Gantt Chart Problem Charts

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

task start date end date duration

excavate 01/04/2018 14/04/2018 2


lay the foundation 15/04/2018 12/05/2018 4
put up the rough wall 13/05/2018 21/07/2018 10
put up the roof 22/07/2018 01/09/2018 6
install exterior plumbing 02/09/2018 29/09/2018 4
install interior plumbing 30/09/2018 03/11/2018 5
put up exterior sliding 04/11/2018 22/12/2018 7
do exterior painting 23/12/2018 09/02/2019 9
do electrical work 10/02/2019 30/03/2019 7
put up wallboard 31/03/2019 18/05/2019 8
install flooring 19/05/2019 15/06/2019 4
do interior painting 16/06/2019 20/07/2019 5
install exterior fixtures 21/07/2019 03/08/2019 2
install interior fixtures 04/08/2019 14/09/2019 6

01/04/2018 10/07/2018 18/10/2018 26/01/2019 06/05/2019 14/08/2019 22/11/2019

excavate

lay the foundation

put up the rough wall

put up the roof

install exterior plumbing

install interior plumbing

put up exterior sliding

do exterior painting

do electrical work

put up wallboard

install flooring

do interior painting

install exteriorfixtures

install interior fixtures