Professional Documents
Culture Documents
Harga Material: Bahan VOL SAT Harga 10% Standar Palas
Harga Material: Bahan VOL SAT Harga 10% Standar Palas
Harga Material: Bahan VOL SAT Harga 10% Standar Palas
HARGA 10%
BAHAN VOL SAT
Standar Palas
1 Pek.Persiapan
a Pek. Pemasangan Bowplank
- Kayu 4 x 6 17.00 Btg Rp 14,000.00 Rp 238,000.00
- Paku 3.50 Kg Rp 16,000.00 Rp 56,000.00
Sub Pekerjaan-1 Rp 294,000.00
2 Pek. Pondasi
a Pek. Pemasangan Bata 1 Batu Bata
- Batu Bata Kecil 4,560.00 Bh Rp 220.00 Rp 1,003,200.00
- Semen Padang 50 Kg 6.00 Sak Rp 59,000.00 Rp 354,000.00
- Pasir Pasang 3.60 M³ Rp 100,000.00 Rp 360,000.00
b Pek. Sloof 15 x 15
- Besi Ø 6 x 10 BJKU 16.00 Btg Rp 19,000.00 Rp 304,000.00
- Besi Ø 6 x 4 Begol 38.00 Btg Rp 6,000.00 Rp 228,000.00
- Kawat Ikat 7.50 Kg Rp 16,000.00 Rp 120,000.00
- Semen Padang 50 Kg 6.00 Sak Rp 59,000.00 Rp 354,000.00
- Pasir Cor 0.34 M³ Rp 125,000.00 Rp 42,500.00
- Koral Cor 0.50 M³ Rp 150,000.00 Rp 75,000.00
c Pek. Timbunan 17.00 M³ Rp 35,000.00 Rp 595,000.00
Sub Pekerjaan-2 Rp 3,435,700.00
3 Pek. Dinding
a Pek. Pemasangan Bata ½ Batu Bata
- Batu Bata Kecil 7,500.00 Bh Rp 220.00 Rp 1,650,000.00
- Semen Padang 50Kg 17.00 Sak Rp 59,000.00 Rp 1,003,000.00
- Pasir Pasang 5.60 M³ Rp 100,000.00 Rp 560,000.00
b Pek. Kolom Praktis
- Besi Ø 6 x 10 BJKU 17.00 Btg Rp 19,000.00 Rp 323,000.00
- Besi Ø 6 x 4 Begol 40.00 Btg Rp 6,000.00 Rp 240,000.00
- Kawat Ikat 8.00 Kg Rp 16,000.00 Rp 128,000.00
- Semen Padang 50Kg 6.00 Sak Rp 59,000.00 Rp 354,000.00
- Pasir Cor 0.40 M³ Rp 125,000.00 Rp 50,000.00
- Koral Cor 0.60 M³ Rp 150,000.00 Rp 90,000.00
c Pek. Ring Balok
- Besi Ø 6 x 10 BJKU 16.00 Btg Rp 19,000.00 Rp 304,000.00
- Besi Ø 6 x 4 Begol 37.00 Btg Rp 6,000.00 Rp 222,000.00
- Kawat Ikat 7.50 Kg Rp 16,000.00 Rp 120,000.00
- Semen Padang 50Kg 5.00 Sak Rp 59,000.00 Rp 295,000.00
- Pasir Cor 0.30 M³ Rp 125,000.00 Rp 37,500.00
- Koral Cor 0.50 M³ Rp 150,000.00 Rp 75,000.00
d Pek. Plesteran
- Semen Padang 50Kg 16.00 Sak Rp 59,000.00 Rp 944,000.00
- Pasir Pasang 6.40 M³ Rp 100,000.00 Rp 640,000.00
e Pek. Pengacian
- Semen Padang 50Kg 4.00 Sak Rp 59,000.00 Rp 236,000.00
Sub Pekerjaan-3 Rp 7,271,500.00
4 Pek. Tembok Layar
