RINCIAN ANGGARAN BIAYA ( RAB )

KEGIATAN : RUMAH SPLOW HOUSE


LOKASI : BEKASI
WILAYAH : BEKASI
TAHUN : 2018

HARGA JUMLAH
NO NAMA BARANG/SPESIFIKASI VOLUME SATUAN SATUAN HARGA
( Rp ) ( Rp )
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 Pembersihan Lahan 96.00 m2 2,717.93 260,920.80
2 Bouwplank 40.00 m' 48,199.36 1,927,974.40
JUMLAH 2,188,895.20
II PEKERJAAN PONDASI
1 Galian Tanah Pondasi 46.50 m3 70,870.46 3,295,476.58
2 Pasir Urug 2.33 m3 231,597.16 538,463.40
4 Pondasi Batu Kali 22.32 m3 691,168.50 15,426,880.92
5 Urug Tanah Kembali 21.86 m3 53,152.85 1,161,655.49
JUMLAH 20,422,476.39
III PEKERJAAN BETON
1 Sloof 20 X 15 cm 1.40 m3 3,767,533.14 5,255,708.72
2 Kolom 20 x 20 cm 5.28 m3 3,767,533.14 19,892,574.95
3 Ring Balok 30 x 15 cm 6.66 m3 3,767,533.14 25,091,770.68
3 Plat Lantai t 12 cm 8.64 m3 2,450,267.14 21,170,308.05
JUMLAH 71,410,362.40
IV PEKERJAAN PASANGAN DINDING
1 Pasangan Bata Merah adukan 1pc : 3 psr 372.00 m2 100,963.46 37,558,408.61
2 Plesteran Dinding 744.00 m2 65,638.62 48,835,133.28
JUMLAH 86,393,541.89
V PEKERJAAN ATAP
1 Pasang rangka baja ringan + atap Beton 32.60 m2 255,709.04 8,334,836.16
JUMLAH 8,334,836.16
VI PEKERJAAN PLAFOND
1 Pasang Plafond Akustik 99.00 m2 128,948.40 12,765,892.00
JUMLAH 12,765,892.00
VII PEKERJAAN PENGECATAN
1 Cat Dinding 744.00 m2 26,791.46 19,932,844.75
2 Cat Plafond 99.00 m2 26,791.46 2,652,354.34
JUMLAH 22,585,199.09
VIII PEKERJAAN KERAMIK
1 Pasang Keramik Lantai 30 x 30 cm 106.00 m2 224,530.44
2 Pasang Keramik Lantai 25 x 25 cm Motif 6.00 m2 213,850.44 1,283,102.64
JUMLAH 1,283,102.64
IX PEKERJAAN INSTALASI LISTRIK
1 Pasang Instalasi Titik Lampu 17.00 ttk 158,013.34 2,686,226.78
2 Pasang Saklar Ganda 9.00 bh 160,313.34 1,442,820.06
JUMLAH 4,129,046.84
X PEKERJAAN INSTALASI AIR BERSIH & AIR KOTOR
1 Pasang Kran air wastafel + instalasi 2.00 unit 203,331.70 406,663.39
2 Pasang Kran double shower + instalasi 4.00 unit 335,111.70 1,340,446.78
3 Pasang air panas + instalasi 2.00 unit 385,111.70 770,223.39
4 Pasang Kran air + instalasi 5.00 unit 134,071.70 670,358.48
5 Pasang Closed duduk + instalasi 4.00 unit 3,176,303.77 12,705,215.10
JUMLAH 15,892,907.14
XI PEKERJAAN PINTU dan JENDELA
1 Pasang pintu sliding kaca rangka alumunium 1.00 unit 1,800,482.67 1,800,482.67
2 Pasang pintu kayu swing 4.00 unit 1,685,436.29 6,741,745.18
3 Pasang pintu kayu double swing 1.00 unit 2,765,445.34 2,765,445.34
4 Pasang kusen dan daun jendela alumunium 2.00 unit 1,352,169.34 2,704,338.67
5 Pasang kusen dan daun jendela kayu 5.00 unit 1,330,269.34 6,651,346.68
JUMLAH 8,451,829.35
JUMLAH HARGA A 519,927,707.40
PPN 10% 51,992,770.74
Overhead & profit 15% 77,989,156.11
TOTAL 649,909,634.25
DIBULATKAN 649,909,000.00

