Professional Documents
Culture Documents
Department of Main Roads - Rod Planning and Desingn Manual-Chapter16
Department of Main Roads - Rod Planning and Desingn Manual-Chapter16
16
Chapter 16
Interchanges
December 2005
i
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Manual Contents
Chapter 1
Chapter 12
Frame of the Road Planning and
Vertical Alignment
Design Manual
Chapter 2 Chapter 13
16 Design Philosophy
Chapter 3
Intersections at Grade
Chapter 14
Road Planning and Design
Roundabouts
Fundamentals
Chapter 4
Chapter 15
Application of Design Principles and
Auxiliary Lanes
Guidelines
Chapter 5
Chapter 16
Traffic Parameters and Human
Interchanges
Factors
Chapter 6 Chapter 17
Speed Parameters Lighting
Chapter 7 Chapter 18
Cross Section Traffic signals
Chapter 8
Chapter 19
Safety Barriers and Roadside
Intelligent Transport Systems
Furniture
Chapter 9 Chapter 20
Sight Distance Roadside Amenities
Chapter 21
Chapter 10
Railway and Cane Railway Level
Alignment Design
Crossings
Chapter 11 Chapter 22
Horizontal Alignment Bridges, Retaining Walls and Tunnels
December 2005
ii
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Table of Contents
16.1 Introduction 16-1
16.1.1 General 16-1
16.1.2 Scope of Chapter 16-2
16.2 Glossary of terms 16-3
16.3 Planning considerations 16-4
16.3.1 General 16-4 16
16.3.2 Warrants 16-5
16.3.3 General spacing 16-6
16.3.4 Access control 16-9
16.3.5 Basic lane numbers and lane balance 16-9
16.3.6 Pedestrian and bicycle requirements 16-13
16.3.7 Level of Service 16-14
16.3.8 High Occupancy Vehicle (HOV) lanes 16-15
16.3.9 Ramp metering 16-16
16.3.10 Very high load movements 16-17
16.3.11 Overall planning factors 16-17
16.4 Interchange forms 16-19
16.4.1 General categories 16-19
16.4.2 System interchanges 16-20
16.4.3 Service interchanges 16-20
16.4.4 Consistency of form 16-23
16.4.5 Route continuity 16-23
16.5 Design process 16-25
16.5.1 General 16-25
16.5.2 Traffic predictions 16-25
16.5.3 Site details 16-25
16.5.4 Stage construction 16-26
16.5.5 Design controls and criteria 16-27
16.5.6 Landscape development 16-27
16.5.7 Design steps 16-27
December 2005
iii
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16 16.6.4
References
Vertical clearance 16-62
16-63
Relationship to other Chapters 16-63
Appendix 16A: Traffic data requirements 16-64
Appendix 16B: Interchange types 16-65
Appendix 16C: Example of ramp speed analysis 16-72
December 2005
iv
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
List of Tables
Table 16-1 Target Levels of Service in the design year 16-15
Table 16-2 Appropriate ramp treatments for various interchange types, movement
types and turning volumes 16-29
Table 16-3 Recommended minimum design speeds for interchange elements
(modified from NAASRA, 1984) 16-34
Table 16-4 Major road sight distance to the nose (exits and diverges) 16-36 16
Table 16-5 Visibility requirements at entry ramp merges & merges of major roads 16-39
Table 16-6 Geometric requirements for interchanges 16-40
Table 16-7 Ramps - lane and shoulder widths 16-43
Table 16-8 Length of parallel lane at entry ramps 16-45
Table 16-9 Radius of outer connection roadway 16-53
Table 16-10 Distances between points – entry and exit ramp terminals 16-55
December 2005
v
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
List of Figures
Figure 16-1 Possible road network arrangements 16-2
Figure 16-2 Ramp configurations for closely spaced interchanges in urban areas 16-8
Figure 16-3 Basic number of lanes 16-10
Figure 16-4 Lane balance 16-12
December 2005
vi
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
vii
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
viii
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
ix
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
x
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Chapter 16
Interchanges
Consistency of form such as all ramps
16.1 Introduction
leaving the through pavement on the left
16.1.1 General hand side and all exit terminals being
before any bridges assists in driver
Interchanges are combinations of ramps and
grade separations designed as a system of
understanding and leads to consistent driver
behaviour when negotiating interchanges
16
interconnecting roadways to separate the (refer to Chapter 2). This improves traffic
turning and through movements at the capacity and reduces the risk of crashes.
junction of two or more roads. They Interchanges can be considered in two
provide the greatest efficiency, safety and categories (refer to Section 16.4):
capacity for handling large volumes of
traffic in these situations. • system interchanges; and
December 2005
16-1
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-2
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-3
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-4
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-5
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
suitable lower cost solutions to address the • major roads are crossed by bikeways
problem. A benefit cost analysis will be and pedestrian crossings;
required to justify a decision to adopt an
• access to public transport stations
interchange solution.
within the confines of a major road is
required;
16.3.2.5 Route conformity
• it is desirable to separate conflict points
A grade separated interchange may be
between movements having high
justified in the absence of other warrants
relative speeds; and
where the provision of an intersection in an
16 otherwise grade separated facility will
result in a combination of at-grade
• future land development will generate a
sufficiently high level of traffic needing
intersections and interchanges not expected to access the major road.
by motorists. This can lead to unsafe
A decision to provide an interchange or
operating conditions (refer also to Chapter
grade separation must be made only after
2).
careful consideration of all of the relevant
factors and the economic analysis of the
16.3.2.6 Jurisdictional
proposal. Justification on the basis of
requirements
economic analysis will depend on the
An interchange is required to meet the relative costs of materials and other inputs
requirements of the Commonwealth if it in the area in question. The actual traffic
involves a National Network Road Link volumes at which these facilities will be
(i.e. a road link included in the AusLink justified are likely to vary from area to area.
National Network).
16.3.3 General spacing
16.3.2.7 Topography
The location of interchanges is usually
There will be cases where the topography
determined by the road network
of the site is such that a grade separation or
requirements for accessibility and route
an interchange is less costly than an at
interconnectivity. However, there are limits
grade intersection.
to the number of interchanges that can be
16.3.2.8 Other factors accommodated and to the spacing of the
ramp terminals without compromising the
A grade separation or interchange may be
capacity and safety of the road.
required where:
Every ramp, whether an entry or exit ramp,
• local roads and streets cannot feasibly
creates conflict and causes some
be terminated outside the limits of a
disturbance to the traffic flow on the
Motorway;
motorway. The effects of this disturbance
• access to areas not served by frontage are felt for some distance on each side of
roads or other means has to be the ramp/carriageway terminal.
provided; Examination of these effects gives a clear
indication of the minimum spacing that can
• a motorway crosses a railway;
be tolerated (refer to Section 16.5.8.8).
• there are large concentrations of
pedestrians and/or cyclists;
December 2005
16-6
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
However, this does not take account of the effectively achieved through the form of the
Manual of Uniform Traffic Control interchange. For example, the ramps can be
Devices’ (MUTCD’s – Main Roads, 2003) grade separated (“braided” ramps) to create
signing requirements and the distance a bigger spacing of the ramp terminals.
required for a driver to change lanes to
Collector-distributor roads can also be used
position the vehicle sufficiently in advance
to achieve this with the added advantage of
of an exit to safely undertake the
keeping local traffic clear of the main
manoeuvre. Buses and heavy vehicles
through traffic. (Also refer to Chapter 4.)
require 200m per lane change, while cars
can be accommodated with 150m per lane
change.
