Professional Documents
Culture Documents
Hfy3 3385 Gen WPR 0044
Hfy3 3385 Gen WPR 0044
PHASE 3 PROJECT
Petrochina CPF1
(Halfaya)
24/02/2017- 02/03/2017
CONTENT
2.0 Work Completed This Week: ...................................... Error! Bookmark not defined.
Deviation Reasons:
No Reason
HALFAYA PROJECT SURFACE FACILITY
PHASE 3 PROJECT
Petrochina CPF1
(Halfaya)
2 Guard Rooms Materials 18/4/2016 18/4/2016 21/4/2016 21/4/2016 28/4/2016 29/08/2016 21/6/2016
3 Water Tank Structure Materials 21/5/2016 27/9/2016 24/5/2016 28/9/2016 31/5/2016 29/9/2016 14/7/2016 30/9/2016
Septic Tanks construction
4 materials
11/5/2016 21/9/2016 14/5/2016 21/9/2016 21/5/2016 22/9/2016 09/6/2016 22/9/2016
5 HDPE membrane Supplying 13/4/2016 1/10/2016 16/4/2016 2/10/2016 23/4/2016 3/10/2016 22/5/2016 3/10/2016
6 Drop Barrier Supplying 10/7/2016 30/12/2016 13/7/2016 04/01/2016 20/7/2016 17/02/2016 08/8/2016 18/02/2016
8 Steel gate Materials 09/8/2016 30/12/2016 12/8/2016 30/12/2016 19/8/2016 21/02/2016 07/10/2016 22/02/2016
9 Fence gate Materials 13/4/2016 21/10/2016 16/4/2016 22/10/2016 23/4/2016 23/12/2016 12/5/2016 23/12/2016
10 11 Kv switch gear 10/7/2016 25/10/2016 13/7/2016 29/10/2016 20/7/2016 09/2/2017 28/8/2016 12/2/2017
11 Electrical Poles 11/5/2016 02/11/2016 14/5/2016 06/11/2016 21/5/2016 19/1/2017 07/10/2016 28/1/2017
12 Electrical cables and wires 10/7/2016 11/9/2016 13/7/2016 13/9/2016 20/7/2016 30/9/2016 08/8/2016 23/11/2016
14 Lightening poles 11/5/2016 22/10/2016 14/5/2016 26/10/2016 21/5/2016 01/01/2017 08/8/2016 10/01/2017
15 Fence Materials 13/4/2016 25/9/2016 16/4/2016 26/9/2016 23/4/2016 27/9/2016 12/5/2016 27/9/2016
16 Sun shelters Materials 01/9/2016 04/2/2017 04/9/2016 05/2/2017 11/9/2016 06/2/2017 30/10/2016 07/2/2017
20 Brick Wall materials 01/5/2016 01/5/2016 04/5/2016 04/5/2016 11/5/2016 11/5/2016 14/7/2016 16/8/2016
2 Guard Rooms Materials 18/4/2016 18/4/2016 21/4/2016 21/4/2016 28/4/2016 29/08/2016 21/6/2016
3 Water Tank Structure Materials 21/5/2016 27/9/2016 24/5/2016 28/9/2016 31/5/2016 29/9/2016 14/7/2016 30/9/2016
Septic Tanks construction
4 materials
11/5/2016 21/9/2016 14/5/2016 21/9/2016 21/5/2016 22/9/2016 09/6/2016 22/9/2016
5 HDPE membrane Supplying 13/4/2016 1/10/2016 16/4/2016 2/10/2016 23/4/2016 3/10/2016 22/5/2016 3/10/2016
6 Drop Barrier Supplying 10/7/2016 30/12/2016 13/7/2016 04/01/2016 20/7/2016 17/02/2016 08/8/2016 18/02/2016
8 Steel gate Materials 09/8/2016 30/12/2016 12/8/2016 30/12/2016 19/8/2016 21/02/2016 07/10/2016 22/02/2016
9 Fence gate Materials 13/4/2016 21/10/2016 16/4/2016 22/10/2016 23/4/2016 23/12/2016 12/5/2016 23/12/2016
10 11 Kv switch gear 10/7/2016 25/10/2016 13/7/2016 29/10/2016 20/7/2016 09/2/2017 28/8/2016 12/2/2017
11 Electrical Poles 11/5/2016 02/11/2016 14/5/2016 06/11/2016 21/5/2016 19/1/2017 07/10/2016 28/1/2017
12 Electrical cables and wires 10/7/2016 11/9/2016 13/7/2016 13/9/2016 20/7/2016 30/9/2016 08/8/2016 23/11/2016
14 Lightening poles 11/5/2016 22/10/2016 14/5/2016 26/10/2016 21/5/2016 01/01/2017 08/8/2016 10/01/2017
15 Fence Materials 13/4/2016 25/9/2016 16/4/2016 26/9/2016 23/4/2016 27/9/2016 12/5/2016 27/9/2016
16 Sun shelters Materials 01/9/2016 04/2/2017 04/9/2016 05/2/2017 11/9/2016 06/2/2017 30/10/2016 07/2/2017
18 Asphalt Road Construction materials 01/9/2016 30/13/2016 04/9/2016 30/13/2016 11/9/2016 07/11/2016 30/9/2016 09/11/2016
20 Brick Wall materials 01/5/2016 01/5/2016 04/5/2016 04/5/2016 11/5/2016 11/5/2016 14/7/2016 16/8/2016
4.0 Change Order : (One Change Order issued on : 22.Dec-2016 Change Orders No : HFY -CON/F&C0717-0741-CO-001).
7.0 Photos
8.0 .Attachments:
No. Attachment
1 Revised Schedule Time
2 Road Equipment Histogram
3 Road Manpower Histogram