BEKASI, 11 APRIL 2018


Dibuat Oleh
TEKNIK SIPIL MERCU BUANA
Pembersihan lahan /1 m2
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Pekerja OH 0.0125 130,200 1,628
Mandor OH 0.00625 174,468 1,090
JUMLAH HARGA TENAGA KERJA 2,718
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 2,718
E Overhead & profit 15% x 408
F Harga Satuan Perkerjaan (D+E) 3,126
Dibulatkan 3,120

Bouwplank /1 m2
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 0.1 149,730 14,973
Pekerja OH 0.1 130,200 13,020
Mandor OH 0.02 174,468 3,489
JUMLAH HARGA TENAGA KERJA 16,509
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
Kayu Kaso 5 / 7 (borneo) m3 0.01 1,650,000 19,800
Paku Biasa 2" - 5" Kg 0.02 17,000 340
Kayu Papan 3 / 20 borneo m3 0.01 1,650,000 11,550
JUMLAH HARGA ALAT 31,690

D Jumlah (A+B+C) 48,199


E Overhead & profit 15% x 7,230
F Harga Satuan Perkerjaan (D+E) 55,429
Dibulatkan 55,420

galian tanah /1 m3
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Pekerja OH 0.48 130,200 62,496
Mandor OH 0.048 174,468 8,374
JUMLAH HARGA TENAGA KERJA 70,870
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 70,870
E Overhead & profit 15% x 10,631
F Harga Satuan Perkerjaan (D+E) 81,501
Dibulatkan 81,501

pasir urug /1 m2
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 0.06 149,730 8,984
Pekerja OH 0.12 130,200 15,624
Mandor OH 0.02 174,468 3,489
JUMLAH HARGA TENAGA KERJA 28,097
B BAHAN
Pasir urug m 1.1 185,000 203,500
JUMLAH HARGA BAHAN 203,500
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 231,597


E Overhead & profit 15% x 34,740
F Harga Satuan Perkerjaan (D+E) 266,337
Dibulatkan 266,300

Pondasi Batu Kali /1 m3


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tk. Batu OH 0.1714 149,730 25,668
Pekerja OH 0.2143 130,200 27,900
Mandor OH 0.0107 174,468 1,869
JUMLAH HARGA TENAGA KERJA 55,437
B BAHAN
Batu Belah 15 / 20 m3 1.2 225,000 270,000
Semen Portland Kg 136 1,639 222,931
Pasir Pasang m3 0.544 262,500 142,800
JUMLAH HARGA BAHAN 635,731
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 691,169
E Overhead & profit 15% x 103,675
F Harga Satuan Perkerjaan (D+E) 794,844
Dibulatkan 794,840

Urugan tanah/1 m3
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Pekerja OH 0.36 130,200 46,872
Mandor OH 0.036 174,468 6,281
JUMLAH HARGA TENAGA KERJA 53,153
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 53,153


E Overhead & profit 15% x 7,973
F Harga Satuan Perkerjaan (D+E) 61,126
Dibulatkan 61,120

Pekerjaan Beton/1 m3
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang Kayu OH 2.0000 149,730 299,460
Tukang batu OH 0.4250 149,730 63,635
Tukang besi OH 0.5200 149,730 77,860
Pekerja OH 0.5250 130,200 68,355
Mandor OH 0.0263 174,468 4,580
JUMLAH HARGA TENAGA KERJA 513,890
B BAHAN
Kayu Terentang m3 0.4 1,650,000 660,000
Paku Biasa 2" - 5" Kg 1.5 17,000 25,500
Minyak Bekisting Lt 0.4 7,800 3,120
Besi Beton Polos Kg 200 6,850 1,370,000
Kawat Beton Kg 2.25 16,000 36,000
Semen Portland Kg 465 1,639 762,228
Pasir Beton m3 0.62 262,000 162,440
Koral Beton m3 0.8223 285,000 234,356
JUMLAH HARGA BAHAN 3,253,644
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 3,767,533
E Overhead & profit 15% x 565,130
F Harga Satuan Perkerjaan (D+E) 4,332,663
Dibulatkan 4,332,660

Pekerjaan Plat Lantai /1 m3


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang Kayu OH 2.0000 149,730 299,460
Tukang batu OH 0.4250 149,730 63,635
Tukang besi OH 0.5200 149,730 77,860
Pekerja OH 0.5250 130,200 68,355
Mandor OH 0.0263 174,468 4,580
JUMLAH HARGA TENAGA KERJA 513,890
B BAHAN
Kayu Terentang m3 0.1 1,650,000 165,000
Paku Biasa 2" - 5" Kg 1.5 17,000 25,500
Minyak Bekisting Lt 0.4 7,800 3,120
Besi Beton Polos Kg 135 6,850 924,750
Kawat Beton Kg 2.25 16,000 36,000
Semen Portland Kg 235 1,639 385,212
Pasir Beton m3 0.62 262,000 162,440
Koral Beton m3 0.8223 285,000 234,356
JUMLAH HARGA BAHAN 1,936,378
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 2,450,267
E Overhead & profit 15% x 367,540
F Harga Satuan Perkerjaan (D+E) 2,817,807
Dibulatkan 2,817,800

