DAFTAR HARGA UPAH DAN BAHAN

A. UPAH
1 Pekerja Hari 53,000.00
2 Tukang Hari 84,000.00
3 Kepala Tukang Hari 100,000.00
4 Mandor Hari 75,000.00

B. BAHAN
1 Tanah Urug M3 60,000.00
2 Pasir Urug M3 127,000.00
3 Pasir Pasang M3 130,000.00
4 Pasir Beton M3 132,000.00
5 Kerikil Beton M 3
132,000.00
6 Batu Kali/Batu Belah M3 165,000.00
7 Batu Bata Buah 600.00
8 Air Liter 60.00
Plaound Asbes 100 x 100 cm' Lbr 19,000.00
9 Roster batu kerawang Buah 20,000.00
10 Semen @ 40 Kg Zak 52,000.00
11 Semen Warna @ 50 Kg Zak 65,000.00
12 Kayu Kosen M3 4,247,000.00
13 Papan Kayu Meuranti M3 4,247,000.00
14 Kayu / Papan Bauwplank M3 3,489,000.00
15 Kayu Rangka Plafond M3 3,792,000.00
16 Kayu Balok / Papan Perancah M 3
3,489,000.00
17 Dolken Kayu ø 8-10/4 m Batang 55,000.00
18 Triplex tebal 4 mm' Lembar 83,000.00
19 Plywood tebal 12 mm Lembar 220,000.00
20 Plywood tebal 9 mm Lembar 174,000.00
21 Besi Beton Polos Kg 15,000.00
22 Besi Beton Ulir Kg 28,000.00
23 Kawat Beton Kg 22,000.00
24 Paku Kayu 2" - 5" Kg 17,000.00
25 Paku 1/2" - 1" Kg 15,000.00
26 Screw/Baut Seng metal 1,5" Buah 5,000.00
27 Profil C 75.75 panjang 6 M' M1 16,000.00
28 Reng U 0.5 panjang 6 M' M1 15,000.00
29 Baut Truss ukuran 12 (14x20) Buah 500.00
30 Baut Reng ukuran 10 (16x16) Buah 350.00
31 Atap Ounduline Lembar 138,000.00
32 Rabung Ounduline Lembar 83,950.00
33 Paku Ounduline Buah 920.00
Plafound Gypsumj 9 mm Lbr 65,000.00
Paku Skrup Bh 1,200.00
33 Keramik 60 x 60 cm' Buah 25,000.00
34 Keramik 40 x 40 cm' Pholised Buah 11,666.67
35 Keramik 40 x 40 cm' Unpholised Buah 12,500.00
36 Keramik 20 x 20 cm' Unpholised Buah 2,600.00
37 Keramik 20 x 25 cm' Unpholised Buah 3,500.00
38 Stepnoising 10 x 40 cm Buah 7,000.00
39 Plamir Kg 14,000.00
40 Cat Dasar Kg 320,000.00
41 Cat Menie Kg 25,000.00
42 Cat Kayu/Minyak Kg 45,000.00
43 Cat Dinding Acrylic Emultion Paint Kg 35,000.00
44 Minyak Bekisting Liter 15,000.00
45 Lem Kayu Kg 20,000.00
46 Kunci Tanam Buah 160,000.00
47 Kunci Tanam Silinder Buah 175,000.00
48 Engsel Pintu Buah 25,000.00
49 Engsel Jendela Buah 25,000.00
50 Kait Angin Buah 15,000.00
51 Tarikan Jendela Buah 10,000.00
52 Pacok Jendela Buah 15,000.00
53 Pegangan pintu double Buah 235,000.00
54 Slot pintu double Buah 120,000.00
55 Kaca Bening Tebal 5 mm M2 121,000.00
56 Lampu TL 1 x 20 watt balk + reflektor Buah 170,000.00
57 Lampu pijar 40 wtt Buah 60,000.00
58 Saklar lampu setara Merk Broco 1 seri Buah 35,000.00
59 Saklar lampu setara Merk Broco 2 seri Buah 35,000.00
60 Stop kontak Buah 25,000.00
61 Box Panel Distribusi Buah 500,000.00
62 Pemasangan titik api/stop kontak Titik 300,000.00
63 Kloset Jongkok Buah 136,000.00
64 Wastafel Buah 800,000.00
65 Kran diameter 1/2" Buah 40,000.00
66 Seal tape Buah 15,000.00
DAFTAR ANALISA HARGA SATUAN

I. PEKERJAAN PERSIAPAN

RSNI T-12-2002-B4
1 M 1 Pengukuran dan Pemasaangan Bowplank
0.019 M3 Kayu / Papan Bauwplank @Rp 3,489,000.00 Rp. 66,291.00
0.020 Kg Paku Kayu 2" - 5" @Rp 17,000.00 Rp. 340.00
0.100 OH Pekerja @Rp 53,000.00 Rp. 5,300.00
0.100 OH Tukang @Rp 84,000.00 Rp. 8,400.00
0.010 OH Kepala Tukang @Rp 100,000.00 Rp. 1,000.00
0.005 OH Mandor @Rp 75,000.00 Rp. 375.00
Jumlah Rp. 81,706.00
Dibulatkan Rp. 81,706.00
RSNI T-12-2002-B8
1 M 2 Membersihkan Lapangan dan Perataan
0.100 OH Pekerja @Rp 53,000.00 Rp. 5,300.00
0.050 OH Mandor @Rp 75,000.00 Rp. 3,750.00
Jumlah Rp. 9,050.00
Dibulatkan Rp. 9,050.00
II. PEKERJAAN TANAH

SNI DT-91-0006-2007-6.2
1 M 3 Galian tanah biasa sedalam 2 m
0.900 OH Pekerja @Rp 53,000.00 Rp. 47,700.00
0.045 OH Mandor @Rp 75,000.00 Rp. 3,375.00
Jumlah Rp. 51,075.00
Dibulatkan Rp. 51,075.00
SNI DT-91-0006-2007-6.9
1 M 3 Urugan Tanah Kembali
0.250 OH Pekerja @Rp 53,000.00 Rp. 13,250.00
0.008 OH Mandor @Rp 75,000.00 Rp. 600.00
Jumlah Rp. 13,850.00
Dibulatkan Rp. 13,850.00
SNI DT-91-0006-2007-6.16
1 M 3 Mengurug Tanah Urug
1.200 M3 Tanah Urug @Rp 60,000.00 Rp. 72,000.00
0.300 OH Pekerja @Rp 53,000.00 Rp. 15,900.00
0.010 OH Mandor @Rp 75,000.00 Rp. 750.00
Jumlah Rp. 88,650.00
Dibulatkan Rp. 88,650.00
SNI DT-91-0006-2007-6.11
1 M 3 Mengurug Pasir Urug
1.200 M3 Pasir Urug @Rp 127,000.00 Rp. 152,400.00
0.300 OH Pekerja @Rp 53,000.00 Rp. 15,900.00
0.010 OH Mandor @Rp 75,000.00 Rp. 750.00
Jumlah Rp. 169,050.00
Dibulatkan Rp. 169,050.00

III. PEKERJAAN PONDASI


SNI DT-91-0007-2007-6.9
1 M 3 Pasangan Batu Kosong (aanstamping)
1.200 M3 Batu Kali/Batu Belah @Rp 165,000.00 Rp. 198,000.00
0.432 M 3
Pasir Pasang @Rp 130,000.00 Rp. 56,160.00
0.780 OH Pekerja @Rp 53,000.00 Rp. 41,340.00
0.390 OH Tukang @Rp 84,000.00 Rp. 32,760.00
0.039 OH Kepala Tukang @Rp 100,000.00 Rp. 3,900.00
0.039 OH Mandor @Rp 75,000.00 Rp. 2,925.00
Jumlah Rp. 335,085.00
Dibulatkan Rp. 335,085.00

SNI DT-91-0007-2007-6.10
1 M 3 Pondasi Beton Cyclopen 1 PC : 2 PB : 3 KR + 40% Batu Belah
0.312 M3 Pasir Beton @Rp 132,000.00 Rp. 41,184.00
0.480 M 3
Batu Kali/Batu Belah @Rp 165,000.00 Rp. 79,200.00
0.468 M3 Kerikil Beton @Rp 132,000.00 Rp. 61,776.00
194.000 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 252,200.00
3.000 Org Pekerja @Rp 53,000.00 Rp. 159,000.00
0.850 Org Tukang @Rp 84,000.00 Rp. 71,400.00
0.085 Org Kepala Tukang @Rp 100,000.00 Rp. 8,500.00
0.150 Org Mandor @Rp 75,000.00 Rp. 11,250.00
Jumlah Rp. 684,510.00
Dibulatkan Rp. 684,510.00

