CYBERSCAPE GAMMA PROJECT

MAJOR BALANCE WORKS UPDATE FOR 30 APRIL 2018 COMPLETION


(B2, B1, GF, MEZZ, 9F, 10F, 11F, 15F, 17F, and BASE BUILDING UTILITIES)
As of: 26 April 2018

CONCERNED COMMITTED COMPLETION


NO: PARTICULARS: STATUS TO DATE:
CONTRACTOR: DATE:

I. AMR SYSTEM:
1.0 Roughing-ins, wiring-ins, and utilities for controls at 6F Work Station. Ongoing April 30, 2018
2.0 Termination for Current Transformer at 11F to 17F. BETA 17F - 26 April 2018 / Mezz. - 28 April 2018 April 26 & 28, 2018
3.0 Testing and commissioning. May 04, 2018

II. CCTV & INTERCOM SYSTEM:


1.0 Roughing-ins, wiring-ins, and utilities at 6F Work Station. Wiring-ins - 26 April 2018 / Monitor Inst. - 27 April 2018 April 26 & 27, 2018
2.0 Installation of CCTV System for Elevators (CE, PE1 & PE2, LZE). Installation will Start tomorrow, 27 April 2018 April 27, 2018
DIGICOM
3.0 Droppings at GF Level and 15F Level. Ongoing April 27, 2018
4.0 Testing and commissioning. April 30, 2018

III. VRF SYSTEM:


1.0 Mounting of balance ACCUs at 2F & 3F. RALGO/ DDTKI DONE
2.0 Terminations of refrigerant pipes to all ACCUs. RALGO Ongoing at 15F Level; 9F to 12F & 17F Done. April 27, 2018
3.0 Completion of power supply for all ACCUs. RALGO/ DDTKI Tapping Point to be complete by 30 April 2018 April 30, 2018
4.0 Repositioning of FCUs and completion of insulation at Mezzanine. RALGO Ongoing April 27, 2018
5.0 Resizing of ERV Ducts at 15F & 17F Leasable. RALGO/ DDTKI Ongoing April 27, 2018
6.0 Testing and commissioning. RALGO May 03, 2018

IV. ELEVATOR SYSTEM:


1.0 High Speed Test and T & C of CE. HST - 03 May 2018 / T&C - 04 May 2018 May 03 & 04, 2018
2.0 T & C of PE1 & PE2. PE-2 Done. Ongoing adjustment of Buttons for PE-1. May 04, 2018
3.0 Permanent Power Connection for PE-1, PE-2 & CE Awaiting Delivery of Breakers. Delivery by 15 May 2018 . May 15, 2018
IEEI
4.0 High Speed Test and T&C of PE5. HST - 28 April 2018 / T&C - 30 April 2018 April 28 & 30, 2018
5.0 Completion of wiring, start-up, high speed test, and T&C of PE6. Ongoing wirings. Start-up by 02 May 2018 . May 02, 2018
6.0 Major works for PE7. Start-up by 04 May 2018 . May 04, 2018
7.0 Installation of glass mirrors and hand rails for PE5 to PE7. Frame for PE-5 - 27 April 2018 ; PE-6 & PE-7 30 April 2018 . April 27 & 30, 2018
DDTKI/ IEEI
8.0 Floor Tile Installation (PE-1, PE-2, CE, PE-5) DDTKI to install this weekend. April 28 & 29, 2018
9.0 Installation of elevator button: call and lantern at 15F and 17F. Complete by 28 April 2018 . April 28, 2018
IEEI
10.0 FML Jamb at 8F Level. April 30, 2018

11.0 Granite slab for all elevators, waterproofing at LZE Pit and above Machine Room, DDTKI/ IEEI
None yet. Granite will be delivered on 28 April 2018 and
April 28 & 30, 2018
and completion of railings & manhole covers for LZE Machine Room. installation to be completed on 30 April 2018.

