Professional Documents
Culture Documents
Perhitungan Alat Berat - Edit
Perhitungan Alat Berat - Edit
A Persiapan
1 Jalan Eksisting 12 km
a Pengukuran
Long Section WP 800 m' 1 hr 14.88 hr
Cross Section TS 25 m' 10 1 hr 47.60 hr
Material Gelam
Long 50 m' 1 m 238 btg
1190 btg
Cross 25 m' 0.5 m 4 btg 952 btg
Paku 119 kg
Upah
Juru Ukur 1 org 3.00 bln
Pembantu Juru Ukur 3 org 9.00 bln
b Pembentukan Badan Jalan 83,300 m2 Grader 350 m'/hr,lebar jln 7m 2450 m2/hr 350 m2/jm 1 unit 238.00 jm 0.0029 jm/m3
Vibro 300 m'/hr,lebar jln 7m 2100 m2/hr 300 m2/jm 1 unit 277.67 jm 0.0033 jm/m3
c Subbase course 26,400 m3 Grader 350 m'@3.5m' t=20cm 1225 m2/jm 4 pass 0.2 m 61.25 m3/jm 1 unit 431.02 jm 0.0163 jm/m3
(Jam kerja alat 1 bln=200 jm) Vibro 300 m' @ 3.5m' ,t=20cm 1050 m2/jm 4 pass 0.2 m 52.50 m3/jm 1 unit 502.86 jm 0.0190 jm/m3
WT Kap.mengikuti Vibro 52.50 m3/jm 1 unit 502.86 jm 0.0190 jm/m3
d Base course 9,900 m3 Grader 350 m'@3.5m' t=15cm 1225 m2/jm 4 pass 0.15 m 45.94 m3/jm 1 unit 215.51 jm 0.0218 jm/m3
(Jam kerja alat 1 bln=200 jm) Vibro 300 m' @ 3.5m' ,t=15cm 1050 m2/jm 4 pass 0.15 m 39.38 m3/jm 1 unit 251.43 jm 0.0254 jm/m3
WT Kap.mengikuti Vibro 39.38 m3/jm 1 unit 251.43 jm 0.0254 jm/m3
1 unit
e Penetration Macadam 44,000 m2 TWR 300 m' @ 3.5m' 1050 m2/jm 3 pass 350.00 m2/jm 1 unit 125.71 jm 0.002857 jm/m2
Batu 5/7 1 m 1.2 m 0.07 m 0.084 m3
Batu 2/3 1 m 1.2 m 0.03 m 0.036 m3
Batu 1/1 1 m 1.2 m 0.01 m 0.012 m3
Pasir 0.015 m3
Aspal 10 liter
f Saluran kiri/kanan
g Pemeliharaan Jalan 12 bln
2 Perbaikan Jembatan
a Jembatan Bentang 50m Class B 1 bh
b Plat Deck 1 set
c Tulangan Ø12 60kg/m3 5,100 kg
d Beton K350 85 m3
Page 2 of 20
Galian tebing (Triming) (20%) 75,216 m3 Excav Kap.Excav 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 1,253.59 jm 0.0033 jm/m3
Loading to DT 376,078 m3 Excav Kap.Excav 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 6,267.97 jm 0.0167 jm/m3
3 Weathered Rock 11,806 m3 Excav Kap. Alat 50 m3/jm 50 m3/jm 50 m3/jm 1 unit 236.12 jm 0.0200 jm/m3
Exc.Breaker Kap. Alat 50 m3/jm 50 m3/jm 50 m3/jm 1 unit 236.12 jm 0.0200 jm/m3
4 Embankment 50,673 m3
a Embankment (0-100) 36,329 m3 Vib.SF Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 807.32 jm 0.022222 jm/m3
WT Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 807.32 jm 0.022222 jm/m3
b Embankment (100-600) 14,345 m3 Vib.SF Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 318.77 jm 0.022222 jm/m3
Grader 350 m'@3.5m' t=20cm 1225 m2/jm 4 pass 0.2 m 61.25 m3/jm 1 unit 234.20 jm 0.0089 jm/m3
WT Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 318.77 jm 0.022222 jm/m3
Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 239.08 jm 0.016667 jm/m2
