Professional Documents
Culture Documents
ESE-2018 Mains Test Series: Civil Engineering Test No: 1
ESE-2018 Mains Test Series: Civil Engineering Test No: 1
ESE-2018 Mains Test Series: Civil Engineering Test No: 1
=
1
3
(
2.3 × 10 −5 × 1 + 5.2 × 1.5 × 10 −5 + 0.2 × 10 −5 × 0.5 )
= 3.4 × 10–5 cm/sec
H0
kV(eq) =
h1 h2 h3
k + k + k
V1 V2 V3
3.0
= = 0.931 × 10 −5 cm/s
1 1 1.5 0.5
+ +
10 −5 2.3 5.2 0.2
k H ( eq ) 3.4 × 10 −5
= = 3.65
kV ( eq ) 0.931 × 10 −5
For below the canal;
H0 = 1.50 + 1.2 + 3.0 = 5.7 m
H0
kV(eq) =
h1 h2 h3
k + k + k
V1 V2 V3
5.70
= = 7.2 × 10 −6 cm/sec
1.5 1.2 3
+ + −6
2 × 10 −6
30 × 10 −6
800 × 10
0.15 m 0.15 m
0.9 m 0.9 m 0.9 m
The negative frictional load is maximum on the pile group is the maximum of
(a) Fng = nFn and (b) Fng = cuLnPg + γLnAg
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
Test No : 1 CIVIL ENGINEERING | 11
q u 60
where Pg = 4 × 3 = 12 m and Ag = 3 × 3 = 9 m2, cu = = = 30 kN/m 2
2 2
(a) Fng = n α cu × As = 16 × 0.6 × 30 × π × 0.3 × 3 = 814.302 kN
(ii)
The depth below the centre of the loaded area (raft), Z = 4 m. Dividing the loaded area into four
equal squares of 2 m size as shown below, the load from each small square may be taken to act
through its centre.
Thus, the point loads at A, B, C and D are each :
QA = QB = QC = QD = 200 × 2 × 2 = 800 kN = Q
The radial distance of each of the load from the center of load area is 2 m.
r 2 1
∴ = =
Z 4 2 2
2m 2m
A B
2m
m
√2
D C
2m
Loaded area
By symmetry the stress increment, ∆σz at 4 m depth is four times that caused by one load.
Q (3 / 2 π ) 4 × 800 ( 3 / 2π )
∴ ∆σz = 4 × 2
× = ×
Z 2 5/2 4×4 2 5/2
r 1
1 + 1 +
Z
2 2
= 71.14 kN/m2
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
12 | ESE 2018 : MAINS TEST SERIES
( γ d )compacted soil 18
= = = 1.11 m 3
( γ d ) borrow pit soil 16.2
∴ Volume of soil required = Swell factor × Volume of borrow pit soil required
= 1.2 × 1.11 = 1.33 m3
(ii) Weight of solids per unit volume of borrow pit soil
γ 17
Ws = = = 16.2 kN/m 3
1 + w 1 + 0.05
Additional water content = (7 – 5)% = 2%
Weight of water, WW = wWS = 0.02 × 16.2 = 0.324 kN
W W 0.32
∴ Volume of water, VW = = = 0.033 m 3 = 33 litres
γw 9.81
2.694 − 2.50
Percentage error = × 100 = 7.2%
2.694
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
Test No : 1 CIVIL ENGINEERING | 13
Q.2 (a) Solution:
(i)
Slip surface
Let us select three points A, B and C on the possible failure surface. The rotational slip surface will
cause compression on element A, shear on element B, and extension on element C.
The stresses on element A are analogeous to a triaxial compression test.
Element B will deform in a manner compatible with simple shear, while element C will suffer an
upward thrust that can be simulated by triaxial extension test.
The following strength tests are recommended:
(a) Triaxial CU compression test with pore water pressure measurements. Parameters required
are φ ′p , φ cs and C u .
(ii)
φ = 35°
Active pressure coefficient of Rankine for inclined surcharge.
cos β − cos 2 β − cos 2 φ
kai = cos β
cos β + cos 2 β − cos 2 φ
When β = 0° for horizontal surface of the backfill.