12.0 Hanger Bracket for FML Hatch Doors (B2 to 17F) DDTKI/ IEEI None yet April 28, 2018

MEPF WORKS/ SYSTEM:


V. MECHANICAL SYSTEM:
1.0 Completion of all duct risers (@ 34F only to date). Duct Riser up to RD Level complete by 10 May 2018 May 10, 2018
2.0 Activation of all blowers at RD Level (no power supply yet). None yet May 30, 2018
3.0 Supply duct for blowers at basement parking. Duct connector not yet delivered. May 10, 2018
4.0 Activation of Jet Fans at basement parking. None yet April 27, 2018
5.0 CO sensors for basement parking (not yet procured). None yet May 30, 2018
6.0 Wall Grilles for stair pressurization. None yet May 10, 2018
DDTKI
7.0 Ceiling grilles at GF & Mezzanine (to include for Commercial Elevator). None yet. Delivery by 27 April 2018 . April 27, 2018
8.0 Wall Grilles for PE1 & PE2 shaft ventilation. None yet May 10, 2018
9.0 Resizing of ERV duct stub-out & Smoke Evac at 15F & 17F. DONE
10.0 Balance blowers at 8F Equipment room (8 units). Awaits completion of louvers. April 28, 2018
11.0 Fuel pipe line (From Storage Tank to Day Tank). Balance at 7F to Day Tank Aprill 30 2018
12.0 Testing and commissioning. 15 & 30 May 2018

VI. ELECTRICAL SYSTEM:


1.0 LVSG Grounding. DONE
2.0 Permanent power for Low Zone Elevators. Ongoing April 27, 2018
3.0 Power supply for ME Equipments at RD Level. RD Level - 15 May 2018 ; Overall Equipments - 30 May 2018 May 15 & 30, 2018
4.0 Power supply for Jet Fans and CO sensors at basements. CO Sensor not yet delivered. May 30, 2018
5.0 Power supply ACCUs. Ongoing April 30, 2018
6.0 Completion of termination for meter center busbar gutter (15F & 17F). Ongoing April 27, 2018
7.0 Completion of Lighting Fixtures with hangers at 17F. Ongoing April 29, 2018
8.0 Power supply for GF canopies. DDTKI Ongoing April 29, 2018
9.0 Power provision for pylon signage. Ongoing April 29, 2018
10.0 Cove lights for toilets (11F, 15F, 17F). Ongoing at 15F April 29, 2018
11.0 Relocation of pull boxes at GF & Mezzanine Leasable. Ongoing April 29, 2018
12.0 Emergency lights for FE Stair 2 (B2, GF to 8F, 15F to 17F). Awaiting Finishing of Paint prior to Installation April 30, 2018
13.0 FE Stair 2 Ceiling Lights for B2 to 8F, 14F to 17F. Awaiting Finishing of Paint prior to Installation April 30, 2018
14.0 Installation of shaft lightings (CE, PE1 & PE2, PE5 to PE7) Ongoing April 30, 2018
15.0 Testing and commissioning. Low Zone - 15 May 2018 ; Overall - 30 May 2018 May 15 & 30, 2018

Page 1 of 3
CONCERNED COMMITTED COMPLETION
NO: PARTICULARS: STATUS TO DATE:
CONTRACTOR: DATE:

VII. AUXILIARY SYSTEM (FDAS and Intercom):


1.0 All works for 6F Control Room.
2.0 Rectification of CCTV’s dropping at GF Level & 15F Level. DONE
3.0 Additional smoke detectors for 11F, 15F, & 17F.
4.0 Remote Annunciator Panel @ GF Reception. DDTKI to verify if already delivered. April 29, 2018
DDTKI
5.0 Stickers/tagging for 17F Level. None yet None
6.0 Relocation of pull boxes at GF & Mezzanine Leasable. None yet April 29, 2018
7.0 Smoke Detectors for FE Stair 2. DDTKI to verify if as per Plan None
8.0 Testing and commissioning. Low Zone - 15 May 2018 ; Overall - 30 May 2018 May 15 & 30, 2018

VIII. PLUMBING & SANITARY SYSTEM:


1.0 Deck drains at 9F Service Deck. None yet None
2.0 Area drains at GF Level. Ongoing April 30, 2018
3.0 Additional parking drains on areas with ponding at basement parkings.
DONE
4.0 Balance FCO at Mezzanine Level.
5.0 Riser and Downfeed for water supply system (36F to elevated water tank). DDTKI Ongoing April 30, 2018
6.0 Gate Valves and PRV (18F to elevated water tank). Ongoing at 17F. Gate Valves installation - 27 April 2018 April 27, 2018
7.0 Water meter at 17F. Ongoing April 30, 2018
8.0 Elevator Pit Drains for CE, PE1 & PE2, LZE. Ongoing April 30, 2018
9.0 Flushing, Testing and commissioning, Water Potability Test. Low Zone - 15 May 2018 ; Overall - 30 May 2018 May 15 & 30, 2018

