Classification: General PRE-COMMISSIONING CHECK LIST FOR

FIRE PUMPS
SAT-100
(rev. 1)
ISSUED BY: DATE: Sheet
ALG 7/JUN/16 1 of 4
PATTERSON PUMP COMPANY LTD

This purpose of this check list is to ensure that the pump installation is ready for commissioning before
Patterson’s service engineers arrive at site. This is so that commissioning can proceed without delays or
problems.

Confirmation of completion is required on each of the following points in order for Patterson to schedule a
commissioning visit. If there are any questions please contact Patterson for assistance.

GENERAL REQUIREMENTS
No. Activity Yes / No
1. The fire water tank is ready and full of water to maximum level (photo is required) YES
2. The pump area is clean and all scaffolding has been removed (photo is required) YES
3. The DCS or other remote control system is operational NO
4. All work permits are ready and the pump(s) can be started YES

HORIZONTAL DIESEL FIRE PUMP SKID


No. Activity Yes / No
1. The skid has been leveled YES
2. The skid has been anchored and grouted with non-shrink grout YES
3. The skid has been filled to top with concrete (photo is required) YES
4. Suction piping has been installed without nozzle loads, and hydrotested YES
5. Discharge piping has been installed without nozzle loads, and hydrotested YES
6. Pressure relief line has been installed, and hydrotested YES
7. Pressure relief valve has been installed (photo is required) YES
Test line and flow meter have been installed, and hydrotested (photo is
8. YES
required)
9. Exhaust piping and muffler have been installed (photo is required) YES
10. All pipes have been supported and pipe clamping has been installed YES
11. The pump and driver are aligned to 0.1mm in all directions YES
If driveshaft is used, DBSE and driveshaft angle are as per IOM
12. Heat exchanger discharge has been piped to tank or drain (photo is required) YES
13. Pump/skid drains have been installed and piped to drain (photo is required) YES
Pressure sensing line is installed with check valves pointing away from
14. YES
controller (photo is required)
15. Fuel tank has been installed and is filled with fuel YES
Fuel tank instruments have been installed and connected (For Connection/
16. YES
waiting for the vendor)
17. Fuel piping supply and return lines are connected (photo is required) YES
18. Batteries have been installed next to skid and battery cables are available YES
Classification: General PRE-COMMISSIONING CHECK LIST FOR
FIRE PUMPS
SAT-100
(rev. 1)
ISSUED BY: DATE: Sheet
ALG 7/JUN/16 2 of 4
PATTERSON PUMP COMPANY LTD

(photo is required) (Batteries have been transferred to the pump shed


beside each pump and to be installed during vendor Presence)
220VAC permanent power is connected to the diesel controller or distribution
19. YES
panel
20. Suction/discharge gauges have been installed YES
The engine has been filled with coolant (refer to the lubricant list document)
21. NO
(During Vendor Presence)
The engine has been filled with oil (refer to the lubricant list document) (During
22. NO
Vendor Presence)
23. Remote alarm signals have been connected to DCS NO

HORIZONTAL ELECTRIC FIRE PUMP SKID


No. Activity Yes / No
1. The skid has been leveled YES
2. The skid has been anchored and grouted with non-shrink grout YES
3. The skid has been filled to top with concrete (photo is required) YES
4. Suction piping has been installed without nozzle loads and hydrotested YES
5. Discharge piping has been installed without nozzle loads and hydrotested YES
6. Test line has been installed and hydrotested YES
7. All pipes have been supported and pipe clamping has been installed YES
8. The pump and driver are aligned to 0.1mm in all directions YES
9. Casing relief valve drain piping has been installed (separately from other drains)
10. Pump/skid drains have been installed YES
Pressure sensing line is installed with check valves pointing away from controller
11. YES
(photo is required)
Cabling between MCC to controller and controller to motor is complete (photo is
12. YES
required)
13. Megger testing is complete and power from MCC is ready to be connected YES
14. The breaker and overload in the MCC are rated according to the motor requirements YES
15. Suction/discharge gauges have been installed YES
16. Remote alarm signals have been connected to DCS NO
Classification: General PRE-COMMISSIONING CHECK LIST FOR
FIRE PUMPS
SAT-100
(rev. 1)
ISSUED BY: DATE: Sheet
ALG 7/JUN/16 3 of 4
PATTERSON PUMP COMPANY LTD

HORIZONTAL JOCKEY PUMP SKID


No. Activity Yes / No
1. The skid has been leveled YES
2. The skid has been anchored and grouted with non-shrink grout YES
3. The skid has been filled to top with concrete (photo is required) YES
4. Suction piping has been installed without nozzle loads and hydrotested YES
5. Discharge piping has been installed without nozzle loads and hydrotested YES
All pipes have been supported and pipe clamping has been installed (Broken PSV at
6. YES
5002A and PO in place)
7. The pump and driver are aligned to 0.1mm in all directions YES
8. Casing relief valve drain piping has been installed (separately from other drains) YES
9. Pressure sensing line is installed (photo is required) YES
Cabling between MCC to controller and controller to motor is complete (photo is
10. YES
required)
11. Megger testing is complete and power from MCC is ready to be connected YES
12. The breaker and overload in the MCC are rated according to the motor requirements YES
13. Suction/discharge gauges have been installed YES
14. Remote alarm signals have been connected to DCS NO
Classification: General PRE-COMMISSIONING CHECK LIST FOR
FIRE PUMPS
SAT-100
(rev. 1)
ISSUED BY: DATE: Sheet
ALG 7/JUN/16 4 of 4
PATTERSON PUMP COMPANY LTD