EXTENSION OF AJMAN SEWERAGE NETWORK - ADDENDUM 6

TASK ORDER # ESTIMATE CUMILATIVE AS-BUILT COST CUMILATIVE


1 512,830.90 512,830.90 614,103.69 614,103.69
2 301,474.76 814,305.66 309,658.97 923,762.66
3 280,876.00 1,095,181.66 278,058.37 1,201,821.03
4 287,957.88 1,383,139.54 329,151.01 1,530,972.04
5 432,492.64 1,815,632.18 216,646.91 1,747,618.95
6 184,704.53 2,000,336.71 196,978.21 1,944,597.16
7 89,945.83 2,090,282.54 92,676.92 2,037,274.08
8 253,089.84 2,343,372.38
UM 6
IPC #
IPC 1
IPC 2
IPC 4
IPC 3
IPC 5
IPC 6
IPC 7
Work in progress