DT jarak angkut ± 300 m' 79 m3/jm 79 m3/jm 1 unit 181.58 jm 0.012658 jm/m2
Kapasitas 1 DT, 8 m3
0.3 km
t1(wkt berangkat) 0.010 jm
30 km/jm
0.3 km
t2(wkt pulang) 0.008 jm
40 km/jm
60 mnt
1 jam kerja DT 8 m3 79.34 m3/jm
6.05 mnt
Asumsi rata-rata Kapasitas angkut DT 79 m3/jm
5 Bench cut 6,362 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 106 jm 0.016667 jm/m2
Page 3 of 20
5 km
t2(wkt pulang) 0.125 jm
40 km/jm
60 mnt
1 jam kerja DT 8 m3 21.33 m3/jm
22.50 mnt
Asumsi rata-rata Kapasitas angkut DT 21 m3/jm
Dozer Kap.Dozer 95.20 m3/jm 95.2 m3/jm 95.2 m3/jm 1 unit 3,917 jm 0.0105 jm/m3
7 Pavement
a Penetration Macadam 102,761 m2 TWR 300 m' @ 3.5m' 1050 m2/jm 3 pass 350.00 m2/jm 1 unit 294 jm 0.002857 jm/m2
Batu 5/7 1 m 1.2 m 0.07 m 0.084 m3
Batu 2/3 1 m 1.2 m 0.03 m 0.036 m3
Batu 1/1 1 m 1.2 m 0.01 m 0.012 m3
Pasir 0.015 m3
Aspal 10 liter
b Base Coarse 15,414 m3 Grader 350 m'@3.5m' (4pass) 1225 m2/jm 4 pass 0.2 m 61.25 m3/jm 1 unit 252 jm 0.0163 jm/m3
Vibro 300 m' @ 3.5m' ,t=20cm 1050 m2/jm 4 pass 0.2 m 52.50 m3/jm 1 unit 294 jm 0.0190 jm/m3
WT Kap.mengikuti Vibro 52.50 m3/jm 1 unit 294 jm 0.0190 jm/m3
c Subbase coarse 41,104 m3 Grader 350 m'@3.5m' (4pass) 1225 m2/jm 4 pass 0.2 m 61.25 m3/jm 1 unit 671 jm 0.016327 jm/m3
Vibro 300 m' @ 3.5m' ,t=20cm 1050 m2/jm 4 pass 0.2 m 52.50 m3/jm 1 unit 783 jm 0.019048 jm/m3
WT Kap.mengikuti Vibro 52.50 m3/jm 1 unit 783 jm 0.019048 jm/m3
C Intake Weir
1 Clearing & Grubbing 22,899 m2 t=20cm 4579.80 m3
Dozer 3 hari @ 1 Ha(10.000m2) 476.19048 m2/jm 0.2 m 95.24 m3/jm 1 unit 48 jm 0.0021 jm/m2
Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 76 jm 0.0033 jm/m2
2 Common Soil 157,927 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 2,632 jm 0.016667 jm/m3
Loading m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 2,632 jm 0.016667 jm/m3
3 Weathered Rock 48,283 m3 Ex+JH Kap. Alat 50 m3/jm 50 m3/jm 50 m3/jm 1 unit 966 jm 0.02 jm/m3
4 Weak Rock 5,714 m3 Ex+JH Kap. Alat 40 m3/jm 30 m3/jm 30 m3/jm 1 unit 190 jm 0.03333 jm/m3
Page 4 of 20
6 Disposal 207,247 m3 DT jarak angkut ± 500 m 71 m3/jm 71 m3/jm 1 unit 2,919 jm 0.0141 jm/m3
(clearing+excavation-embankment) Kapasitas 1 DT, 8 m3
0.5 km
t1(wkt berangkat) 0.017 jm
30 km/jm
0.5 km
t2(wkt pulang) 0.013 jm
40 km/jm
60 mnt
1 jam kerja DT 8 m3 71.11 m3/jm
6.75 mnt
Asumsi rata-rata Kapasitas angkut DT 71 m3/jm
Dozer Kap.Dozer 95.20 m3/jm 95.2 m3/jm 95.2 m3/jm 1 unit 2,177 jm 0.0105 jm/m3
D Intake
1 Backfill 7,460 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 124 jm 0.016667 jm/m3
Vibro 300 m' @ 3.5m' ,t=20cm 1050 m2/jm 4 pass 0.2 m 52.50 m3/jm 1 unit 142 jm 0.019048 jm/m3
