1. GENERAL
1.1. SYSTEM DESCRIPTION
1.2. STANDARDS AND REGULATIONS FULFILLMENT
2. EQUIPMENT
2.1. MANUFACTURER
2.2. MANUFACTURED UNITS
2.3. EQUIPMENT
3. QUALITY CONTROL
3.1. SUBMITTALS (FOR APPROVAL)
3.2. DESIGN TESTS
3.3. APPROVAL TESTS
3.4. CHECKING
3.5. SHIPPING AND DELIVERY
4. WARRANTY
HOJA 2/15
PROJECT No. DATE:
1. GENERAL
1.1.1. The Emergency Generator Set described in this Specification, including the
Motor-Generator Set, will be constructed and tested by manufacturer, and
shipped by provider. The provider will be the one and only responsible for
warranty spare parts and maintenance. The provider must have a local
responsible and provide the service of manufacturing training, spare parts in
existence, and technical assistance. The capacity of the Motor-Generator Set
shall be 1500 kW at p.f.=0.8, 60 Hz, 3 phases, 3 wires, and 13.2 HVAC on
continuity stand-by as indicated on the documents annex to this Specification.
1.1.2. The Emergency Generator Set will be in accordance to the latest edition of the
NFPA 110 Specification, including the design specifications, prototype tests,
full-load starting at one-step and the approval Level 1 Facility as indicated on
NFPA 110 Specification, paragraph 2-2.4 to 2-2.4.1. The responsibility of the
provider in the fulfillment of this specification will not be divided between the
individual providers of the Emergency Generator Set.
1.1.4. As son as the Emergency Generator Set detects the energy lacking, shall be in
operation at its nominal speed, producing energy on 10 seconds.
1.2.1. All equipment shall be designed and constructed in accordance to the latest
editions of the following Standards and Regulations:
HOJA 3/15
PROJECT No. DATE:
If the equipment supplier does not use the above standards and regulations,
shall prove that its own codes and standards are similar or better than the listed
above.
2. EQUIPMENTS
2.1. MANUFACTURER
2.1.1. The System shall include a Motor-Generator Set as the published specifications
for the model. All the controls shall be manufacturer’s standard, the
manufacturer shall commit oneself on the manufacturing of the Motor-
Generator Set, Transfer Switch and accessories, and shall have available for
purchasing. The control parts shall be identified with manufacturer’s tags and
shall have a second tags where it apply. The control systems provided by a
vendor’s sub-manufacturer not included on the manufacturer’s drawings or
documents will not be accepted.
2.2.1. The Emergency Generator Set shall be tropicalized and shall include a
combination of Motor-Generator Set, Cooling Fan, Radiator, Mounting Rails,
Silencer, Exit Circuit Breaker, Controls Mounted to the Unit and other
Components, Accessories, Spare Parts, Tests, Documents and the required
services to accomplish with this Specification.
HOJA 4/15
PROJECT No. DATE:
2.2.2. Motor: The Motor-Generator Set shall be mounted on a heavy-duty steel frame;
in order to maintain a proper alignment between components and it will
incorporate vibration shock absorbers as manufacturers indicate. The motor
will be stationary, liquid cooled, fuel starting by spark. While normal power
system interruptions, the motor shall be capable to impulse the required
generator on continuity stand-by as indicated on SAE J1349 Specification. The
spare capacity shall be as it is indicated on drawings and other documents annex
to this specification.
HOJA 5/15
PROJECT No. DATE:
HOJA 6/15
PROJECT No. DATE:
2.2.3. Motor cooling system. Motor will be cooling by a radiator; it shall be mounted
in the same motor frame, including a tread fan, cooling liquid pump and
temperature control thermostat. The accomplishment of these components shall
be as manufacturer required. The provider of the Emergency Generator Set
must supply 50% of anti-freeze solution of ethilen-glicol to fill the motor’s
starting cooling system.
2.2.4. Motor Exhaust System: The exhaust silencer shall be per manufacturer
required. Hospital type silencer required. The silencer shall be installed at the
top of the motor chassis; the motor will not support it. The vacuum pipe
galvanized steel and it’s cover shall be supplied by the provider. The flexible
exhaust connection will be supplied as required for the interconnection between
the motor multiple exhaust and the exhaust pipe. All the exhaust system
components shall be properly dimensioned to ensure the right operation without
excessive pressure after the mounting process. The contractor shall provide the
required facilities for the contraction and expansion of the exhaust system.
2.2.5. Fuel Motor System. Provide the required incoming lines, pressure governors,
fuel filters, operations cuts, solenoids valves, vacuum lines, etc., and all the
required accessories. All the connections for the fuel motor system shall be
provided in accordance with applicable Codes and Standards.
2.2.6. The fuel storage tanks and its accessories must be new brand and shall be Class
X, with a minimum of 24 hours of operation time at the generator nominal
capacity, as indicated on the NFPA 110, chart 2-2.3. Provider must supply a low
incoming fuel sensing device on the primary line governor. The sensing device
must be adjusted for a 2 hours minimum fuel level, based on the consumption
capacity of the specified generator.