Figure 16-2 shows some possible solutions.
Maximum spacing is less easily determined
16
A further consideration is the extent of and will depend on the needs for
weaving caused by the placement of accessibility and service to the local road
successive entry and exit ramps. Weaving network.
introduces an additional element of conflict In urban areas, spacing above about 4km
and has a negative effect on both levels of would not be expected. Where spacing
service and safety. The HCM (TRB, 2000) above this is proposed, the overall level of
provides details of the methodology service provided by the road system must
required to address the weaving issue from be reviewed.
a level of service point of view (refer
In rural areas, a spacing greater than about
Section 16.5.8.8).
12km must be carefully examined for
The general conclusion is that the adequacy of service. Where long lengths of
minimum spacing of interchanges on rural motorway do not need interchanges
four lane motorways (i.e. two lanes in for access and service reasons, the need for
each direction) is about 2km in urban rest areas and/or Service Centres has to be
areas and between 5km and 8km in rural assessed to ensure that drivers have
areas. The minimum spacing in urban adequate facilities for rest, refreshment and
areas must be increased to 3km for six refuelling (refer to Chapter 20). The need
lane roads and 4km for eight lane roads. for “U” turn facilities must also be
It follows that the ultimate number of considered (also refer to Chapter 7).
lanes must be considered when
Details of individual ramp spacing
interchanges are initially planned. The
requirements are covered in Section
desirable spacing is greater than these
16.5.8.8.
values. Notwithstanding the above
removing an existing interchange is usually
difficult due to the land uses and traffic
patterns that have been established during
its life and the impacts and adjustments
needed to accommodate its removal.
Where other factors dictate the need to have
the interchanges at closer spacing than
these, the required spacing can be
December 2005
16-7
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
Figure 16-2 Ramp configurations for closely spaced interchanges in urban areas
December 2005
16-8
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
•
vicinity of the interchange;
what alternative access arrangements
The basic number of lanes is therefore
defined as the minimum number of lanes
16
are available/possible; designated and maintained over a
• costs involved in prohibiting abutting significant length of a link exclusive of
access; auxiliary lanes. This basic number of lanes
is maintained throughout irrespective of
• intersection design at the ramp
changes in traffic volume as vehicles enter
terminals;
and leave the facility. This is a further
• provision for pedestrians/cyclists; and extension of the principle of consistency in
operational expectations. In addition,
• status of the road involved (declared or
forced lane changes over the length of the
otherwise).
facility are reduced.
Complete control of access must be
Figure 16-3 illustrates this concept in the
enforced over the full length of all ramps
context of a major road network (e.g. A to
and ramp terminals in the interchange as
B and C to D). The basic number of lanes
well as through the intersections at the ramp
is predicated on the general traffic volume
terminals. No entrance to or exit from a
over a substantial length of road. Assessing
ramp is permitted except to the through
the basic number of lanes is undertaken
roads at the ramp terminals. A special case
using design volumes from traffic
may exist where a Service Centre requires
predictions developed as part of the
access, an enforcement site is required
planning process.
(refer to Chapter 20) or restricted access for
emergency services is to be provided. Specialist traffic engineering advice must
be sought for predicting traffic volumes for
Care must be taken that any permitted
the design year. Traffic predictions may be
access point within or adjacent to the
based on projections of future growth for
interchange is far enough from conflict
rural roads, origin-destination studies for
points for ramps to satisfy deceleration and
town bypasses, or computer generated
acceleration requirements. Any storage that
traffic assignments from planning studies
may occur on site or entering the access
for more complex urban road networks.
must not impede the through traffic on the
Consult the Road Corridor Planning Guide
major facility.
for guidance on obtaining traffic
Control of entry to a ramp from the local assignment volumes.
road system is dealt with in Section 16.3.9.
December 2005
16-9
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
Traffic assignments are based on various can then be more dependent on the
assumptions and predictions. As a matter sequence of assigning zones than on the
of caution, there are two facts that make the final traffic conditions when all trips
more detailed output of traffic assignments are assigned. Thus, although in the
of unknown reliability: absence of other data one must look at
the assignment figures for turning and
• Normally daily assignments are used,
weaving movements, these cannot be
and an equivalent daily running speed
accepted without critical appraisal.
is used. This disguises, in an average
figure, the completely different patterns It is unsound practice to base lane numbers
that can occur in peak and off- peak on assigned volumes only. As well as
periods. considering peak hour traffic which is
mainly home to work and work to home,
• Most assignment packages (even peak
the following situations may cause high
hour methods) use a form of multi-
traffic peaks:
route or capacity-restraint technique or
a combination of both. These tend to • unforeseen concentration of
use single pass techniques where zone development;
pairs or parts of zone pairs are assigned
• holiday or weekend travel;
sequentially, with extra updates of
travel times or addition of random time • special events;
elements to distribute trips about the • stage construction and partial
shortest route. Turning movements development of the freeway network;
calculated for a particular interchange
• accidents; and
December 2005
16-10
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
• the travelled way of the carriageway Together, the combination of the basic
must not be reduced by more than one number of lanes criteria and the lane
lane at a time. balance criteria ensure that a motorist can
enter in the left hand lane of an entry ramp
Check the lane numbers obtained from step
and have to move right at most one lane in
2 for “the basic number of lanes”, as
order to continue along the road and not
described above. A section of the
find her/himself inadvertently exiting at
motorway with eight lanes may have a
some further interchange.
basic number of lanes of six, the other two
being auxiliary lanes. However, depending
on overall traffic volumes, level of service
December 2005
16-11
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
Figure 16-4 Lane balance
December 2005
16-12
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
This can be achieved through the usual Chapter 5 and the Guide to Traffic
provision of facilities at the ramp terminal Engineering Practice Part 14 (Austroads,
intersections (footways, traffic signal 2000) provide some additional guidance
phases, and separate footway and bikeway about catering for cyclists at interchanges.
facilities). It is essential that pedestrians Notwithstanding the above, planners and
and cyclists on the adjacent street network designers must provide for bicycles as
can traverse the interchange in a convenient detailed in Main Roads’ Policy for
and safe way and that appropriate levels of Cycling on State Controlled Roads (Main
service are maintained for both the traffic Roads, 2004).
and the pedestrians.
Main Roads, in planning and delivering the
Where specific provision for pedestrians is roads program, is to “positively provide”
required, a footway width of not less than for cycling on identified cycling routes and
1.8m should be provided. make other routes “cycle friendly” where
Cyclist access may be denied on motorways appropriate (refer to the policy for full
due to the difficulties and hazards details).
associated with high speed, high volume
traffic environments. In this case, a
separated facility is usually required in the
December 2005
16-13
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-14
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Rural Urban
Road Type
Desirable Absolute Desirable Absolute
B normally acceptable C (design hour) As per policy/planning (set in
National Network (excluding design hour) normally acceptable consultation with the
Road Links but consult but consult Commonwealth), C normally
Commonwealth. Commonwealth. acceptable.
