ANNEX G1 – METHOD OF STATEMENT

Bidder should prepare and submit method statement for all types of pipes. Including excavtion method,
trench preparation method, pipe welding method, inside/outside corrosion protection for welding seams
(steel pipelines), pipe laying method, backfill method, quality control process, method of crossing of
canyons (if necessary) and etc.
Method of Statement for DN 1016 pipe laying

Method of Statement for DN 813 pipe laying

Bidder Signature___________________________
Method of Statement for DN 711 pipe laying

Method of Statement for DN 609 pipe laying

Bidder Signature___________________________
Method of Statement for DN 530 pipe laying

HDPE Pipe DN250 PN10

Bidder Signature___________________________
HDPE Pipe DN315 PN10

HDPE Pipe DN400 PN10

Bidder Signature___________________________
HDPE Pipe DN450 PN10

HDPE Pipe DN500 PN10

AIR OUTLET MANHOLE

Bidder Signature___________________________
WELLS FOR VALVE UNDERGROUND

METHOD OF WELDINGS COATING