IX. FIRE PROTECTION SYSTEM:


1.0 Fire Department Connection (plates, cap & chain, restoration and cladding). DDTKI to complete all requirements from BFP. None
2.0 Droppings and sprinklers at GF & Mezzanine Level. GF Done. Ongoing at Mezzanine April 28, 2018
3.0 Floor control valves at FE Stairs at 15F to 17F. None yet April 28, 2018
DDTKI
4.0 Installation of Fire Extinguishers. Ongoing April 30, 2018
5.0 Sprinkler Heads for FE Stair 2 (B2 to 8F, 16F to 17F). Ongoing April 27, 2018
6.0 Testing and commissioning. Low Zone - 15 May 2018 ; Overall - 30 May 2018 May 15 & 30, 2018

UNDERGROUND TANKS & BASE UTILITIES:


X. PUMP ROOM:
1.0 Alarm Gong None yet April 27, 2018
2.0 Completion of painting works for pipes, walls, ceiling, and doors DDTKI Ongoing April 27, 2018
3.0 Epoxy Paint for flooring. Ongoing May 02, 2018

XI. FUEL STORAGE TANK:


1.0 Completion of anchoring enhancements. DDTKI to commence tomorrow, complete by 1 Month May 27, 2018
2.0 Leak test for the concrete enclosure. None yet 1st Week of June 2018
3.0 Procurement and installation of fuel pump. DDTKI P.O. already secured. May 02, 2018
4.0 Repainting of Fuel Storage Tank. Awaiting completion of Waterproofing & Testing 1st Week of June 2018
5.0 Termination of Electrical Supply DONE

XII. STP:
1.0 Exhaust Duct (SS and G.I. Extensions) Not yet delivered. May 25, 2018
2.0 Ladder Rungs Awaiting details prior to procurement. None
DDTKI
3.0 STP Room Doors & Rails For installation of railing. April 30, 2018
4.0 Civil & architectural Finishing Works (painting) Ongoing preparation of Epoxy Paint application May 02, 2018

XIII. GREASE TANK:


1.0 Strainer None yet April 30, 2018
DDTKI
2.0 Manhole Cover None yet May 05, 2018

XIV. SUMP PIT:


1.0 Manhole Cover & Ladder Rungs None yet May 05, 2018
DDTKI
2.0 Installation of Sump Pump None yet None

CIVIL & ARCHITECTURAL/ FINISHING WORKS:


XV. WATERTIGHTNESS:
1.0 Sealant for Punch Windows at Topaz’s Alimak Area. with Balance on 2F Level April 30, 2018
2.0 Completion of Field Tests. Awaiting confirmation from ALT May 07, 2018
3.0 Completion of sealants for precast gaps. DDTKI DONE
4.0 Waterproofing at 2F Ramp and Perimeter. Ongpoing at perimeter
5.0 Enclosure of chase at RD Level. None yet Next Week

XVI. BASEMENT PARKING (B1 & B2):


1.0 Completion of restoration works for B1 Beam at FML. Ongoing restoration works April 26, 2018
2.0 Concrete filler for FML Jambs. None yet April 28, 2018
3.0 Replacement of tiles at Garbage room (with different shades). None yet April 30, 2018
4.0 Improvement of Broom Finish. None yet April 30, 2018
5.0 Steel doors for mechanical room & storage room of B1 (2 sets). For completion by 27 April 2018 . April 27, 2018
6.0 Repair works for ponding at driveways/parking areas. DDTKI None yet None
7.0 Completion of humps and parking numbers. 6 Balance on Humps; Parking Numbers at 77%. April 28, 2018
8.0 Floor directional arrows. None yet None
9.0 ACP cladding at elevator door header. None yet April 30, 2018

Page 2 of 3
CONCERNED COMMITTED COMPLETION
NO: PARTICULARS: STATUS TO DATE:
CONTRACTOR: DATE:

