Professional Documents
Culture Documents
Project Management: Dr. James A. Bednar
Project Management: Dr. James A. Bednar
Project Management: Dr. James A. Bednar
project:
Build Shed
Install siding
1 day
Pour foundation Build frame Finish
Planning Obtaining Materials Constructing
1 day 2 days Install roof 1 day
Pour foundation
2 days
Build frame
Install siding
Install roof
Finish (door, etc.) Network diagrams can be constructed from the WBS,
adding dependencies and estimated durations. See slides
Rule of thumb: break things down as far as necessary to
on estimation for caveats. (Dates are optional.)
estimate and schedule them, and no further.
SAPM Spring 2006: Project Management 5 SAPM Spring 2006: Project Management 6
Install siding
Install siding
1 day
1 day Pour foundation Build frame Finish
Pour foundation Build frame Finish
2 days
2 days
The critical path is the longest path through the network Tasks not on the critical path have slack – the duration by
diagram – it is the minimum duration of the project if there which they can be late without making the project later
are infinite resources (so that tasks can occur in parallel) than the critical path duration.
and accurate estimates. Here, putting up the siding has one day of slack: one day
Here, everything but putting up the siding is on the critical longer than estimated is ok, but if it takes longer it will be
path, and must happen in the order specified. the new critical path, and delay the project.
SAPM Spring 2006: Project Management 7 SAPM Spring 2006: Project Management 8
PERT/CPM Charts Gantt Chart
Network diagrams come in a variety of flavors with
different names:
Both show similar information, but use different methods graphically, in calendar form, with one bar per activity. The
for calculating the critical path and slack. bar shows the earliest start date and duration.
SAPM Spring 2006: Project Management 9 SAPM Spring 2006: Project Management 10
Gantt charts can also show summary activities (see E.g. if only one person is available to work on the shed
‘Planning’ entry), dependencies (arrows), and milestones project, the siding and roofing tasks must be done in
(diamonds). serial, due to the resource constraint.
SAPM Spring 2006: Project Management 11 SAPM Spring 2006: Project Management 12
Crashing/Fast tracking For more info
If the critical path is still not fast enough, it’s possible to Project Management Institute (PMI): Largest
shorten the duration by changing some assumptions. E.g.: international PM organization; US-based (pmi.org)
Crashing: Change the duration of some critical task, e.g., International Project Management Association (IPMA):
if it is possible to parallelize it by assigning more Oldest international PM organization
people to it. (www.ipma.ch)
Fast tracking: Allow tasks to be done in parallel by Association for Project Management (APM): UK-based
changing the logic in the network diagram. national organization (www.apm.org.uk)
SAPM Spring 2006: Project Management 13 SAPM Spring 2006: Project Management 14
Summary References
• Project management charts and techniques are useful PMI (2004). A Guide to the Project Management Body of Knowledge
for scheduling tasks with complex dependencies (3rd Ed.). Project Management Institute.