a Pek. Pemasangan Bata ½ Batu Bata
- Batu Bata Kecil 1,580.00 Bh Rp 220.00 Rp 347,600.00
- Semen Padang 50Kg 4.00 Sak Rp 59,000.00 Rp 236,000.00
- Pasir Pasang 2.40 M³ Rp 100,000.00 Rp 240,000.00
Sub Pekerjaan-4 Rp 823,600.00
5 Pek. Atap
a Pek. Kuda_kuda
- Kayu 5 x 7 35.00 Btg Rp 20,500.00 Rp 717,500.00
- Kayu 5 x 10 25.00 Btg Rp 29,000.00 Rp 725,000.00
- Paku 5.00 Kg Rp 16,000.00 Rp 80,000.00
b Pek. Atap
- Atap Seng Warna 6kk 50.00 Lbr Rp 49,000.00 Rp 2,450,000.00
- Paku Seng 4.00 Ktk Rp 15,000.00 Rp 60,000.00
- Rabung Warna 5.00 Lbr Rp 26,000.00 Rp 130,000.00
- Kayu Lisplank 10.00 Lbr Rp 40,000.00 Rp 400,000.00
Sub Pekerjaan-5 Rp 4,562,500.00
6 Pek. Lantai
a Pek. Lantai Finishing Acian
a.1 Pek. Pengecoran Lantai
- Semen Padang 50kg 21.00 Sak Rp 59,000.00 Rp 1,239,000.00
- Pasir Cor 1.44 M³ Rp 125,000.00 Rp 180,000.00
- Koral Cor 2.16 M³ Rp 150,000.00 Rp 324,000.00
a.2 Pek. Acian Lantai
- Semen Padang 50kg 5.00 Sak Rp 59,000.00 Rp 295,000.00
b Pek. Keramik Kamar Mandi T_3cm
b.1 Pek. Lantai K. Mandi T_3cm
- Semen 1.00 Sak Rp 59,000.00 Rp 59,000.00
- Pasir Pasang 0.40 M³ Rp 100,000.00 Rp 40,000.00
- Keramik 20 x20_Valencia 3.00 Ktk Rp 50,000.00 Rp 150,000.00
b.2 Pek. Dinding K. Mandi T_3cm
- Semen 1.00 Sak Rp 59,000.00 Rp 59,000.00
- Pasir Pasang 0.20 M³ Rp 100,000.00 Rp 20,000.00
- Keramik 20 x 25_Masterina 7.00 Ktk Rp 51,000.00 Rp 357,000.00
Sub Pekerjaan-6 Rp 2,723,000.00
7 Aksesories K. Mandi
- Bak Fiber Kecil 1.00 Bh Rp 190,000.00 Rp 190,000.00
- Pintu Fiber 1.00 Bh Rp 190,000.00 Rp 190,000.00
- Closed Dutty 1.00 Bh Rp 90,000.00 Rp 90,000.00
- Saringan K. Mandi Standar 1.00 Bh Rp 4,000.00 Rp 4,000.00
Sub Pekerjaan-7 Rp 474,000.00
8 Pek. Kuzen & Jendela 1.00 Unit Rp 3,000,000.00 Rp 3,000,000.00
Sub Pekerjaan-8 Rp 3,000,000.00
9 Pek. Gantungan
- Kunci Surento Sedang 2.00 Bh Rp 80,000.00 Rp 160,000.00
- Kunci Napoly 2.00 Bh Rp 25,000.00 Rp 50,000.00
- Hak Angin RRT 8.00 Psng Rp 3,000.00 Rp 24,000.00
- Engsel Nylon 3" 7.00 Psng Rp 5,000.00 Rp 35,000.00
- Engsel Nylon 4" 3.00 Psng Rp 7,000.00 Rp 21,000.00
- Tarekan D/N 4.00 Bh Rp 1,500.00 Rp 6,000.00
- Sekrup 1 x 6" 2.00 Ktk Rp 5,000.00 Rp 10,000.00
Sub Pekerjaan-10 Rp 306,000.00