Pasangan dinding Bata /1 m2


URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tk. Batu OH 0.1114 149,730 16,684
Pekerja OH 0.0343 130,200 4,464
Mandor OH 0.0051 174,468 897
JUMLAH HARGA TENAGA KERJA 22,045
B BAHAN
Bata bh 60.0000 650 39,000
Semen Kg 13.5000 1,693 22,856
Pasir m3 0.0650 262,500 17,063
JUMLAH HARGA BAHAN 78,918
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 100,963
E Overhead & profit 15% x 15,145
F Harga Satuan Perkerjaan (D+E) 116,108
Dibulatkan 116,100

Plester Aci /1 m2
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tk. Batu OH 0.1252 149,730 18,746
Pekerja OH 0.2250 130,200 29,295
Mandor OH 0.0080 174,468 1,396
JUMLAH HARGA TENAGA KERJA 49,437
B BAHAN
Semen portland kg 5.4000 1,639 8,852
Pasir m3 0.0280 262,500 7,350
JUMLAH HARGA BAHAN 16,202
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 65,639
E Overhead & profit 15% x 9,846
F Harga Satuan Perkerjaan (D+E) 75,484
Dibulatkan 75,480

Pasang rangka baja ringan + atap Beton /1 m²


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 0.33 130,200 42,966
Pekerja OH 0.2 130,200 26,040
Mandor OH 0.03 174,468 5,234
JUMLAH HARGA TENAGA KERJA 74,240
B BAHAN
Baja Ringan btg 1.333 68,000 90,644
Genteng Beton m2 1.050 86,500 90,825
JUMLAH HARGA BAHAN 181,469
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 255,709
E Overhead & profit 15% x 38,356
F Harga Satuan Perkerjaan (D+E) 294,065
Dibulatkan 294,000

Pasang plafond akustik /1 m²


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 0.1 149,730 14,973
Pekerja OH 0.06 130,200 7,812
Mandor OH 0.003 174,468 523
JUMLAH HARGA TENAGA KERJA 23,308
B BAHAN
Akustik 60x60 cm lbr 2.78 38,000 105,640
JUMLAH HARGA BAHAN 105,640
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 128,948
E Overhead & profit 15% x 19,342
F Harga Satuan Perkerjaan (D+E) 148,291
Dibulatkan 148,290

Pengecatan dinding dan plafond /1 m²


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tk. Cat OH 0.063 149,730 9,433
Pekerja OH 0.02 130,200 2,604
Mandor OH 0.001 174,468 174
JUMLAH HARGA TENAGA KERJA 12,211
B BAHAN
Plamir kg 0.1 27,000 2,700
Cat Dasar kg 0.1 33,000 3,300
Cat Penutup kg 0.26 33,000 8,580
JUMLAH HARGA BAHAN 14,580
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 26,791
E Overhead & profit 15% x 4,019
F Harga Satuan Perkerjaan (D+E) 30,810
Dibulatkan 30,810

Pasang keramik 30x30cm /1 m²


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 0.175 149,730 26,203
Pekerja OH 0.35 130,200 45,570
Mandor OH 0.0175 174,468 3,053
JUMLAH HARGA TENAGA KERJA 74,826
B BAHAN
Keramik 30x30 m² 1.068 105,000 112,140
Semen PC m² 10.0000 1639.20 16,392
Pasir pasang m² 0.045 262,500 11,813
Semen Warna kg 1.5 6,240 9,360
JUMLAH HARGA BAHAN 149,705
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 224,530
E Overhead & profit 15% x 33,680
F Harga Satuan Perkerjaan (D+E) 258,210
Dibulatkan 258,210

Pasang keramik toilet /1 m²


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 0.175 149,730 26,203
Pekerja OH 0.35 130,200 45,570
Mandor OH 0.0175 174,468 3,053
JUMLAH HARGA TENAGA KERJA 74,826
B BAHAN
Keramik 25x25 m² 1.068 95,000 101,460
Semen PC m² 10.0000 1639.20 16,392
Pasir pasang m3 0.045 262,500 11,813
Semen Warna kg 1.5 6,240 9,360
JUMLAH HARGA BAHAN 139,025
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 213,850
E Overhead & profit 15% x 32,078
F Harga Satuan Perkerjaan (D+E) 245,928
Dibulatkan 245,920