1 − sin φ
ka =
1 + sin φ
kai for β = 20° and φ = 35° is given by
cos 20° − cos 2 20° − cos 2 35°
kai = cos 20°
cos 20° + cos 2 20° − cos 2 35°
⇒ kai = 0.322
ka for β = 0 and φ = 35° is given by
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
14 | ESE 2018 : MAINS TEST SERIES
1 − sin 35°
ka = = 0.271
1 + sin 35°
Percentage error in the computed active thrust by assuming a level fill when it is actually inclined
at 20° to horizontal.
0.322 − 0.271
⇒ × 100 = 15.84%
0.322
Q.2(b)(i) Solution:
Given:
Total head at A, hA = Datum head + Peizometric head
= 2+5=7m
⇒ At B, hB = 0 + 6.8 = 6.8 m
⇒ Head loss, ∆H = hA – hB = 7 – 6.8 = 0.2 m
Length, L = 2 m
∆H
Hydraulic gradient, i =
L
0.20
⇒ i = = 0.10
2.0
Assuming this hydraulic gradient as the average hydraulic gradient for the entire soil mass, then
effective stress is
= ( γ sat − γ w ) z + iγ w z
= (18.5 – 9.81)6 + 0.1 × 9.81 × 6 = 58.1 kPa
(ii)
(a) We know,
Settlement of foundation on cohesionless soil,
( )
2
B b p + 0.3
Sf = SP
b p ( B + 0.3 )
2
2(0.3 + 0.3)
= 10 = 30.25 mm
0.3(2 + 0.3)
(b) A load intensity of 160 kN/m2 induces a settlement of 30.25 mm.
Assuming the load-settlement to be linear within small range,
q2 S f2
=
q1 S f1
S f2
⇒ q2 = q 1 ×
S f1
where q1 = 160 kN/m2, Sf = 30.25 mm and Sf = 40 mm, substituting the known value,
1 2
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
Test No : 1 CIVIL ENGINEERING | 15
40
q2 = 160 × = 211.57 kN/m 2
30.25
Now, Sf = m v H 0 ∆σ
Settlement rate : Since U is proportional to t for U < 0.60, the settlement is also proportional to
t . Thus,
S2 ∝ t
or, t = CS 2
when t = 1 year, S = 0.286 m.
1
Therefore, C = 2
= 12.226 year/m 2
(0.286)
t
∴ t = 12.226S 2 ⇒ S=
12.226
dS 1 1 1
⇒ = = = = 0.143 m/year
dt 2 t 12.226 2 × 12.226 6.993
0.143
Discharge per unit area in one year = = 0.072 m 3 /year/m 2
2
σ ′1 − σ ′3 300 − 100 2 1
(i) sin φ′ = σ ′ + σ ′ = 300 + 100 = 4 = 2
1 3
φ′ = 30°
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
16 | ESE 2018 : MAINS TEST SERIES
σ1 ′ + σ 3 ′ σ1 ′ − σ 3 ′
(ii) σ′n = + cos 2θ
2 2
σ ′1 − σ ′3 300 − 100
(iv) τmax = = = 100 kPa
2 2
= τmax > τ′c
Hence, shear stress is greater than the failure shear stress.
∆h
∆h
Flow path
a3
b3
a1 3
Flow line b1 a2
1
2 b2 ∆q
Equipotential lines
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
Test No : 1 CIVIL ENGINEERING | 17
∆h 1 ∆h ∆h
∆q1 = k a1 × 1; ∆q 2 = k 2 a 2 × 1; ∆q 3 = k 3 a3 × 1
b1 b2 b3
a1 a2 a3
= = =1
b1 b2 b3
H
∴ ∆q = k
Nd
If the number of flow channels in a flow net is Nf , the rate of flow q through all the flow channels
per unit length is given by
q = ∆q × Nf
Nf
q = kH
Nd
∂2h ∂2h
kx + kz = 0
∂x 2 ∂z 2
∂2h ∂2h
⇒ + = 0
kz 2 ∂z 2
∂x
kx
Substituting for x a new coordinate variable xt such that
kz
xt = x
kx
kz
( ∂x t ) 2 = ∂x
2
kx
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
18 | ESE 2018 : MAINS TEST SERIES
∂2h ∂2h
∴ + = 0
∂xt2 ∂z 2
The above equation envisages a scale transformation in the x-direction to transfer a given anisotropic
medium into a fictitious isotropic medium for which the Laplacian equation is valid, so that a flow
net can be constructed. The flow net is drawn for the transformed section - a section obtained by
kz
shortening the horizontal dimensions of the new section by the ratio , while keeping the
kx
vertical dimensions unchanged. The flow net on the transformed section will have orthogonal
intersections of flow lines and equipmential lines with all its field being elementary squares.