E Diversion Works
1 Perataan (include Disposal) 2,866,053 m3 Dozer
1 Common Soil 339,167 m3 Vibro Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 7,537 jm 0.022222 jm/m3
(Embankment with compaction) WT Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 7,537 jm 0.022222 jm/m3
2 Embankment 2,526,886 m3 Vibro Kap. Alat 45 m3/jm 45 m3/jm 45 jm 1 unit 56,153 jm 0.0222 jm/m3
(With Compaction) WT Kap. Alat 45 m3/jm 45 m3/jm 45 jm 1 unit 56,153 jm 0.0222 jm/m3
F Connecting Channel
1 Common Soil 75 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 1 jm 0.016667 jm/m3
DT jarak angkut ± 0.5 km 71 m3/jm 71 m3/jm 1 unit 1 jm 0.014085 jm/m3
Page 5 of 20
2 Common Soil 106,060 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 1,768 jm 0.0167 jm/m3
Loading m3 Excav Kap. Alat 60 m3/jm 0 m3/jm 60 m3/jm 1 unit 1,768 jm 0.0167 jm/m3
3 Weathered Rock 66,278 m3 Ex+JH Kap. Alat 60 m3/jm 50 m3/jm 50 m3/jm 1 unit 1,326 jm 0.0200 jm/m3
4 Weak Rock 36,989 m3 Ex+JH Kap. Alat 60 m3/jm 30 m3/jm 30 m3/jm 1 unit 1,233 jm 0.0333 jm/m3
5 Backfill 13,968 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 233 jm 0.016667 jm/m3
Vibro 300 m' @ 3.5m' ,t=20cm 1050 m2/jm 4 pass 0.2 m 52.50 m3/jm 1 unit 266 jm 0.019048 jm/m3
6 Disposal 199,939 m3 DT jarak angkut ± 1 km 56 m3/jm 56 m3/jm 1 unit 3,570 jm 0.0179 jm/m3
(clearing+excavation-embankment) Kapasitas 1 DT, 8 m3
1 km
t1(wkt berangkat) 0.033 jm
30 km/jm
1 km
t2(wkt pulang) 0.025 jm
40 km/jm
60 mnt
1 jam kerja DT 8 m3 56.47 m3/jm
8.50 mnt
Asumsi rata-rata Kapasitas angkut DT 56 m3/jm
Dozer Kap.Dozer 95.20 m3/jm 95.20 m3/jm 95.2 m3/jm 1 unit 2,100 jm 0.0105 jm/m3
Page 6 of 20
Galian tebing (Triming) (20%) 550,346 m3 Excav Kap.Excav 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 9,172 jm 0.003333 jm/m3
Loading to DT 2,751,729 m3 Excav Kap.Excav 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 45,862 jm 0.016667 jm/m3
3 Weathered Rock 279,023 m3 Ex+JH Kap. Alat 60 m3/jm 50 m3/jm 50 m3/jm 1 unit 5,580 jm 0.02000 jm/m3
4 Embankment 652,725 m3
a Embankment (0-100) 60,503 m3 Vib.SF Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 1,345 jm 0.022222 jm/m3
WT Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 1,345 jm 0.022222 jm/m3
b Embankment (100-600) 99,915 m3 Vib.SF Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 2,220 jm 0.022222 jm/m3
Grader 350 m'@3.5m' t=20cm 1225 m2/jm 4 pass 0.2 m 61.25 m3/jm 1 unit 1,631 jm 0.016327 jm/m3
WT Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 2,220 jm 0.022222 jm/m3
Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 1,665 jm 0.016667 jm/m2
