Professional Documents
Culture Documents
004 MS ITP RA Porland Cement Plaster Works
004 MS ITP RA Porland Cement Plaster Works
004 MS ITP RA Porland Cement Plaster Works
Title :
METHOD STATEMENT FOR PORTLAND CEMENT PLASTER
REVIEWER / APPROVER
REV DATE STATUS REVISION DETAILS Sub Main
EXTERNAL
Con Con
0 13-Sep -15 FA FOR REVIEW & APPROVAL
Status Code:
D : Draft FI : For Information FC : For Construction
* External Authorization (Client),
P : Preliminary FA : For Approval
where required
Distribution :
Method Statement for Portland Cement Plaster Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 1 of 9
Project Logo Project Name : VVIP Beach Villa
Project No. : SP/C/1616/14 Location: Al Khor
Client Project Manager Consultant Contractor
Table of Contents
1 Scope /Objectives
2 Reference
3 Access/Egress
4 Logistics
5 Health and Safety Hazards
6 Definitions
7 Responsibilities / Supervision
8 Procedures /Method to be Employed
9 Training
10 Working hours
11 House keeping
12 Manpower Requirement & Supervision
13 Material Requirement
14 Plant & Equipment Requirement
15 Q.C Approvals and other Documentation
16 Supporting documentation
17 Distribution
18 Other information
19 Site Safety Engineer’s Approval
20 Attachments (Compulsory)
21 Risk Assessment
22 Inspection and Test Plan
23 Checklist
Method Statement for Portland Cement Plaster Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 2 of 9
Project Logo Project Name : VVIP Beach Villa
Project No. : SP/C/1616/14 Location: Al Khor
Client Project Manager Consultant Contractor
The Purpose of this procedure is to outline procedure for rendering using ordinary Portland cement mix for
masonry and concrete surfaces.
2 REFERENCES
Project Specification - Volume 2, Architectural, Civil & Structural section 24 – Finishes – Portland Cement
Plaster.
3 ACCESS/ EGRESS
4 LOGISTICS
Plastering materials and accessories are neatly stored / stacked in allocated areas for safe storage and easy
distribution.
Inspection Request will be raised and approved prior to start these activities, Permits if required and shall be
taken and will be available on site.
6 DEFINITIONS
MS – Method Statement
Method Statement for Portland Cement Plaster Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 3 of 9
Project Logo Project Name : VVIP Beach Villa
Project No. : SP/C/1616/14 Location: Al Khor
Client Project Manager Consultant Contractor
7 RESPONSIBILITIES/ SUPERVISION
Project Manager – Ensure the work is progressing as per the approved schedule and contractual requirement
Project Engineer – Responsible to carrying out the work in accordance with approved shop drawing, Project
Specification and QCS 2014.
QA/QC Engineer – Ensure the quality requirement as outlined in the Project Quality Plan are being achieved
Safety Engineer – study the health and Safety aspects of the job, achieve remedial measure and oversees
implementation of these.
Foremen / Charge Hand – Carry out the work as advised by the project engineer.
8.2 Mock-up
Prior to the applying of plastering work and proceeding wall plastering mock-up for all types of 15 mm thick
Cement plaster at least 9.3 sq. m ( 3.05 m x 3.05 m ) in surface area to demonstrate aesthetic effects and
set quality standards for materials and execution will be built on site.
Provide each sample wall plastering panel using materials, together with bond and joint tooling, shown or
Request for inspection will be issued to the consultant to approve setting out prior to start of work.
MEP coordination should be conducted for provision of MEP duct opening and Holes of MEP pipes and
Method Statement for Portland Cement Plaster Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 4 of 9
Project Logo Project Name : VVIP Beach Villa
Project No. : SP/C/1616/14 Location: Al Khor
Client Project Manager Consultant Contractor
8.3 Preparation
Storage tanks are provided for the storage of potable curing water.
Prior to applying any plaster coat, surfaces shall be thoroughly cleaned to remove dust, loose particles,
foreign materials, form oils, remains of wood forms. Use stiff brush as necessary, and reduce suction in
plaster backgrounds by applying water in uniform rates.
