Fire Water Pumps Pre Commissioning Checklist.
Fire Water Pumps Pre Commissioning Checklist.
Fire Water Pumps Pre Commissioning Checklist.
FIRE PUMPS
SAT-100
(rev. 1)
ISSUED BY: DATE: Sheet
ALG 7/JUN/16 1 of 4
PATTERSON PUMP COMPANY LTD
This purpose of this check list is to ensure that the pump installation is ready for commissioning before
Patterson’s service engineers arrive at site. This is so that commissioning can proceed without delays or
problems.
Confirmation of completion is required on each of the following points in order for Patterson to schedule a
commissioning visit. If there are any questions please contact Patterson for assistance.
GENERAL REQUIREMENTS
No. Activity Yes / No
1. The fire water tank is ready and full of water to maximum level (photo is required) YES
2. The pump area is clean and all scaffolding has been removed (photo is required) YES
3. The DCS or other remote control system is operational NO
4. All work permits are ready and the pump(s) can be started YES