Motorways and
roads performing a
motorway
function
B C C D
16
Rural arterial –
B C -
two-lane, two-way
Rural arterial – B (excluding design
C (design hour) -
multi-lane hour)
As per policy/planning,
Urban arterial -
otherwise C
December 2005
16-15
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
*Appropriate acceleration distance required (normally based on car acceleration). This length is
to be determined using the through road speed when metering is in operation. Notwithstanding
this the maximum speed to be used for determining the acceleration length shall be 80km/h.
Figure 16-8 Example of ramp metering with a HOV bypass lane (HOVs not subject to
metering or given priority)
December 2005
16-16
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Main Roads District must be consulted to should be consulted to assess the likely
determine whether such a provision is to be incidence of such loads and their preferred
made; specialist advice should also be routes.
sought (e.g. from Main Roads’ Traffic and
Rood Use Management Division). If 16.3.11 Overall planning factors
included, a heavy vehicle bypass is also
16.3.11.1 Land use planning
likely to require a special layout and special
delineation (e.g. signage), and have Planning of an interchange or a system of
enforcement issues associated with it (e.g. interchanges must be undertaken in
in defining what is an eligible heavy vehicle
so that it can operate and be enforced
harmony with the land use planning of the
area in question. The distribution of the
16
effectively). Specialist advice must be land use will have an effect on the location
sought to determine the necessary of interchanges as well as the layout of the
requirements. interchange.
In particular, the future land use pattern
16.3.10 Very high load
may cause the distribution of the traffic and
movements
the patterns of traffic to change, thereby
Overpasses restrict the vertical clearance changing the traffic demand on the
available on a route. Chapter 7 sets out the interchange. This will have to be
vertical clearance requirements for roads in accommodated either by designing the
Queensland. initial interchange to cater for these
changes, or by providing flexibility in the
However, it is the case that very high loads
layout to allow the future demands to be
are required to move over the road system
met on additional elements of the
from time to time. The routes adopted are
interchange (i.e. allow capacity to be
normally restricted to major roads and the
increased).
immediate access roads to the origin and
destination of the loads. Further, the future land use planning may
indicate development of additional major
Consideration should be given to the
traffic generators, which will have to be
desirability of increasing vertical clearances
accommodated on the road system. This
on these routes where economically
traffic will have to be provided with
feasible; or adopting alternatives where the
facilities to distribute it to the road network
major road forms the overpass; or providing
in a way that will be least disruptive to the
suitable means for a very high load to avoid
system. Additional interchanges and/or
the restricting underpass.
road elements such as service roads may be
This can be achieved by suitable needed. Planning of the first-stage
arrangement of ramps at interchanges; and interchange locations and the design of their
appropriate connecting roads between ramps will have to provide for these future
interchanges where overpasses without additions (e.g. spacing of ramp terminals).
ramps are located between interchanges.
Land use planning will also give guidance
In all cases, care must be taken to avoid on the extent of other mode use, particularly
precluding the movement of very high walking and cycling. These road users
loads. Industry and the Queensland Police must be catered for on the local road system
December 2005
16-17
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
to which the interchange is oriented and the The needs of pedestrians and cyclists will
facilities required for these users must be be important factors in the planning and
properly accommodated in the interchange design of grade separations and
design. These requirements are discussed interchanges along the facility. The style
further in other sections of this Chapter. and adequacy of these facilities will
determine their usage and the potential
Public transport use and its location are also
benefits in reducing the demands on the
dependent on the land use planning of the
major road system.
area. The road system and its interchanges
December 2005
16-18
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-19
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-20
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-21
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-22
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
If loops are added to the interchange, operation and the safety of the network
retaining consistency will require the use of (refer to Chapter 2). While interchanges
collector-distributor roads to allow a single must be custom-designed to suit the
exit and entrance to be used. specific conditions of the site, consistency
can be achieved along a link through the
Details of some of these are discussed in
use of a consistent form of interchange, but
Appendix 16B. AASHTO (2001) and
it is also achieved by a consistent approach
Vicroads (1998) provide more
to the pattern of the exits and entrances and
comprehensive discussion and give a large
their signing.
number of examples.
For any particular situation, elements from
For example, drivers expect to exit to the
left and they expect the ramp to start in
16
various types of interchange may be
advance of the separation structure. If this
combined to meet the specific requirements
feature is incorporated regardless of the
of that situation. Thus an interchange may
form of the interchange beyond the exit,
have some free-flow elements and some
consistency will have been achieved. A
stop condition elements.
similar approach to entrance ramps is to be
In rural areas, the most common type of taken. (Refer to Figure 16-11.)
interchange is the Diamond interchange,
generally with the ramps spread to 16.4.5 Route continuity
minimise earthworks. This type of
interchange will often be appropriate An important element of consistency is
because of the relatively low traffic route continuity. Drivers expect to travel a
volumes at these sites. designated route in a directional path and
adopt consistent behaviour throughout the
The intersection of the diamond ramps with
route. It simplifies the driving task in that it
the local road is often designed as a
reduces lane changes, simplifies signing,
roundabout. Where this results in a
delineates the through route and reduces the
roundabout on both sides of the major road,
driver’s search for directional signing. The
this form of interchange is sometimes
driver on the designated route should not
referred to as a “spectacles” type. This is
have to change lanes and all entering and
particularly appropriate where the space
exiting of other traffic should occur on the
exists since this form of intersection
driver’s left. (Also refer to Section 16.3.5.)
provides fewer delays and provides a higher
level of safety than other forms of This means that the form of the interchange
intersection. (Refer to Chapter 14 for may be determined by the need for route
details of roundabout design.) continuity rather than by the direction of the
heavy traffic movements. Figure 16-12
A more comprehensive discussion of the
illustrates this concept.
various types of interchange is included in
Appendix 16B.
December 2005
16-23
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-24
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
The expected traffic volumes for the design • drainage and flooding issues; and
year and any intermediate years suitable for • location, standard and function of the
staging must be determined. These are intersecting roadways that the
essential for the analysis of ramp layouts interchange will be serving.
(including intersections) and lane numbers
The style, economy and layout of an
required for the interchange.
interchange will be heavily dependent on
Interchanges are expected to provide the topography and other physical
adequate capacity and level of service to the constraints existing at the site. Rolling and
through and turning traffic expected to use hilly topography presents opportunities to
them from their commissioning to the end mould the design of the interchange into the
of the planning horizon, or as otherwise landscape and take advantage of level
determined using a staged approach. To differences to reduce cost. In flat terrain,
December 2005
16-25
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
the design will have to create the level when traffic reaches a predetermined
differences occurring naturally in volume.
undulating country and detailed attention to
Factors to consider include:
the relative grades will be required to
achieve the most economical and • providing flexibility for future and
aesthetically pleasing result. ultimate stages (refer to Section
16.3.11.6);
Interchanges require a significant area of
land and the availability of right of way can • geometry of the initial and final
interchange elements;
16 influence the type of interchange adopted.
The detailed location of the facility may
also have to be tailored to the available land
• traffic growth over the life of the staged
development and traffic operations and
with appropriate adjustments to the local management at each stage of the
road system to ensure that the facility is development;
properly used.