HOJA 7/15
PROJECT No. DATE:
2.2.8. Transfer Switch: provide a 13.2 kVac, 60 Hz, 1800 rpm, p.f.= 0.8, 3 phases, 3
wires, automatic transfer switch with 100 Amps vacuum breakers, NEMA 12,
tropicalized finished. The Transfer Switch must provide the following benefits:
HOJA 8/15
PROJECT No. DATE:
a) Gauges and Meters: oil pressure gauge, temperature cooling liquid gauge,
and voltammeter of load capacity and operation time meter.
b) Manual Selector interrupter: MANUAL – OFF/RESET - AUTO.
c) Remote, 2-wire start control.
d) Field reset manual interrupter.
a) Overcranking.
b) Overspeed.
c) Low Oil pressure.
d) High motor temperature.
HOJA 9/15
PROJECT No. DATE:
2.2.12. Provide a reset switch, to clean the fault conditions and let the motor
crank again after the fault. The control design must permit that the indicating
lamps be on until the fault reset. The indicating fault memory will not be
dependent of AC or DC voltage and will storage the historic events after the
elimination or replacement of starting batteries. The “reset fault” function will
works only when the manual selector interrupter “MANUAL–OFF/RESET-
AUTO” is on “OFF/RESET” position.
2.3. EQUIPMENT
2.3.1. Cranking Battery. Provide a cranking battery for motor; battery shall be
mounted on a battery rack on the Motor-Generator Set frame.
2.3.2. Battery Charger: Provide a 12 Vdc battery charger, continuous and slow load, 2
Amps. for the Motor-Generator Set. The required power for battery charger
will be provided from the normal power source. Contractor shall provide the
required circuit for this purpose.
2.3.3. Shock Absorbers. The Motor-Generator Set will be mounted over “internal
vibration” shock absorbers, installed on the Motor-Generator Set frame.
HOJA 10/15
PROJECT No. DATE:
2.3.4. Remote Audible Indicator. Provide a remote audible indicator for the Motor-
Generator Set with three indicating lamps as follows:
3. QUALITY CONTROL
Provider shall supply a complete set of wiring diagrams for the Motor-
Generator Set. Manufacturer shall print out all the literature and brochures that
discribe all the specified standards (not about manufacturing type). Unless noted
otherwise in this Specification, the manufacturing process shall be as
manufacturer indicates..
Provider must submit for approval a set of workshop drawings, based on the
contract drawings and what is established on this Specification.
a) Design Data
HOJA 11/15
PROJECT No. DATE:
Provider shall submit the required calculation to demonstrate that the exciter
voltage governor will let to use at least 80% of maximum torque available
between 50% and nominal speed, and unit power factor when load is connected
to the generator.
b) Testing Reports
3.2.1. Manufacturer shall carry out with the design tests or demonstrate that the
manufacture process is according to what the prototype design accomplishes
the tests indicated on the standards mentioned at paragraph 1.1.1. of this
Specification.
3.2.2. The Design Tests required, in order to manufacturer must have to accomplish,
are the following:
HOJA 12/15
PROJECT No. DATE:
After the successful finishing of the initial Starting and System final
verification, provider must execute the Approval Facility Test according to
the latest edition of NFPA 110 Standard. An owners representative, shall be
notified, at least one week prior to conduct or supervise the tests.
3.4. CHECKING
3.4.1. All the equipment will be subject to be checked by the owner during any stage
of the manufacturing process. The owners checking do not relegate the
responsibility of manufacturer to accomplish with the requirements of this
Specification and the Technical Data Sheets.
3.4.2. Manufacturer will provide 3 printed sets of the following drawings and
documents for approval, before manufacturing process.
HOJA 13/15
PROJECT No. DATE:
a) Equipment Plan View showing all dimensions and details required for
foundation construction.
b) Elevations and Sections required, showing all dimensions.
c) Material List.
The manufacturing process will begin after owner approves drawings. Provider
shall supply two sets of Operation’s Manual and renewable parts, Two offset
and one original sets printed on mylar paper.
3.5.1. Responsibilities
3.5.2. Manufacturer will provide a package for the Emergency Generator Set, which
accomplish with the following requirements.
a) Prevent rainwater side and top penetration while transportation and storage
to the equipment interior.
b) Prevent the equipment against knocking while transportation.
c) Provide accurate alignment, leveling shims and suitable anchors for
mounting.
d) Provide a paintable black color exterior for the following minimum data
information:
HOJA 14/15
PROJECT No. DATE:
3.5.3. Every package of spare parts or tools that has to be shipped apart of must have
to show the above data information and the description of the package content.
4. WARRANTY
a) The Emergency Generator Set, including the 1800 rpm Motor-Generator Set equipped
with bench-bank and time operation meter, will be guaranteed for a (5) years period or
1,500 operation hours, counted since the initial starting date.
b) Multiple warranties for the individual components of the system (motor, generator,
controls, etc.) will not be accepted.
c) Warranty documents will be supplied to the owner, for the satisfactory approval. The
required documents will be detailed on the warranty.
a) Voltage 13.2 kV
b) Phases/Wires 3/3
c) Frequency 60 Hz
d) Short Circuit Level kA
e) Incoming feeders Top Underground x
HOJA 15/15