DT jarak angkut ± 300 m' 79 m3/jm 79 m3/jm 1 unit 1,265 jm 0.012658 jm/m2
Kapasitas 1 DT, 8 m3
0.3 km
t1(wkt berangkat) 0.010 jm
30 km/jm
0.3 km
t2(wkt pulang) 0.008 jm
40 km/jm
60 mnt
1 jam kerja DT 8 m3 79.34 m3/jm
6.05 mnt
Asumsi rata-rata Kapasitas angkut DT 79 m3/jm
c Embankment (1Km-3Km) 492,307 m3 Vib.SF Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 10,940 jm 0.022222 jm/m3
Grader 350 m'@3.5m' t=20cm 1225 m2/jm 4 pass 0.2 m 61.25 m3/jm 1 unit 8,038 jm 0.016327 jm/m3
WT Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 10,940 jm 0.022222 jm/m3
Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 8,205 jm 0.016667 jm/m2
DT jarak angkut ± 2 Km 40 m3/jm 40 m3/jm 1 unit 12,308 jm 0.025 jm/m2
5 Backfill 30,864 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 514 jm 0.016667 jm/m3
Vibro 300 m' @ 3.5m' ,t=20cm 1050 m2/jm 4 pass 0.2 m 52.50 m3/jm 1 unit 588 jm 0.019048 jm/m3
6 Bench cut 23,173 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 jm 1 unit 386 jm 0.016667 jm/m3
Page 7 of 20
2 km
t2(wkt pulang) 0.050 jm
40 km/jm
60 mnt
1 jam kerja DT 8 m3 40 m3/jm
12.00 mnt
Asumsi rata-rata Kapasitas angkut DT 40 m3/jm
Dozer Kap.Dozer 95.20 m3/jm 95.20 m3/jm 95.2 m3/jm 1 unit 25,719 jm 0.0105 jm/m3
J Headtank
1 Clearing & Grubbing 5,910 m2 t=20cm 1182.00 m3
Dozer 3 hari @ 1 Ha(10.000m2) 476.19 m2/jm 0.2 m 95.24 m3/jm 1 unit 12 jm 0.0021 jm/m2
Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 20 jm 0.003333 jm/m2
2 Common Soil 68,005 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 1,133 jm 0.0167 jm/m3
3 Weathered Rock 10,702 m3 Ex+JH Kap. Alat 50 m3/jm 50 m3/jm 50 m3/jm 1 unit 214 jm 0.0200 jm/m3
4 Weak Rock 617 m3 Ex+JH Kap. Alat 40 m3/jm 30 m3/jm 30 m3/jm 1 unit 21 jm 0.0333 jm/m3
5 Backfill 16,127 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 269 jm 0.016667 jm/m3
Vibro 300 m' @ 3.5m' ,t=20cm 1050 m2/jm 4 pass 0.2 m 52.50 m3/jm 1 unit 307 jm 0.019048 jm/m3
6 Disposal 64,379 m3 DT jarak angkut ± 8 km 14 m3/jm 14 m3/jm 1 unit 4,599 jm 0.0714 jm/m2
(clearing+excavation-embankment) Kapasitas 1 DT, 8 m3
8 km
t1(wkt berangkat) 0.267 jm
30 km/jm
8 km
t2(wkt pulang) 0.200 jm
40 km/jm
Dozer Kap.Dozer 95.20 m3/jm 95.20 m3/jm 95.2 m3/jm 1 unit 676 jm 0.0105 jm/m3
K Penstock
1 Clearing & Grubbing 59,563 m2 t=20cm 11912.60 m3
Dozer 3 hari @ 1 Ha(10.000m2) 476.19 m2/jm 0.2 m 95.24 m3/jm 1 unit 125 jm 0.0021 jm/m2
Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 199 jm 0.003333 jm/m2
2 Common Soil 1,156,794 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 19,280 jm 0.0167 jm/m3
3 Weathered Rock 88,190 m3 Ex+Brek Kap. Alat 50 m3/jm 50 m3/jm 50 m3/jm 1 unit 1,764 jm 0.0200 jm/m3