SNI DT-91-0007-2007-6.11
1 M 3 Pondasi Sumuran diameter 100 cm
0.450 M3 Batu Kali/Batu Belah @Rp 165,000.00 Rp. 74,250.00
0.312 M3 Pasir Pasang @Rp 130,000.00 Rp. 40,560.00
0.468 M 3
Kerikil Beton @Rp 132,000.00 Rp. 61,776.00
194.000 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 252,200.00
2.380 Org Pekerja @Rp 53,000.00 Rp. 126,140.00
0.300 Org Tukang @Rp 84,000.00 Rp. 25,200.00
0.030 Org Kepala Tukang @Rp 100,000.00 Rp. 3,000.00
0.080 Org Mandor @Rp 75,000.00 Rp. 6,000.00
Jumlah Rp. 589,126.00
Dibulatkan Rp. 589,126.00
IV. PEKERJAAN BETON
SNI DT-91-0008-2007-6.1
1 M3 Beton mutu f'c = 7,4 Mpa (K100), slump (12 ± 2) cm, w/c = 0,87
869.000 Kg Pasir Beton @Rp 82.50 Rp. 71,692.50
999.000 Kg Kerikil Beton @Rp 73.33 Rp. 73,260.00
247.000 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 321,100.00
215.000 Liter Air @Rp 60.00 Rp. 12,900.00
1.650 OH Pekerja @Rp 53,000.00 Rp. 87,450.00
0.275 OH Tukang @Rp 84,000.00 Rp. 23,100.00
0.028 OH Kepala Tukang @Rp 100,000.00 Rp. 2,800.00
0.083 OH Mandor @Rp 75,000.00 Rp. 6,225.00
Jumlah Rp. 598,527.50
Dibulatkan Rp. 598,528.00
SNI DT-91-0008-2007-6.8
1 M3 Beton mutu f'c = 21,7 Mpa (K250), slump (12 ± 2) cm, w/c = 0,56
692.000 Kg Pasir Beton @Rp 82.50 Rp. 57,090.00
1,039.000 Kg Kerikil Beton @Rp 73.33 Rp. 76,193.33
384.000 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 499,200.00
215.000 Liter Air @Rp 60.00 Rp. 12,900.00
1.650 OH Pekerja @Rp 53,000.00 Rp. 87,450.00
0.275 OH Tukang @Rp 84,000.00 Rp. 23,100.00
0.028 OH Kepala Tukang @Rp 100,000.00 Rp. 2,800.00
0.083 OH Mandor @Rp 75,000.00 Rp. 6,225.00
Jumlah Rp. 764,958.33
Dibulatkan Rp. 764,958.00
SNI DT-91-0008-2007-6.5
1 M3 Beton mutu f'c = 14,5 Mpa (K175), slump (12 ± 2) cm,
760.000 Kg Pasir Beton @Rp 82.50 Rp. 62,700.00
1,029.000 Kg Kerikil Beton @Rp 73.33 Rp. 75,460.00
326.000 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 423,800.00
215.000 Liter Air @Rp 60.00 Rp. 12,900.00
1.650 OH Pekerja @Rp 53,000.00 Rp. 87,450.00
0.275 OH Tukang @Rp 84,000.00 Rp. 23,100.00
0.028 OH Kepala Tukang @Rp 100,000.00 Rp. 2,800.00
0.083 OH Mandor @Rp 75,000.00 Rp. 6,225.00
Jumlah Rp. 694,435.00
Dibulatkan Rp. 694,435.00
SNI DT-91-0008-2007-6.17
1 Kg Besi Polos
1.050 Kg Besi Beton Polos @Rp 15,000.00 Rp. 15,750.00
0.015 Kg Kawat Beton @Rp 22,000.00 Rp. 330.00
0.007 OH Pekerja @Rp 53,000.00 Rp. 371.00
0.007 OH Tukang @Rp 84,000.00 Rp. 588.00
0.0007 OH Kepala Tukang @Rp 100,000.00 Rp. 70.00
0.0004 OH Mandor @Rp 75,000.00 Rp. 30.00
Jumlah Rp. 17,139.00
Dibulatkan Rp. 17,139.00
SNI DT-91-0008-2007-6.18
1 Kg Besi Ulir
1.050 Kg Besi Beton Ulir @Rp 28,000.00 Rp. 29,400.00
0.015 Kg Kawat Beton @Rp 22,000.00 Rp. 330.00
0.007 OH Pekerja @Rp 53,000.00 Rp. 371.00
0.007 OH Tukang @Rp 84,000.00 Rp. 588.00
0.0007 OH Kepala Tukang @Rp 100,000.00 Rp. 70.00
0.0004 OH Mandor @Rp 75,000.00 Rp. 30.00
Jumlah Rp. 30,789.00
Dibulatkan Rp. 30,789.00
SNI DT-91-0008-2007-6.20
1 M 2 Bekisting untuk Pondasi
0.040 M3 Kayu Balok / Papan Perancah @Rp 3,489,000.00 Rp. 139,560.00
0.300 Kg Paku Kayu 2" - 5" @Rp 17,000.00 Rp. 5,100.00
0.100 Liter Minyak Bekisting @Rp 15,000.00 Rp. 1,500.00
0.520 OH Pekerja @Rp 53,000.00 Rp. 27,560.00
0.260 OH Tukang @Rp 84,000.00 Rp. 21,840.00
0.026 OH Kepala Tukang @Rp 100,000.00 Rp. 2,600.00
0.026 OH Mandor @Rp 75,000.00 Rp. 1,950.00
Jumlah Rp. 200,110.00
Digunakan 2 kali Pakai Rp. 100,055.00
Dibulatkan Rp. 100,055.00
SNI DT-91-0008-2007-6.21
1 M 2 Bekisting untuk Sloof
0.045 M3 Kayu Balok / Papan Perancah @Rp 3,489,000.00 Rp. 157,005.00
0.300 Kg Paku Kayu 2" - 5" @Rp 17,000.00 Rp. 5,100.00
0.100 Liter Minyak Bekisting @Rp 15,000.00 Rp. 1,500.00
0.520 OH Pekerja @Rp 53,000.00 Rp. 27,560.00
0.260 OH Tukang @Rp 84,000.00 Rp. 21,840.00
0.026 OH Kepala Tukang @Rp 100,000.00 Rp. 2,600.00
0.026 OH Mandor @Rp 75,000.00 Rp. 1,950.00
Jumlah Rp. 217,555.00
Digunakan 2 Kali Pakai Rp. 108,777.50
Dibulatkan Rp. 108,778.00
SNI DT-91-0008-2007-6.22
1 M 2 Bekisting untuk Kolom
0.055 M3 Kayu Balok / Papan Perancah @Rp 3,489,000.00 Rp. 191,895.00
0.400 Kg Paku Kayu 2" - 5" @Rp 17,000.00 Rp. 6,800.00
0.200 Liter Minyak Bekisting @Rp 15,000.00 Rp. 3,000.00
0.350 Lembar Plywood tebal 12 mm @Rp 220,000.00 Rp. 77,000.00
2.000 Batang Dolken Kayu ø 8-10/4 m @Rp 55,000.00 Rp. 110,000.00
0.660 OH Pekerja @Rp 53,000.00 Rp. 34,980.00
0.330 OH Tukang @Rp 84,000.00 Rp. 27,720.00
0.033 OH Kepala Tukang @Rp 84,000.00 Rp. 2,772.00
0.033 OH Mandor @Rp 75,000.00 Rp. 2,475.00
Jumlah Rp. 456,642.00
Digunakan 2 x Rp. 228,321.00
Dibulatkan Rp. 228,321.00
SNI DT-91-0008-2007-6.23
Memasang M 2 Bekisting untuk Balok
0.058 M3 Kayu Balok / Papan Perancah @Rp 3,489,000.00 Rp. 202,362.00
0.400 Kg Paku Kayu 2" - 5" @Rp 17,000.00 Rp. 6,800.00
0.200 Liter Minyak Bekisting @Rp 15,000.00 Rp. 3,000.00
0.350 Lembar Plywood tebal 9 mm @Rp 174,000.00 Rp. 60,900.00
2.000 Batang Dolken Kayu ø 8-10/4 m @Rp 55,000.00 Rp. 110,000.00
0.660 OH Pekerja @Rp 53,000.00 Rp. 34,980.00
0.330 OH Tukang @Rp 84,000.00 Rp. 27,720.00
0.033 OH Kepala Tukang @Rp 100,000.00 Rp. 3,300.00
0.033 OH Mandor @Rp 75,000.00 Rp. 2,475.00
Jumlah Rp. 451,537.00
Digunakan 2 x Rp. 225,768.50
Dibulatkan Rp. 225,769.00
SNI DT-91-0008-2007-6.24
Memasang 1 M 2 Bekisting untuk Lantai
0.055 M3 Kayu Balok / Papan Perancah @Rp 3,489,000.00 Rp. 191,895.00
0.400 Kg Paku Kayu 2" - 5" @Rp 17,000.00 Rp. 6,800.00
0.200 Liter Minyak Bekisting @Rp 15,000.00 Rp. 3,000.00
0.350 Lembar Plywood tebal 9 mm @Rp 174,000.00 Rp. 60,900.00
6.000 Batang Dolken Kayu ø 8-10/4 m @Rp 55,000.00 Rp. 330,000.00
0.660 OH Pekerja @Rp 53,000.00 Rp. 34,980.00
0.330 OH Tukang @Rp 84,000.00 Rp. 27,720.00
0.033 OH Kepala Tukang @Rp 100,000.00 Rp. 3,300.00
0.033 OH Mandor @Rp 75,000.00 Rp. 2,475.00
Jumlah Rp. 661,070.00
Dibulatkan Rp. 661,070.00
SNI DT-91-0008-2007-6.26
Memasang 1 M 2 Bekisting untuk Tangga
0.045 M3 Kayu Balok / Papan Perancah @Rp 3,489,000.00 Rp. 157,005.00
0.400 Kg Paku Kayu 2" - 5" @Rp 17,000.00 Rp. 6,800.00
0.150 Liter Minyak Bekisting @Rp 15,000.00 Rp. 2,250.00
0.350 Lembar Plywood tebal 9 mm @Rp 174,000.00 Rp. 60,900.00
2.000 Batang Dolken Kayu ø 8-10/4 m @Rp 55,000.00 Rp. 110,000.00
0.660 OH Pekerja @Rp 53,000.00 Rp. 34,980.00
0.330 OH Tukang @Rp 84,000.00 Rp. 27,720.00
0.033 OH Kepala Tukang @Rp 100,000.00 Rp. 3,300.00
0.033 OH Mandor @Rp 75,000.00 Rp. 2,475.00
Jumlah Rp. 405,430.00
Dibulatkan Rp. 405,430.00
Pekerjaan Lain-lain
1.0000 Ls Membongkar dan Menyiram Beton @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 50,000.00
REKAPITULASI PEKERJAAN BETON
Suplemen 1A
1 M3 Beton Bertulang Pondasi Tapak 120 X 120 CM'
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
187.000 Kg SNI DT-91-0008-2007-6.17 @Rp 17,139.00 Rp. 3,204,993.00
4.000 M2 SNI DT-91-0008-2007-6.20 @Rp 100,055.00 Rp. 400,220.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 4,420,171.00
Dibulatkan Rp. 4,420,171.00
Suplemen 1B
1 M3 Beton Bertulang Pondasi Tapak 150 X 150 CM'
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
212.000 Kg SNI DT-91-0008-2007-6.17 @Rp 17,139.00 Rp. 3,633,468.00
7.000 M2 SNI DT-91-0008-2007-6.20 @Rp 100,055.00 Rp. 700,385.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 5,148,811.00
Dibulatkan Rp. 5,148,811.00
Suplemen 2
1 M3 Sloof Beton Bertulang Ukuran 30 x 50 cm'
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
134.130 Kg SNI DT-91-0008-2007-6.18 @Rp 30,789.00 Rp. 4,129,728.57
16.457 Kg SNI DT-91-0008-2007-6.17 @Rp 17,139.00 Rp. 282,056.52
9.000 M 2
SNI DT-91-0008-2007-6.21 @Rp 108,778.00 Rp. 979,002.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 6,205,745.09
Dibulatkan Rp. 6,205,745.00

