Problem 1 (CE Board May 2009) A staggered has rivets arranged as shown. Diameter of the rivets is 28 mm. Diameter of the holes is
assumed to be 2mm bigger than the of the rivet. Fy = 24 MPa
1. Which of the following gives the distance “b” so that the net area in chain 1-2-3-4 is equal to the net area of the chain 1-2-4?
2. Using the computed value of “b”, solve for the net width.
3. Which of the following gives the maximum tensile force P that the riveted connection could carry if the allowable tensile stress is
0.6Fy?
Solution :
[
Net area= 253.63+
b2
360 ]
10 ..........(E 1)
[ 253.63+
b2
360 ] [
10= 253.63+
(60−b)2
720
10 ]
using calculator.....
b = 81.99 mm say 82 mm