• land use planning;
16.5.4 Stage construction • overall road network development in
the vicinity;
Since the design of an interchange is based
on traffic volumes estimated for 20 or more • land acquisition requirements, costs and
years into the future, it is sometimes other constraints;
possible to provide for the development of • structures needed at each stage of the
the interchange in stages to minimise the development and their design life;
initial cost. If this course is to be pursued,
• earthworks at each stage;
careful attention to the way the future
works are to be undertaken will be required • drainage requirements at each stage;
and it should not be at the expense of
• signing requirements at each stage;
flexibility (refer to Section 16.3.11.6).
• location of PUP; and
It is desirable that future works be
constructed without interrupting the • landscaping and planting needs at each
existing traffic as far as possible so the first stage and in the final stage.
stage will generally include the outside Most complex interchanges are “staged”.
elements of the facility. For example, if an That is, some pavements are constructed
interchange with one or more loops is initially, and the complete interchange may
needed in the future, it may be possible to be developed in a series of steps, which
omit the loops in the first stage, using the may extend over a period of many years.
outer connection ramps as legs of a Therefore, when developing layouts,
diamond interchange in the interim. These designers should be familiar with the
ramps would be positioned in their final proposed development programme and
locations allowing the loops to be attempt to minimise early stage
constructed inside these ramps at a later construction costs if this can be done
date. Another example could be to make without compromising flexibility (refer to
provision in the first stage for a third level Section 16.3.11.6).
to be “easily” added to the interchange
December 2005
16-26
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Minimising first stage costs will be layout and grading can be designed to meet
economic if the net present value of the both the functional and aesthetic
total cost of the final interchange is not requirements. A better result at a lower
increased. In some cases, designing to cost can be achieved if these factors are
minimise early expenditure may be justified incorporated as part of the design, rather
where the net present value increases (e.g. than as an “add-on” at a later stage.
because of funding limitations; additional
disruption). 16.5.7 Design steps
December 2005
16-27
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
o potential for signing; The types of ramps are usually known as:
o cost; • directional;
o availability of right of way; • semi-directional;
o potential for stage construction; • loop;
o constructability (including • outer connectors; and
sequencing of works) especially if
• diagonal.
the works conflict with existing
16 o
traffic;
pedestrian and cycle movements;
There are only two ramp movements, right
turn and left turn. Figure 16-13, Figure
16-14 and Figure 16-15 and summarise the
and
various types of ramps. Depending on the
o social and environmental impacts. type of interchange, the right-turn and the
left-turn movements can be accommodated
o other criteria that could be relevant
on the same ramp or they may be
such as
accommodated on two separate ramps.
- aesthetics;
Table 16-2 indicates possible applications
- type of bridge structures; and of the various ramp types.
- community expectations. Directional ramps
4. Review the options developed in this Directional ramps are exclusively for one
planning process to ensure that the right turn movement. These ramps provide
criteria set out at the beginning are still the most direct right turn connection
relevant and that the design satisfies the between two roadways. They must only be
expectations of the road network used as part of a major fork or branch
strategy. Changes in traffic patterns, connection (refer to Sections 16.5.8.9 and
land use, clearance controls, 16.5.8.10 respectively).
environmental considerations and
The operating speed on a directional ramp
community expectations can cause
should desirably be no less than the
some of the criteria to be superseded.
operating speed of the approach on the
5. Select the preferred option. through road minus 10km/h. Speed drops
above 20km/h must only be provided where
16.5.8 Interchange elements
dictated by economic constraints, and must
be accompanied by treatments to reduce
16.5.8.1 Ramp layouts
speed (as given in Section 16.5.8.2 and
The exchange of traffic between grade- Appendix 16C).
separated roads is accomplished by ramps.
The type of ramp is influenced by several
factors including operating speed, grade,
physical restrictions (including
topography), volume and character of
traffic, and angle of intersection of the
highways.
December 2005
16-28
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Table 16-2 Appropriate ramp treatments for various interchange types, movement types
and turning volumes
System interchange
Turning
movement
Ramp type*
High turning
volumes
Low turning
volumes
Service interchange
16
Major forks and
Directional** Unsuitable Unsuitable
branch connections
Use only in
Loop Unsuitable Unsuitable
constrained locations
*Refer to Figure 16-13, Figure 16-14 and Figure 16-15 for illustrations of these ramp types.
**Refer to Section 16.5.8.9 for details of, and requirements for, major forks. Refer to Section
16.5.8.10 for details of, and requirements for, branch connections.
December 2005
16-29
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-30
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-31
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
Figure 16-15 Ramp types – diagram 2 of 2
December 2005
16-32
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Geometric details are discussed in Section to support the pavement is sufficient (refer
16.5.8.4. to Table 16-7 and Section 16.5.8.5).
On exit diagonal ramps, the maximum If the design year traffic volumes require
operating speed prior to the intersection two lanes on the ramp, two alternative
should be limited to not more than 60km/h. approaches may be taken, namely:
This can be achieved by the treatments
• provide a single lane at the nose, using
given in Section 16.5.8.2.
the restricted capacity of this lane to
Lane numbers control the volume of traffic entering
Turning roadways (generally directional or
semi-directional ramps) should normally be •
the motorway; or
provide a full two lane entry with an
16
designed for two-lane operation with added lane on the motorway (refer to
provision for emergency parking, unless the Figure 16-21).
expected volume exceeds the capacity of
These ramps require the capacity of the two
two through lanes. In this case, three-lane
lanes and must therefore be provided with
operation on the ramp must be provided.
sufficient shoulder width to allow a stalled
Entry and exit ramps may be one lane or vehicle to be passed.
two lanes at the nose depending on traffic
The transition from two lanes to one lane at
volumes. Where they intersect with the
the nose is to be implemented as shown in
street, two or more lanes will be required.
Figure 16-21 and Figure 16-22.
The length and number of these lanes will
be determined from intersection design Single lane (at the nose) exit ramps has to
principles (refer to Chapter 13). be widened to two lanes as shown in Figure
16-22 when:
For an entry ramp with a single lane at the
nose, and with a design speed of the • a truck will exit at less than 50km/h at
through roadway of 80km/h or more, a the nose, and a significant number of
second entry ramp lane has to be provided trucks use the ramp; or
when: • the ramp is longer than 600m.
• the length of a single lane ramp exceeds Shorter ramps may be widened to cater for
300m on a level grade and a truck storage requirements at the minor road
accelerating from rest at the ramp intersection. Where two lanes are required
terminus would not be expected to at the nose to meet the traffic demand, the
reach 50km/h at the nose and a cross section must allow for a stalled
significant number of trucks use the vehicle to be passed in addition to the full
ramp; or traffic lanes.
• very long (i.e. length >600m) ramps are
16.5.8.2 Design speed
provided.
The speed adopted by a driver within an
Two lane ramps with a single lane at the
interchange depends on:
nose are effectively one-lane ramps with
provision for overtaking. It is therefore not • driver work load;
necessary to have full shoulder widths on
• the types of roads intersecting and their
these ramps. A 1.0m shoulder on each side
geometric limitations on speed;
December 2005
16-33
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
• terminal characteristics; the nose and the curve of the ramp (if
applicable) to enable vehicles to reach the
• the presence of manoeuvring vehicles;
appropriate speed (refer to Figure 16-21,
• physical speed limitations of the overall Figure 16-22, Figure 16-23 and Figure
geometry; 16-24).
