Slab Cranked Bar (From Centre) Extra Bars (From Edge) C/C Length Edge (0.15) Mid/ Cantilever (0.2 5) Edge (0.15) Mid/ Cantilever (0.3)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

slab

cranked bar (from centre) extra bars (from edge)

mid/
C/C edge( cantilever(0.2 edge( mid/ cantilever
length 0.15) 5) 0.15) (0.3)
12.75 1.913 3.1875 1.913 3.825
0 0 0 0

2.9375
LENGTH 0.25L
14.58 3.645
REGAN
FOOTING CONCRETE

LENGTH WIDE HT NO.


7 7 1.5 1
6.5 6.5 1.5 2
6 6 1.5 2
5.5 5.5 1.5 2
5 5 1.5 2
TOTAL CONCRETE
TOTAL
73.5
126.75
108
90.75
75
474

CEMENT 94.8 BAG


SAND 237 CUFT. 3.646154 TRIP
AGGREGAT 355.5 CUFT. 5.469231