Professional Documents
Culture Documents
Daily Report Pt. Citra Lampia Mandiri
Daily Report Pt. Citra Lampia Mandiri
Total Total
Hari/Tanggal BLOCK Material 07.00-17.00 19.00-23.00 Ritase Produksi
Ritase Tonase Ritase Tonase
OB 0.0 0.0 0.0 0.0
PIT-ETO 0.0 0.0 0.0 0.0
Saturday, May 05, 2018 Pit A ORE PIT-EFO 0.0 0.0 0.0 0.0
ETO-EFO 0.0 0.0 0.0 0.0
Quarry 0.0 0.0 0.0 0.0 0.0 0.0
PRODUKSI WEEK 19 0.0
TOTAL PRODUKSI 10477.759
PRODUKSI MEI 0.0
KETERANGAN ;
1. PRODUKSI DAN AKTIVITAS TAMBANG TERHAMBAT OLEH MASALAH SOSIAL ( CLM & PIHAK ISRULLAH ) A. JUMLAH DOME ETO = 10 DOME
B. JUMLAH DOME EFO = 22 DOME
C. TONGKANG BARGING = TONGKANG KE-1, 290 RIT
TOTAL
KETERANGAN :
MONITORING EQUIPMENT
PT. CITRA LAMPIA MANDIRI
No Equipment HM st. Prestart st.fuel greasing st.hujan slippery No.optr st.Cont brk/down
1 PC-200, PC-300,DZ,GD,CT 0
KETERANGAN :
No Equipment HM st. Prestart st.fuel greasing st.hujan slippery No.optr st.Cont brk/down
1 DT 0
KETERANGAN :
ANDIRI DAILY REPORT PT. CITRA LAMP
PLAN VS ACTUAL EQUIPMENT
MINE ACTIVITY
ACTIVITY PLAN ACTUAL
OB REMOVAL 1 PC 200, 3 PC 300, 2 DZ, 6 DT NO ACTIVITY
STOCK ETO STOCK EFO TOTAL BARGING ORE GETTING 2 PC 200 NO ACTIVITY
A. HAULING PIT-EFO 1 PC 200, 1 PC 200, 1 PC 300, 39 DT NO ACTIVITY
B. HAULING ETO-EFO 1 PC 200, 1 PC 300, 4 DT
C. HAULING PIT -ETO 2 PC 200, 1 PC 300, 35 DT
1981 4756.43 5721.329 1 PC 200, 1 PC 300, 1 DZ NO ACTIVITY
MHR
3 GD, 3 CT, 3 DT
BARGING 2 PC 200, 1 PC 300, 6 DT NO ACTIVITY
SR 1 : 3 DPP OB = 5000 WMT
DPP ORE = 1667 WMT KETERANGAN ALAT :
TO = 10 DOME
FO = 22 DOME
ING = TONGKANG KE-1, 290 RIT
Keterangan Dome
DOME AA-1,AA-2,AA-3,AA-4,AA-4,AA-6,AA-7,AA-8,AA-
9,AA10,AA-11,AA-12,AA-13,AA14,AA-15,AA-18
HM
st. Prestart
st.fuel
greasing
st.hujan
slippery
No.optr
st.Cont
st. Soci al Is s ue; 13.0 brk/down
Waiting Spare
st. Operator
st. Social Issue
Waiting Spare st. Operator st. Social Issue HEAVY EQUIPMENT
13
HM
st. Prestart
st.fuel
greasing
st.hujan
slippery
No.optr
st.Cont
st. Soci al Is s ue; 13.0 brk/down
Waiting Spare
st. Driver
Waiting Spare st. Driver st. Social Issue
st. Social Issue
13 DUMP TRUCK
. CITRA LAMPIA MANDIRI
%
0.00%
0.00%
0.00%
0.00%
0.00%
PT Citra Lampia
Mandiri
Tanggal
BLOCK Material
Hari Tanggal Bulan Tahun Week
Top Soil
OB
Rabu 11 April 2018 15 Pit A Pit-EFO
ORE
ETO-EFO
Quarry
Daily Target produksi Aktual produksi ( % )
Material BCM Material BCM Persentase
OB 3048 OB 0 0.00%
ORE 1200 ORE 292 24.37%
