AMAR JANAKI CONSULT & BUILDERS Pvt. Ltd.

Itahari, Nepal

Client:
Location:
Project: Date: 2073/…./….

DETAILS ESTIMATE

S.N. Description of Work No. Unit Length Breath Height Quantity Remarks
A Excavation
i Excavation for posts Cft 2.00 2.00 3.33 0.00
ii Excavation for 9" brick masonry Cft 1.00 2.33 0.00
Sub Total 0.00 Cft

B 2" Flat Brick Solling in wall foundation 1 Sft 0.00 0.75 0.00
2" Flat Brick Solling in post foundation 0 Sft 2.00 2.00 0.00
Sub Total 0.00 Sft

C 9" Brick Masonry 1 Cft 0.00 0.75 2.00 0.00 Cft

D 4" PCC (1:3:6:) 1 Cft 0.33 0.00 Cft

E RCC For Post 0 Cft 2.00 2.00 2.67 0.00


(Note: There are total ….. posts) Sub Total 0.00 Cft

F 8mm Reinforcement bar 1 kg 0.00 0.00 kg

G Foundation anchor posts 0 No 0.00 No.


Sub Total 0.00

H Metal Works
Structural Works
ISMB250 Posts kg 0.00
ISMB200 Posts kg 0.00
ISMB150 Posts kg 0.00
90x90x2.5 MS Posts kg 0.00
75x75x2.5 MS Posts kg 0.00
60x60x2.5 MS Posts kg 0.00
50x50x2.5 MS Posts kg 0.00
ISMB250 Horizontals kg 0.00
ISMB200 Horizontals kg 0.00
ISMB150 Horizontals kg 0.00

Prepared by: ............................... Checked by: Er. Sabin Budhathoki


90x90x2.5 MS Horizontals kg 0.00
75x75x2.5 MS Horizontals kg 0.00
60x60x2.5 MS Horizontals kg 0.00
50x50x2.5 MS Horizontals kg 0.00
Truss Works
75x75x2.5 Bottom Chords kg 0.00
60x60x2.5 Bottom Chords kg 0.00
50x50x2.5 Bottom Chords kg 0.00
75x75x2.5 Rafters kg 0.00
60x60x2.5 Rafters kg 0.00
50x50x2.5 Rafters kg 0.00
75x75x2.5 Struts and Bracings kg 0.00
60x60x2.5 Struts and Bracings kg 0.00
50x50x2.5 Struts and Bracings kg 0.00
40x40x2.5 Struts and Bracings kg 0.00
75x75x2.5 Purlins kg 0.00
60x60x2.5 Purlins kg 0.00
50x50x2.5 Purlins kg 0.00
40x40x2.5 Struts and Bracings kg 0.00
Sub Total Metalwork: 0.00 kg

I Panel Works
i …… mm thick Gorkha Eco Panel
a Exterior walls
Long walls Sft 0.00
Short walls Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
b Interior walls
………………... Partition 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Deduction: ……….. Sft 0.00
Sum: 0.00 0.00
5% wastage: 0.00
Sub Total 1: 0.00
No. of Panels: 0.00
Total Area for fitting Charge 1 Sft 0.00 Sft

Prepared by: ............................... Checked by: Er. Sabin Budhathoki


J Aluminium Works
78mm Aluminium Door Chinese Series Sft
78mm Aluminium Window Chinese Series Sft

K CCGI Sheet
Truss ………. Sft
Truss ………. Sft
Truss ………. Sft
Sub Total: 0.00 Sft

L False Ceiling Work


Inner False Ceiling 1 Sft
Outer False Ceiling 1 Sft
0.00 Sft

M Cement board enclosure


Truss ………. Sft 0.00
Truss ………. Sft 0.00
Truss ………. Sft 0.00
0.00 Sft

N Wall putty and paints


Exterior wall Sft
Interior wall Sft
false ceiling Sft

Note: All measurements are in feet or inches

Prepared by: ............................... Checked by: Er. Sabin Budhathoki


AMAR JANAKI CONSULT & BUILDERS Pvt. Ltd.
Itahari, Nepal

Client: karmachari sancahie kosh


Location: birtnagar
Project: Storey Expansion

COST ESTIMATE
S.N. Descriptions Quantity Unit Rate

A Metal Works and color c.g.i 0.39mm roofing 598.00 sqft 280
works
B Panel Works (Prefab Wall 7.5'x2' )
50 mm thick Gorkha Eco Panel with 5%
i 53 No. 3,000
wastage (Interior Wall)
ii Installation accessories 798.00 Sft 25
iii Installation Charge 798.00 Sft 25
Sub Total:

C Aluminium Works
Metal Frame Door with flush panel 21.00 Sft 400
40.00 Sft 425
78mm Aluminium Window
Sub Total:

E Wall putty & coloring works


i All walls 1596.00 Sft 30

F. Transport 8000.00lumpsum

Total:

Note:-
i VAT is excluded.
ii Water & Electricity should be provided by the client during construction works.
iii Actual quantity may vary as per site condition.
iv Transpotation Charge is free only in Itahari.
v We prefer client to do the foundation work by himself
vi Lodging and fooding for installers should be done by client.