• the approach speed of the vehicle Ramps are to be designed for speeds as
entering the interchange area – shown in Table 16-3. These speeds apply
determined by the speed environment to the sharpest or the controlling ramp
of the approaches;
16 • the proportion of trucks in the traffic
curvature, usually on the ramp proper.
They do not apply to the terminals, which
must be designed in accordance with the
stream; and
speed change facilities appropriate to the
• traffic volumes and levels of service.
roadway concerned.
While any one of these can be the
For loops, a design speed above 50km/h
predominant factor, it is often the
requires large areas of land to accommodate
combination of the factors that produces the
the ramps with little gain in the travel time
final result.
required to achieve the turning manoeuvre.
There should be a relationship between the There is little point in using a speed greater
design speed of the ramp and that of the than this for loop ramps. However,
through road so that there will be little adequate speed change arrangements must
conscious effort required in a decrease be incorporated to provide for the transition
from, or increase to the operating speed of from the highway speed to the ramp speed.
through traffic. All ramps and connections
are to be designed with a section between
Table 16-3 Recommended minimum design speeds for interchange elements (modified
from NAASRA, 1984)
December 2005
16-34
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Higher range speeds are required for direct • providing large advance warning signs;
connections as shown in Table 16-3.
• providing appropriate speed limit signs;
Appropriate transition arrangements will be
required to move from the highway speed • providing pavement markings across
to the speed value for the connection. the pavement;
December 2005
16-35
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-36
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
Figure 16-16 Vertical curve radius required for sight distance - 1.15m to 0m
Figure 16-17 Visibility to nose and 60m past the nose for a crest vertical curve
December 2005
16-37
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-38
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Table 16-5 Visibility requirements at entry ramp merges & merges of major roads
Visibility Requirement
Design
Mutual visibility between
Domain Approach to nose Terminal visibility
carriageways
6s of travel at respective 4s of travel at respective operating 6s of travel at
Desirable operating speeds on each speeds on each carriageway prior to operating speed to any
lower carriageway prior to nose point where merging lanes are point on merge taper2
bound (1.15m eye height to 0.1m separated by 2m (1.15m eye height (1.15m eye height to
object height) to 1.15m eye height) 0.0m object)
Absolute
4s of travel at respective
operating speeds on each
4s of travel at respective operating
speeds on each carriageway prior to
6s of travel at
operating speed to any
16
lower carriageway prior to nose point where merging lanes are point on merge taper2
bound (1.15m eye height to 0.1m separated by 1m1 (1.15m eye height (1.15m eye height to
object height) to 1.15m eye height) 0.0m object)
Notes:
1. Only for tunnels and low speed non-motorway interchanges.
2. In practice, this means:
a. all of a taper type merge has to be seen prior to the nose; and
b. most of the parallel lane of a parallel type merge will be seen from the nose.
Where an entry ramp coincides with a left- Designers must also be aware of the
hand curve, designers should be aware that: potential sight distance problems on
roundabout interchanges where bridge
• curves requiring greater than the
parapets occur. The height of the parapets
maximum desirable “f” value must not
has increased over time and could interrupt
be used as they can inhibit vehicle
the sight line for drivers.
control (true for both right-hand and
left-hand curves); Visualisation aids can be useful for
designers in reviewing sight distance
• it is difficult for an entering driver on
requirements on all elements of the design.
the ramp to see approaching vehicles on
the motorway because of the
16.5.8.4 Alignment
observation angle;
Major road alignment – horizontal and
• it is difficult for the entering driver to
vertical
judge the length of approaching multi-
combination vehicles; and The major road alignment in the vicinity of
an interchange should be as close to straight
• approaching vehicles on the motorway
as possible in the horizontal and vertical
can be in the blind spot of entering
planes to ensure that the sight distance
trucks.
requirements to the noses of ramps are met.
A possible solution is to provide a parallel
Chapter 4 sets out the design principles and
lane as it gives drivers of entering vehicles
guidelines for roads performing a motorway
more room and time to decide what to do
function.
(Figure 16-21).
December 2005
16-39
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-40
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Ramp grades should be as flat as feasible to • curved structures cost more than
minimise the driving effort required. Since straight ones;
slowing down on ascending ramps is not as
• curved bridges (particularly box
serious as on the through roadway, grades
girders) cost more to widen than
entry ramps can be steeper than those on
straight ones;
the through road.
• the horizontal curvature restricts sight
The actual grade adopted will be the result
distance from the exit ramp across the
of a balance between the length of ramp,
structure on the inside of the curve –
the vertical curve requirements at the
terminals and the potential operating
difficulties that may occur on the grades.
this can require the structure to be
widened;
16
• superelevation on the bridge can
In general, providing adequate sight
adversely affect sight distance from one
distance is more important than a specific
of the ramps; and
grade control. However, some limits can be
placed on the maximum grades to be used. • skew bridges cost more than square
ones.
Maximum grades on motorway interchange
ramps are based on the ability of a heavy The problems are not as great if the minor
vehicle to enter or leave high speed traffic road passes under the major road, provided
at the operating speed at the nose, and in that adequate sight distance is achieved at
the case of an exit ramp to allow that the ramp terminals. Safe Intersection Sight
vehicle to safely negotiate the ramp Distance (SISD) is required (refer to
geometry. Lower speed interchanges which Chapter 13).
will be required to accept a higher degree of Further, for close diamonds, the bridge
interruption to flow can accept steeper parapets and safety barrier may adversely
grading on both exit and entry connections. affect the SISD for both of the ramp
Local limits in each situation should be terminals. The parapets and safety barrier
based on acceleration/deceleration criteria. may have to be set back (including
Some examples of grading issues at appropriate bridge widening) to achieve the
diamond interchanges are shown in Figure required sight distance. Alternatively, the
16-19. location of the intersections may have to be
changed.
Vertical curvature must be designed in
accordance with the principles of Chapter On simple diamond interchanges (Figure
12. 16-32) where the minor road is a two-way
two-lane road passing over the major road,
Horizontal curvature must be designed in
medians are developed on the minor road at
accordance with the principles of Chapter
the ramp terminals (or intersections) on the
11.
minor road to provide for protected right
Minor Road Alignment turns or roundabouts. Deviation of the
minor road alignment is required to
Where the minor road passes over the major
accommodate these medians.
road, it should be as straight as possible and
square to the alignment of the major road.
This is because:
December 2005
16-41
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-42
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
Figure 16-20 Alignment of minor road traffic lanes - spread diamond
December 2005
16-43
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
On loops designed for one lane of traffic, traffic lanes will determine the traffic flow
curve widening may be required to allow characteristics in the interchange area.
for the tracking of the design vehicle. For
Good design practice ensures that vehicles
two lane loops, the lane widths must allow
can decelerate and accelerate without
for a semi-trailer and a car to travel side by
impeding through traffic. In addition, the
side.
ramp length and number of lanes on the
Crossfalls and batter slopes are discussed in ramp must be such as to ensure that queued
Chapter 7. vehicles will not impede through traffic.