Aktual produksi OB 0.00% & Ore 24.37% disebabkan kegiatan produksi baru berjalan 1 shif
Jumlah 4 Exca maintenance pit road, Striping OB & Loading Ore, 24 DT Hauling Ore
Kegiatan hauling dari Pit ke EFO
Kegiatan dimulai pukul 07.00-17.00, Lembur pukul 19.00-20.30
Tanggal
BLOCK Material
Hari Tanggal Bulan Tahun Week
Rabu 11 April 2018 15 MHR Quarry
Tanggal
Keterangan :
Total dome yang telah di hauling ke EFO adalah 10 dome sehingga sisa dome di ETO 21 dome dengan tonase 4195
Material Lokasi
No. Equipment Kode
Shift 1 Shift 2 Shift 1
1 KOBELCO 200 EXC-01
2 KOBELCO 200 EXC-02 Quarry Jetty
3 KOMATSU 200 EXC-03 Quarry MHR
4 SANY 215 EXC-04 Ore EFO
5 SANY 215 EXC-05 Ore SEQ1
6 SANY 215 EXC-09 Ore SEQ1
7 HITACHI EXC-11 Quarry MHR
8 KOBELCO 200 EXC-13 OB SEQ1
9 KOMATSU 200 EXC-14
10 KOBELCO 200 EXC-15 Quarry MHR
11 KOBELCO 330 EXC-17 Ore SEQ1
12 KOBELCO 330 EXC-18 Quarry MHR
13 KOMATSU 300 EXC-19
14 KOMATSU 300 EXC-20 Quarry MHR
15 DOZER-D68ESS DZ-01 Quarry MHR
16 SAKAI CT-01 Quarry MHR
17 HAMM CT-02 Quarry MHR
18 KOMATSU GD405A GD-01
Keterangan :
4 Exca Breakdown
Material Lokasi
No. Equipment Kode
Shift 1 Shift 2 Shift 1
1 ISUZU DT-006
2 ISUZU DT-007
3 NISSAN DT-008 Quarry MHR
4 DT-009
5 DT-010
6 DT-011
4 HINO DT-012
8 DT-013
9 DT-014
10 DT-015
11 DT-016
12 DT-017
5 MITSUBISHI DT-013 Ore (LS) Pit-EFO
6 MITSUBISHI DT-014 Ore (LS) Pit-EFO
7 MITSUBISHI DT-015 Ore (LS) Pit-EFO
8 HINO DT-016 Ore (LS) Pit-EFO
9 HINO DT-017 Ore Pit-EFO
10 MITSUBISHI DT-018 Ore&Quarry Pit-EFO & MHR
11 MITSUBISHI DT-019 Ore&Quarry Pit-EFO & MHR
12 MITSUBISHI DT-020 Ore Pit-EFO
13 MITSUBISHI DT-021
14 MITSUBISHI DT-022 Ore Pit-EFO
15 MITSUBISHI DT-023 Ore Pit-EFO
16 MITSUBISHI DT-024 Ore Pit-EFO
17 MITSUBISHI DT-025 Ore Pit-EFO
18 HINO DT-026 Ore Pit-EFO
19 MITSUBISHI DT-027
20 MITSUBISHI DT-028 Ore Pit-EFO
21 HINO DT-029
22 HINO DT-030
23 MITSUBISHI DT-031 Ore Pit-EFO
24 HINO DT-032 Ore (LS) Pit-EFO
25 HINO DT-033
26 DT-034
27 DT-035 Ore Pit-EFO
28 DT-036 Ore Pit-EFO
29 HINO DT-037 Ore Pit-EFO
30 MITSUBISHI DT-038 Ore Pit-EFO
31 DT-039 Ore Pit-EFO
32 DT-040
33 ISUZU DT-041 Ore Pit-EFO
34 ISUZU DT-042 Ore Pit-EFO
35 ISUZU DT-043 Ore Pit-EFO
36 ISUZU DT-044 Ore Pit-EFO
37 ISUZU DT-045 Quarry MHR
Keterangan :
1. LS = Long Shift
2. 4 Unit Standby (No operator)
3. 6 Unit breakdown
Lokasi
No. Equipment Kode
Shift 1 Shift 2
1 DYNA 130 HT WT-001 KM 5 Maintenance Jalan MHR KM 4-6