11 Pek. Pengecatan
a Pek. Pengecatan Dinding
- Cat jotun@20kg_Cream Lunak 1.00 Pail Rp 910,000.00 Rp 910,000.00
- Cat Jotun@20kg_Stone 1.00 Pail Rp 195,000.00 Rp 195,000.00
- Cat Jotun@2,5kg_Merah Neon 1.00 Gln Rp 115,000.00 Rp 115,000.00
- Cat Jotun@2,5kg_Orange 1.00 Gln Rp 115,000.00 Rp 115,000.00
- Cat Jotun@2,5kg_Coklat Gelap 1.00 Gln Rp 115,000.00 Rp 115,000.00
- Kuas 3" 1.00 Bh Rp 8,000.00 Rp 8,000.00
- Kuas 2½" 1.00 Bh Rp 7,000.00 Rp 7,000.00
- Kuas Golong" 1.00 Bh Rp 12,000.00 Rp 12,000.00
b Pek. Pengecatan Pintu & Jendela
- Cat Minyak Sendai Maritex_Putih 1.00 Gln Rp 185,000.00 Rp 185,000.00
- Tinner Kapanis 1.00 Gln Rp 55,000.00 Rp 55,000.00
Sub Pekerjaan-11 Rp 1,717,000.00
12 Pek. Plafond
- Kayu 4 x 6 36.00 Btg Rp 14,000.00 Rp 504,000.00
- Triplek 3mm 16.00 Lbr Rp 41,000.00 Rp 656,000.00
- Paku Triplek 1.00 Ktk Rp 12,000.00 Rp 12,000.00
Sub Pekerjaan-12 Rp 1,172,000.00
13 Pek. Instalasi Listrik 6.00 Titik Rp 150,000.00 Rp 900,000.00
Sub Pekerjaan-13 Rp 900,000.00
14 Pek. Instalasi Air
- Pipa 3" ( pipa abu"@4m ) 1.00 Btg Rp 35,000.00 Rp 35,000.00
- Pipa 2,5" ( pipa abu"@4m ) 2.00 Btg Rp 30,000.00 Rp 60,000.00
- Pipa ½" ( champion @6m ) 1.00 Btg Rp 15,000.00 Rp 15,000.00
- Soket 3" 1.00 Bh Rp 6,000.00 Rp 6,000.00
- Soket 2½" 1.00 Bh Rp 4,000.00 Rp 4,000.00
- Soket Drat ½" 1.00 Bh Rp 2,000.00 Rp 2,000.00
- Elbo ½" 3.00 Bh Rp 2,000.00 Rp 6,000.00
Sub Pekerjaan-14 Rp 128,000.00
15 Pek. Sumur Bor 2.00 Bh Rp 100,000.00 Rp 200,000.00
- Pipa 2,5" 2.00 Bh Rp 65,000.00 Rp 130,000.00
Sub Pekerjaan-15 Rp 330,000.00
16 Pek. Septictank
- Besi Ø 6 x 10 Polos 8.00 Btg Rp 19,000.00 Rp 152,000.00
- Kawat Ikat 4.00 Kg Rp 16,000.00 Rp 64,000.00
- Semen Padang 50Kg 4.00 Sak Rp 59,000.00 Rp 236,000.00
- Pasir Cor 0.10 M³ Rp 125,000.00 Rp 12,500.00
- Koral Cor 0.15 M³ Rp 150,000.00 Rp 22,500.00
- Pipa hawa Panjang 1.00 Bh Rp 20,000.00 Rp 20,000.00
Sub Pekerjaan-16 Rp 507,000.00
Dibuat oleh:
Isyatur Radhiah
Adm Proyek
PT. WAHANA TATA GRIYA
DEVELOPER REAL ESTATE
SURAT PERINTAH KERJA (SPK) Alamat :Jl. Dahlia Ujung No. 60 Telp. (0761) 7048800
NOMOR DAN TANGGAL SPK : N0.001/SPK-WTG/2013
Tgl. -
Halaman dari
PAKET PEKERJAAN :
Pembangunan Rumah GRIYA BUKIT ASRI