Rincian Anggaran Biaya (Rab) : Pasang Closed Duduk + Instalasi
Rincian Anggaran Biaya (Rab) : Pasang Closed Duduk + Instalasi
Rincian Anggaran Biaya (Rab) : Pasang Closed Duduk + Instalasi
HARGA JUMLAH
NO NAMA BARANG/SPESIFIKASI VOLUME SATUAN SATUAN HARGA
( Rp ) ( Rp )
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan 96.00 m2 2,717.93 260,920.80
2 Bouwplank 40.00 m' 48,199.36 1,927,974.40
JUMLAH 2,188,895.20
II PEKERJAAN PONDASI
1 Galian Tanah Pondasi 46.50 m3 70,870.46 3,295,476.58
2 Pasir Urug 2.33 m3 231,597.16 538,463.40
4 Pondasi Batu Kali 22.32 m3 691,168.50 15,426,880.92
5 Urug Tanah Kembali 21.86 m3 53,152.85 1,161,655.49
JUMLAH 20,422,476.39
III PEKERJAAN BETON
1 Sloof 20 X 15 cm 1.40 m3 3,767,533.14 5,255,708.72
2 Kolom 20 x 20 cm 5.28 m3 3,767,533.14 19,892,574.95
3 Ring Balok 30 x 15 cm 6.66 m3 3,767,533.14 25,091,770.68
3 Plat Lantai t 12 cm 8.64 m3 2,450,267.14 21,170,308.05
JUMLAH 71,410,362.40
IV PEKERJAAN PASANGAN DINDING
1 Pasangan Bata Merah adukan 1pc : 3 psr 372.00 m2 100,963.46 37,558,408.61
2 Plesteran Dinding 744.00 m2 65,638.62 48,835,133.28
JUMLAH 86,393,541.89
V PEKERJAAN ATAP
1 Pasang rangka baja ringan + atap Beton 32.60 m2 255,709.04 8,334,836.16
JUMLAH 8,334,836.16
VI PEKERJAAN PLAFOND
1 Pasang Plafond Akustik 99.00 m2 128,948.40 12,765,892.00
JUMLAH 12,765,892.00
VII PEKERJAAN PENGECATAN
1 Cat Dinding 744.00 m2 26,791.46 19,932,844.75
2 Cat Plafond 99.00 m2 26,791.46 2,652,354.34
JUMLAH 22,585,199.09
VIII PEKERJAAN KERAMIK
1 Pasang Keramik Lantai 30 x 30 cm 106.00 m2 224,530.44
2 Pasang Keramik Lantai 25 x 25 cm Motif 6.00 m2 213,850.44 1,283,102.64
JUMLAH 1,283,102.64
IX PEKERJAAN INSTALASI LISTRIK
1 Pasang Instalasi Titik Lampu 17.00 ttk 158,013.34 2,686,226.78
2 Pasang Saklar Ganda 9.00 bh 160,313.34 1,442,820.06
JUMLAH 4,129,046.84
X PEKERJAAN INSTALASI AIR BERSIH & AIR KOTOR
1 Pasang Kran air wastafel + instalasi 2.00 unit 203,331.70 406,663.39
2 Pasang Kran double shower + instalasi 4.00 unit 335,111.70 1,340,446.78
3 Pasang air panas + instalasi 2.00 unit 385,111.70 770,223.39
4 Pasang Kran air + instalasi 5.00 unit 134,071.70 670,358.48
5 Pasang Closed duduk + instalasi 4.00 unit 3,176,303.77 12,705,215.10
JUMLAH 15,892,907.14
XI PEKERJAAN PINTU dan JENDELA
1 Pasang pintu sliding kaca rangka alumunium 1.00 unit 1,800,482.67 1,800,482.67
2 Pasang pintu kayu swing 4.00 unit 1,685,436.29 6,741,745.18
3 Pasang pintu kayu double swing 1.00 unit 2,765,445.34 2,765,445.34
4 Pasang kusen dan daun jendela alumunium 2.00 unit 1,352,169.34 2,704,338.67
5 Pasang kusen dan daun jendela kayu 5.00 unit 1,330,269.34 6,651,346.68
JUMLAH 8,451,829.35
JUMLAH HARGA A 519,927,707.40
PPN 10% 51,992,770.74
Overhead & profit 15% 77,989,156.11
TOTAL 649,909,634.25
DIBULATKAN 649,909,000.00
Bouwplank /1 m2
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 0.1 149,730 14,973
Pekerja OH 0.1 130,200 13,020
Mandor OH 0.02 174,468 3,489
JUMLAH HARGA TENAGA KERJA 16,509
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Kayu Kaso 5 / 7 (borneo) m3 0.01 1,650,000 19,800
Paku Biasa 2" - 5" Kg 0.02 17,000 340
Kayu Papan 3 / 20 borneo m3 0.01 1,650,000 11,550
JUMLAH HARGA ALAT 31,690
galian tanah /1 m3
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Pekerja OH 0.48 130,200 62,496
Mandor OH 0.048 174,468 8,374
JUMLAH HARGA TENAGA KERJA 70,870
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 70,870
E Overhead & profit 15% x 10,631
F Harga Satuan Perkerjaan (D+E) 81,501
Dibulatkan 81,501
pasir urug /1 m2
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 0.06 149,730 8,984
Pekerja OH 0.12 130,200 15,624
Mandor OH 0.02 174,468 3,489
JUMLAH HARGA TENAGA KERJA 28,097
B BAHAN
Pasir urug m 1.1 185,000 203,500
JUMLAH HARGA BAHAN 203,500
C PERALATAN
JUMLAH HARGA ALAT
Urugan tanah/1 m3
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Pekerja OH 0.36 130,200 46,872
Mandor OH 0.036 174,468 6,281
JUMLAH HARGA TENAGA KERJA 53,153
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
Pekerjaan Beton/1 m3
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang Kayu OH 2.0000 149,730 299,460
Tukang batu OH 0.4250 149,730 63,635
Tukang besi OH 0.5200 149,730 77,860
Pekerja OH 0.5250 130,200 68,355
Mandor OH 0.0263 174,468 4,580
JUMLAH HARGA TENAGA KERJA 513,890
B BAHAN
Kayu Terentang m3 0.4 1,650,000 660,000
Paku Biasa 2" - 5" Kg 1.5 17,000 25,500
Minyak Bekisting Lt 0.4 7,800 3,120
Besi Beton Polos Kg 200 6,850 1,370,000
Kawat Beton Kg 2.25 16,000 36,000
Semen Portland Kg 465 1,639 762,228
Pasir Beton m3 0.62 262,000 162,440
Koral Beton m3 0.8223 285,000 234,356
JUMLAH HARGA BAHAN 3,253,644
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 3,767,533
E Overhead & profit 15% x 565,130
F Harga Satuan Perkerjaan (D+E) 4,332,663
Dibulatkan 4,332,660
Plester Aci /1 m2
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tk. Batu OH 0.1252 149,730 18,746
Pekerja OH 0.2250 130,200 29,295
Mandor OH 0.0080 174,468 1,396
JUMLAH HARGA TENAGA KERJA 49,437
B BAHAN
Semen portland kg 5.4000 1,639 8,852
Pasir m3 0.0280 262,500 7,350
JUMLAH HARGA BAHAN 16,202
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 65,639
E Overhead & profit 15% x 9,846
F Harga Satuan Perkerjaan (D+E) 75,484
Dibulatkan 75,480