4 Weak Rock 18,508 m3 Ex+Brek Kap. Alat 40 m3/jm 30 m3/jm 30 m3/jm 1 unit 617 jm 0.0333 jm/m3
5 Backfill 136,333 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 2,272 jm 0.016667 jm/m3
Vibro 300 m' @ 3.5m' ,t=20cm 1050 m2/jm 4 pass 0.2 m 52.50 m3/jm 1 unit 2,597 jm 0.019048 jm/m3
6 Disposal 1,139,072 m3 DT jarak angkut ± 8 km 14 m3/jm 14 m3/jm 1 unit 81,362 jm 0.0714 jm/m2
(clearing+excavation-embankment) Kapasitas 1 DT, 8 m3
8 km
t1(wkt berangkat) 0.267 jm
30 km/jm
8 km
t2(wkt pulang) 0.200 jm
40 km/jm
60 mnt
1 jam kerja DT 8 m3 14.55 m3/jm
33.00 mnt
Asumsi rata-rata Kapasitas angkut DT 14 m3/jm
Dozer Kap.Dozer 95.20 m3/jm 95.20 m3/jm 95.2 m3/jm 1 unit 11,965 jm 0.0105 jm/m3
L Power House
1 Clearing & Grubbing 12,186 m2 t=20cm 2437.20 m3
Dozer 3 hari @ 1 Ha(10.000m2) 476.19 m2/jm 0.2 m 95.24 m3/jm 1 unit 26 jm 0.0021 jm/m2
Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 41 jm 0.003333 jm/m2
2 Common Soil 114,426 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 1,907 jm 0.0167 jm/m3
3 Weathered Rock 10,736 m3 Ex+JH Kap. Alat 50 m3/jm 50 m3/jm 50 m3/jm 1 unit 215 jm 0.0200 jm/m3
Page 9 of 20
5 Backfill 8,493 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 142 jm 0.016667 jm/m3
Vibro 300 m' @ 3.5m' ,t=20cm 1050 m2/jm 4 pass 0.2 m 52.50 m3/jm 1 unit 162 jm 0.019048 jm/m3
6 Disposal 129,017 m3 DT jarak angkut ± 8.5 km 13 m3/jm 13 m3/jm 1 unit 9,924 jm 0.0769 jm/m2
(clearing+excavation-embankment) Kapasitas 1 DT, 8 m3
8.5 km
t1(wkt berangkat) 0.283 jm
30 km/jm
8.5 km
t2(wkt pulang) 0.213 jm
40 km/jm
60 mnt
1 jam kerja DT 8 m3 13.81 m3/jm
34.75 mnt
Asumsi rata-rata Kapasitas angkut DT 13 m3/jm
Dozer Kap.Dozer 95.20 m3/jm 95.20 m3/jm 95.2 m3/jm 1 unit 1,355 jm 0.0105 jm/m3
7 Pavement
a Penetration Macadam 2,690 m2 TWR 300 m' @ 3.5m' 1050 m2/jm 3 pass 350.00 m2/jm 1 unit 8 jm 0.002857 jm/m2
Batu 5/7 1 m 1.2 m 0.07 m 0.084 m3
Batu 2/3 1 m 1.2 m 0.03 m 0.036 m3
Batu 1/1 1 m 1.2 m 0.01 m 0.012 m3
Pasir 0.015 m3
Aspal 10 liter
b Base Coarse 404 m3 Grader 350 m'@3.5m' (4pass) 1225 m2/jm 4 pass 0.2 m 61.25 m3/jm 1 unit 252 jm 0.0163 jm/m3
Vibro 300 m' @ 3.5m' ,t=20cm 1050 m2/jm 4 pass 0.2 m 52.50 m3/jm 1 unit 294 jm 0.0190 jm/m3
WT Kap.mengikuti Vibro 52.50 m3/jm 1 unit 294 jm 0.0190 jm/m3
c Subbase coarse 1,076 m3 Grader 350 m'@3.5m' (4pass) 1225 m2/jm 4 pass 0.2 m 61.25 m3/jm 1 unit 671 jm 0.016327 jm/m3
Vibro 300 m' @ 3.5m' ,t=20cm 1050 m2/jm 4 pass 0.2 m 52.50 m3/jm 1 unit 783 jm 0.019048 jm/m3
WT Kap.mengikuti Vibro 52.50 m3/jm 1 unit 783 jm 0.019048 jm/m3
Page 10 of 20
Galian tebing (Triming) (20%) 96,902 m3 Excav Kap.Excav 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 1,615 jm 0.003333 jm/m3
