Paper No.

668

a) Cost saving 50% of the execution cost of Monopiles meaning one pile per pier instead
foundations. of group of piles. These piles are in usage in
b) Time savings almost 50% of piling time. Metro-rail transport and bridge construction
5.4.2 Case Study -2 throughout world. Monopiles are preferred for
supporting heavy foundation loads of viaducts.
Lodha world place – India
Typical sizes of these piles range from 1 m to 3 m
a) Tested piles - 2 No. – Initial
or more also, the length can be more than 80 m and
2 No. – Routine working loads about 5000T and more. Normally
b) Pile dia & length - 1.20 m & 26.70 m in viaducts of Dubai metro, where pier size is
c) Pre-estimated value of side shear – 1.75 m to 2.00 m diameter are supported by
0.10 Mpa 2.00 m or 2.40 m monopoles. These pile diameters
d) Side shear mobilised in test – 2.00 Mpa go beyond 3.00 m also. Normally these piles
against estimated 0.10 Mpa are designed as friction cum end bearing and in
e) No load transfer to end bearing majority of cases as friction only. Designs are
f) Final length of pile’s reduced from 26.7 M also optimised to eliminate the need for pile caps.
- to 19.00 M, percentage reduction in pile There are drill rigs available to drill pile’s more
length – 28.83 than 3.00 m dia and depth more than 100 m. In
5.4.3 Case study -3- Seacaucus NJ transfer addition many have used vibro hammer to drive
station down steel single or double casing, than removal
a) Initial design of the same while concreting.
 9 m rock sockets (Typical) Considering 4 or 8 pile system per pier in a bridge
 Design side shear; 1.30 Mpa or metro-rail the time saving is more than 50% and
b) As per Bi-directional tests cost saving can be more than 30%.
 2 shafts with 1.50m rock sockets 7. Introduction of such piling
Measured side shear; 2.70 Mpa systems which can drill 30 M
c) Estimated vs actual costs in 30 hours per pile including
 Final design: 4.50m rock sockets concreting
 Design factors of safety; 3 Measured Dubai metro, piling works undertaken using many
factor of safety > 5 types of rigs, typical being the BAUER BG 22/28
 Redesigned F.S > 2 rotary rig whose average construction time is 30
hours per pile including concreting.
Foundation cost estimates : USD 18 million
There are many types of piling rigs available in
Redesigned foundation : USD 9.155 million
India also like BAEUER, BG, 22/28 Rotary rig
cost with testing
which can drill with an average pile construction
Net savings : USD 8.845 million time of 30 hours from commencement of boring
Percentage of saving – 49.14% to completion of concreting of about 30m average
Estimate cost and time saving length pile.
 Cost – Almost 50% saving Considering 1 km length of bridge with an average
 Time – Almost 50% Saving 35 m length spans will normally have around
200 piles, with the usage of such 10 Nos. of rigs
6. Introduction of very large
will take around 32-35 days to complete the
diameter monopoles
piling. Whereas, presently we are taking more than
Dubai metro, majority of the piles for the viaduct 4-6 months to complete this 200 piles.
are monopoles ranging diameters 2.2 m to 2.4 m and
were designed as friction piles as end bearing was Cost saving – depends on project
ignored due to potential risks of weak substrata’s. Time saving – more than 50%.

Journal of the indian Roads Congress, July - September, 2017 77