April Electrical

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Tower 2

Conduiting & Target


LEVEL Back Box Completion Point Wiring Cable Tray Contractor LT Cables
Installation Date
Podium 1
Handed Over
Podium 2 2488
to Civil
Handed Over
Level 1 2488
to Civil
Level 2
Level 3
Level 4
Level 5
Level 6
Level 7
Level 8 14-Apr-18
Level 9 17-Apr-18
Level 10 20-Apr-18
Handed Over
Level 11 7464 25-Apr-18
to Civil 23-Apr-18
Level 12 7464 25-Apr-18 26-Apr-18
Level 13 14928 15-Apr-18 29-Apr-18
Level 14 14928 15-Apr-18 2-May-18
Level 15 14928 20-Apr-18 5-May-18
Level 16 7464 20-Apr-18
Level 17
Level 18
Per Day Target 933

Target Productivity
90
(S.ft / Day)

# of Teams /
10
Masons Required