Suplemen 2.a
1 M3 Sloof Beton Bertulang Ukuran 30 x 30 cm'
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
295.740 Kg SNI DT-91-0008-2007-6.17 @Rp 17,139.00 Rp. 5,068,687.86
10.000 M2 SNI DT-91-0008-2007-6.21 @Rp 108,778.00 Rp. 1,087,780.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 6,971,425.86
Dibulatkan Rp. 6,971,426.00

Suplemen 3
1 M3 Kolom Induk Beton Bertulang Ukuran 45 x 45 cm
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
79.470 Kg SNI DT-91-0008-2007-6.18 @Rp 30,789.00 Rp. 2,446,801.83
3.857 Kg SNI DT-91-0008-2007-6.17 @Rp 17,139.00 66,105.12
10.000 M2 SNI DT-91-0008-2007-6.21 @Rp 228,321.00 Rp. 2,283,210.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 5,611,074.95
Dibulatkan Rp. 5,611,075.00

Suplemen 3.a
1 M3 Kolom Induk Beton Bertulang Ukuran 30 x 30 cm
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
343.430 Kg SNI DT-91-0008-2007-6.17 @Rp 17,139.00 Rp. 5,886,046.77
8.000 M2 SNI DT-91-0008-2007-6.21 @Rp 228,321.00 Rp. 1,826,568.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 8,527,572.77
Dibulatkan Rp. 8,527,573.00

Suplemen 4
1 M3 Kolom Beton Bertulang Ukuran 25 x 25 cm
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
273.000 Kg SNI DT-91-0008-2007-6.17 @Rp 17,139.00 Rp. 4,678,947.00
8.500 M2 SNI DT-91-0008-2007-6.21 @Rp 228,321.00 Rp. 1,940,728.50
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 7,434,633.50
Dibulatkan Rp. 7,434,634.00
Suplemen 5
1 M3 Kolom Beton Bertulang Ukuran 13 x 13 cm'
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
306.000 Kg SNI DT-91-0008-2007-6.17 @Rp 30,789.00 Rp. 9,421,434.00
8.000 M2 SNI DT-91-0008-2007-6.21 @Rp 228,321.00 Rp. 1,826,568.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 12,062,960.00
Dibulatkan Rp. 12,062,960.00
Suplemen 6
1 M3 Balok latai Beton Bertulang Ukuran 13 x 13 cm'
1.000 M3 SNI DT-91-0008-2007-6.5 @Rp 694,435.00 Rp. 694,435.00
306.000 Kg SNI DT-91-0008-2007-6.17 @Rp 30,789.00 Rp. 9,421,434.00
8.000 M2 SNI DT-91-0008-2007-6.23 @Rp 225,769.00 Rp. 1,806,152.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 11,972,021.00
Dibulatkan Rp. 11,972,021.00
Suplemen 7
1 M3 Balok lantai Beton Bertulang Ukuran 25 x 40 cm'
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
123.200 Kg SNI DT-91-0008-2007-6.18 @Rp 30,789.00 Rp. 3,793,204.80
5.696 Kg SNI DT-91-0008-2007-6.17 @Rp 17,139.00 Rp. 97,623.74
8.000 M2 SNI DT-91-0008-2007-6.23 @Rp 225,769.00 Rp. 1,806,152.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 6,511,938.54
Dibulatkan Rp. 6,511,939.00
Suplemen 8
1 M3 Balok lantai Beton Bertulang Ukuran 25 x 40 cm'
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
193.000 Kg SNI DT-91-0008-2007-6.18 @Rp 30,789.00 Rp. 5,942,277.00
8.000 M2 SNI DT-91-0008-2007-6.23 @Rp 225,769.00 Rp. 1,806,152.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 8,563,387.00
Dibulatkan Rp. 8,563,387.00
Suplemen 9
1 M3 Balok lantai Beton Bertulang Ukuran 30 x 50 cm'
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
134.130 Kg SNI DT-91-0008-2007-6.18 @Rp 30,789.00 Rp. 4,129,728.57
16.457 Kg SNI DT-91-0008-2007-6.17 @Rp 17,139.00 Rp. 282,056.52
8.000 M 2
SNI DT-91-0008-2007-6.23 @Rp 225,769.00 Rp. 1,806,152.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 7,032,895.09
Dibulatkan Rp. 7,032,895.00
Suplemen 10
1 M3 Balok lantai Beton Bertulang Ukuran 25 x 60 cm'
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
231.000 Kg SNI DT-91-0008-2007-6.18 @Rp 30,789.00 Rp. 7,112,259.00
8.500 M2 SNI DT-91-0008-2007-6.23 @Rp 225,769.00 Rp. 1,919,036.50
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 9,846,253.50
Dibulatkan Rp. 9,846,254.00
Suplemen 11
1 M3 Balok Beton Bertulang Ukuran 20 x 30 cm'
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
123.000 Kg SNI DT-91-0008-2007-6.17 @Rp 30,789.00 Rp. 3,787,047.00
8.000 M2 SNI DT-91-0008-2007-6.23 @Rp 225,769.00 Rp. 1,806,152.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 6,408,157.00
Dibulatkan Rp. 6,408,157.00
Suplemen 12
1 M3 Plat Lantai Beton Bertulang tebal 12 cm'
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
4.355 Kg SNI DT-91-0008-2007-6.17 @Rp 30,789.00 Rp. 134,086.10
9.200 M2 SNI DT-91-0008-2007-6.24 @Rp 661,070.00 Rp. 6,081,844.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 7,030,888.10
Dibulatkan Rp. 7,030,888.00
Suplemen 13
1 M3 Anak Tangga & Bordes
1.000 M3 SNI DT-91-0008-2007-6.8 @Rp 764,958.00 Rp. 764,958.00
101.500 Kg SNI DT-91-0008-2007-6.17 @Rp 30,789.00 Rp. 3,125,083.50
8.100 M2 SNI DT-91-0008-2007-6.26 @Rp 405,430.00 Rp. 3,283,983.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 7,224,024.50
Dibulatkan Rp. 7,224,025.00
Suplemen 14
1 M3 Cicin Sumuran
1.000 M3 SNI DT-91-0007-2007-6.11 @Rp 589,126.00 Rp. 589,126.00
158.970 Kg SNI DT-91-0008-2007-6.17 @Rp 30,789.00 Rp. 4,894,527.33
5.000 M2 SNI DT-91-0008-2007-6.26 @Rp 405,430.00 Rp. 2,027,150.00
1.000 Ls Pekerjaan Lain-lain @Rp 50,000.00 Rp. 50,000.00
Jumlah Rp. 7,560,803.33
Dibulatkan Rp. 7,560,803.00
V. PEKERJAAN DINDING
SNI DT-91-0009-2007-6.7
1 M 2 Pasangan bata merah tebal 1/2 bata adukan 1PC : 2 PP
0.038 M3 Pasir Pasang @Rp 130,000.00 Rp. 4,940.00
70.000 Buah Batu Bata @Rp 600.00 Rp. 42,000.00
18.950 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 24,635.00
0.300 OH Pekerja @Rp 53,000.00 Rp. 15,900.00
0.100 OH Tukang @Rp 84,000.00 Rp. 8,400.00
0.010 OH Kepala Tukang @Rp 100,000.00 Rp. 1,000.00
0.015 OH Mandor @Rp 75,000.00 Rp. 1,125.00
Jumlah 98,000.00
Dibulatkan 98,000.00
SNI DT-91-0009-2007-6.9
1 M 2 Pasangan bata merah tebal 1/2 bata adukan 1PC : 4 PP
0.043 M3 Pasir Pasang @Rp 130,000.00 Rp. 5,590.00
70.000 Buah Batu Bata @Rp 600.00 Rp. 42,000.00
11.500 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 14,950.00
0.300 OH Pekerja @Rp 53,000.00 Rp. 15,900.00
0.100 OH Tukang @Rp 84,000.00 Rp. 8,400.00
0.010 OH Kepala Tukang @Rp 100,000.00 Rp. 1,000.00
0.015 OH Mandor @Rp 75,000.00 Rp. 1,125.00
Jumlah Rp. 88,965.00
Dibulatkan Rp. 88,965.00
VI. PEKERJAAN PLESTERAN
SNI DT-91-0010-2007-6.2
Memasang 1 M 2 Plesteran 1 PC : 2 PP : tebal 15 mm
0.020 M3 Pasir Pasang @Rp 130,000.00 Rp. 2,600.00
10.224 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 13,291.20
0.200 OH Pekerja @Rp 53,000.00 Rp. 10,600.00
0.150 OH Tukang @Rp 84,000.00 Rp. 12,600.00
0.015 OH Kepala Tukang @Rp 100,000.00 Rp. 1,500.00
0.010 OH Mandor @Rp 75,000.00 Rp. 750.00
Jumlah Rp. 41,341.20
Dibulatkan Rp. 41,340.00
SNI DT-91-0010-2007-6.3
Memasang 1 M 2 Plesteran Beton 1 PC : 3 PP, tebal 15 mm
0.023 M3 Pasir Pasang @Rp 130,000.00 Rp. 2,990.00
7.776 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 10,108.80
0.200 OH Pekerja @Rp 53,000.00 Rp. 10,600.00
0.150 OH Tukang @Rp 84,000.00 Rp. 12,600.00
0.015 OH Kepala Tukang @Rp 100,000.00 Rp. 1,500.00
0.010 OH Mandor @Rp 75,000.00 Rp. 750.00
Jumlah Rp. 38,548.80
Dibulatkan Rp. 38,549.00
SNI DT-91-0010-2007-6.4
Memasang 1 M 2 Plesteran 1 PC : 4 PP : tebal 15 mm
0.024 M3 Pasir Pasang @Rp 130,000.00 Rp. 3,120.00
6.240 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 8,112.00
0.200 OH Pekerja @Rp 53,000.00 Rp. 10,600.00
0.150 OH Tukang @Rp 84,000.00 Rp. 12,600.00
0.015 OH Kepala Tukang @Rp 100,000.00 Rp. 1,500.00
0.010 OH Mandor @Rp 75,000.00 Rp. 750.00
Jumlah Rp. 36,682.00
Dibulatkan Rp. 36,682.00