Pas. Instalasi lampu TL /1 ttk


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang Listrik/Intalator OH 0.2 160,510 32,102
Pekerja/Pembantu Instalator OH 0.1 139,390 13,939
Mandor OH 0.005 174,468 872
JUMLAH HARGA TENAGA KERJA 46,913
B BAHAN
Lampu TL + Armatur bh 1 60,000 60,000
Kabel NYM 3 x 2,5 mm² m' 5 8,340 41,700
Pipa listrik 5/8" btg 1 6,000 6,000
Tee Dus bh 1 1,400 1,400
Inbowdus bh 1 1,400 1,400
Isolasi roll 0.2 3,000 600
JUMLAH HARGA BAHAN 111,100
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 158,013
E Overhead & profit 15% x 23,702
F Harga Satuan Perkerjaan (D+E) 181,715
Dibulatkan 181,710

Pas. Instalasi Saklar ganda /1 ttk


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang Listrik/Intalator OH 0.2 160,510 32,102
Pekerja/Pembantu Instalator OH 0.1 139,390 13,939
Mandor OH 0.005 174,468 872
JUMLAH HARGA TENAGA KERJA 46,913
B BAHAN
Saklar Ganda bh 1 62,300 62,300
Kabel NYM 3 x 2,5 mm² m' 5 8,340 41,700
Pipa listrik 5/8" btg 1 6,000 6,000
Tee Dus bh 1 1,400 1,400
Inbowdus bh 1 1,400 1,400
Isolasi roll 0.2 3,000 600
JUMLAH HARGA BAHAN 113,400
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 160,313
E Overhead & profit 15% x 24,047
F Harga Satuan Perkerjaan (D+E) 184,360
Dibulatkan 184,360

Pasang Kran air wastafel + instalasi/1 unit


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 0.038 149,730 5,690
Pekerja OH 0.08 130,200 10,416
Mandor OH 0.017 174,468 2,966
JUMLAH HARGA TENAGA KERJA 19,072
B BAHAN
Kran air unit 1 68,500 68,500
Seal tape bh 0.2 5,200 1,040
instalasi m 4 28,680 114,720
JUMLAH HARGA BAHAN 184,260
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 203,332
E Overhead & profit 15% x 30,500
F Harga Satuan Perkerjaan (D+E) 233,831
Dibulatkan 233,830

Pasang Kran double shower + instalasi /1 unit


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 0.038 149,730 5,690
Pekerja OH 0.08 130,200 10,416
Mandor OH 0.017 174,468 2,966
JUMLAH HARGA TENAGA KERJA 19,072
B BAHAN
Kran double unit 1 315,000 315,000
Seal tape bh 0.2 5,200 1,040
JUMLAH HARGA BAHAN 316,040
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 335,112
E Overhead & profit 15% x 50,267
F Harga Satuan Perkerjaan (D+E) 385,378
Dibulatkan 385,370

Pasang air panas + instalasi /1 unit


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 0.038 149,730 5,690
Pekerja OH 0.08 130,200 10,416
Mandor OH 0.017 174,468 2,966
JUMLAH HARGA TENAGA KERJA 19,072
B BAHAN
Kran air panas unit 1 365,000 365,000
Seal tape bh 0.2 5,200 1,040
JUMLAH HARGA BAHAN 366,040
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 385,112
E Overhead & profit 15% x 57,767
F Harga Satuan Perkerjaan (D+E) 442,878
Dibulatkan 442,870

Pasang Kran air + instalasi /1 unit


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 0.038 149,730 5,690
Pekerja OH 0.08 130,200 10,416
Mandor OH 0.017 174,468 2,966
JUMLAH HARGA TENAGA KERJA 19,072
B BAHAN
Kran dinding ex. TOTO unit 1 115,000 115,000
Seal tape bh 0.2 5,200 1,040
JUMLAH HARGA BAHAN 115,000
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 134,072
E Overhead & profit 15% x 20,111
F Harga Satuan Perkerjaan (D+E) 154,182
Dibulatkan 154,180