Fix expanded metal strips with minimum width of 200mm at services chases and at interfaces with RCC.
Install plaster beads and stops as specified.
Surfaces to be rendered will receive a spatter dash treatment of one part of cement and two parts of coarse
sand, mixed with sufficient water to give a consistency of thick slurry is to be dashed on to the dampened
background with either a trowel or a scoop to give a thin coating with a roughcast uneven appearance.
Concrete surfaces will either receive the spatter dash or be hacked by hand or mechanical means to
remove all laitance and to roughen the whole of the surface to a depth of at least 3 mm to expose the
aggregate.
Set the level on the surface at a uniform intervel to guide the masons during plastering.
Overall thickness of internal render (plaster) coat shall be 15 mm to be applied on internal block wall, extra
over on curved face of wall ,internal concrete ceiling, soffit of an concrete staircase and other miscellaneous
location where ever noticed in IFC drawing and project specification
Cement: sand proportions for render mixes shall be as follows, by volume: 1 part cement: 5 parts sand.
Mixing shall be done using mixer machines and transported to place of application on dumpers. Alternatively,
mobile mixers can also be used.
The mix will be used within 1hr of mixing.
Interior Plasterwork: Maintain room temperatures within range recommended in writing by manufacturer for
at least 48 hours before plaster application, and continuously during and after application.
Method Statement for Portland Cement Plaster Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 5 of 9
Project Logo Project Name : VVIP Beach Villa
Project No. : SP/C/1616/14 Location: Al Khor
Client Project Manager Consultant Contractor
Avoid conditions that result in plaster drying out during curing period. Distribute heat evenly; prevent
concentrated or uneven heat on plaster.
Protect plaster coats from freezing for not less than 48 hours after set of plaster coat has occurred.
Job-Mixed Finish-Coat Mix for Use over Concrete: Single final coat for two-coat
plasterwork as follows
Portland Cement Mix: 1 part Portland cement and 5 parts aggregate per parts
Before application, the background is to be brushed down to remove any loose particles and is to be
dampened sufficiently to ensure uniform absorption.
The render is to be applied either by laying on with, or throwing from, a trowel or float the applied mix will be
levelled by the straight edge and the smooth finishing of the surface will be brought by the travel and the
float.
All the corners of the walls will be checked by the right angels. The plastered surface, in case of walls to
receive tile finish is to be left rough and open from the edge of the trowel, and after it has been left long
enough to set firm, it should be combed with evenly spaced wavy horizontally lines.
After application, the surfaces are to be kept damp for a minimum of three days to allow the render to cure.
The surface of the finish coat is to be smooth, true and free from waviness, irregularities or blemishes with
straight, level or plumb angles
9 TRAINING
Work specific training will be given to the personals. All workmen will be informed about the nature and
hazard involved in the complete scope of the job.
Emergency drills will be conducted to test preparedness and response within every six months.
Contract specific occupational health and safety meeting chaired by Al-Balagh representative will be
conducted on a monthly basis throughout duration of the work.
Eye protection, head protection, hearing protection, foot protection and hand protection will be provided. This
will include safety glass or goggles, face mask, safety helmet, ear plug, safety foot wear and safety gloves.
Method Statement for Portland Cement Plaster Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 6 of 9
Project Logo Project Name : VVIP Beach Villa
Project No. : SP/C/1616/14 Location: Al Khor
Client Project Manager Consultant Contractor
10 WORKING HOUR
All the works will be carried on during the site working hours 05:00 a.m. to 05:00 p.m.
Inspection Request will be raised only during the working hours of consultant.
.
11 HOUSE KEEPING
Working Areas will be kept clean by disposing the waste materials at the designated areas. At the end of days’
work, installation supervisor will ensure that the debris is disposed off.
