CHINA STATE HUALONG CONSTRUCTION COMPANY..

MINUTES OF MEETING

MEETING PRELIMINARIES
Project : Extension to MP`s Offices-Job 600 Annex.
Subject : Meeting 1
Place : Job 600Annex-Parliament house. Date : 27/10/17
Time : 10:00 am Pages : 2

MEETING ATTENDANCE:

Consultant: MEP Director (China


Present State): Present
ADK Consortium. Mr.Wu

Client: Parliament Of
Abscent Civil Works Engineer:
Ghana.
Present
Emmanuel Siaw

APPROVAL:
Minutes By : Emmanuel Siaw Date : 27/10/17
Vetted By : Mr. Wu Date : 27/10/17
Approved By : Date : 27/10/17

1 GENERAL INTRODUCTION OF MEETING ATTENDEES:

The meeting began at 10:00 am with the introduction of member both from
1.1 ADK Consortium and China State Hualong Construction.

2 SUBJECT MATTER
The MEP Director requested for a layout on the existing services lines(cable) on
2.1 the site from which the above project is to be executed.

3 CONSULTANTS RESPONSE TO ITEM 2.1

The Consultant (ADK Consortium) indicated that the three appointed


service/utility providers companies namely Vodafone Ghana,Ghana Water
Company and lastly ECG are yet to produce the existing layout drawing of
services on the site but assured its availability a week from this day of
meeting.He further indicated that the Client(Parliament of Ghana) requested
for a detailed financial and Insurance arrangement from China State before
the Client can hand over construction site to China State.

Page 1 of 2
CHINA STATE HUALONG CONSTRUCTION COMPANY..

3.3 Conclusion:
The meeting was ended at 11:30 am.

Page 2 of 2