GENERAL ABSTRACT OF COST

Name of work :- Construction of RCC Bridge over Saijirok River

SL No Sub -Head/ Items of Work Quantity Rate(Rs-p) Unit Amount(Rs-p) Remarks

1) MAIN BRIDGE 1.00 6531799.29 Each 6531799.29 Annexure-I

2) PROTECTION WORK 1.00 887382.14 Each 887382.14 Annexure-II

3) DISMENTLING 1.00 66944.03 Each 66944.03 Annexure-III


Rs 7486125.46 A
Add . 12% GST on (A) Rs 898335.06
Add 1% labour cess on (A) Rs 74861.25
Say Rs 8459321.77 B
Add 3% contingency charge on (B) _ Rs 253779.65
Rs 8713101.42 C
Add 11.75% Agency charge on (C) _ Rs 1023789.417
Rs 9736891
(Rupees Ninety Seven lakh Thirty Six thousand Eight hundred and Ninety One) only