Progress Calculation Procedure for Engineering
Normally in an EPC project, progress calculation
procedure for engineering deliverables is
developed and used to monitor project
performance against man hour spent. When
working with progress calculation, you should
know the level of reporting. In a typical project,
engineering progress is measured as level 2
(phase wise) and level 3 (engineering discipline
wise) and level 4 (document wise). Refer to the
following procedure to calculate engineering
progress,
1) Engineering progress for each document
(Level 4) = the sum of the product of weight
factor for each work step and engineering
progress for each work step
2) Engineering pragress for each discipline (level 3) = the sum of the product of weight factor for each document
and engineering progress for each document
3) Calculate total engineering progress (level 2)
‘engineering progress for each discipline
the sum of the product of weight factor for each discipline and
How to Get an Engineering Drawing Progress - Level 4
‘The progress calculation is done based on engineering work steps and their weight factors for an engineering
drawing. See the below sample work steps and weight factors.
Sample weight factor for each work step for each engineering drawing
Weight factors calculated based on effort required for each work step fora particular drawingldocument. The
rato of weight factor foreach work step could be diferent depending on your project team's exper judgment.
The folowing work steps are required to produce an engineering drawing as minimum
4. Star
2. Study/Preparation
3. Issue for intemal roviow
4 Issue to client
5. Approval by client
6. Issue for construction
‘The projects | involved describe the weight factors forthe above work steps are as follows:
1) 8% (0.05) of total hours for “Start” work stop
2) 45% (0.45) of total hours for "Study and preparation" step
3) 10% (0.10) of total hours for “Issue for Internal Revio\4) 10% (0.10) of total hours for “Issue to client"
5) 15% (0.16) of total hours for to get "Approval by Client”
6) 15% (0.15) of total hours for “Issue for construction”
‘The sum of total weight factors forall work steps must be 100% (1).
Let's find out how a piping drawing progress is calculated, Suppose a piping isometric drawing design has been
completed 50% of “Study and Preparation’ work step. See the detal's calculation and below figure for easy
understanding
Progress for a piping isometric drawing at that stage = Weight factor for “Start” work step (0.05) x progress for
“Start” work step (100%) + Weight factor for “Study and Preparation” (0.45) x progress for "Study and
Preparation” work step (50%)
‘Therefore, the actual progress for that drawing up to 50% completion of study and preparation step is 27.5 %.
The actual progress would be 50% when “Study/Preparation” work is completed 100%.
150 drawing for
pump station
iscipline| 2 e Fe . 59 re
Piping
Quantity Progress(% Complete) = D3 x D4 + E3 x E4
= 0.05 x 100% + 0.45 x 50% = 27.5%
Progress Calculation for Engineering
Specification/Requisition-Level 4
Progress calculation for an engineering specification/requisition is done using the same exercise for engineering
drawing. The only different is its work Step and weight factor as weight factor for each work step for each
specification/requisition is required to calculate the quantity progress.
Sample weight factor for each work step for each engineering
specification/requisition
‘The following are work steps and weight factors for a production of engineering specification/requisition.
41) 8% (0.05) of total hours for “Start" work step
2) 45% (0.45) of total hour for "Study and preparation” step.
3) 15% (0.15) of total hours for "Issue to client"
4) 20% (0.20) of total hours for to get "Approval by Client"
5) 15% (0.15) of total hours for “Issue for construction/Purchase” Once again, the sum of total weight factors for
all work steps must be 100% (1).How to Get Engineering Progress by Discipline -Level
3
To calculate discipline wise (level-3) engineering progress, in other word, physical progress for an engineering
discipline = the sum of the product of weight factor for each document and engineering progress (quantity) for
‘each document,
How to find weight factor for engineering document
Weight factor calculation for engineering document is required to calculate engineering progress for each
discipline. Engineering documents are normally categorized drawings, specifications, requisitions and
information documents. P&ID drawings, isometric drawings, pump GA, foundation drawings, etc. are in drawing
category. Material specification, equipmentipiping fabrication and erection specification and Instrument cable
specification are in specification category. REQ for piping material, REQ for pump/compressor/blower and etc.
are in requisition category.
Weight factor for an engineering document
documents in each discipline,
‘Assume the budgeted man hour for an iso metric drawing is 200 and 10,000 hours for all piping documents.
‘Therefore, weight factor for that iso drawing is (200/10,000) 0.02
1udgeted man hour for a documentitotal budgeted man hour for all
Progress Calculation for Mechanical Engineering Discipline
Progress calculation for mechanical engineering discipline = the sum of the product of weight factor for each
document and the actual progress of each document in mechanical discipline for a particular project.