16 Kerbs
Kerbs are not to be used on diverge or exit
Details of the dimensions to be adopted for
ramps are shown in Figure 16-21, Figure
16-22, Figure 16-23, Figure 16-24 and
noses on interchanges where the operating
Figure 16-25 for high-speed operation.
speed of the through roadway is 80km/h or
greater, but may be used on low speed The entrance to the motorway for high
interchange roadways to: speed conditions is based on providing
drivers with an opportunity to merge after
• delineate edges;
reaching the motorway road speed. A
• control pavement drainage; parallel lane adjacent to the through lanes
• restrain undesirable traffic movement; should generally be used to assist the merge
and operation, both from a capacity and a safety
point of view, especially at high traffic
• improve the roadway appearance.
volumes. Table 16-8 sets out the length of
However, irrespective of the above, using the parallel lane for various conditions.
kerbs on loops should be avoided as any
Drivers will merge as gaps become
impact of the tyres with the kerb can
available and do not necessarily follow the
destabilise and roll a semi-trailer. Barrier
taper.
kerb must not be used within the
interchange particularly on loops. If semi- A different mode of operation applies in
mountable kerb is used on the outside of Figure 16-25 where merging of two high
loops, the shoulder must be at least 2.0m speed roads occurs. In this case, the two
wide. roadways meet tangentially instead of at a
slight angle as with a ramp (1:50). The
Details of the standard kerb shapes and
angle associated with the ramp is intended
their uses are provided in Chapter 7.
to provide a cue for a pending lane change.
16.5.8.6 Ramp terminals
Through pavement entry and exit ramp
terminals
The efficiency of the through road
operation and the capacity of the ramps
depend largely on the through pavement to
ramp terminal design. The ease with which
vehicles can enter or leave the through
December 2005
16-44
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
1.
time.
The desirable length is also the typical upper bound of the design domain. The upper bound is
16
limited by the likelihood of drivers mistaking the parallel lane for an added lane. This can occur for
drivers of both entering and through lane vehicles at heavy vehicle flows. The length should only be
extended if:
a. a traffic analysis (i.e. HCM analysis) and/or operating experience shows the need for a
longer lane; or
b. the lane has to go over a crest and suitable sight distance to the end of the lane has to be
achieved.
2. Use only if in very constrained circumstances.
Details of the design of the exit terminal keep this area free from fixed objects but
from the major road are shown in Figure where this is not possible supports must be
16-22. This design is based on direct exit provided with breakaway bases. When
from the through lane with deceleration these requirements cannot be met,
occurring after the vehicle has left the appropriate protection must be provided to
through lane. Some Authorities are now shield the driver of an errant vehicle.
using a parallel lane in advance of the exit Energy absorbing barriers are the most
to ensure that the exiting traffic is removed effective devices where a rigid object is
from the through lane before it starts to located in this area. (Refer to Chapter 8.)
decelerate. This lane also emphasises the
Loops
presence of the exit and is highly desirable
where the exit occurs on a right hand curve. Where loops are used and the minor road
passes over the major road, the exit from
A parallel lane is the desirable minimum
the major road should be in advance of the
layout for a high volume road or where a
overpass structure to ensure that the bridge
high Level of Service is required for a ramp
abutment does not obscure the location of
on a motorway.
the nose. For cloverleaf interchanges, a
The gore area of diverges and exits from collector-distributor road must be used to
high speed roads should be traversable by provide for this.
vehicles for at least 120m past the nose (i.e.
Care is required in the design of the exit
where the pavements separate) (desirable
loop from the major road. The alignment
maximum slope 1 on 10, absolute
should be straight for a distance past the
maximum slope 1 on 4). It is desirable to
nose to allow vehicles to decelerate to the
December 2005
16-45
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
operating speed of the loop (refer to Figure the loop. A “run out” area should be
16-22 for deceleration distances). Where provided around the outside of the loop as
feasible, an alternative treatment is to shown in Figure 16-26 and should be free
provide a series of speed reduction curves of obstructions and hazards. If a driveable
to produce the desired result (refer to area cannot be provided as shown, road
Example 16C, Appendix 16C). safety barrier is to be installed around the
outside of the curve.
Drivers must be able to estimate the safe
speed of the loop and therefore need For entry loops, the minimum radius should
December 2005
16-46
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-47
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-48
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
Figure 16-23 Special cases of ramp design – entry ramp for non-motorway interchanges
with a design speed [80km/h and for motorways with a design speed [80km/h in very
constrained circumstances (e.g. no parallel lane)
December 2005
16-49
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
Figure 16-24 Special cases of ramp design – two-lane two-way motorways (staged
construction)
December 2005
16-50
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-51
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-52
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Table 16-9 Radius of outer connection Where the interchange is spread sufficiently
roadway to allow the necessary transitions between
2
cross-sections, and these requirements
Left turn radius
1
Ramp angle (degrees) would require undue widening of the
(m)
overpass structure, the extent of the median
25-30 175
may be reduced by starting it 50m upstream
50-69 120 of the nose of the entry ramp. This layout
70-80 80 should only be adopted where significant
3
Oblique 20 cost savings can be made.
Notes:
1. Minimum angle is 25°.
Widening of the two-lane pavement
approaching the median must be
16
2. Radii are approximate.
accomplished with tapers at least 60m long
3. For oblique angle, use a deceleration lane
(1.1m lateral movement for each lane in
and a smaller radius.
each direction). Figure 16-24 shows the
extent of the median with the required
16.5.8.7 Ramps on two-lane two-
dimensions.
way motorways
The design of the ramps is to be in
Two-lane two-way motorways sometimes
accordance with Figure 16-21 and Figure
occur as a result of stage construction; and
16-22 (only ramps with one-lane at the nose
ramps to the through pavement are required
will be applicable). The ramps must be
at the interchanges. In these cases, the
located in their final position suitable for
through road design within the interchange
the ultimate interchange design with
is to either:
appropriate temporary connections to the
• include sufficient length of median to initial through pavement.
prevent wrong way and other
Appropriate signing in accordance with the
inappropriate movements at the
MUTCD must be included in the design.
terminals; or
Entering traffic must be made fully aware
• provide full interchange design with all of the fact that the roadway they are
roadway elements in their final entering is a two-way carriageway.
positions.
Pavement markings are to be in accordance
Where the staged interchange is to be used, with the MUTCD.
a raised median at least 1.2m wide between
A better solution is to provide the full
kerb faces must be installed over the full
interchange design with all roadway
extent of the interchange geometry
elements located in their final positions.
(including tapers) plus 100m beyond the
The through road would then be a divided
final entry ramp taper. This extent of
road through the extent of the interchange.
median is necessary to ensure that the
This is probably more expensive than the
entering traffic is prevented from crossing
staged construction, but the life of the stage
to the on-coming lane in the mistaken belief
works, its relative safety and efficiency and
that they are entering a one-way
the extent of wasted construction (which
carriageway. Two-way carriageway signs
affects both options) must be considered
must be used to reinforce this.
December 2005
16-53
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
before adopting the two-lane two-way Where practicable and affordable, the
through pavement through the interchange. preferred location for weaving sections is
on collector-distributor roads, which
16.5.8.8 Distance between ramp operate at lower speeds, rather than the
terminals through carriageways.