The value of coefficient of permeability applicable to the transformed section is
k eq = kx kx
⇒ kA = 0.70
3
γsat = 17.3 kN/m
H1 = 4.57 m φ = 20°
2
c = 12 kN/m
WT
H2 = 2.75 m
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
Test No : 1 CIVIL ENGINEERING | 19
Z0 = 1.98 m
2.59 m
a b
Pa = 140 kN/m
2.75 m
1.66 m
c d e f
2
21.94 10.1 27 kN/m
2
59.04 kN/m ; 59
1 1 1
= × 2.59 × 21.94 + 2.75 × 21.94 + × 2.75 × 10.1 + × 2.75 × 27
2 2 2
1 2.75 2.75
Now, 140 × h = 28.41 × × 2.59 + 2.75 + 60.34 × + 13.89 × +
3 2 3
37.13 × 2.75
+
3
= 102.65 + 83 + 12.7 + 34.0 = 232.40
232.40
∴ h = = 1.66 m above base
140
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
20 | ESE 2018 : MAINS TEST SERIES
Qf = qb· Ab + qs· As
(qb · Ab is the bearing action at base, which is to be neglected)
∴ Qf = qs · As
where, qs = α· cu
Here cu is averaged cu over entire depth. Since change of cu with depth is not given, we may take
cu = cu = 15 t/m 2 .
∴ qs = 0.9 × 15 = 13.5 t/m2
As = Skin friction area of the pile
= π × 0.3 × 10 m = 9.42 m 2
∴ Qf = 13.5 × 9.42 = 127.17 t
Therefore, ultimate load carrying capacity of each individual pile = 127.17t
Case II: When piles are acting in a group.
0.9 m 0.9 m
2.1 m
2.1 m
Let us assume that the 9 piles are arranged in square pattern, with side
= 2s + d = 2 × 0.9 + 0.3 = 2.1 m
The ultimate load carrying capacity (Qfg ) is now given as:
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
Test No : 1 CIVIL ENGINEERING | 21
∴ Qfg = 15 × 84 = 1260t
Q fg 1260
∴ Efficiency of pile group = = = 1.10
n· Q f 9 × 127.17
Ground surface
1m
4m
Ground anchors
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
22 | ESE 2018 : MAINS TEST SERIES
3
= 45.24 × 5.7 1 + 0.3 × + γ sub D f × 1
6
= 45.24 × 5.7 × 1.15 + (18 – 9.81) × 2 = 312.93 kN/m2
or, qnu = qu – γ ′Df = 312.93 – (18 – 9.81) × 2 = 296.55 kN/m2
q nu 296.55
or, qna = = = 98.85 kN/m 2
Fs 3
(ii) Skempton’s method,
We know,
qu = CuNcr + qNq
Df 0.2 B
For φ = 0, Ncr = 5 1 + 0.2 1 +
B L
2 0.2 × 3
= 5 1 + 0.2 1 + = 6.23
3 6
⇒ qu = 45.24 × 6.23 + (18 × 2) = 317.84 kN/m2
qnu = 317.84 – 18 × 2 = 281.84 kN/m2
q nu 281.84
qna = = = 94 kN/m 3
Fs 3
1 n
(ii) Leq = 10 log 10 ∑ (10)Li /10 × ti
T i=1
where T = 1 hour
1 0.1 L 0.1 L
Leq = 10 log 10 (10 1 × ∆t1 + 10 2 × ∆t2 )
T
where ∆t1 = 5 min and L1 = 75 dB
∆t2 = 55 min and L2 = 55 dB
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
Test No : 1 CIVIL ENGINEERING | 23
1
Leq = 10 log 10 (107.5 × 5 + 10 5.5 × 55) = 64.66 dB
60
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
24 | ESE 2018 : MAINS TEST SERIES
Power SO2
Particulate matter, acid
Production – sulphate and nitrate,
NOx NO 3 organic matter
NOx
Automobile exhaust
CO
VOC + NOx → O3 O3 (Ozone) + HNO3,
PAN, Aldehydes etc.
VOCs
Industrial HAPs
Sources
Particulate matter
Multiple
organic-matter +
Source
-------------
5. (e) Solution :
Gross Air Gas flow rate
=
Cloth Total fabric area
Given : Gas flow rate = 1,200,000 m3/min
(i) To calculate the total fabric area, calculate bag area using equation for area of cylinder.
