BRIEF

GENERAL CONTRACT DATA WORK PROGRESS SUMMARY

Section No: 1 Length (Km) Date 30-Jan-18

Original Cost 45,778,303,952.00 Elapsed Time Months

From 380+000 Planned Progress


Physical
To 435+000 Progress Actual Progress
(%age)
In House Consultant E.A % ahead or behind (+/-)

Notice to
Contract Award 22-Dec-15 Commence
5-Aug-16 Planned Progress

Financial
Extension of
Contract Period 36 Time
Nil Progress Actual Progress
(%age)
Revised
Completion Date 4-Aug-19 Completion Nil % ahead or behind (+/-)
Date

PHYSICAL PROGRESS OF MAJOR ITEMS

Cumulative
Total Quantity in Remaining
Items Unit Completed Completed %
Quantity Progress Quantity
Quantity

Earthworks L.S/KM 55 2.555 1.96 50.49 91.80%

Improved Subgrade L.S/KM 55 1.695 29.91 23.39 42.53%

Granular Sub-Base L.S/KM 55 3.05 40.72 11.23 20.42%

Agg: Base Course L.S/KM 55 4.83 49.90 0.27 0.49%

Box Culverts No. 16 0 0.00 16 100.00%

Multiple Cell Culverts No. 16 0 0.00 16 100.00%

Cattle Creep No. 26 0 0.00 26 100.00%

Subway No. 27 0 0.00 27 100.00%

Underpass No. 3 0 0.00 3 100.00%

Standard Underpass No. 11 2 0.00 9 81.82%

RCP Culverts No. 84 2 1.00 81 96.43%


BRIDGES

Cumulative
Total Quantity in Remaining
Items Unit Completed Completed %
Quantity Progress Quantity
Quantity

Piles No. 807 0 24.00 783 97.03%

Girder Casting No. 588 3 186.00 399 67.86%

Girders Lounching No. 588 3 418.00 167 28.40%

Pier No. 210 2 66.00 142 67.62%

Abutment/Transom No. 140 2 26.00 112 80.00%


ESS SUMMARY

30-Jan-18

Days

30.78%

37.08%

6.30%

30.78%

30.08%

-0.70%

Remarks
Remarks