2 DYNA 115 ET WT-002 Standby (No operator) KM 5, Masih menungg
3
4
Shift
1 2
Retase Bcm Tonase Retase
0 0.0 0.0
43 292.4 526.3
0 0.0 0.0
0 0 0.0
Shift
1 2
Retase Bcm Tonase Retase
34 340 612
TOTAL PRO
STANDBY
WAITING
RAIN SLIPERY SOCIAL ISSUE
INSTRUCTION
0.72 1.28
STANDBY
WAITING
RAIN SLIPERY SOCIAL ISSUE
INSTRUCTION
0.63
MONITORING ETO
PT. CITRA LAMPIA MANDIRI
Lokasi Keterangan
Shift 2 Shift 1
Breakdown (Lepas track)
Maintenance Jetty
Maintenance MHR (Breaker), KM 5.7
Maintenance EFO, KM 2
Loading Ore, Pit area
Loading Ore & Maintenance pit road, Pit area
Maintenance MHR, KM 12
Striping OB, Pit area
Breakdown (Bateray/Tidak bisa start)
Maintenance MHR
Loading Ore, Breakdown (Low power) 10.00-17.00
Maintenance Jetty & Jalan MHR, KM 6
Breakdown
Maintenance Jetty & Jalan MHR, KM 5.7, Breakdown (Pecah hose) 13.00-17.00
Maintenance jalan MHR, KM 11-5
Maintenance jalan MHR, KM 13
Maintenance jalan MHR, KM 5.7
Breakdown (pecah hose)
Lokasi Keterangan
Shift 2 Retase Shift 1
Breakdown (Kampas bermasalah), KM 5
Standby (No Operator)
10 Hauling Quarry, Maintenance MHR KM 10-8
Standby (No Operator)
Standby (No Operator)
Standby (No Operator)
Standby (No Operator)
Breakdown (Ban bocor)
Breakdown (Ban bocor)
Breakdown (Ban bocor)
Breakdown (Ban bocor)
Breakdown (Ban bocor)
2 Hauling Ore, Pit ke EFO
2 Hauling Ore, Pit ke EFO
2 Pukul 07.00-09.00 Breakdown (Ban pecah), Hauling Ore, Pit ke EFO
3 Hauling Ore, Pit ke EFO
2 Hauling Ore, Pit ke EFO
Ore(1)&Quarry(3) Hauling Ore, Pit ke EFO & Hauling Quarry Km 6-Jetty
Ore(1)&Quarry(3) Hauling Ore, Pit ke EFO & Hauling Quarry Km 6-Jetty
2 Hauling Ore, Pit ke EFO
Breakdown (Kerja dudukan mesin)
2 Hauling Ore, Pit ke EFO
1 Hauling Ore, Pit ke EFO
1 Hauling Ore, Pit ke EFO
1 Hauling Ore, Pit ke EFO
1 Pukul 07.00-09.00 Breakdown (Aki pecah), Hauling Ore, Pit ke EFO
Breakdown (Aki bermasalahh)
1 Hauling Ore, Pit ke EFO
Breakdown (Tambah oli)
Breakdown (Overhead & Kampas kopleng)
2 Hauling Ore, Pit ke EFO
2 Pukul 07.00-11.00 Breakdown (Ganti ban), Hauling Ore, Pit ke EFO
Breakdown (Radiator)
Keluar dari site
1 Pukul 07.00-10.30 Breakdown (Kerja rem), Hauling Ore, Pit ke EFO
2 Hauling Ore, Pit ke EFO
2 Hauling Ore, Pit ke EFO
2 Hauling Ore, Pit ke EFO
1 Hauling Ore, Pit ke EFO
Keluar dari site
2 Hauling Ore, Pit ke EFO
2 Hauling Ore, Pit ke EFO
2 Hauling Ore, Pit ke EFO
3 Hauling Ore, Pit ke EFO
15 Hauling Quarry, Maintenance MHR KM 10-8
Keterangan
Shift 1
