Wish List To Complete The Project Upto June 2018 Description of The Work Remarks Reply
Wish List To Complete The Project Upto June 2018 Description of The Work Remarks Reply
15 Third party The client and Engineer to have We shall inform client about the
liasonsing resourceful team to resolve issues with M/s JISL recommendations about
agencies like Electric board, Gas bodies the competency of the staff. It is
, Road authority , telecom cables, city reminded once again to mobilize a
water authority, work permit related competent staff from M/s JISL so
that he can plan and obtain the
authority , tax exemption authority , etc
required approvals instead of
since all this causes delay in work blaming.
16 Claims for extra We notice hesitation in providing As a consultant we only not
work approvals approvals for extra work which is due to hesitate, we feel embarrassed by
variationsgiven by Enginner instructions. the false claims by our Indian
This should be fast tracked. The payment Exporter M/s JISL. Actual claims
( towards installtion) for extra pipe as per the contract and site
supplied for conditions shall be recommended
29 Km of HDPE to be made since we and paid.
have no instruction till date for installtion
of the same
17 Salasala 40 Km The design is being submitted, request This shall be approved on the
HDPE laying work for faster approval of the same so that it receipt on the drawings from M/s
approval can be executed fast JISL.
18 Pending drawings Air valve chamber, The revised drawings were
approval revised during the second week of
Dec 17 and was communicated
on 22nd January 2018.
19 Reroute survey as per the coordinates given by UDSM for We received the request from M/s
approval lot 4 pipeline reroute in forest area from CH JISL vide letter no 868 dated 11th
1340m to CH Jan 2018 and the same was
2400m total length is 1060 m & Width approved on 17th January 2017
should be enough for the truck pass, vide our letter number No:
pipe laying on the side of trench, trench, WAP/COMML/TAN/18/03/55.
excavated soil stacking, total width 8m
approx.