North RW Cost Increase
North RW Cost Increase
Depth 2m
Width 1.5 m
Option -1
Quantity m3 Cost
GSB & soleing in 300mm layers 1500 2300 3,450,000
Excavation 1500 125 187500
Total 3,637,500
Option -2
RCC wall taking to firm soil
Concrete 150 7847 1177050
Steel 12 70000 840000
Formwork 1500 1004 1506000
Excavation 1500 125 187500
Filling with compaction 1500 161 241500
3,952,050
Option -3
Driving rods at 200mm spacing 25 mm
1000 5 5
Nos 5000
Area of bar 0.0004909375 m2
Quantity 38.53859375 MT
Cost 2,697,702
Option -4
Excavation 1500 125 187500
GSB filling 1.5 m 1125 1300 1462500
Remaining soil to be filled in 0.5 375 300 112500
200 mm layers to 98% proctor density 1,762,500