Professional Documents
Culture Documents
EHV Cable Installation Technology For Tunnels and Ducts in Japan
EHV Cable Installation Technology For Tunnels and Ducts in Japan
http : //www.cigre.org
SUMMARY
Long-length cables have been installed in tunnels for purposes of total project cost reduction,
construction period shortening and joint quantity reduction in a view point of a cable circuit reliability
advancement in Japan. Recently, the long-length cable installation technology are also developed and
applied for successive installation in multiple duct sections.
Meanwhile, for cases in which older Oil-Filled cables are replaced with new XLPE cables, the
effective use of existing narrow utility tunnels through the use of triplex type large conductor XLPE
cables is being applied, and for duct applications, narrow manhole installation technology for
installing XLPE cables in existing manholes is also being applied.
This report introduces the technological issues involved in long-length cable installations in tunnels,
ducts and means of addressing those issues, also introduces the effective use of existing infrastructure
through the use of triplex type large conductor cables, new joint installation technology for existing
narrow manholes, and installation technology for deep vertical shafts.
KEYWORDS
Long length cable installation - Tunnels - Ducts - Triplex type large conductor size cable -
Narrow manholes - Deep vertical shafts
kurata.tatsuo@jpowers.co.jp
Foreword
Long length cable installation projects for tunnels and ducts application have been completed
successfully in Japan since 1990’s. Max. continuous cable length 2500 m and 1050 m were installed in
a tunnel and duct respectively. The long length cable installation technology has developed for
purposes of total project cost reduction, construction period shortening and joint quantity reduction in
a view point of a cable circuit reliability advancement. Long-length cable installation has mostly been
used for tunnels, in which the limitations at the time of installation are few—as long as various
technical issues concerning matters such as the cable manufacturing equipment, the transport method,
and the installation base have been adequately addressed. However, practical needs and improved
installation technology have led to the increasing application of long-length cable installation to duct
installation. It is said that we are now at a point where long-length cable installation is no longer
limited by manufacturing and installation technology but by transport limitations. Various cable
installation achievements in Japan are shown in Table 1-1.
Opportunities for using utility tunnels and ducts are increasing even in countries that have mostly used
direct buried cable application, and the long-length cable installation technologies have the potential to
be applied widely.
In addition to introducing action assignments and their counter approaches for long length cable
installation, this report also introduces Japanese trends in unique power cable installation technology,
such as a retrofit jointing technology for existing narrow manhole, installation technology in vertical
shaft.
Table 1-1 Achievements in Long-Length Cables Installation in Tunnels and Ducts, Narrow Manhole Cable installation,
and Vertical Shaft cable Installation
Cable Cable Commission
Length Year
500 kV XLPE 1/C 800 mm2 1150 m 1994
275 kV XLPE 1/C 2500 mm2 1800 m 1998
500 kV XLPE 1/C 1000 mm2 1200 m 1999
500 kV XLPE 1/C 1000 mm2 1100 m 1999
500 kV XLPE 1/C 2500 mm2 1800 m 2000
Tunnel
200 m 2005
-ft
(Vertical Shaft)
1
1. Installation Technology for Long-Length Cable
1-1 Long-Length Cable Installation in Tunnel
A number of factors have to be taken into consideration when long-length cables are installed in
tunnels. These include the length to which cable length can be installed, the installation method, the
time allotted for installation, the installation cost, the power supply capacity required for cable
installation, cable installation base type, workability, cable drum sizes, cable drum transport methods,
transport vehicle selection, and necessity to apply for permission to transport ultra-heavy vehicle.
For the 2500 m long 275 kV 2500 mm2 XLPE cable whose installation was completed in 2002,
because the overall drum weight was approximately 140 tons, a variety of factors needed to be taken
into detailed consideration when the drum was transported from the factory to the port and then by
land from the port to the installation base. These factors included traffic permissions and other legal
regulations, subgrade durability, and load restrictions for bridges crossed. Also, even for shipping the
drum by sea, taking the ease of operation of the approximately 300-ton floating crane used to lift the
drum into consideration, an appropriate time, when the waves would be calm, had to be carefully
determined.
The typical methods for installing long-length cables in tunnels are (1) the hauling machine method,
(2) the motor driven roller method, (3) the magnetic belt method, and (4) the twin pulley method. The
hauling machine method or the motor driven roller method is used typically, but the magnetic belt
method, which makes high-speed cable installation possible, and the twin pulley method are used
when multiple cables must be installed from the same base over a long conveyance distance in tunnel.
A recent achievement of long-length cable installation is a 2250 m long 275 kV 1 x 2500 mm2 XLPE
cable (transport drum width 11.8 m, Flange diameter 3.7 m) using both a motor roller and a hauling
[1]
machine, which was completed in 2006.
2
installation in 2003.