For instance, a project includes the mechanical scope required to produce a list of drawings and documents and
the work is in-progress. Suppose a table of mechanical documents are shown as the following,
°% Complete = = 5% x 100%+45%x100%+
45%X400420%X100415%X33% = 90%
Bocgced weg
loocument Ti category] iecitne Sudeeted| Weel .
eee aan |Spec/Req| Mech er 100.0%} 100.0%) 100.0%) 100.0%) 23.0% | S&S
rox abin aes, |" : ee
lacie Bane ISpecit 500} 0.08 | 1000 a0 100.0% 100.0% | 100.0% | 100.08 5
Reaver Pues 10H jee ech 459[a0%27| 1000%| 100.05] rec0%| woos] woox | one [2%
eect [secre ech asolaacze| soao%| 20.5| so00%| soos] 22.08 | sacs | sa
feectcton frPUME sc/nee|Mech 250] aaen|sonos| soos] toues| 7508) oom soa] 5.1
eaters at } i
eal vese ims cn ssofaxm| poe] ss25| cox] aon] aon | soon ao
Featorteat exer. oececfech oo] e069] 000%] 55%] cox] a0x| 00% oon] 2.3%
Physical Progress =0.03656x90% =3.3%
ocameneite _[eatgor[oinine| mere ME wow) 0 s
lonowinstorsunes:oraving fess | | 024s) oon] ons] cox! aos) om oo | or} aon
eager | |
emese-aatce ong aoa | 0) ss] aun] an] cas) aus) oun aos | 00s] omWeight factor for pump data sheet is 0.0356 obtained based on 200 budgeted hours/ 5470 total budgeted hours
‘of mechanical discipline.
‘The progress data in “Quantity Progress (% complete)" column is referred to the document progress calculation
based on work step completion and work step weight factor.
For example,
‘Quantity Progress (% complete)" for pump data sheet = 5% x 100%+45%x100%+15%x100+20%
x100%115%x33% = 90% ,
This is the same calculation method used for a piping isometric drawing progress as explained on above.
‘The progress data in "Weight Progress" which also known as physical progress column is referred to the
progress calculation based on document weight and Quantity Progress (% Complete).
For example,
Physical Progress of pump data sheet document
03656 x 90% = 3.3%,
Finally, the total progress for mechanical engineering section, 37.8% is the sum of weight progress for each
document.
Progress calculation procedure for process, piping, civil, structure, electrical and instrumentation is done using
the same methodology as mechanical discipline.
How to Get Overall Engineering Phase/Stage — Level 2
Progress data for engineering phase can be oblained using the same exercise like discipline wise pragress
calculation. The difference is the way how you want to group it. That means weight factor for each engineering
discipline is required to analyse the total progress of all disciplines.
‘See the below formula to get overall engineering progress.
Progress for engineering phase/stage = the sum of the product of weight factor for each discipline and progress
for each discipline, see how weight factor for each engineering discipline as below.
How to find weight factors for engineering disciplines
‘Weight factor = budgeted hour for each discipline/Total budgeted hour for all discipline for a particular project,
For example
‘Assuming that budgeted man hour for mechanical, process, piping, civil, structure, electrical and
instrumentation are listed as table below.
Weight factor for mechanical engineering disciplin
man hour) = 0.1744
‘5470 (Budgeted man hour) / 31370 (Overall engineeringMechnical
Process 3000 0.0956
Piping ‘8000 0.2550
civil 3200 0.1020
[Structure 3500 0.1116
[Electrical 4000 (0.1275
Instrumentation “4200 0.1339
TAL 31370
eering
Progress Calculation for Overall En:
Mechanical engineering progress is 37.8 % as stated above and assuming that the individual progress for other
disciplines is listed as below table.
‘Then, Overall Engineering phase/stage progress = the sum of the product of weight factor for each discipline
and physical progress for each discipline,
= 0.1744 x 37.8% + 0.0956 x 50% + 0.2550 x 20% + 0.1020 x 30% + 0.1116 x 25% + 0.1275 x 15% + 0.1339 x
13% = 26%
Process 3000 0.0956 50%
Piping 3000 0.2550 20%
civil 3200 0.1020 30%
Structure 3500 0.1116 25%
Electrical 4000 0.1275 15%
2200) 0.1339 13%
or Be
Download sample progress calculation sheet to leam more,