VII. PEKERJAAN KAYU


SNI DT-91-0011-2007-6.1
Membuat dan Memasang 1 M 3 Kusen Pintu dan Jendela Kayu
1.100 M3 Kayu Kosen @Rp 4,247,000.00 Rp. 4,671,700.00
1.000 Kg Lem Kayu @Rp 20,000.00 Rp. 20,000.00
1.250 Kg Paku Kayu 2" - 5" @Rp 17,000.00 Rp. 21,250.00
6.000 OH Pekerja @Rp 53,000.00 Rp. 318,000.00
20.000 OH Tukang @Rp 84,000.00 Rp. 1,680,000.00
2.000 OH Kepala Tukang @Rp 100,000.00 Rp. 200,000.00
0.300 OH Mandor @Rp 75,000.00 Rp. 22,500.00
Jumlah Rp. 6,933,450.00
Dibulatkan Rp. 6,933,450.00
SNI DT-91-0011-2007-6.5
Membuat dan Memasang 1 M 2 Daun Pintu Panel kayu
0.040 M3 Papan Kayu Meuranti @Rp 4,247,000.00 Rp. 169,880.00
0.500 Kg Lem Kayu @Rp 20,000.00 Rp. 10,000.00
1.000 OH Pekerja @Rp 53,000.00 Rp. 53,000.00
3.000 OH Tukang @Rp 84,000.00 Rp. 252,000.00
0.300 OH Kepala Tukang @Rp 100,000.00 Rp. 30,000.00
0.050 OH Mandor @Rp 75,000.00 Rp. 3,750.00
Jumlah Rp. 518,630.00
Dibulatkan Rp. 518,630.00
SNI DT-91-0011-2007-6.6
Membuat dan Memasang 1 M 2 Daun Jendela Kaca
0.024 M3 Papan Kayu Meuranti @Rp 4,247,000.00 Rp. 101,928.00
0.300 Kg Lem Kayu @Rp 20,000.00 Rp. 6,000.00
1.200 M 2
Kaca Bening Tebal 5 mm @Rp 121,000.00 Rp. 145,200.00
0.800 OH Pekerja @Rp 53,000.00 Rp. 42,400.00
2.000 OH Tukang @Rp 84,000.00 Rp. 168,000.00
0.200 OH Kepala Tukang @Rp 100,000.00 Rp. 20,000.00
0.040 OH Mandor @Rp 75,000.00 Rp. 3,000.00
Jumlah Rp. 486,528.00
Dibulatkan Rp. 486,528.00
SNI DT-91-0011-2007-6.10
Memasang 1 M 2 Jalusi Kusen Kayu
0.040 M3 Papan Kayu Meuranti @Rp 4,247,000.00 Rp. 169,880.00
0.150 Kg Paku Kayu 2" - 5" @Rp 17,000.00 Rp. 2,550.00
0.500 OH Pekerja @Rp 53,000.00 Rp. 26,500.00
2.000 OH Tukang @Rp 84,000.00 Rp. 168,000.00
0.200 OH Kepala Tukang @Rp 100,000.00 Rp. 20,000.00
0.025 OH Mandor @Rp 75,000.00 Rp. 1,875.00
Jumlah Rp. 388,805.00
Dibulatkan Rp. 388,805.00
SNI DT-91-0013-2007-6.7
Memasang 1 M 3 langit Langit Gypsum Board Tebal 9 mm
0.3640 M3 Gypsum Board @Rp 65,000.00 Rp. 23,660.00
0.110 Kg Paku Skrup @Rp 1,200.00 Rp. 132.00
0.250 OH Pekerja @Rp 53,000.00 Rp. 13,250.00
0.300 OH Tukang @Rp 84,000.00 Rp. 25,200.00
0.030 OH Kepala Tukang @Rp 100,000.00 Rp. 3,000.00
0.005 OH Mandor @Rp 75,000.00 Rp. 375.00
Jumlah Rp. 65,617.00
Dibulatkan Rp. 65,617.00
SNI DT-91-0013-2007-6.1
Memasang 1 M 3 langit Langit Asbes 5 mm
1.1000 M3 Asbes Semen @Rp 19,000.00 Rp. 20,900.00
0.010 Kg Paku Tripleks @Rp 15,000.00 Rp. 150.00
0.250 OH Pekerja @Rp 53,000.00 Rp. 13,250.00
0.300 OH Tukang @Rp 84,000.00 Rp. 25,200.00
0.030 OH Kepala Tukang @Rp 100,000.00 Rp. 3,000.00
0.005 OH Mandor @Rp 75,000.00 Rp. 375.00
Jumlah Rp. 62,875.00
Dibulatkan Rp. 62,875.00
SNI DT-91-0013-2007-6.5
Memasang 1 M 3 langit Langit Triplek 4 mm
0.3750 M3 Triplek @Rp 83,000.00 Rp. 31,125.00
0.030 Kg Paku Tripleks @Rp 15,000.00 Rp. 450.00
0.250 OH Pekerja @Rp 53,000.00 Rp. 13,250.00
0.300 OH Tukang @Rp 84,000.00 Rp. 25,200.00
0.030 OH Kepala Tukang @Rp 100,000.00 Rp. 3,000.00
0.005 OH Mandor @Rp 75,000.00 Rp. 375.00
Jumlah Rp. 73,400.00
Dibulatkan Rp. 73,400.00
SNI DT-91-0011-2007-6.19
Memasang 1 M 3 Rangka langit-langit
0.0154 M3 Kayu Rangka Plafond @Rp 3,792,000.00 Rp. 58,396.80
0.200 Kg Paku Kayu 2" - 5" @Rp 17,000.00 Rp. 3,400.00
0.150 OH Pekerja @Rp 53,000.00 Rp. 7,950.00
0.250 OH Tukang @Rp 84,000.00 Rp. 21,000.00
0.025 OH Kepala Tukang @Rp 100,000.00 Rp. 2,500.00
0.075 OH Mandor @Rp 75,000.00 Rp. 5,625.00
Jumlah Rp. 98,871.80
Dibulatkan Rp. 98,872.00
SNI DT-91-0011-2007-6.21
Memasang 1 M 1 Lisplank
0.0108 M3 Papan Kayu Meuranti @Rp 4,247,000.00 Rp. 45,867.60
0.100 Kg Paku Kayu 2" - 5" @Rp 17,000.00 Rp. 1,700.00
0.100 OH Pekerja @Rp 53,000.00 Rp. 5,300.00
0.200 OH Tukang @Rp 84,000.00 Rp. 16,800.00
0.025 OH Kepala Tukang @Rp 100,000.00 Rp. 2,500.00
0.005 OH Mandor @Rp 75,000.00 Rp. 375.00
Jumlah Rp. 72,542.60
Dibulatkan Rp. 72,543.00
VIII. PEKERJAAN PENUTUP LANTAI DAN DINDING
SNI DT-91-0012-2007-6.65
Memasang 1 M 2 Lantai Keramik 40 x 40 cm
0.045 M3 Pasir Pasang @Rp 130,000.00 Rp. 5,850.00
6.250 Buah Keramik 40 x 40 cm' @Rp 11,666.67 Rp. 72,916.67
10.000 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 13,000.00
1.500 Kg Semen Warna @ 50 Kg @Rp 1,300.00 Rp. 1,950.00
0.620 OH Pekerja @Rp 53,000.00 Rp. 32,860.00
0.350 OH Tukang @Rp 84,000.00 Rp. 29,400.00
0.035 OH Kepala Tukang @Rp 100,000.00 Rp. 3,500.00
0.030 OH Mandor @Rp 75,000.00 Rp. 2,250.00
Jumlah Rp. 161,726.67
Dibulatkan Rp. 161,727.00
SNI DT-91-0012-2007-6.66
Memasang 1 M 2 Lantai Keramik 40 x 40 cm (Kulit Jeruk)
0.045 M3 Pasir Pasang @Rp 130,000.00 Rp. 5,850.00
6.250 Buah Keramik 40 x 40 cm' Kulit Jeruk @Rp 11,666.67 Rp. 72,916.67
10.000 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 13,000.00
1.500 Kg Semen Warna @ 50 Kg @Rp 1,300.00 Rp. 1,950.00
0.620 OH Pekerja @Rp 53,000.00 Rp. 32,860.00
0.350 OH Tukang @Rp 84,000.00 Rp. 29,400.00
0.035 OH Kepala Tukang @Rp 100,000.00 Rp. 3,500.00
0.030 OH Mandor @Rp 75,000.00 Rp. 2,250.00
Jumlah Rp. 161,726.67
Dibulatkan Rp. 161,727.00