3
Space for Triplex
Type Cable
6 ccts
newly
installed
Space for 2 ccts
Single-Core XLPE removed
Cable with Vertical
Snaking
Fig. 2-1 Space comparison between Triplex Type Fig. 2-2 Advantage of Large Size Triplex XLPE Cables
Cable and vertically snaked Single-Core cable in pre-existing tunnel
Although the triplex type XLPE cable thermal expansion and contraction can be ignored comparing
with single-core XLPE cables, mock-up test on triplex type large conductor cable was conducted to
figure out the thermo-mechanical behaviors.
Approx. 90 m of 154 kV 1000 mm2, approx. 60 m of 154 kV 600 mm2 and 66 kV 1000 mm2 triplex
type XLPE cables were used in the tests.
The mock-up test assembly is shown in Fig. 2-3. As test results, even though the triplex type XLPE
cable, it was observed that the cable sag between support structure. The large conductor cross-section
triplex type XLPE cable characteristics are similar to snaking cable with applying long support
distance. Therefore, cable fixing shall be considered at the end portion. Summary of test results are
shown in Table 2-1.
For the actual application of 154 kV 1000 mm2 triplex type XLPE cable, 1.5 m support intervals were
applied. Thus, cable occupation space in a tunnel was minimized. Then, since the joint spacing in the
tunnel was limited, the long-length triplex type XLPE cable was installed with considering the joint
allocation and long distance conveyance in the tunnel. The long distance conveyance of the triplex
type large conductor size XLPE cable was accomplished by using motor driven roller method as
shown in Fig. 2-4. Records of the triplex type large conductor cable installation with long distance
conveyance in tunnels are shown n Table 2-2.
4
Table 2-2 154kV Triplex Type Cable installation Records
Conveyance
Conveyance
Cable Length Distance in
Period
Tunnel
627m 4300m 3 days
Motor Roller Free Roller Control Cable 706m 4800m 3-4 days
ダミー線路
Not
90oC 3
Apply
IJ側 Test本線路
Sample NJ側 4 90oC Both ends Applied 10
W W
5 90oC Both ends N/A 10
6 90oC Single end Applied 10
Movable Movable 7 90oC*3 Both ends Applied 25
Support Support 8 105oC*3 Both ends Applied 5
(Voltage )
AC
Step 2
5
100 1.20
No.1 :ヒートサ イクルの み No. 3:連続 負荷 一定 No .5: クリート無し
No.1 No.2 No.3 No.4 No.5 No.6
60 0.90
Temp(oC).
0.80
40
面圧[MPa]
温度(℃)
0.70
20
0.60
Interface Pressure
0 Ambient Temp.外気温 Interface Temp.
界面温度 界面面圧 0.50
0.40
-20
0.30
許 容面 圧
-40 0.20
0 5 10 15 20 25 30 35 40 45
試験日数 最低許容面圧
Day Minimum allowable0.2MPa
interface pressure 0.2MPa
Fig. 2-6 Variation of temperature and pressure at interface between
RBJ and cable core (STEP1) EPR Rubber Unit Fig. 2-7 Workability Verifying in Narrow Manhole
Cable
Guide Pipe
6
Table 3-2 Installation Methods Considered for the 200 m Deep Vertical Shaft
Back-up Winch
Winch Winch Winch
Wire Wire
Pulling Pulling
Direction Direction Wire
Guide wall Pulling
Backup wire
Direction
Guide wire
Pulling Eye Pulling Eye Pulling Eye
Outline
Bond Clamp
Guide Guide Hauling
Machine Hauling
Hauling Hauling Machin Back tension
Machine Machine Winch
・Pulling by upper side winch. ・Distribute the pulling tension by ・ Bonding cable with the pulling
Feature
・Upper guide wall radius shall be using hauling machines set in wire by fixing bond clamp. Pulling
larger to minimize the side wall vertical shaft. tension is distributed to the pulling
pressure of cable wire.
4. Conclusions
This report introduced the technological issues involved in long-length cable installations in tunnels
/ducts and means of addressing those issues, also introduced the effective use of existing infrastructure
through the use of triplex type large conductor cables, new joint installation methods for existing
narrow manholes, and installation methods for deep vertical shafts.
BIBLIOGRAPHY
[1] K. Fukuda et al; Recent Installation Technology for XLPE Cables in Japan, CIGRE B1-303,
2006
[2] K. Iwasaki et al; Recent Technologies for Replacement of Underground Cable Systems, CIGRE
SYMPOSIUM, Osaka, Japan Nov. 2007, No.103
[3] T. Shiro et al; Evaluation of 154kV Factory-Expanded Cold Shrinkable Joint in Narrow Manhole,
Proceedings of the eighteenth Annual Conference of Power & Energy Society, IEEJ, No. 126,
2007 [in Japanese]
[4] T. Shiro et al; Evaluation of 154kV Site-Expanded Type Rubber Block Joint in Narrow Manhole,
Proceedings of the eighteenth Annual Conference of Power & Energy Society, IEEJ, No.127,
2007 [in Japanese]
[5] T. Fujichika et al; Installation of High-voltage XLPE cable into 200m deep vertical shaft,
Proceedings of the sixteenth Annual Conference of Power & Energy Society, IEEJ, No.300, 2005
[in Japanese]