"
* BIT SUB 8 5/8X 7 5/8
** ENTP FUEL RIG/CAMP STORAGE :/m3, USED m3
********************************** NEEDS AND MISSING EQUIPMENT****************
* NEED STINGER 4"1/2 IF
* CARTOUCHE IMPRIMANTE HP LASER JET P3005 PCL6 (51A)
* V-SAT DOWN FROM OLD WELL GED-2
** RECTIFIER (onduleur)
OpenWells Printed: février 09, 2017 at 6:33 am SHDDR v5.0_22/Nov/2014
Page 3 sur 3
SONATRACH

Daily Drilling Report


WELL & SIDETRACK : DATE: DAY: DOP: DFS: TMD: TVD: FORMATION TOP: PROGRESS: ROT:
ATK-29 08/02/2017 1 47,10 1,00 35,00 m 35,00 m SENONIAN @ 12,0 m 23,00 m 19,50 hr
SUPERVISOR/SUPERINTENDENT: RIG NAME & No: FIELD: ACC. FREE: AFE (KD): DAILY (KD): CUM (KD): WELL OBJECTIVE:
S.DOUADI / A.ROUAIGUIA TP 180 AIT KHEIR 657 153 8 149 83 763 DEVELOPMENT
LAST CSG/LNR SHOE: LAST CSG/LNR TOP: LAST FM. TEST/EMW: L. BOP TEST: L.SAFETY MEETG: DAILY NPT: CUM NPT: I.SERVICE:
0,00 m 08/02/2017 3,00 hr 0,13 days NONE
ACCIDENT / INCIDENT TOPICS:
NILL
** KOOMEY UNIT WITHOUT ELECTRICAL ALARM
** UNSUFFICIENT LIGHT IN RIG AND CAMPS
** 10JTS DC 6"1/2
** SHAKER SCREEN 20 API 180 & 16 API 140
** KELLY SPINNER
** Upper Kelly valve , 5000 psi minimum WP
** 02 Lower Kelly valves, 4 1/2" IF Box x 3 1/2" IF Pin, 5000 psi minimum WP (02)
** 02 Lower Kelly valves, 3"1/2 IF Box x 3 1/2" IF Pin, 5000 ps minimum WP (02)
** MRT F/4" TO 17" OUT OF REQUIRMENT
** 75 TON GRIP ELEVATOR 4"1/2 CASING
** Eqpts certificats:Koomey, Choke manifold, Choke panel, and Tubular.
** IWCF certification for Personnal.
** 20ft PUP JOINT
** XO 4"1/2 IF PIN X 4’’ IF BOX
** Inside BOP (Safety Valve), 3 1/2" IF connection ,minimum 5 000 psi WP
** 16” STB + NBIT OUT OF SH REQUIRMENT
** Basket Sub For 16 ", hole 7 5/8" Reg pin x 7 5/8" Reg box down
** Fishing Magnet 5" OD with 3 1/2" REG Pin Up
** CHILL ROOM (CHAMBRE FROIDE) IN BAD CONDITION
** BIG LEAKS OF WATER IN THE RIG AND CAMPS
** TOILET ROOM OUT OF SEVICE IN MAIN CAMP
** 10 CUMULS

OpenWells Printed: février 09, 2017 at 6:33 am SHDDR v5.0_22/Nov/2014