lan MHR KM 4-6
erator) KM 5, Masih menunggu kesepakatan dengan pemilik alat(Pak Rahman yang masukkan)
A LAMPIA MANDIRI
I MATERIAL IN PIT
MANDIRI
Shift
Total Produksi
2 Total Retase
Bcm Tonase Bcm
0 0.0
43 292.4
0 0.0
0 0
TOTAL PRODUKSI TOP SOIL/WEEK 15
TOTAL PRODUKSI OB/WEEK 15 0.0 0.0
TOTAL PRODUKSI ORE/WEEK 15 168.0 1263.1
TOTAL PRODUKSI QUARRY/WEEK 15 0 0
G ROAD MAINTENANCE
MANDIRI
Shift
Total Produksi
2 Total Retase
Bcm Tonase Bcm
34 340
TOTAL PRODUKSI QUARRY/WEEK 15 254 2540
DELAY
0.23 1.88
DELAY
1.95
G ETO
MANDIRI
NT ACTIVITY
MANDIRI
Keterangan
Shift 1 Shift 2
ecah hose) 13.00-17.00
CK ACTIVITY
MANDIRI
Keterangan
Shift 1 Retase Shift 2
ermasalah), KM 5
)
)
)
)
)
ukan mesin)
kdown (Aki pecah), Hauling Ore, Pit ke EFO
salahh)
i)
& Kampas kopleng)
UIPMENT ACTIVITY
MANDIRI
Keterangan
Shift 2
ng masukkan)
Total Produksi
Keterangan TOTAL PRODUKSI BCM
Tonase
PRODUKSI OB/MONTH 0.0
0.0 PRODUKSI ORE/MONTH 1263.1
526.3
0.0
0.0
TOTAL PRODUKSI OB 40639
0.0 TOTAL PRODUKSI ORE 6032
2273.6
0.0
Total Produksi
Keterangan TOTAL PRODUKSI QUARRY BCM
Tonase
612 Maintance MHR PRODUKSI QUARRY/MONTH 4560
4572 TOTAL PRODUKSI QUARRY 57500
BREAKDOWN
BREAKDOWN 100.00%
Keterangan :
Total dome yang ada di EFO adalah 6 dome
Total tonase 4050
EQUI
DUMP
SUPPORTING
100.00%
100.00%
MONITORING EFO
PT. CITRA LAMPIA MANDIRI
Worktime plan : 9 jam ( sementara baru berjalan 1 shift ) = 266 jam pkl 07.00 sd 17.00 ( Rencana 2 Shift masih menunggu Lighti
Tolerance Breakdown 42 jam = 5 Hari kerja
Worktime plan : 9 jam ( sementara baru berjalan 1 shift ) = 266 jam pkl 07.00 sd 17.00 ( Rencana 2 Shift masih menunggu Lighti
Tolerance Breakdown 42 jam = 5 Hari kerja
TOLERANCE (HM)
Kode TOTAL BREAKDOWN (HM) MARET KETERANGAN
WT-001 33
WT-002 33
33
33
ANDIRI
IN PIT
24 58.14%
Loading Factor
Tonase/Ret
Vol_BU
0.83 19.60
0.83 17.93
N MHR
Loading Factor
Tonase/Ret
Volume- DT
10 18.00
EAVY EQUIPMENT
100.00%
KETERANGAN
KETERANGAN
KETERANGAN
PT Citra Lampia
Mandiri DAILY REPORT PT. CITRA LAMPIA MANDIRI
Shift
Tanggal Total Produksi
BLOCK 1 2
Hari Tanggal Bulan Tahun Week Retase Tonase Retase Bcm Bcm
0 0.0 0.0
Rabu 4 April 2018 14 Pit A
5 89.6 49.8
0 0.0 0
Daily Target produksi Aktual produksi ( % )
Material BCM Material BCM 0.0
OB 4980 OB 0.00% 0.0
ORE 1815 ORE 0.00% 0
Aktual produksi OB 0.00% & Ore 0.00% disebabkan kegiatan produksi baru berjalan 1 shif
Jumlah 4 Exca maintenance stockpile, Striping OB & Loading Ore, 1 Dozer Striping OB, 5 DT Hauling Ore
