ETAP FAQ # 13
Create A Cable Pulling Project
ETAP 4.7.0 includes a completely new Cable Pulling program. This new version has been enhanced with many
intelligent features including three-dimensional display of the conduit system, which make it a powerful tool for the design
of conduit cable systems.
To create a Cable Pulling project right click on the cable pulling systems folder and select “create new”. To open the
CP1 presentation, double click on its icon and a blank presentation will open. You can rename the presentation by right
clicking on its icon and selecting the properties option.
Insert Cables
ETAP’s Cable Pulling program is a fully integrated software package and this allows the capability of inserting cables
from existing ETAP one-line diagrams and underground raceway systems. You can easily transfer them to your Cable
Pulling presentation.
The conduit cross-sectional view allows you to see the conduit percent fill. The program will give automatic warnings if
the percent fill is exceeded.
ETAP FAQ # 13 - Create A Cable Pulling Project
Results
When you perform the Cable Pulling calculation, the program displays the calculated forward, reverse and sidewall
tensions below each location on the cable pulling presentation. Complete results are shown on the Cable Pulling reports.
The program flags violations on the reports, Alert View Window, and the Cable Pulling presentation.
In the following example, the program has detected two sidewall pressure violations. These problems can be corrected
by changing the bend radius from 2 ft to 3 ft.