SNI DT-91-0012-2007-6.36
Memasang 1 M 2 Lantai Keramik Ukuran 20 x 20 cm (Kulit Jeruk)
0.045 M3 Pasir Pasang @Rp 130,000.00 Rp. 5,850.00
25.000 Buah Keramik 20 x 20 cm' Kulit Jeruk @Rp 11,666.67 Rp. 291,666.67
10.400 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 13,520.00
1.620 Kg Semen Warna @ 50 Kg @Rp 1,300.00 Rp. 2,106.00
0.620 OH Pekerja @Rp 53,000.00 Rp. 32,860.00
0.350 OH Tukang @Rp 84,000.00 Rp. 29,400.00
0.035 OH Kepala Tukang @Rp 100,000.00 Rp. 3,500.00
0.030 OH Mandor @Rp 75,000.00 Rp. 2,250.00
Jumlah Rp. 381,152.67
Dibulatkan Rp. 381,153.00
SNI DT-91-0012-2007-6.66
Memasang 1 M 2 Dinding Keramik 20 x 25 cm
0.018 M3 Pasir Pasang @Rp 130,000.00 Rp. 2,340.00
20.000 Buah Keramik 20 x 25 cm' @Rp 3,500.00 Rp. 70,000.00
9.300 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 12,090.00
1.940 Kg Semen Warna @ 50 Kg @Rp 1,300.00 Rp. 2,522.00
0.600 OH Pekerja @Rp 53,000.00 Rp. 31,800.00
0.450 OH Tukang @Rp 84,000.00 Rp. 37,800.00
0.045 OH Kepala Tukang @Rp 100,000.00 Rp. 4,500.00
0.030 OH Mandor @Rp 75,000.00 Rp. 2,250.00
Jumlah Rp. 163,302.00
Dibulatkan Rp. 163,302.00

IX. PEKERJAAN LANGIT-LANGIT


SNI DT 9-0013-2007-6.5
Memasang 1 M 2 Triplex tebal 4 mm
0.020 Kg Paku 1/2" - 1" @Rp 15,000.00 Rp. 300.00
0.375 Lembar Triplex @Rp 83,000.00 Rp. 31,125.00
0.030 OH Pekerja @Rp 53,000.00 Rp. 1,590.00
0.070 OH Tukang @Rp 84,000.00 Rp. 5,880.00
0.007 OH Kepala Tukang @Rp 100,000.00 Rp. 700.00
0.002 OH Mandor @Rp 75,000.00 Rp. 150.00
Jumlah Rp. 39,745.00
Dibulatkan Rp. 39,745.00

X. PEKERJAAN BESI DAN ALUMINIUM


SNI DT 9-0014-2007-6.20
1 M 2 Rangka Kuda-kuda Aluzing 55 % Aluminium (Zincalume) Untuk Genteng Metal
4.2600 M1 Profil C 75.75 panjang 6 M' @Rp 16,000.00 Rp. 68,160.00
4.9300 M1 Reng U 0.5 panjang 6 M' @Rp 15,000.00 Rp. 73,950.00
14.0000 Buah Baut Truss ukuran 12 (14x20) @Rp 500.00 Rp. 7,000.00
11.0000 Buah Baut Reng ukuran 10 (16x16) @Rp 350.00 Rp. 3,850.00
0.1400 OH Pekerja @Rp 53,000.00 Rp. 7,420.00
0.1000 OH Tukang @Rp 84,000.00 Rp. 8,400.00
0.0400 OH Kepala Tukang @Rp 100,000.00 Rp. 4,000.00
0.0700 OH Mandor @Rp 75,000.00 Rp. 5,250.00
Jumlah Rp. 178,030.00
Dibulatkan Rp. 178,030.00