Kegiatan Hauling DT berupa pemindahan Ore dari ETO ke EFO
Kegiatan dimulai pukul 07.00-17.00
DELAY B
Tanggal
WAITING
Hari Tanggal Bulan Tahun Week Work Time RAIN INSTRUCTION SOCIAL ISSUE PRESTART TROUBLE
DELAY B
Tanggal
WAITING
Hari Tanggal Bulan Tahun Week Work Time RAIN INSTRUCTION SOCIAL ISSUE PRESTART TROUBLE
Tonase
No Tanggal Masuk Dome Retase By Survey KETERANGAN
Retase Tonase Bcm Tonase
1 Monday, February 05, 2018 Dome A-1 15 229.5 142.82 214.23
2 Monday, February 05, 2018 Dome A-2 15 229.5 109.56 164.34
3 Monday, February 05, 2018 Dome A-3 15 229.5 102.66 153.99
4 Tuesday, February 06, 2018 Dome A-4 15 229.5 101.72 152.58
5 Tuesday, February 06, 2018 Dome A-5 15 229.5 113.58 170.37
6 Thursday, February 08, 2018 Dome A-6 15 229.5 104.93 157.395
7 Thursday, February 08, 2018 Dome A-7 15 229.5 102.32 153.48
8 Thursday, February 08, 2018 Dome A-8 15 229.5 98.03 147.045
9 Thursday, February 08, 2018 Dome A-9 15 229.5 98.28 147.42
10 Friday, February 09, 2018 Dome A-10 15 229.5 98.67 148.005
11 Friday, February 09, 2018 Dome A-11 15 229.5 88.52 132.78
12 Saturday, February 10, 2018 Dome A-12 15 229.5 134.68 202.02
13 Saturday, February 10, 2018 Dome A-13 15 229.5 121.22 181.83
14 Saturday, February 10, 2018 Dome A-14 15 229.5 110.72 166.08
15 Saturday, February 10, 2018 Dome A-15 15 229.5 106.98 160.47
16 Saturday, March 17, 2018 Dome A-17 15 268.92 164.56 246.84
17 Saturday, March 17, 2018 Dome A-18 15 268.92 150.64 225.96
18 Saturday, March 17, 2018 Dome A-19 15 268.92 155.31 232.965
19 Tuesday, March 27, 2018 Dome A-21 23 412.344 246.78 370.17
20 Wednesday, March 28, 2018 Dome A-22 15 268.92 177.42 266.13
21 Wednesday, March 28, 2018 Dome A-23 15 268.92 186.51 279.765
22 Wednesday, March 28, 2018 Dome A-24 15 268.92 183.48 275.22
23 Wednesday, March 28, 2018 Dome A-25 15 268.92 173.64 260.46
24 Wednesday, March 28, 2018 Dome A-26 15 268.92 160.23 240.345
25 Thursday, March 29, 2018 Dome A-27 15 268.92 178.77 268.155
26 Thursday, March 29, 2018 Dome A-28 10 179.28 113.59 170.385
Total 393 6454.404 3525.62 5288.43
Keterangan :
Nama dome direvisi berdasarkan Area PIT ( mis : PIT A - penomoran Dome menjadi A-01, Dome A-02)
Kadar Dome Rata-rata adalah hasil perhitungan Dome A-1 sampai Dome A-15
Material
No. Equipment Kode
Shift 1 Shift 2 Shift 2
1 KOBELCO 200 EXC-01 OB
2 KOBELCO 200 EXC-02 Quarry
3 KOMATSU 200 EXC-03 Quarry
