White palace

Zoom events

CHECK LIST FOR:


Form No:
Toilets partition Works Rev. No: 00
Page : 1 of 1

SUBCONTRACTOR CONTRACTOR

SECTION OF WORK: Toilets partition LOCATION: Parcel 18 , plot 405


LEVEL: ground and first floor WIR No.:

1. PURPOSE

The purpose of this Work Method Statement for Toilet Partition of Building is to outline and describe in
detail the procedure such as setting and lay-out plan on actual location, installation of panels and all
other related activity. Inform all concerned supervisor including workers the value and importance of
this activity prior to implementation. This activity should be performed with strict compliance and
implementation of Safety Requirements & Procedure and project specifications to complete the work
both for toilet partition of building.

2. SCOPE OF WORKS

The scope of this Method Statement covers the works in any Project

(Building and Substation) including buildings in existing plant.

3. MATERIALS, ACCESSORIES and TOOLS

Panel Height, Beams and Post

Door, Door Handle, Shields

U-profile with hole, plug, washer and counter fit screws

Head rail, end cap and anti-theft bolt

Electric drill and screw driver

4. STEP OF WORKS (As per Manufacturer’s Manual Instruction)

4.1 Preliminary preparation


White palace

Zoom events

 Work is to be performed by experienced workers under the direction of a qualified supervisor


who is fully aware of the project requirements. Prior to commence the work make sure that all tools
are prepared by workers and ready for usage. All electric power tools that are to be use for the work
should have been properly checked and colour coded and inspected by HSE department.

4.2 Markings, Lay-Out and Installation

 Mark the center line for the U-profiles. Clearance from the floor to the bottom of U-profile +/-
160mm. Copy the height of the U-profiles on the wall. Mark the holes from the U-profiles. Drill holes
and fix the U-profile to the wall with plugs, washer and screw.
 Drill holes (+/- 28mm) for the legs according to the drawing. Put the panels into the top of the
profiles. Put the front panels onto the partition panels. Adjust the head rail to the front length and fix
with screws 4.8 x 50. Apply pre-drill using 4.30mm diameter. Put the plastic end cap on the end of
the head rail.
 After putting the doors in place, level all panels so the doors are closing properly.
 Fix the walls with the screws of 3.5mm diameter x 11. Apply pre-drill using the 3.1mm diameter.
 Mix the component A with Component B and pour it into the hole for the legs. Fill until the floor
levels and after 24 hours later, checked if it is properly cured then removed the temporary support.
 Mount the lower (plastic) shield with screws 3.5 x 16. Apply pre-drill with 3.1mm diameter.
Mount the upper (aluminium) shield (with a click) and put the door handles together.