XI. PEKERJAAN PENUTUP ATAP


SNI 03-3436-1994-6.1
1 M 2 Atap Ounduline
1.023 Lembar Atap Ounduline @Rp 138,000.00 Rp. 141,174.00
9.000 Buah Paku Ounduline @Rp 920.00 Rp. 8,280.00
0.200 OH Pekerja @Rp 53,000.00 Rp. 10,600.00
0.100 OH Tukang @Rp 84,000.00 Rp. 8,400.00
0.010 OH Kepala Tukang @Rp 100,000.00 Rp. 1,000.00
0.001 OH Mandor @Rp 75,000.00 Rp. 75.00
Jumlah Rp. 169,529.00
Dibulatkan Rp. 169,529.00
SNI 03-3436-1994-6.2
1 M' Nok Ounduline
1.150 Lembar Rabung Ounduline @Rp 83,950.00 Rp. 96,542.50
9.000 Buah Paku Ounduline @Rp 920.00 Rp. 8,280.00
0.250 OH Pekerja @Rp 53,000.00 Rp. 13,250.00
0.150 OH Tukang @Rp 84,000.00 Rp. 12,600.00
0.015 OH Kepala Tukang @Rp 100,000.00 Rp. 1,500.00
0.013 OH Mandor @Rp 75,000.00 Rp. 975.00
Jumlah Rp. 133,147.50
Dibulatkan Rp. 133,148.00
XIII. PEKERJAAN KUNCI DAN KACA
RSNI T-30-200-B.2
1 Buah Kunci Tanam Biasa
1.000 Buah Kunci Tanam @Rp 160,000.00 Rp. 160,000.00
0.010 OH Pekerja @Rp 53,000.00 Rp. 530.00
0.500 OH Tukang @Rp 84,000.00 Rp. 42,000.00
0.010 OH Kepala Tukang @Rp 100,000.00 Rp. 1,000.00
0.005 OH Mandor @Rp 75,000.00 Rp. 375.00
Jumlah Rp. 203,905.00
Dibulatkan Rp. 203,905.00
RSNI T-30-200-B.4
1 Buah Kunci Tanam Silinder
1.000 Buah Kunci Tanam Silinder @Rp 175,000.00 Rp. 175,000.00
0.005 OH Pekerja @Rp 53,000.00 Rp. 265.00
0.500 OH Tukang @Rp 84,000.00 Rp. 42,000.00
0.005 OH Kepala Tukang @Rp 100,000.00 Rp. 500.00
0.00025 OH Mandor @Rp 75,000.00 Rp. 18.75
Jumlah Rp. 217,783.75
Dibulatkan Rp. 217,784.00
RSNI T-30-200-B.5
1 Buah Engsel Pintu
1.000 Buah Engsel Pintu @Rp 25,000.00 Rp. 25,000.00
0.015 OH Pekerja @Rp 53,000.00 Rp. 795.00
0.150 OH Tukang @Rp 84,000.00 Rp. 12,600.00
0.015 OH Kepala Tukang @Rp 100,000.00 Rp. 1,500.00
0.00075 OH Mandor @Rp 75,000.00 Rp. 56.25
Jumlah Rp. 39,951.25
Dibulatkan Rp. 39,951.00
RSNI T-30-200-B.6
1 Buah Engsel Jendela Kupu - kupu
1.000 Buah Engsel Jendela @Rp 25,000.00 Rp. 25,000.00
0.010 OH Pekerja @Rp 53,000.00 Rp. 530.00
0.100 OH Tukang @Rp 84,000.00 Rp. 8,400.00
0.010 OH Kepala Tukang @Rp 100,000.00 Rp. 1,000.00
0.0005 OH Mandor @Rp 75,000.00 Rp. 37.50
Jumlah Rp. 34,967.50
Dibulatkan Rp. 34,968.00
RSNI T-30-200-B.9
1 Buah Kait Angin Jendela
1.000 Buah Kait Angin @Rp 15,000.00 Rp. 15,000.00
0.015 OH Pekerja @Rp 53,000.00 Rp. 795.00
0.150 OH Tukang @Rp 84,000.00 Rp. 12,600.00
0.015 OH Kepala Tukang @Rp 100,000.00 Rp. 1,500.00
0.00075 OH Mandor @Rp 75,000.00 Rp. 56.25
Jumlah Rp. 29,951.25
Dibulatkan Rp. 29,951.00
RSNI T-30-200-B.26
1 Buah Hak Tarikan Jendela
1.000 Buah Tarikan Jendela @Rp 10,000.00 Rp. 10,000.00
0.015 OH Pekerja @Rp 53,000.00 Rp. 795.00
0.150 OH Tukang @Rp 84,000.00 Rp. 12,600.00
0.015 OH Kepala Tukang @Rp 100,000.00 Rp. 1,500.00
0.00075 OH Mandor @Rp 75,000.00 Rp. 56.25
Jumlah Rp. 24,951.25
Dibulatkan Rp. 24,951.00
RSNI T-30-200-B.25
1 Buah Pacok Jendela
1.000 Buah Pacok Jendela @Rp 15,000.00 Rp. 15,000.00
0.020 OH Pekerja @Rp 53,000.00 Rp. 1,060.00
0.200 OH Tukang @Rp 84,000.00 Rp. 16,800.00
0.020 OH Kepala Tukang @Rp 100,000.00 Rp. 2,000.00
0.00075 OH Mandor @Rp 75,000.00 Rp. 56.25
Jumlah Rp. 34,916.25
Dibulatkan Rp. 34,916.00
RSNI T-30-200-B.12
1 Buah Pegangan pintu double
1.000 Buah Pegangan pintu double @Rp 235,000.00 Rp. 235,000.00
0.050 OH Pekerja @Rp 53,000.00 Rp. 2,650.00
0.500 OH Tukang @Rp 84,000.00 Rp. 42,000.00
0.050 OH Kepala Tukang @Rp 100,000.00 Rp. 5,000.00
0.0025 OH Mandor @Rp 75,000.00 Rp. 187.50
Jumlah Rp. 284,837.50
Dibulatkan Rp. 284,838.00
RSNI T-30-200-B.11
1 Buah Slot pintu double
1.000 Buah Slot pintu double @Rp 120,000.00 Rp. 120,000.00
0.020 OH Pekerja @Rp 53,000.00 Rp. 1,060.00
0.200 OH Tukang @Rp 84,000.00 Rp. 16,800.00
0.020 OH Kepala Tukang @Rp 100,000.00 Rp. 2,000.00
0.001 OH Mandor @Rp 75,000.00 Rp. 75.00
Jumlah Rp. 139,935.00
Dibulatkan Rp. 139,935.00
RSNI T-30-200-B.17
1 M 2 Pasang Kaca tebal 5 mm
1.100 M2 Kaca Bening Tebal 5 mm @Rp 121,000.00 Rp. 133,100.00
0.015 OH Pekerja @Rp 53,000.00 Rp. 795.00
0.150 OH Tukang @Rp 84,000.00 Rp. 12,600.00
0.015 OH Kepala Tukang @Rp 100,000.00 Rp. 1,500.00
0.00075 OH Mandor @Rp 75,000.00 Rp. 56.25
Jumlah Rp. 148,051.25
Dibulatkan Rp. 148,051.00

XIV. PEKERJAAN PENGECATAN


PT. T-38-2000-C-B8
1 M 2 Pengecatan Bidang Kayu
0.200 Kg Cat Menie @Rp 25,000.00 Rp. 5,000.00
0.150 Kg Plamir @Rp 14,000.00 Rp. 2,100.00
0.170 Kg Cat Dasar @Rp 320,000.00 Rp. 54,400.00
0.260 Kg Cat Kayu/Minyak @Rp 45,000.00 Rp. 11,700.00
0.070 OH Pekerja @Rp 53,000.00 Rp. 3,710.00
0.009 OH Tukang @Rp 84,000.00 Rp. 756.00
0.006 OH Kepala Tukang @Rp 100,000.00 Rp. 600.00
0.0025 OH Mandor @Rp 75,000.00 Rp. 187.50
Jumlah Rp. 78,453.50
Dibulatkan Rp. 78,454.00
PT. T-38-2000-C-B14
1 M 2 Pengecatan Tembok dan Plafond
0.100 Kg Plamir @Rp 14,000.00 Rp. 1,400.00
0.100 Kg Cat Dasar @Rp 320,000.00 Rp. 32,000.00
0.260 Kg Cat Dinding Acrylic Emultion Paint @Rp 35,000.00 Rp. 9,100.00
0.020 OH Pekerja @Rp 53,000.00 Rp. 1,060.00
0.063 OH Tukang @Rp 84,000.00 Rp. 5,292.00
0.006 OH Kepala Tukang @Rp 100,000.00 Rp. 630.00
0.0025 OH Mandor @Rp 75,000.00 Rp. 187.50
Jumlah Rp. 49,669.50
Dibulatkan Rp. 49,670.00

XII. PEKERJAAN SANITASI


RSNI T-15-2002-B.2
1 Buah Kloset Jongkok Porselen
1.000 Buah Kloset Jongkok @Rp 136,000.00 Rp. 136,000.00
0.010 M3 Pasir Pasang @Rp 130,000.00 Rp. 1,300.00
6.000 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 7,800.00
1.000 OH Pekerja @Rp 53,000.00 Rp. 53,000.00
1.500 OH Tukang @Rp 84,000.00 Rp. 126,000.00
1.500 OH Kepala Tukang @Rp 100,000.00 Rp. 150,000.00
0.160 OH Mandor @Rp 75,000.00 Rp. 12,000.00
Jumlah Rp. 486,100.00
Dibulatkan Rp. 486,100.00
RSNI T-15-2002-B.5
Memasang 1 Buah Wastafel
1.000 Buah Wastafel @Rp 800,000.00 Rp. 800,000.00
10.000 % Perlengkapan dari harga Wastafel @Rp 80,000.00 Rp. 8,000.00
0.010 M3 Pasir Pasang @Rp 130,000.00 Rp. 1,300.00
6.000 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 7,800.00
1.200 OH Pekerja @Rp 53,000.00 Rp. 63,600.00
1.450 OH Tukang @Rp 84,000.00 Rp. 121,800.00
0.150 OH Kepala Tukang @Rp 100,000.00 Rp. 15,000.00
0.100 OH Mandor @Rp 75,000.00 Rp. 7,500.00
Jumlah Rp. 1,025,000.00
Dibulatkan Rp. 1,025,000.00

RSNI T-15-2002-B.8
1 Buah Bak Mandi Batu Bata 0,3 M3 di Lapisi Keramik
180.000 Buah Batu Bata @Rp 600.00 Rp. 108,000.00
0.300 M3 Pasir Pasang @Rp 130,000.00 Rp. 39,000.00
80.000 Kg Semen @ 40 Kg @Rp 1,300.00 Rp. 104,000.00
80.000 Buah Keramik 20 x 20 cm' @Rp 2,600.00 Rp. 208,000.00
6.000 Kg Semen Warna @ 50 Kg @Rp 1,300.00 Rp. 7,800.00
6.000 OH Pekerja @Rp 53,000.00 Rp. 318,000.00
3.000 OH Tukang @Rp 84,000.00 Rp. 252,000.00
0.300 OH Kepala Tukang @Rp 100,000.00 Rp. 30,000.00
0.300 OH Mandor @Rp 75,000.00 Rp. 22,500.00
Jumlah Rp. 1,089,300.00
Dibulatkan Rp. 1,089,300.00