Area of bag, A = πdh
= π × 11 × 30
= 1036.7 m2/bag
Total number of bags = 360 × 20 = 7200
∴ Total fabric area = 7200 × 1036.2
= 7.46 × 106 m2
Air 1200000
∴ (Gross) = = 0.161 m/min
Cloth 7.46 × 106
(ii) The net air to cloth ratio is calculated by subtracting out the compartment which are not in
filtering service.
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
Test No : 1 CIVIL ENGINEERING | 25
Total no. of bags = 360 × 18 = 6480 bags
∴ Total fabric area = 6480 × 1036.7 = 6.718 × 106 m2
Air 1200000
∴ (Net) = = 0.178 m/min
Cloth 6.718 × 10 6
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
26 | ESE 2018 : MAINS TEST SERIES
O2 CO2
Influent Unused
BOD effluent BOD
Assimilative
respiration
(synthesis) New
cell
Return growth
activated
sludge
Endogenous
respiration
(Resynthesis)
Excess
Sludge
CO2 O2
R 250
log 10 = log 10 = 3.398
r 0.10
2.728 × 12 × 60 × 3 3
∴ Q= m /day
3.398
= 1734 m3/day = 72.25 m3/hour
(ii) When both the wells are discharging, the discharge from the well is given by
2.728 kbs
Q1 = Q2 = =
R2
log 10
rB
2.728 × 60 × 12 × 3 2.728 × 60 × 12 × 3
= =
250 × 250 3.796
log 10
0.1 × 100
= 1552 m3/day = 64.67 m3/hour
72.25 − 64.67
∴ % decrease in the discharge = × 100 = 10.49%
72.25
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
Test No : 1 CIVIL ENGINEERING | 27
Q.6 (c) Solution:
Population of colony = 6000
⇒ Quantity of sewage produced from residential colony = 150 × 6000
= 0.9 × 106 litres/day
BOD5 of sewage = 250 mg/l
⇒BOD content in sewage produced = 250 × 0.9 × 106
= 225 kg/day
For hot climate conditions, assuming the organic loading in the oxidation pond as 300 kg/ha/day.
BOD content
∴ Surface area of pond required =
Organic loading
225
= = 0.75 ha = 7500 m 2
300
Assuming length to width ratio of pond as 1 : 2
∴ L × B = 7500
⇒ 2B × B = 7500
⇒ B = 61.24 m say 61.50 m
∴ L = 2B = 123.0 m
Using pond with effective depth as 1.2 m, we get
Capacity of pond = 123 × 61.50 × 1.2 = 9077.4 m3
But capacity of pond = Sewage flow per day × Detention time in days
0.9 × 10 6
⇒ 9077.4 = × Detention time in days
10 3
⇒ Detention time = 10 days
Hence, provide an oxidation pond with length = 123 m, width = 61.5 m and overall
depth = 1.2 + 1 = 2.2 m and detention period = 10 days.
dD
where is absolute change of DO deficit in D mg/l over an increment of time dt.
dt
kR = Reaeration constant/day
Integrating the above equation from t1 to t2 gives
D2 t2
dD
∫ D
= − k R ∫ dt
D1 t1
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
28 | ESE 2018 : MAINS TEST SERIES
D2
⇒ ln = − k R (t 2 − t1 )
D1
D
ln 2
D1
⇒ kR = −
∆t
For temperature correction
T − 20
kR (@T) = k R( @ 20° ) ( 1.02 )
D 2.77
ln 2 ln
D1 3.55
kR(26.5°) = − =−
∆t 0.67
( −0.248)
= − = 0.37 day −1
0.67
0.370 0.370
∴ kR(@20°C) = 26.5 − 20
= = 0.325 day −1
(1.02) 1.137
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
Test No : 1 CIVIL ENGINEERING | 29
1.058 kW 1 hr
×
( )
(iii) E = 3
0.566 m /sec (3600 sec)
V 1452.68
∴ Detention time, t = = = 42.78 minutes
Q 0.566 × 60
(v) We have
1/2
P
G =
µV
1/2
1.058 × 10 3
= −6 (∵ µ = νρ)
1452.68 × 1.31 × 10 × 1000
= 23.57 sec–1
Gt = 23.72 × Detention time
= 23.72 × 42.78 × 60 = 60522.13
Q 0.566
(v) Loading rate, = × 24 × 60 × 60
V 1452.68
33.66 × 1000 lit/day
= = 33.66 kl/day/m 3
m3
Q.7 (c) Solution:
(i) For average flow conditions, the required surface area
Q 20000 m 3 /day
A = = = 500 m 2
Overflow rate 40 m 3 /m 2 day
Area 500 m 2
L = = = 41.7 m
Width 2 × 6 m
Q 20000 m 3 /day
Overflow rate on average flow = = = 39.70 m 3 /m 2 d
A 2(6 m × 42 m)
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
30 | ESE 2018 : MAINS TEST SERIES
Volume 2016 × 24 hr
Detention time = = = 2.42 hours
Q (20000 m 3 / day)
Detention time and overflow rate at peak flow
Overflow rate =
3
Q 50000 m /day
=
( )
= 99.2 m 3 /day/m 2
A 2(6 m × 42 m)
Peak flow
Peak flow horizontal velocity, VH =
Cross-sectional area
50000 1
= = 0.012 m/sec
2 ( 6 m × 4 m ) 24 h/ d× 3600 s/h
∵ VH < V S
Therefore, settled matter should not be resuspended.