The spacing of ramp terminals is the most Table 16-10 provides the minimum
significant factor in determining the spacings for the different entry/exit ramp
operating characteristics of a motorway. terminal combinations. Greater spacings
Each exit and entry ramp terminal creates
16 some level of turbulence in the traffic
stream on each side of the exit or entry
are always preferred, and the proposed
spacing must always be checked in
accordance with the procedures outlined in
point. The extent of this disturbance is the HCM and increased if necessary to
approximately: produce a consistent level of service for the
• 450m upstream from the exit point of overall road link.
the exit ramp in the two through lanes Conditions in both peak and off-peak
closest to the exit ramp; and conditions are to be analysed to ensure that
• 450m downstream of the entry point of the level of service is consistent within each
the entry ramp in the two through lanes period. The actual level of service will not
closest to the exit ramp. be the same for both situations as it is
expected that the level of service will be
In addition to this disturbance, drivers need
lower in peak conditions.
a significant distance to change lanes to
position themselves for the exit manoeuvre It is important for off-peak operation to
after they recognise the need to do so maintain the operating speed through the
following the appropriate signage. section to minimise speed differentials in
the interests of safer operation.
In those cases where an entry is followed by
an exit, a weaving section will be created if 16.5.8.9 Major forks
the points of entry and exit of the ramps are
A major fork is the split of a directional
sufficiently close. This introduces an
roadway or of a terminating major road
additional disturbance to the traffic stream
route into two directional ramps connecting
as well as increasing the hazard to drivers.
to another major road; or the diverging area
Weaving is a complex traffic flow issue and created by the separation of a major route
requires careful analysis where it occurs into two separate major routes of about
and a full discussion of weaving analysis is equal importance. They often occur in
beyond the scope of this Manual. major road to major road interchanges such
Designers must refer to the HCM (TRB, as Y and T interchanges.
2000) which sets out the methodology for
Figure 16-28 illustrates two examples of
analysing weaving sections of up to
major fork design together with design
approximately 750m in length. Weaving
details.
segments longer than 750m are treated as
isolated merge and diverge areas using the
procedures for those manoeuvres.
December 2005
16-54
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Table 16-10 Distances between points – entry and exit ramp terminals
1,3 1,3
1 1 Desirable Minimum
Configuration Type of carriageway
(m) (m)
Successive exits (i.e. exit followed by exit) or
successive entrances (i.e. entry followed by
Motorway - 3007
entry)2
L
Service Road or
L Collector-Distributor - 2407
Motorway - 150 7
16
Service Road or
Collector-Distributor - 1207
L Road
Successive exits or successive entries on
connecting roads (or turning roadways, i.e.
distance between terminals within
interchange itself). System Interchange - 2407
L
L 4 lanes 15005,6 -6
Notes:
1. This table is a guide only. All configurations must be analysed in accordance with the HCM (TRB,
2000). The distance/s (i.e. “L”) must be increased where required to achieve the design level of
service (analysed using the HCM) or to achieve a consistent level of service along the link. The
distances given do not apply to major forks or merges. In determining the required spacing the
number of lanes in the ultimate stage of the motorway must be used.
2. Not a preferred configuration for a motorway.
3. It is preferable for the distances to be greater than the minimum to provide drivers with more decision
making time.
4. Based on providing no overlapping areas of turbulence.
5. Based on signage and lane changing requirements of a four lane motorway carriageway.
6. Figure 16-21, Figure 16-22, Figure 16-23 and Figure 16-24 indicate the points between which the
distance “L” is to be measured. Dimensions less than the desirable must be justified by a complete
analysis undertaken in accordance with the HCM. Notwithstanding this table or the HCM analysis, it
is desirable that not less than 4s of travel, at the desired speed of the major road, be provided between
the end of the last taper of the entry terminal and the start of the first taper of the following exit
terminal.
7. The distance “L” is measured from like point to like point. This length is subject to signage
requirements (i.e. length may need to be increased so that the motorway and ramps can be signed
adequately [e.g. to provide sufficient distance between signs or between sign and exit/entry]) and a
HCM analysis (as per Note 1 of this table.)
December 2005
16-55
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-56
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Direct right hand exits are to be used when • Gantry signs should be used to ensure
the traffic in that direction exceeds 50% of that drivers know which lane to enter
the through traffic. If the right turning (gantry supports are not to be placed in
traffic is less than 30% of the total, a the gore).
normal exit to the left is to be used. For
Downstream of the fork, the speeds on the
right turning traffic between 30% and 50%,
two roadways must be consistent with the
the decision on whether the right turning
operating speed on the major road.
traffic is to depart from the traffic stream on
Depending on the geometry possible, speed
the left or the right has to take account of
route continuity considerations.
divergence should be treated as a major
The
drops of 10km/h are acceptable provided
the diverging roadways are clearly visible
to the driver.
16
fork regardless of the orientation of the two
legs of the fork after the divergence. For those cases where the turning traffic is
less than 30% of the total, the turning
The layouts shown in Figure 16-28 have the
roadway can be designed as a normal ramp.
appropriate lane balance in which the
The major movement would appear as a
number of lanes downstream of the split is
continuation of the major road proper (refer
one more than the total approaching the
to Figure 16-28(e)).
split. The central lane (or at least one of the
central lanes) must allow the traffic in that The turning roadways in both of the above
lane to choose which direction to take. If cases must have at least two lanes.
this is not done operational difficulties will
16.5.8.10 Branch connections
occur (AASHTO, 2001).
A branch connection is defined as the
The operating conditions at locations of
beginning of a carriageway of a major road
major forks are different from those at other
formed by the convergence of two
interchanges and some stringent controls
directional multi-lane ramps from another
are required to ensure their safe operation,
major road, or by the convergence of two
including the following:
motorway routes to form a single motorway
• The approach to the nose should be route.
straight or nearly so.
These connections often form part of
• Long sight distances should be system interchanges. Figure 16-29 shows
provided both on the approach to the two possible branch connections.
gore area and to all signs to allow
drivers adequate time to assess the
situation and take the appropriate
action. It must be remembered that
some drivers may have to change lanes
to position themselves for the correct
roadway. Sight distance to the nose is
to be at least 440m measured from an
eye height of 1.15m to zero object
height.
December 2005
16-57
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-58
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
The layout depicted by Figure 16-29(a) is • Positioning of the signs with respect to
preferred unless the volumes of traffic the major road lanes (either overhead
entering from the right are low and on gantries or mounted to the side).
adopting this layout would create a forced
• Location and type of support legs for
right hand merge (refer to Figure 16-30(a)).
the signs - fixed base sign supports
Right-hand merges shall not be used for
must not be placed in the gore areas at
new interchanges. If low traffic volumes
ramps or in run out areas.
from the right are forecast, the layout
depicted in Figure 16-29(b) becomes the • Gantry signs are essential for major
most suitable solution. In cases where the
left-hand roadway is near capacity and the
forks to avoid
the gore is
driver confusion because
long and narrow to
16
volumes from the right are low, the layout accommodate the large radius curves
shown in Figure 16-30(b) shall be adopted. involved.
This avoids a forced right-hand merge. • Gantry signs are required for
Figure 16-30 shows the details of the lane carriageways with three or more lanes.
arrangements for branch connections. The • Breakaway (i.e. frangible) sign supports
length of parallel lane shown in Figure and lighting poles must be used if the
16-30(b) must be at least 400m downstream sign supports and lighting poles are not
of the nose. This is the principal difference protected by safety barrier.
in design from the normal ramp details.