RSNI T-15-2002-B.35
Memasang 1 Buah Kran Ø ¾" atau Ø ½"
1.000 Buah Kran diameter 1/2" @Rp 40,000.00 Rp. 40,000.00
0.025 Buah Seal tape @Rp 15,000.00 Rp. 375.00
0.010 OH Pekerja @Rp 53,000.00 Rp. 530.00
0.100 OH Tukang @Rp 84,000.00 Rp. 8,400.00
0.010 OH Kepala Tukang @Rp 100,000.00 Rp. 1,000.00
0.005 OH Mandor @Rp 75,000.00 Rp. 375.00
Jumlah Rp. 50,680.00
Dibulatkan Rp. 50,680.00
RSNI T-15-2002-B.36
Memasang 1 Buah Floor Drain
1.000 Buah Floor Drain @Rp 20,000.00 Rp. 20,000.00
0.010 OH Pekerja @Rp 53,000.00 Rp. 530.00
0.100 OH Tukang @Rp 84,000.00 Rp. 8,400.00
0.010 OH Kepala Tukang @Rp 100,000.00 Rp. 1,000.00
0.005 OH Mandor @Rp 75,000.00 Rp. 375.00
Jumlah Rp. 30,305.00
Dibulatkan Rp. 30,305.00
RENCANA ANGGARAN BIAYA

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SAT ANALISA SATUAN HARGA
(Rp.) (Rp.)
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1.1 Pembersihan Lapangan 147.84 M2 RSNI T-12-2002-B8 9,050.00 1,337,952.00
1.2 Pengukuran dan Pemasangan Bowplank 57.20 M' RSNI T-12-2002-B4 81,706.00 4,673,583.20
Sub Jumlah 6,011,535.20
II PEKERJAAN PEMBANGUNAN LANTAI I 38.00
A.I. Pekerjaan Tanah Dan Pondasi
Pondasi Tapak TP 1
1.1 Galian Tanah Pondasi Tapak 27.04 M3 SNI DT-91-0006-2007-6.2 51,075.00 1,381,068.00
1.2 Urugan Kembali Bekas Galian (Pondasi Tapak) 6.76 M3 SNI DT-91-0006-2007-6.9 13,850.00 93,626.00
1.3 Pondasi Tapak 150 x 150 cm' 6.98 M3 Suplemen 1B 5,148,811.00 35,918,105.54
1.4 Pas. Pasir Alas 0.68 M3 SNI DT-91-0008-2007-6.1 598,528.00 404,604.93
1.5 Pasangan Batu Aanstamping 1.35 M3 SNI DT-91-0007-2007-6.9 335,085.00 453,034.92
Pondasi Tapak TP 2
1.1 Galian Tanah Pondasi Tapak 19.36 M3 SNI DT-91-0006-2007-6.2 51,075.00 988,812.00
1.2 Urugan Kembali Bekas Galian (Pondasi Tapak) 4.84 M3 SNI DT-91-0006-2007-6.9 13,850.00 67,034.00
1.3 Pondasi Tapak 120 x 120 cm' 5.34 M3 Suplemen 1A 4,420,171.00 23,621,393.82
1.4 Pas. Pasir Alas 0.48 M3 SNI DT-91-0006-2007-6.11 169,050.00 81,820.20
1.5 Pasangan Batu Aanstamping 0.97 M3 SNI DT-91-0007-2007-6.9 335,085.00 324,362.28
Pondasi Tapak TP 3
1.1 Galian Tanah Pondasi Tapak 13.52 M3 SNI DT-91-0006-2007-6.9 51,075.00 690,534.00
1.2 Urugan Kembali Bekas Galian (Pondasi Tapak) 3.38 M3 SNI DT-91-0006-2007-6.16 13,850.00 46,813.00
1.3 Pondasi Tapak 120 x 120 cm' 4.86 M3 4,420,171.00 21,482,031.06
1.4 Pas. Pasir Alas 0.34 M3 169,050.00 57,138.90
1.5 Pasangan Batu Aanstamping 0.68 M3 SNI DT-91-0007-2007-6.9 335,085.00 226,517.46
Pondasi menerus 102.00
1.1 Galian Tanah Pondasi M3 SNI DT-91-0006-2007-6.2 51,075.00 0.00
1.2 Urugan Kembali Pondasi M3 SNI DT-91-0006-2007-6.9 13,850.00 0.00
1.3 Pas. Pasir Alas M3 SNI DT-91-0006-2007-6.11 169,050.00 0.00
1.4 Pas. Batu Aanstamping M3 SNI DT-91-0007-2007-6.9 335,085.00 0.00
1.5 Pas. Batu Gunung M3 SNI DT-91-0007-2007-6.10 684,510.00 0.00
Selasar Keliling
1.1 Galian Tanah M3 SNI DT-91-0006-2007-6.2 51,075.00 0.00
1.2 Urugan Kembali M3 SNI DT-91-0006-2007-6.9 13,850.00 0.00
1.3 Pas. Pasir Alas M3 SNI DT-91-0006-2007-6.11 169,050.00 0.00
1.4 Pas. Batu Aanstamping M3 SNI DT-91-0007-2007-6.9 335,085.00 0.00
1.5 Pas Batu Bata 1 : 2 M3 SNI DT-91-0009-2007-6.7 98,000.00 0.00
1.6 Pas. Plesteran 1 : 2 M3 SNI DT-91-0010-2007-6.2 41,340.00 0.00
Sub Jumlah 85,836,896.11
B Pekerjaan Beton Bertulang
1.1 Sloof Beton 25 x 30 cm 3.13 M3 Suplemen 2 6,205,745.00 19,436,393.34
1.2 Sloof Beton 25 x 40 cm 5.85 M3 0.00
1.3 Kolom K2 1.80 M3 0.00
1.5 Kolom K3 7.20 M3 0.00
1.6 Kolom K4 3.52 M3 0.00
1.8 Kolom K5 1.60 M3 0.00
1.9 Reng balok 20/30 cm' teras depan M3 0.00
1.10 Balok Latai 13/13 cm' M3 0.00
1.11 Plat Lantai T = 12 cm' M3 0.00
1.12 Plat Daap T = 7 cm' M3 0.00
Sub Jumlah 19,436,393.34
C Pekerjaan Tanggga
1.1 Balok Bordes 20/30 cm' M3 Suplemen 11 6,408,157.00 0.00
1.2 Cor Beton Bertulang Anak Tangga M3 Suplemen 13 7,224,025.00 0.00
1.3 Plat Lantai Bordes T = 12 cm' M3 0.00 0.00 0.00
1.4 Pipa Steinless 3" M' Taksir 330,000.00 0.00
1.5 Pipa Steinless 1,5" M' Taksir 155,000.00 0.00
Sub Jumlah 0.00
D Pekerjaan Pasangan dan Plesteran
1.1 Pasangan Trasram Bata 1 PC : 2 PP M2 SNI DT-91-0009-2007-6.7 98,000.00 0.00
1.2 Plesteran Trasram Bata 1 PC : 2 PP M2 SNI DT-91-0010-2007-6.2 41,340.00 0.00
1.3 Pasangan Dinding Bata 1 PC : 4 PP M2 SNI DT-91-0009-2007-6.9 88,965.00 0.00
1.4 Plesteran Dinding Bata 1PC : 4 PP M2 SNI DT-91-0010-2007-6.3 36,682.00 0.00
Sub Jumlah 0.00
E Pek. Pasangan Kuzen Pintu Dan Jendela UPVC
1.1 Pintu UPVC Type P1 + Lengkap Terpasang Unit Taksir 850,000.00 -
1.2 Jendela UPVC Type J1 + lengkap Terpasang Unit Taksir 850,000.00 -
1.3 Ventilasi Jalusi 2 Unit
1.3.1 - Kosen Kayu 6/13 m' Taksir 130,000.00 -
1.3.2 - Ventilasi Jalusi M2 Taksir 65,000.00 -
Sub Jumlah 0.00
F Pekerjaan Lantai
I Dalam Ruangan
1.1 Timbunan Tanah Bawah Lantai M3 SNI DT-91-0006-2007-6.16 88,650.00 -
1.2 Urugan Pasir Bawah Lantai M3 SNI DT-91-0006-2007-6.11 169,050.00 -
1.3 Beton Cor T = 7 cm' M3 SNI DT-91-0008-2007-6.1 598,528.00 -
1.4 Lantai Keramik 40 x 40 cm' Pholised M2 SNI DT-91-0012-2007-6.65 161,727.00 -
1.5 Lantai Keramik 40 x 40 cm' Unpholised (Luar ruangan) M2 SNI DT-91-0012-2007-6.66 161,727.00 -
1.6 Lantai Keramik Anak Tangga 40 x 40 cm' Unpholised M2 SNI DT-91-0012-2007-6.66 161,727.00 -
II Diluar Ruangan Selasar
2.1 Timbunan Tanah Bawah Lantai M3 SNI DT-91-0006-2007-6.16 88,650.00 -
2.2 Urugan Pasir Bawah Lantai M3 SNI DT-91-0006-2007-6.11 169,050.00 -
2.3 Beton Cor T = 7 cm' M3 SNI DT-91-0008-2007-6.1 598,528.00 -
2.4 Lantai Keramik 40 x 40 cm Unpholised M2 SNI DT-91-0012-2007-6.66 161,727.00 -
Sub Jumlah 0.00
G Pekerjaan Plafoung Gypsum dalam ruangan
1.2 Plafound Gypsum setara jayaboard M2 SNI DT-91-0013-2007-6.7 65,617.00 -
1.3 List Plafound M' Taksir 45,000.00 -
Sub Jumlah 0.00
H Pekerjaan Pengecetan
1.1 Cat Tembok (L/D) M2 PT. T-38-2000-C-B14 49,670.00 -
1.2 Cat List Plafond M2 PT. T-38-2000-C-B14 49,670.00 -
1.4 Cat Mengkilat Jalusi M2 PT. T-38-2000-C-B8 78,454.00 -
Sub Jumlah 0.00
I Pekerjaan Lain - lain
1.1 Pembentukkan Tiang Kolom Sesuai Gambar M2 Taksir 300,000.00 -
1.2 Batu Krawang Sesuai Gambar M2 Taksir 150,000.00 -
1.3 Pembentukkan Batu Alam + terpasang M2 Taksir 250,000.00 -
1.5 Septictank Unit Taksir 3,000,000.00 -
Sub Jumlah 0.00
J Pekerjaan Instalasi Listrik
1.1 Armatur
- Lampu TL 1 x 20 watt balk + reflektor Buah Taksir 170,000.00 0.00
- Lampu pijar 40 wtt Buah Taksir 60,000.00 0.00
1.2 Saklar lampu Merk Broco 2 seri
- Sakalar 1 Seri setara Broco Buah Taksir 35,000.00 0.00
- Sakalar 2 Seri setara Broco Buah Taksir 35,000.00 0.00
1.3 Stop Kontak Buah Taksir 25,000.00 0.00
1.4 Instlasi titik penerangan, instalasi termasuk kabel NYA 2,5
mm dalam pipa PVC fitting lampu dan kelengkapan instalasi
terpasang Titik Taksir 300,000.00 0.00
1.5 Instalasi titik Stop kontak, instalasi termasuk kabel NYA
2,5 mm dalam pipa PVC, kotak kontak dan kelengkapan
instalasi terpasang. Titik Taksir 300,000.00 0.00
Sub Jumlah 0.00
II PEKERJAAN PEMBANGUNAN LANTAI II 38.00
A. Pekerjaan Struktur
1.1 Kolom K2 35/35 cm' M3 0.00 0.00 0.00
1.2 Kolom Praktis 13/13 cm' M3 0.00 0.00 0.00
1.4 Balok Reng Balk 20/30 cm' M3 0.00 0.00 0.00
1.5 Balok Latai 13/13 cm' M3 0.00 0.00 0.00
1.6 Balok Top Geuvel 13/15 cm' M3 0.00 0.00 0.00
1.7 Plat daap T = 7 cm M3 0.00 0.00 0.00
Sub Jumlah 0.00
B. Pekerjaan Pasangan dan Plesteran
1.1 Pasangan Dinding Bata 1 PC : 4 PP M2 SNI DT-91-0009-2007-6.9 88,965.00 0.00
1.2 Plesteran Dinding Bata 1PC : 4 PP M2 SNI DT-91-0010-2007-6.3 36,682.00 0.00
1.3 Pasangan Dinding Bata 1 PC : 4 PP ( Selasar Deapan) M2 SNI DT-91-0009-2007-6.9 88,965.00 0.00
1.4 Plesteran Dinding Bata 1PC : 4 PP (Selasar Depan) M2 SNI DT-91-0010-2007-6.3 88,965.00 0.00
Sub Jumlah 0.00
C Pek. Pasangan Kuzen Pintu Dan Jendela UPVC
1.1 Pintu UPVC Type P1 + Lengkap Terpasang Unit Taksir 850,000.00 -
1.2 Pintu Fiber Kamar Mandi Unit Taksir 500,000.00 -
1.3 Jendela UPVC Type J1 + lengkap Terpasang Unit Taksir 850,000.00 -
Sub Jumlah 0.00
D Pekerjaan Lantai
1.1 Lantai Keramik 40 x 40 cm' Pholised Dlm Ruangan M2 SNI DT-91-0012-2007-6.65 161,727.00 -
1.2 Lantai Keramik 40 x 40 cm' Unpholised Luar Ruangan M2 SNI DT-91-0012-2007-6.66 161,727.00 -
Sub Jumlah 0.00
E Pekerjaan Langit - langit Dan Atap
1.1 Rangka kuda-kuda dan gording baja ringan Multytruss M2 SNI DT 9-0014-2007-6.20 178,030.00 -
1.2 Penutup Atap Ounduline M2 SNI 03-3436-1994-6.1 169,529.00 -
1.3 Rabung Ounduline M' SNI 03-3436-1994-6.2 133,148.00 -
1.4 Lesplank M' SNI DT-91-0011-2007-6.21 72,543.00 -
1.4 Pek. Plafound Gypsum Setara Jayaboard dlm ruangan M2 SNI DT-91-0013-2007-6.7 65,617.00 -
1.5 Pek. Plafound Asbes 100 x 100 cm' selasar depan M2 SNI DT-91-0013-2007-6.1 62,875.00 -
1.6 Pek Plafound Triplek 4 mm Tritisan Luar Ruangan M2 SNI DT-91-0013-2007-6.5 73,400.00 -
1.8 Pek. Kayu Rangka Plafound M2 SNI DT-91-0011-2007-6.19 98,872.00 -
1.8 List Plafound dlm ruangan M' Taksir 45,000.00 -
Sub Jumlah 0.00
F Pekerjaan Instalasi Listrik
1.1 Armatur
- Lampu TL 1 x 20 watt balk + reflektor Buah Taksir 170,000.00 -
- Lampu pijar 40 wtt Buah Taksir 60,000.00 -
1.2 Saklar lampu Merk Broco 2 seri -
- Sakalar 1 Seri setara Broco Buah Taksir 35,000.00 -
- Sakalar 2 Seri setara Broco Buah Taksir 35,000.00 -
1.3 Stop Kontak Buah Taksir 25,000.00 -
1.4 Instlasi titik penerangan, instalasi termasuk kabel NYA 2,5 -
mm dalam pipa PVC fitting lampu dan kelengkapan instalasi -
terpasang Titik Taksir 300,000.00 -
1.5 Instalasi titik Stop kontak, instalasi termasuk kabel NYA -
2,5 mm dalam pipa PVC, kotak kontak dan kelengkapan -
instalasi terpasang. Titik Taksir 300,000.00 -
Sub Jumlah 0.00
G Pekerjaan Sanitasi Dan Kamar Mandi
1.1 Lantai Keramik 20 x 20 cm' M2 SNI DT-91-0012-2007-6.36 381,153.00 -
1.1 Dinding Keramik 20 x 25 cm' M2 SNI DT-91-0012-2007-6.66 163,302.00 -
1.2 Floor Drain Bh RSNI T-15-2002-B.36 30,305.00 -
1.3 Kran Air 3/4" Bh RSNI T-15-2002-B.35 50,680.00 -
1.4 Bak Air Fiber Bh Taksir 500,000.00 -
1.5 Kloset Jongkok Setara KIA Bh RSNI T-15-2002-B.2 486,100.00 -
1.6 Pipa PVC Air bersih Unit Taksir 500,000.00 -
1.7 Pipa PVC Air Kotor Unit Taksir 500,000.00 -
Sub Jumlah 0.00
H Pekerjaan Pengecetan
1.1 Cat Tembok (L/D) M2 PT. T-38-2000-C-B14 49,670.00 -
1.2 Cat Plafound M2 PT. T-38-2000-C-B14 49,670.00 -
1.3 Cat Kayu Lesplank M2 PT. T-38-2000-C-B8 78,454.00 -
1.2 Cat List Plafond M2 PT. T-38-2000-C-B8 78,454.00 -
Sub Jumlah 0.00
REKAPULITASI RENCANA ANGGARAN BIAYA
0
0