4 SANY 215 EXC-04 Quarry
5 SANY 215 EXC-05 OB
6 SANY 215 EXC-09 OB
7 HITACHI EXC-11 OB
8 KOBELCO 200 EXC-13 OB
9 KOMATSU 200 EXC-14
10 KOBELCO 200 EXC-15 OB
11 KOBELCO 330 EXC-17 Ore
12 KOBELCO 330 EXC-18 Quarry
13 KOBELCO 330 EXC-19 Quarry
14 DOZER-D68ESS DZ-01 OB
15 SAKAI CT-01
16 HAMM CT-02 Quarry
17 KOMATSU GD405A GD-01 Quarry
Keterangan :
1 unit Bomag Breakdown
5 Exca Standby (Diberhentikan oleh pemilik alat)
Material
No. Equipment Kode
Shift 1 Shift 2 Shift 2 Shift 1 Shift 2
1 ISUZU DT-001 Dikeluarkan oleh pemilik alat
2 HINO DT-002 Dikeluarkan oleh pemilik alat
3 ISUZU DT-003 Dikeluarkan oleh pemilik alat
4 HINO DT-004 Dikeluarkan oleh pemilik alat
5 ISUZU DT-005 Dikeluarkan oleh pemilik alat
6 ISUZU DT-006 Breakdown (Ganti Kampas), KM 5
7 ISUZU DT-007 Standby (No Operator)
8 NISSAN DT-008 Standby (No Operator)
9 HINO DT-012 Standby (No Operator)
10 DT-013 Quarry Hauling Quarry, Maintenance Jetty
11 DT-014 Quarry Hauling Quarry, Maintenance Jetty
12 DT-015 Quarry Hauling Quarry, Maintenance Jetty
13 DT-016 Quarry Standby (No Operator)
14 DT-017 Quarry Hauling Quarry, Maintenance Jetty
15 DT-018 Quarry Standby (No Operator)
16 DT-019 Quarry Hauling Quarry, Maintenance Jetty
17 DT-020 Quarry Hauling Quarry, Maintenance Jetty
18 DT-021 Quarry Hauling Quarry, Maintenance Jetty
19 DT-022 Quarry Hauling Quarry, Maintenance Jetty
20 DT-023 Quarry Standby (No Operator)
21 DT-024 Quarry Hauling Quarry, Maintenance Jetty
22 DT-025 Quarry Hauling Quarry, Maintenance Jetty
23 DT-026 Quarry Hauling Quarry, Maintenance Jetty
24 DT-027 Quarry Hauling Quarry, Maintenance Jetty
25 DT-028 Quarry Hauling Quarry, Maintenance Jetty
26 DT-029 Quarry Hauling Quarry, Maintenance Jetty
27 DT-9436 Ore Hauling Ore, ETO ke EFO
28 DT-9128 Ore Hauling Ore, ETO ke EFO
29 DT-9165 Ore Hauling Ore, ETO ke EFO
30 DT-9469 Ore Hauling Ore, ETO ke EFO
31 DT-9141 Ore Hauling Ore, ETO ke EFO
Keterangan :
1. 1 Unit Breakdown (Ganti Kampas) 4. DT-9436, DT-9128, DT-9165, DT-9469, DT-9141 belum diberi penomoran ID, pencatatan masih me
2. 6 Unit Standby (Diberhentikan oleh pemilik)
3. 5 Unit dikeluarkan oleh pemilik alat
Lokasi
No. Equipment Kode
Shift 1 Shift 2
1 DYNA 130 HT WT-001 KM 5
2 DYNA 115 ET WT-002
3
4
MONITORI
PT. C
Equipment Plan
Total Produksi PIT ACTIVITY
Keterangan TOTAL PRODUKSI BCM PC 200 PC 300
Tonase OB REMOVAL 1 3
PRODUKSI OB/MONTH 0.0 ORE GETTING 3 1
