How To Calculate The Quantity of Shuttering: Example
How To Calculate The Quantity of Shuttering: Example
will be built up there. To work out the quantity of shuttering plywood, nails, shuttering oil,
clamps etc. the following formula will be used :-
Here, the wooden shuttering is used. The quantity of the shuttering should be calculated
in numbers or running foots.
1. PLYWOOD: 12 MM THICK (8′ X 4′)
= Covered area x Thumb rule
= 2000 sft x 0.02
= 40 No’s
2. WOODEN BATTENS : (3” X 3”)
= Covered area x Thumb rule
=2000 sft x 0.4
= 800 rft (running feet)
3. BEAM BOTTOM PLATES: (1.5” THICK)
= Covered area x Thumb rule
= 2000 x 0.24
= 480 rft (running feet)
Before calculating the quantity lest’s clear this first which are going to use in our calculation.
What is thumb rule?
It is defined as we chose a constant number for the approximately quantity calculation (Any
think), with the help of our experience and our daily practice. The result we get by using thumb
rule is nearly equal to the actual quantity. So thumb rule is considered as the easiest way to
calculate the approx quantities.
For better understanding lets solve this example for shuttering quantity calculation.
EXAMPLE:
Suppose we have a covered area is 200o square feet and over there we need to construct the
R.C.C slab. So we need to calculate the quantity to tell the contractor.
1. So calculate the quantity of Shuttering Plywood, Nails, Shuttering oil, clamps etc.?
IMAGE SOURCE
GIVEN DATA:
Covered Area = 2,000 square foot.
Shuttering type = Wooden
Quantity of shuttering = ?
SOLUTION:
The quantity of the shuttering is to be done in numbers or in running foots.
4. WOODEN BALLIES:
For Slab = Covered area x thumb rule
= 2000 x 0.16
= 320 No’s Ans..
For Beam = Beam bottom plate running feet x thumb rule
= 480 x 0.5
= 240 No’s Ans…
5. MS CLAMPS:
= Covered area x thumb rule
= 2000 x 0.08
= 160 No’s An..
6. SHUTTERING OIL:
= Covered Area x thumb rule
= 2000 x 0.006
= 12 litters Ans..
Note: These all quantities are approximately little less or more to the actual quantity is going to
use at the site. For actual quantity measurement you need to proper take all the dimensions
(Length, Width ) and then subtract that areas over which shuttering is not going to use and then
you can calculate the exact calculation.