10.0 Final painting at lobbies and parking areas. None yet April 28, 2018
11.0 Final painting and epoxy paint at storage rooms and mechanical rooms. Latex Paint - 05 May 2018 / Epoxy - 08 May 2018 May 05 & 08, 2018

XVII. GF LEVEL:
1.0 ACP cladding and glass for Ruby Canopy. Ongoing April 27, 2018
2.0 Finishing works for Ruby & Beta Arcade. Ongoing April 28, 2018
3.0 Trench Grating at Beta Side. None yet 1st Week of May 2018
4.0 Seismic gap cover (ceiling). None yet None
5.0 Completion of Store Fronts (balance glass panels, capping & doors). Ongoing May 05, 2018

6.0 Completion of demishing walls at leasable 6 (no sealant yet on other leasables). Ongoing April 30, 2018
DDTKI
7.0 Cladding and restoration of slab for MEPF vertical utilities. None yet April 30, 2018
8.0 Completion of granite works at façade. Ongoing April 30, 2018
9.0 FHC at ruby side. DONE
10.0 Buffing of granite stones for flooring, walls, and counters. Ongoing April 27, 2018
11.0 3M sticker at lift lobby ceiling. Ongoing None
12.0 Ceiling finishes, Mirror and Grab Bar at PWD Toilet. None yet April 30, 2018
13.0 Finishing works for water meter room. None yet None

XVIII. MEZZANINE LEVEL:


1.0 Repair/reinstallation of ceiling seismic gap cover. Still for Checking if already done.
2.0 Wall seismic gap cover staring at 2F Level. None yet None
3.0 Epoxy floor paint & concreting of aux riser at rentable storage. None yet None
4.0 Completion of Store Fronts (balance on capping & doors). DDTKI Ongoing None
5.0 Sealant works for demishing walls. Ongoing None
6.0 Completion of wall cladding on leasables (above store front). None yet None
7.0 Completion of glass railings. None yet None

XIX. 8F EQUIPMENT ROOM, ADMIN OFFICE & LOBBY:


1.0 Epoxy Floor Paints at equipment room. None yet None
2.0 Balance Louvers at Ruby Side of equipment room. Ongoing April 27, 2018

3.0 Zocallo and Cladding for refrigent pipes at Transformer Room (with drain
None yet None
provision).
DDTKI
4.0 Ceiling for Admin & lobby. None yet None
5.0 Painting works for Admin Office. None yet None
6.0 Glass Doors for Admin Office. None yet None
7.0 ACP cladding at elevator door headers. None yet None

XX. OFFICE FLOORS (9F, 10F, 11F, 15F & 17F):

1.0 Epoxy floor finish and, improvement of wall and ceiling finishes at EE, Aux and
Ongoing April 28, 2018
Watermeter Room.

2.0 Rectification of cracks at flooring for leasable. Ongoing April 28, 2018
3.0 Epoxy injection for 11F, 15F & 17F leasable flooring. Ongoing April 28, 2018
4.0 Ready to receive carpet for leasable flooring (floor grinding). DDTKI Ongoing April 28, 2018
5.0 Repainting of steel doors. Ongoing at 15F & 17F April 28, 2018
6.0 Alignment of ceiling frames for leasable (except 9F). Ongoing April 27, 2018
7.0 Adjustment/resizing and cladding of ducts at leasable areas at 15F and 17F. Done resizing. Ceiling frame should be fixed. April 30, 2018
8.0 ACP cladding at FML door header at 15F and 17F. None yet April 30, 2018

XXI. FIRE EXIT STAIRS (B2 to 17F):


1.0 Epoxy paint for flooring. None yet May 03, 2018
2.0 Automotive paint for railings & stair nosing. Ongoing at 9F Only May 03, 2018
3.0 Painting on FHC Area at 9F to 17F None yet May 03, 2018
DDTKI
4.0 Plastering and painting at the back of FHC at B2 to 8F. Ongoing at B2 to GF Level May 03, 2018
5.0 Ceiling and wall painting for B2 to 8F. Ongoing at B2 to GF Level May 03, 2018
6.0 Door hardwares for B2 to 8F None yet May 03, 2018