Pasang Closed duduk /1 unit


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tukang OH 1.473 149,730 220,552
Pekerja OH 3.80 130,200 494,760
Mandor OH 0.063 174,468 10,991
JUMLAH HARGA TENAGA KERJA 726,304
B BAHAN
Closed duduk Amerika standart unit 1 2,450,000 2,450,000
JUMLAH HARGA BAHAN 2,450,000
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 3,176,304
E Overhead & profit 15% x 476,446
F Harga Satuan Perkerjaan (D+E) 3,652,749
Dibulatkan 3,652,740
Pasang pintu sliding kaca rangka alumunium /1 bh
NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tk. Besi OH 1.9845 149,730 297,139
Pekerja OH 1.9845 130,200 258,382
Mandor OH 0.099225 174,468 17,312
JUMLAH HARGA TENAGA KERJA 572,833
B BAHAN
Daun Pintu alumunium m' 5.8 115,000 667,000
Kaca polos 5 mm m² 1.89 85,000 160,650
Asessoris unit 1 150,000 150,000
Kunci set 1 250,000 250,000
JUMLAH HARGA BAHAN 1,227,650
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 1,800,483
E Overhead & profit 15% x 270,072
F Harga Satuan Perkerjaan (D+E) 2,070,555
Dibulatkan 2,070,550

Pasang pintu kayu swing /1 bh


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tk. Kayu OH 3.2 149,730 479,136
Pekerja OH 1.15 130,200 149,730
Mandor OH 0.03892 174,468 6,790
JUMLAH HARGA TENAGA KERJA 635,656
B BAHAN
Daun Pintu Kayu m' 4.8 95,000 456,000
Multiplek 12 mm lbr 2 144,000 288,000
Engsel pintu bh 3 42,500 127,500
Paku biasa kg 0.2 17,000 3,400
Lem kayu kg 1.2 44,900 53,880
Kunci pintu bh 1 550,000 550,000
Amplas lbr 3 9,000 27,000
JUMLAH HARGA BAHAN 1,049,780
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 1,685,436
E Overhead & profit 15% x 252,815
F Harga Satuan Perkerjaan (D+E) 1,938,252
Dibulatkan 1,938,250

Pasang pintu kayu double swing /1 bh


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tk. Kayu OH 3.969 149,730 594,278
Pekerja OH 3.969 130,200 516,764
Mandor OH 0.19845 174,468 34,623
JUMLAH HARGA TENAGA KERJA 1,145,665
B BAHAN
Daun Pintu Kayu m' 6 95,000 570,000
Multiplek 12 mm lbr 2 144,000 288,000
Engsel pintu bh 3 42,500 127,500
Paku biasa kg 0.2 17,000 3,400
Lem kayu kg 1.2 44,900 53,880
Kunci pintu bh 1 550,000 550,000
Amplas lbr 3 9,000 27,000
JUMLAH HARGA BAHAN 1,619,780
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 2,765,445
E Overhead & profit 15% x 414,817
F Harga Satuan Perkerjaan (D+E) 3,180,262
Dibulatkan 3,180,260

Pasang kusen dan daun jendela alumunium /1 bh


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tk. Besi OH 0.99225 149,730 148,570
Pekerja OH 0.99225 130,200 129,191
Mandor OH 0.0496125 174,468 8,656
JUMLAH HARGA TENAGA KERJA 286,416
B BAHAN
Daun jendela alumunium m' 3.66 115,000 420,900
Kaca polos 5 mm m² 0.96 85,000 81,600
Asessoris unit 1 150,000 150,000
Kunci set 1 250,000 250,000
Kusen set 1 163,253 163,253
JUMLAH HARGA BAHAN 1,065,753
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 1,352,169
E Overhead & profit 15% x 202,825
F Harga Satuan Perkerjaan (D+E) 1,554,995
Dibulatkan 1,554,990

Pasang kusen dan daun jendela kayu /1 bh


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH
(Rp) HARGA
(Rp)
A TENAGA
Tk. Kayu OH 0.99225 149,730 148,570
Pekerja OH 0.99225 130,200 129,191
Mandor OH 0.0496125 174,468 8,656
JUMLAH HARGA TENAGA KERJA 286,416
B BAHAN
Daun jendela kayu m' 4.2 95,000 399,000
Kaca polos 5 mm m² 0.96 85,000 81,600
Asessoris unit 1 150,000 150,000
Kunci set 1 250,000 250,000
Kusen set 1 163,253 163,253
JUMLAH HARGA BAHAN 1,043,853
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 1,330,269
E Overhead & profit 15% x 199,540
F Harga Satuan Perkerjaan (D+E) 1,529,810
Dibulatkan 1,529,810