• Non-breakaway (i.e. non-frangible)
Characteristics of the layouts shown in
sign posts and lighting poles must be
Figure 16-30 are:
located behind safety barriers or
• Layout (a) is appropriate when both protected with appropriate devices.
roadways are close to capacity; and
• Signs must be clearly visible in all
• Layout (b) is appropriate when the conditions and individual lighting of
volumes on the left roadway (or both signs should be considered if the
roadways) is low. ambient or general lighting is not
adequate.
16.5.9 Signs, marking and
lighting Lighting must be provided at all
interchanges in accordance with the
Signing and marking through interchanges requirements of Chapter 17.
is essential to their efficient operation. A
major criterion for acceptability of a layout 16.6 Grade separations
for an interchange is the ability to properly
and effectively sign that layout to make it 16.6.1 General
work.
This section discusses grade separation
The MUTCD sets out the requirements for structures as a part of interchanges and as
signing and marking of major roads and stand-alone structures. In addition to the
associated interchanges. Significant issues need to have structures at interchanges to
to be considered include the following: carry the intersecting road across the major
• Location of signs to ensure adequate road, it is often necessary for access and
decision times. network continuity to carry other roads
December 2005
16-59
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-60
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-61
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-62
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-63
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
traffic) - current and design values; rates are known and stable and future
• approach speeds; development is taking a steady path. In
other areas, a more comprehensive
• accident rates and types;
modelling approach must be adopted to
• pedestrian and cyclist movements and obtain a better insight into the likely future
volumes to be accommodated; and position (refer to Chapter 2).
• public transport movements and
volumes - current and design values.
In urban areas, the design volumes will be
determined from transport planning studies
taking account of land use planning, public
transport use, other mode shares and
distribution to the overall network of roads.
The influence of various transport strategies
on the generation and distribution of traffic
in the future has to be taken into account in
determining the design volume.
It is likely that traffic demand will approach
the design levels of service in a short time
after opening in urban areas. It is therefore
important that the design provide a
balanced level of service throughout to
avoid “bottleneck” situations developing.
In rural areas, the design is based on an
estimated design hourly volume assessed
from the traffic patterns peculiar to that
road and area. This can vary from the 30th
highest hour to the 120th highest hour
depending on the type of route. A guide to
the most economical design hour can be
gained from a plot of the hourly volume
December 2005
16-64
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Disadvantages
Appendix 16B: Interchange
types • Conflicting movements on the minor
road limit capacity and safety.
Service interchanges • Where the minor road crosses over the
The design of service interchanges is major road, provision of adequate
generally a matter of adapting one of the visibility at the ramp - minor road
various types to the particular site and intersections may be difficult.
traffic flows. Some of the typical
• Possibility of wrong-way movements.
interchanges used are discussed in the
following paragraphs. Figure 16-9 and • Turning traffic from the major road is 16
Figure 16-10 illustrate some variations on obliged to stop at the minor road.
the simple diamond shown in Figure 16-32. Additional lanes may be required for
storage. Queuing may affect ramp
Simple diamond
capacity.
• Little possibility of allowing for future
expansion of the interchange, but
increased volumes may be handled by:
o Channelisation of the ramp - minor
road intersections; and
o Installing signals on the minor road
Figure 16-32 Simple diamond (three phase).
interchange Single point diamond (fast diamond)
Advantages The distinguishing features of this type of
• High standard single exits and interchange are that all four turning
entrances in advance of and beyond the movements are controlled by a single set of
structure respectively. traffic signals and the opposing right turns
operate to the right of each other (Figure
• Economical in property use and
16-33).
construction Costs.
Advantages
• Where the major road passes under the
minor road, the grades of the ramps • Right of way requirements are smaller
assist the deceleration of exiting traffic than the conventional diamond.
and the acceleration of entering traffic. • The opposing right turns do not cross
• Single exit feature simplifies major each other’s path, therefore eliminating
road signing. a major source of conflict.
• No need for speed change lanes on or • Reduced delay through the intersection
under the structure. since there is only one set of traffic
signals.
• No weaving on major road.
• The right turns operate on larger radius
curves and therefore are faster than at
December 2005
16-65
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-66
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
Disadvantages Advantages
• The right turn from the ramp to the • Single exit feature simplifies signing
minor road will require storage on the and promotes consistency of operation.
ramp and additional lanes may be • No weaving on the major road.
required.
• Not conducive to wrong way
• Signals required on the minor road movements.
when the through and turning
movements are high. • Depending on right turn movements,
this is a high capacity interchange.
• Future expansion of the interchange
cannot easily be achieved. Disadvantages
• Property and construction costs higher • Property and construction costs higher
than for a diamond interchange. than for a diamond interchange.
December 2005
16-67
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
Figure 16-36 Three level diamond
Figure 16-37 Three level diamond -
Advantages single point intersection
December 2005
16-68
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
and expensive, especially if all possible direct B requires a right hand merge.
movements are provided. In the extreme Neither of these types is favoured since
case where all turning volumes are so heavy they contravene the principles of
that direct connections are required for consistency of operation.
them all, a four level interchange results.
Right turns
Because of the expensive and complex
The five possible free-flow right turn
nature of these interchanges, the expected
movements are illustrated in Figure 16-39.
turning volumes must be carefully assessed
and examined. The ultimate interchange
layout is to provide for the expected traffic
and maintain sufficient flexibility to allow
16
for future modification if required.
These interchanges generally have to be
designed to suit the site and traffic flows as
the turning volumes and site controls often
make adapting a “standard” type
impractical. To rationally approach the
design of an interchange, the three possible
movements must be analysed and
appropriate ramps designed to Figure 16-39 Free-flow right turns
accommodate them. Right hand exits and entries, as shown in
Left turns Figure 16-39, may be used for direct, semi-
direct A and semi-direct B movements
Figure 16-38 illustrates free-flow left turns. where wide medians permit their
construction and an additional lane is
provided; and provided traffic volumes and
route continuity considerations as set out in
Section 16.4 warrant their use. These cases
are to be treated as a major fork or branch
connection (refer to Sections 16.5.8.9 and
16.5.8.10).
The resulting interchange will be tailored to
the conditions prevailing at the site in
Figure 16-38 Free-flow left turns question and the traffic conditions expected.
A wide range of solutions for these types of
With all median widths, the direct left turn
interchanges has been generated around the
outer connector ramp is usually the least
world, some of which are illustrated in
expensive. If one or both medians are wide
outline form in Figure 16-40 and Figure
then semi-direct left turns may be used to
16-41. While the application of these types
avoid a control or to reduce weaving while
of interchanges has been limited in
maintaining directionality at the next
Queensland, situations requiring at least
diverge. Note that the semi-direct A
some of the elements described will arise
requires a right hand exit and the semi-
and the solutions generated elsewhere will
December 2005
16-69
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
serve to provide ideas on what may be included in AASHTO (2001) and Vicroads
required. (1998). These references also provide more
examples of possible forms of interchanges.
This Manual will not discuss these in detail
but more comprehensive discussion is
16
December 2005
16-70
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
December 2005
16-71
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
December 2005
16-72
Department of Main Roads Chapter 16
Road Planning and Design Manual Interchanges
16
Figure 16-42 Example 16C – exit ramp of a partial clover leaf interchange
December 2005
16-73