0.0 PRODUKSI ORE/MONTH 0.0 A. HAULING PIT-ETO 2
89.6 B. HAULING ETO-EFO 2 1
0.0 SPARE
TOTAL PRODUKSI OB 40639
0.0 TOTAL PRODUKSI ORE 4769 Loading Factor
PC 300 Density
0.0 n-BU
0.0 OB 1.64 5
ORE 1.5 5
Keterangan :
Fill Factor : 1.2 V1 plan : 20 km/jam
SR : 3 V2 plan : 25 km/jam
Catatan : Kondisi MHR banyak tikungan dan penurunan sehingga
MONITORIN
E PT. C
Equipment Plan
MHR ACTIVITY
MHR ACTIVITY
PC 200 PC 300
Total Produksi
Keterangan TOTAL PRODUKSI QUARRY BCM MHR MAINTANANCE 1 1
Tonase Support (WT-Unit) 5 Unit
1026 Maintance MHR PRODUKSI QUARRY/MONTH 1090 Keterangan :
1962 TOTAL PRODUKSI QUARRY 54030 V WT = 5 km/jam , radius 11 km/hari
V Grader = 4 km/jam , radius 10.5 km/hari
Catatan : Kondisi MHR banyak tikungan dan penurunan
DUMP TRUCK
BREAKDOWN
NT
TROUBLE; 22.31%
BREAKDOWN
Tonase
KETERANGAN No Tanggal Masuk Dome Asal Dome Retase
Retase
1 Thursday, March 22, 2018 AA-1, Subload 1 Dome A-16 & A-20 32
2 Wednesday, April 04, 2018 AA-1, Subload 2 Dome A-19 5
3
4
5
6
7
8
9
10
11
12
13
14
Total 37
Keterangan :
1 Dome di EFO terdiri dari 4 Subload
Keterangan : MA unit minimal 85% Worktime plan : 9 jam ( sementara baru berjalan 1 shift ) = 266 jam p
Tolerance Breakdown 42 jam = 5 Hari kerja
UNIT YANG MELEBIHI TOLERANSI HM BREAKDOWN AKAN DIBUATKAN BERITA ACARA REKOMENDASI ALAT YANG HARUS DIKELUARKA
Keterangan : MA unit minimal 85% Worktime plan : 9 jam ( sementara baru berjalan 1 shift ) = 266 jam p
nomoran ID, pencatatan masih menggunakan nomor plat Tolerance Breakdown 42 jam = 5 Hari kerja
UNIT YANG MELEBIHI TOLERANSI HM BREAKDOWN AKAN DIBUATKAN BERITA ACARA REKOMENDASI ALAT YANG HARUS DIKELUARKA
4
40 1 5 13.95%
9
HEAVY EQUIPMENT
ime; 44.15%
NO OPERATOR; 45.20% Work Time; 45.20%
WAITING INSTRUCTION;
TROUBLE; 6.33% 3.28%
ORING EFO
AMPIA MANDIRI
Tonase
Grade %
Retase By Survey KETERANGAN
Bcm Tonase Bcm Tonase Ni Fe
318.72 478.08 2.127 21.131
49.8 74.7
April KETERANGAN
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
ru berjalan 1 shift ) = 266 jam pkl 07.00 sd 17.00 ( Rencana 2 Shift masih menunggu Lighting Tower )
KDOWN MONITORING
AMPIA MANDIRI
KETERANGAN
TOLERANCE (HM) April
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
43
43
43
43
43
ru berjalan 1 shift ) = 266 jam pkl 07.00 sd 17.00 ( Rencana 2 Shift masih menunggu Lighting Tower )
T BREAKDOWN MONITORING
AMPIA MANDIRI
TOLERANCE (HM)
MARET KETERANGAN
33
33
33
33
21 13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
273