I PEKERJAAN PERSIAPAN 6,011,535.20


II PEKERJAAN PEMBANGUNAN LANTAI I
A Pekerjaan Tanah Dan Pondasi 85,836,896.11
B Pekerjaan Beton Bertulang 19,436,393.34
C Pekerjaan Tanggga 0.00
D Pekerjaan Pasangan dan Plesteran 0.00
E Pek. Pasangan Kuzen Pintu Dan Jendela UPVC 0.00
F Pekerjaan Lantai 0.00
G Pekerjaan Plafoung Gypsum dalam ruangan 0.00
H Pekerjaan Pengecetan 0.00
I Pekerjaan Lain - lain 0.00
J Pekerjaan Instalasi Listrik 0.00
TOTAL LANTAI I 111,284,824.65
II PEKERJAAN PEMBANGUNAN LANTAI II
A Pekerjaan Struktur 0.00
B Pekerjaan Pasangan dan Plesteran 0.00
C Pek. Pasangan Kuzen Pintu Dan Jendela UPVC 0.00
D Pekerjaan Lantai 0.00
E Pekerjaan Langit - langit Dan Atap 0.00
F Pekerjaan Instalasi Listrik 0.00
G Pekerjaan Sanitasi Dan Kamar Mandi 0.00
H Pekerjaan Pengecetan 0.00
TOTAL LANTAI II 0.00
Total Jumlah Pekerjaan I + II 111,284,824.65
PPn 10% 11,128,482.46
Total 122,413,307.11
Dibulatkan 122,413,000.00

Terbilang : Dua Milliar Enam Ratus Juta Tujuh Ratus Tiga Belas Ribu Rupiah

Banda Aceh, Juni 2013


CV. GIBRALTAR KONSULTINDO

IR. SUFLIWA WAHAB


DIREKTUR