Loading to DT 484,509 m3 Excav Kap.Excav 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 8,075 jm 0.016667 jm/m3
3 Weathered Rock 5,755 m3 Ex+JH Kap. Alat 50 m3/jm 50 m3/jm 50 m3/jm 1 unit 115 jm 0.0200 jm/m3
4 Weak Rock 3,775 m3 Ex+JH Kap. Alat 40 m3/jm 30 m3/jm 30 m3/jm 1 unit 126 jm 0.0333 jm/m3
5 Embankment 21,844 m3 Vib.SF Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 485 jm 0.022222 jm/m3
WT Kap. Alat 45 m3/jm 45 m3/jm 45 m3/jm 1 unit 485 jm 0.022222 jm/m3
6 Backfill 218,925 m3 Excav Kap. Alat 60 m3/jm 60 m3/jm 60 m3/jm 1 unit 3,649 jm 0.016667 jm/m3
Vibro 300 m' @ 3.5m' ,t=20cm 1050 m2/jm 4 pass 0.2 m 52.50 m3/jm 1 unit 4,170 jm 0.019048 jm/m3
6 Disposal 264,630 m3 DT jarak angkut ± 9 km 13 m3/jm 13 m3/jm 1 unit 20,356 jm 0.0769 jm/m2
(clearing+excavation-embankment) Kapasitas 1 DT, 8 m3
9 km
t1(wkt berangkat) 0.300 jm
30 km/jm
9 km
t2(wkt pulang) 0.225 jm
40 km/jm
60 mnt
1 jam kerja DT 8 m3 13.15 m3/jm
36.50 mnt
Asumsi rata-rata Kapasitas angkut DT 13 m3/jm
Dozer Kap.Dozer 95.20 m3/jm 95.20 m3/jm 95.2 m3/jm 1 unit 2,780 jm 0.0105 jm/m3
JADWAL PERALATAN
Embankment 50,673 m3
Embankment 36,329 m3 Sifut R 1 45.00 m3 807 4.04 2 2.02 2 2
(jarak 0-100 m) WTT 1 45.00 m3 807 4.04 2 2.02 2 2
M.Grader 2 2 2 - - - 1 2 2 2
Vibro R 2 2 2 - - - - 2 2 2
Sifoot Roller - - - - 2 2 2 - - -
Water T - 2 2 - 2 2 2 - 2 2
Bulldozer - - 2 4 4 4 4 - - -
Excavator - - 3 12 12 13 15 - - -
Excavator Breaker - - - - - 1 1 - - -
DT - - 1 22 22 22 24 - - 1
Sprayer - - 1 - - - - - - 1
TW.Roller - - 1 - - - - - - 1
JADWAL PERALATAN
WATERWAY 200
Clearing & Grubbing 390,801 m2 Bulldozer 1 95.24 m3 821 4.10 1 4.10 1 1 1 1
78,160 m3 Excavator 2 60.00 m3 1,303 4.10 1 4.10 2 2 2 2
Embankment 652,725 m3
Embankment 60,503 m3 Vibro Roller 1 45.00 m3 1,345 6.72 4 1.68 4 4
(jarak 0-100 m) WTT 1 45.00 m3 1,345 6.72 4 1.68 4 4
M.Grader - - - - - - - - 3 3 3 4 4 4 4 4 4 4 4 4 - - - -
Vibro Roller - - - - - - 4 4 4 4 4 6 6 6 6 6 6 6 6 6 - - - -
Water T - - - - - - 4 4 4 4 4 6 6 6 6 6 6 6 6 6 - - - -
Bulldozer - - - - 17 17 17 17 16 16 16 16 16 16 16 16 16 16 16 - - - - -
Excavator - - - - 5 9 9 9 10 10 10 12 12 12 12 12 12 12 12 5 - - - -
Excavator Breaker - - - - - 2 2 2 2 2 2 2 2 2 2 2 2 2 2 - - - - -
DT - - - - 18 18 18 18 21 21 21 27 27 27 27 27 27 27 27 9 - - - -
JADWAL PERALATAN
Volume Komposisi Jam Kerja Jumlah Jmlh Waktu BULAN :
Jenis Pekerjaan
Pekerjaan Alat / Fleet Produk/jam Jam Bulan Fleet (Bulan) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Sifoot Roller
Water T
Bulldozer - - - - 2 1 1 1 1 1 1 - - - - - - - - - - - - -
Excavator - - - - 4 5 5 5 5 5 5 - - - - - - - - - - - - -
