Karmachari Sancahie Kosh
Karmachari Sancahie Kosh
Itahari, Nepal
Client:
Location:
Project: Date: 2073/…./….
DETAILS ESTIMATE
S.N. Description of Work No. Unit Length Breath Height Quantity Remarks
A Excavation
i Excavation for posts Cft 2.00 2.00 3.33 0.00
ii Excavation for 9" brick masonry Cft 1.00 2.33 0.00
Sub Total 0.00 Cft
B 2" Flat Brick Solling in wall foundation 1 Sft 0.00 0.75 0.00
2" Flat Brick Solling in post foundation 0 Sft 2.00 2.00 0.00
Sub Total 0.00 Sft
H Metal Works
Structural Works
ISMB250 Posts kg 0.00
ISMB200 Posts kg 0.00
ISMB150 Posts kg 0.00
90x90x2.5 MS Posts kg 0.00
75x75x2.5 MS Posts kg 0.00
60x60x2.5 MS Posts kg 0.00
50x50x2.5 MS Posts kg 0.00
ISMB250 Horizontals kg 0.00
ISMB200 Horizontals kg 0.00
ISMB150 Horizontals kg 0.00
I Panel Works
i …… mm thick Gorkha Eco Panel
a Exterior walls
Long walls Sft 0.00
Short walls Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
b Interior walls
………………... Partition 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Sum: 0.00 0.00
5% wastage: 0.00
Sub Total 1: 0.00
No. of Panels: 0.00
Total Area for fitting Charge 1 Sft 0.00 Sft
K CCGI Sheet
Truss ………. Sft
Truss ………. Sft
Truss ………. Sft
Sub Total: 0.00 Sft
COST ESTIMATE
S.N. Descriptions Quantity Unit Rate
A Metal Works and color c.g.i 0.39mm roofing 598.00 sqft 280
works
B Panel Works (Prefab Wall 7.5'x2' )
50 mm thick Gorkha Eco Panel with 5%
i 53 No. 3,000
wastage (Interior Wall)
ii Installation accessories 798.00 Sft 25
iii Installation Charge 798.00 Sft 25
Sub Total:
C Aluminium Works
Metal Frame Door with flush panel 21.00 Sft 400
40.00 Sft 425
78mm Aluminium Window
Sub Total:
F. Transport 8000.00lumpsum
Total:
Note:-
i VAT is excluded.
ii Water & Electricity should be provided by the client during construction works.
iii Actual quantity may vary as per site condition.
iv Transpotation Charge is free only in Itahari.
v We prefer client to do the foundation work by himself
vi Lodging and fooding for installers should be done by client.
Date: 2074/12/13
MATE
Amount (NPR) Remarks 49
167,440.00 Assuming 1.5' projection
of Gable roof on all sides
19,950.00
19,950.00
199,500.00
17,000.00
no@window size 2@5'x4'
25,400.00
47,880.00
8,000.00
NPR 448,220.00
nstruction works.
61
821
Client:
Location:
Project: Date: 2073/…./….
Total: 7000.00
Advance: -3000.00
Grand Total: 4000.00