Priority Floors & Major Balance Works Update (04!26!2018)
Priority Floors & Major Balance Works Update (04!26!2018)
I. AMR SYSTEM:
1.0 Roughing-ins, wiring-ins, and utilities for controls at 6F Work Station. Ongoing April 30, 2018
2.0 Termination for Current Transformer at 11F to 17F. BETA 17F - 26 April 2018 / Mezz. - 28 April 2018 April 26 & 28, 2018
3.0 Testing and commissioning. May 04, 2018
11.0 Granite slab for all elevators, waterproofing at LZE Pit and above Machine Room, DDTKI/ IEEI
None yet. Granite will be delivered on 28 April 2018 and
April 28 & 30, 2018
and completion of railings & manhole covers for LZE Machine Room. installation to be completed on 30 April 2018.
12.0 Hanger Bracket for FML Hatch Doors (B2 to 17F) DDTKI/ IEEI None yet April 28, 2018
Page 1 of 3
CONCERNED COMMITTED COMPLETION
NO: PARTICULARS: STATUS TO DATE:
CONTRACTOR: DATE:
XII. STP:
1.0 Exhaust Duct (SS and G.I. Extensions) Not yet delivered. May 25, 2018
2.0 Ladder Rungs Awaiting details prior to procurement. None
DDTKI
3.0 STP Room Doors & Rails For installation of railing. April 30, 2018
4.0 Civil & architectural Finishing Works (painting) Ongoing preparation of Epoxy Paint application May 02, 2018
Page 2 of 3
CONCERNED COMMITTED COMPLETION
NO: PARTICULARS: STATUS TO DATE:
CONTRACTOR: DATE:
10.0 Final painting at lobbies and parking areas. None yet April 28, 2018
11.0 Final painting and epoxy paint at storage rooms and mechanical rooms. Latex Paint - 05 May 2018 / Epoxy - 08 May 2018 May 05 & 08, 2018
XVII. GF LEVEL:
1.0 ACP cladding and glass for Ruby Canopy. Ongoing April 27, 2018
2.0 Finishing works for Ruby & Beta Arcade. Ongoing April 28, 2018
3.0 Trench Grating at Beta Side. None yet 1st Week of May 2018
4.0 Seismic gap cover (ceiling). None yet None
5.0 Completion of Store Fronts (balance glass panels, capping & doors). Ongoing May 05, 2018
6.0 Completion of demishing walls at leasable 6 (no sealant yet on other leasables). Ongoing April 30, 2018
DDTKI
7.0 Cladding and restoration of slab for MEPF vertical utilities. None yet April 30, 2018
8.0 Completion of granite works at façade. Ongoing April 30, 2018
9.0 FHC at ruby side. DONE
10.0 Buffing of granite stones for flooring, walls, and counters. Ongoing April 27, 2018
11.0 3M sticker at lift lobby ceiling. Ongoing None
12.0 Ceiling finishes, Mirror and Grab Bar at PWD Toilet. None yet April 30, 2018
13.0 Finishing works for water meter room. None yet None
3.0 Zocallo and Cladding for refrigent pipes at Transformer Room (with drain
None yet None
provision).
DDTKI
4.0 Ceiling for Admin & lobby. None yet None
5.0 Painting works for Admin Office. None yet None
6.0 Glass Doors for Admin Office. None yet None
7.0 ACP cladding at elevator door headers. None yet None
1.0 Epoxy floor finish and, improvement of wall and ceiling finishes at EE, Aux and
Ongoing April 28, 2018
Watermeter Room.
2.0 Rectification of cracks at flooring for leasable. Ongoing April 28, 2018
3.0 Epoxy injection for 11F, 15F & 17F leasable flooring. Ongoing April 28, 2018
4.0 Ready to receive carpet for leasable flooring (floor grinding). DDTKI Ongoing April 28, 2018
5.0 Repainting of steel doors. Ongoing at 15F & 17F April 28, 2018
6.0 Alignment of ceiling frames for leasable (except 9F). Ongoing April 27, 2018
7.0 Adjustment/resizing and cladding of ducts at leasable areas at 15F and 17F. Done resizing. Ceiling frame should be fixed. April 30, 2018
8.0 ACP cladding at FML door header at 15F and 17F. None yet April 30, 2018
Page 3 of 3