13 MATERIAL REQUIREMENT
OPC
Washed sand
Water
Accessories
Mixer Machine
Skid Loader
Angle Grinder
Scaffoldings
Board Planks
Shovel & Other masonry hand tools
Survey Equipment’s
Wheel Barrows
Mechanical Level/Spirit level
Aluminum Straight Edges tubes
Method Statement for Portland Cement Plaster Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 7 of 9
Project Logo Project Name : VVIP Beach Villa
Project No. : SP/C/1616/14 Location: Al Khor
Client Project Manager Consultant Contractor
Follow approved Method Statement, ITP, QCP, HSE Plan, and Material Approval & Checklist.
16 SUPPORTING DOCUMENTATION:
This MS to be read in conjunction with the below referenced documents Contract Specification & approved
drawings.
17 DISTRIBUTION
Copies of this MS will be circulated to the following for Information & action.
Project Manager
Project Engineer
QA/QC Engineer
HSE Engineer
Supervisor
Foremen/Charge hand
18 OTHER INFORMATION
Ensure that all the activities have been carried out to suit the site conditions and involved with Site –in –
charge.
20 ATTACHEMENTS (Compulsory)
Risk Assessment
Method Statement for Portland Cement Plaster Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 8 of 9
Project Logo Project Name : VVIP Beach Villa
Project No. : SP/C/1616/14 Location: Al Khor
Client Project Manager Consultant Contractor
Method Statement for Portland Cement Plaster Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 9 of 9
Document Reference No.: ISSUE:
BV-ITP-ST-004 REV: 00 Date: 13-Sep-2015
A
Inspection and Test Plan for Portland Cement Plaster Page No. 1 of 2
Legend: S-Surveillance Inspection, W-Witness Inspection, H-Mandatory Hold point, work will not proceed until Inspection approved,R -
Review Record, final status shall be notified by AEB.
Document Reference No.: ISSUE:
BV-ITP-ST-004 REV: 00 Date: 13-Sep-2015
A
Inspection and Test Plan for Portland Cement Plaster Page No. 2 of 2
Project Specification -
Minimum 3 Days after
Volume 2, section 24 –
6 Curing plastered Location by W W S
Portland Cement
Visual check
Plaster/ QCS 2014
Project Specification -
Before starting of next Volume 2, section 24 –
7 Final Inspection W/R H S
activity Plastring Portland Cement
Plaster/ QCS 2014
Legend: S-Surveillance Inspection, W-Witness Inspection, H-Mandatory Hold point, work will not proceed until Inspection approved,R -
Review Record, final status shall be notified by AEB.
RISK ASSESSMENT
Project name: VVIP BEACH VILLA –AL-KHOR.
Activity: Plastering Works Revision: 00
Date of assessment: April 10, 2015
Residual Risk
Item Who is at Risk Rating Action
Task/ Activity Hazard Risk Necessary Control Measures Rating
No. risk By
S L R S L R
Personal PM/
Mis handling injuries. Training should be provided.
General PE/HSE/
Noise hazard Hearing All the workers should wear correct
Power Tools worker/si Forema
4 Electrical Problem 3 3 9 PPE’s to complete the task 3 1 3
te staff / n
Hazard Diseases caused Power tools should be inspected
through dust visitors /Electric
periodically
ian
Chronic cough
Impairment of
Engage only competent person
Inhalation of lung function PM/
General Training on cement hazards & PPE
Cement dust Skin irritation PE/HSE/
Working with worker/si requirement to be regularly given to
5 Prolong contact Conjunctivitis 4 3 12 Forema 4 1 4
cement te staff / the workers
with skin & eyes extremes n
visitors Appropriate respirators for cement
Ingestion causes may
dust to be provided
possible to
death
Material to be stacked in a separate
PM/
Collapse of General area in an appropriate manner at
Personal Injury PE/HSE/
stacked cement worker/si same height
6 Housekeeping (possibly 3 3 9 Forema 3 1 3
bags te staff / Access & walkway should be clear
serious) n
Slips & trips visitors Housekeeping should be done at end
of work everyday
Date of assessment: Jul. 02, 2015 Date of review: Jul. 03, 2015 Date of acceptance: Jul. 03, 2015
LEGEND:
Prepared By:
Reviewed HSE Manager: Major Injury, Illness resulting in disability (Permanent Disability) 4 Very Likely to Happen