Prepared by: ...................... Checked by: Er. Sabin Budhathoki


& BUILDERS Pvt. Ltd.
pal

Date: 2074/12/13

MATE
Amount (NPR) Remarks 49
167,440.00 Assuming 1.5' projection
of Gable roof on all sides

159,600.00 Interior Wall

19,950.00
19,950.00
199,500.00

8,400.00 no@door size 1@7'x3'

17,000.00
no@window size 2@5'x4'
25,400.00

47,880.00

8,000.00

NPR 448,220.00

nstruction works.

Prepared by: ...................... Checked by: Er. Sabin Budhathoki


882

61
821

Prepared by: ...................... Checked by: Er. Sabin Budhathoki


AMAR JANAKI CONSULT & BUILDERS Pvt. Ltd.
Itahari, Nepal

Client:
Location:
Project: Date: 2073/…./….

PROJECT FINAL REPORT

S.No. Particulars Unit Quantity Remarks


1 Panel Works
a …… mm sandwich panel Nos …… sent …… returned
…… mm sandwich panel Nos …… sent …… returned
…… mm sandwich panel Nos …… sent …… returned
b Quantity Including Door & Windows Sft
c Adhesive Cement kg …… sent …… returned
d PU-Foam Nos …… sent …… returned
e PU-Cleaner Nos …… sent …… returned
f 6" Nail kg …… sent …… returned
g Anti-Crack Tape Roll …… sent …… returned
h Fibre Mesh m …… sent …… returned

2 Metal Works kg …… sent …… returned


3 Aluminium Works
a 78mm Doors Sft
b 78mm Windows Sft
4 Roofing (CCGI / UPVC) Sft
5 False Ceiling Work Sft
6 18mm Cement Board Sft
7 Wall Putty and Paints Sft
i External Sft
ii Internal Sft
iii False Ceiling Work Sft

Prepared by: ............................... Checked by: Er. Krishna Sundar Kumpakha


AMAR JANAKI CONSULT & BUILDERS Pvt. Ltd.
Itahari, Nepal

Client: Date: 2073/…./….


Location:
Project:
BILL OF QUANTITY

S.N. Particulars Unit Quantity Rate Amount Remarks


1 Gorkha Eco Panel Work
i …… mm sandwich panel Nos 0.00 Err:509 Err:509
ii Install accessories Sft 0.00 25.00 -
iii Fitting charge Sft 0.00 25.00 -
Sum: Err:509
Discount:
Sub Total: Err:509
2 Metal Works kg 0.00 160.00 -
3 Aluminium Works
a 78mm Doors Sft 0.00 650.00 -
b 78mm Windows Sft 0.00 550.00 -
4 Roofing (CCGI / UPVC) Sft 0.00 100.00 -
5 False Ceiling Work Sft 0.00 120.00 -
6 18mm Cement Board Sft 0.00 130.00 -
7 Wall Putty
i External Sft 0.00 20.00 -
ii Internal Sft 0.00 16.00 -
iii False Ceiling Sft 0.00 16.00 -
8 Wall Paints
i External Weathercoat Sft 0.00 25.00 -
ii Internal Distemper Sft 0.00 20.00 -
iii False Ceiling Sft 0.00 20.00 -
Total: Err:509
Advance:
Grand Total: Err:509

Prepared by: ............................... Checked by: Er. Krishna Sundar Kumpakha


AMAR JANAKI CONSULT & BUILDERS Pvt. Ltd.
Itahari, Nepal

Name: Krishna Prasad Duwal and Sunil Bohaju Date: 2073/04/04

BILLING FOR TRAINEE PANEL INSTALLER

S.N. Particulars Unit Quantity Rate Amount Remarks


1 Krishna Prasad Duwal Day 5.00 700 3500.00
2 Sunil Bohaju Day 5.00 700 3500.00

Total: 7000.00
Advance: -3000.00
Grand Total: 4000.00

Prepared by: ........................... Checked by: Er. Krishna Sundar Kumpakha