Excavator Breaker - - - - - 1 1 1 1 1 1 - - - - - - - - - - - - -
DT - - - - 2 2 2 2 2 2 2 - - - - - - - - - - - - -
Vibro Roller - - - - - - - - - - - - - - - - - - - - - - - -
JADWAL PERALATAN
WTT - - - - 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 17 -
Sifoot Roller
Water T
Bulldozer - - - - - - - - - - - 3 2 2 2 2 2 - - - - - - -
Excavator - - - - - - - - - - - 8 6 6 6 6 6 - - - - - - -
Excavator Breaker - - - - - - - - - - - 2 2 2 2 2 2 - - - - - - -
DT - - - - - - - - - - - 3 3 3 3 3 3 - - - - - - -
Vibro Roller - - - - - - - - - - - - - - - - - - - - - - - -
JADWAL PERALATAN
Bulldozer - - - - - - - - - - - - - - - - - 1 1 1 1 - - -
Excavator - - - - - - - - - - - - - - - - - 2 4 5 5 - - -
Excavator Breaker - - - - - - - - - - - - - - - - - - - 1 1 - - -
DT - - - - - - - - - - - - - - - - - - 8 8 8 - - -
Vibro Roller - - - - - - - - - - - - - - - - - - - - - - - -
JADWAL PERALATAN
Bulldozer - - - - - - - 5 4 4 4 4 4 4 4 4 4 4 4 4 - - - -
Excavator - - - - - - - 16 15 15 15 15 15 15 15 15 15 15 15 15 - - - -
Excavator Breaker - - - - - - - - 1 1 1 1 1 1 1 1 1 1 1 1 - - - -
DT - - - - - - - 30 30 30 30 30 30 30 30 30 30 30 30 30 - - - -
Vibro Roller - - - - - - - - - - - - - - - - - - - - - - - -
JADWAL PERALATAN
Bulldozer - - - - - - - - 3 2 2 2 - - - - - - - - - - - -
Excavator - - - - - - - - 2 9 9 9 - - - - - - - - - - - -
Excavator Breaker - - - - - - - - - 1 1 1 - - - - - - - - - - - -
DT - - - - - - - - 12 12 12 12 - - - - - - - - - - - -
Vibro Roller - - - - - - - - - - - - - - - - - - - - - - - -
JADWAL PERALATAN
Water T - - - - - - - - - - - - - - - - - 1 1 1 - - - -
Bulldozer - - - - - - - - - - - - 1 7 7 7 7 7 7 7 - - - -
Excavator - - - - - - - - - - - - 2 7 7 7 7 7 8 8 - - - -
Excavator Breaker - - - - - - - - - - - - - - - - - - 1 1 - - - -
DT - - - - - - - - - - - - - 32 32 32 32 32 32 32 - - - -
Vibro Roller - - - - - - - - - - - - - - - - - - - - - - - -
TOTAL KEBUTUHAN
M.Grader 2 2 2 - - - 1 2 5 5 3 4 4 4 4 4 4 4 4 4 - - - -
Vibro R 2 2 2 - 17 17 21 23 23 23 21 23 23 23 23 23 23 23 23 23 17 17 17 -
Sifoot Roller - - - - 2 2 2 - - - - - - - - - - - - - - - - -
Water T - 2 2 - 19 19 23 21 23 23 21 23 23 23 23 23 23 24 24 24 17 17 17 -
Bulldozer - - 2 4 23 22 22 23 24 23 23 24 23 29 29 29 29 28 29 13 1 - - -
Excavator - - 3 12 20 27 29 29 32 39 39 43 34 40 40 40 40 35 39 33 5 - - -
Excavator Breaker - - - - - 4 4 3 4 5 5 6 5 5 5 5 5 3 4 3 1 - - -
DT - - 1 22 42 42 44 50 65 66 65 72 60 92 92 92 92 89 97 79 8 - - -
JADWAL PERALATAN
Sprayer - - 1 - - - - - - 1 - - - - - - - - - - - - - -
TW.Roller - - 1 - - - - - - 1 - - - - - - - - - - - - - -