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
Test No : 1 CIVIL ENGINEERING | 31
• The general relationship between COD and BOD for sewage and human waste is about BOD
= 0.64 to 0.68 of COD. The relationship is not consistent and it may vary considerably for
industrial wastewaters.
(iii)Population equivalent : Population equivalent (PE) is an important parameter for characterising
industrial wastewater. PE reflects the equivalence between the polluting potential of an industry
(commonly in terms of biodegradable organic matter) and a certain population which produces
the same polluting load.
The formula of calculation of population equivalent based on BOD test is
BOD load from industry (kg/day)
PE (Population equivalent) =
Per capita BOD load (kg/person/day)
BOD BOD
(iv) Significance of ratio: The typical values of ratio for untreated municipal
COD COD
BOD
wastewater are in the range from 0.3 to 0.80. If the ratio for untreated wastewater is
COD
0.50 or greater, the waste is considered to be easily treatable by biological means. If the ratio
is below about 0.30, either the waste may have some toxic components or acclimated
microorganisms may be required in its stabilization.
Type of wastewater BOD/COD
1. Untreated 0.30 – 0.80
2. After primary settling 0.40 – 0.60
3. Final effluent 0.10 – 0.30
Ws Wf Wv
= +
Gs ρ w G f ρw G vρw
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
32 | ESE 2018 : MAINS TEST SERIES
1
⇒ Gs =
0.76
= 1.56 (Primary solids )
2. Specific gravity of primary sludge
1 0.05 0.95
= +
Gsludge 1.56 1
1
Gsludge = = 1.02
0.99
500 kg
3. ∴ Volume of primary sludge = 3
= 9.9 m 3
(1000) kg/m × 1.02 × 0.05
4. Percentage of volatile matter after digestion,
Total volatile solids after digestion
Volatile matter, % = × 100
Total solids after digestion
0.4(0.6 × 1000)
= × 100 = 37.5%
400 + 0.4 × 600
5. Average specific gravity of all solids in the digested sludge
1 0.625 0.375 1
= + =
Gs 2.5 1 0.625
Gs = 1.6
6. Specific gravity of the digested sludge (Gds)
1 0.10 0.90
= + = 0.96
G ds 1.6 1.0
1
Gds = = 1.04
0.96
200 + 0.4 × 300
7. Volume of digested sludge, V = = 3.1 m 3
(1000 kg/m 3 )(1.04 × 0.10)
8. Percentage reduction in sludge volume after digestion
9.8 − 3.1 3
= m × 100 = 68.36%
9.8
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in
Test No : 1 CIVIL ENGINEERING | 33
Sources
Natural Manmade
1. Radioactive minerals 1. Nuclear power plants
2. Cosmic rays 2. Radio-active wastes
3. Radio nuclides 3. Nuclear explosions
4. Radio-isotopes
The categorization-high, intermediate and low-helps to determine how wastes are treated and
where they end up. High level wastes require shielding and cooling, low-level wastes can be handled
easily without shielding.
Low level and intermediate wastes are buried closed to the surface. For low level waste, its disposal
is not much different from a normal municipal landfill.
High level wastes are disposed off in deep underground engineered facilities built in stable
geological formations.
© Copyright: www.madeeasy
www.madeeasy.in
.madeeasy.in