FAST TRACK LNG PROJECT - TIMELINE OF ACTIVITIES CARRIED OUT AFTER COMMERCIAL EVALUATION

OF PROPOSALS

Date Activity
26 November 2013 LNG commercial evaluation presented to SSSGC Board
26 November 2013 Meeting of SSGC Management with Mr. Sheikh Imranul Haque, CEO M/s. Elengy
Terminal Pakistan Limited (ETPL)
26 November 2013 Letter issued to the successful bidder M/s. Elengy Terminal Pakistan Limited for
LSA negotiations in Islamabad
27 November 2013 Meeting of PD with Secretary MP&NR
27 November 2013 LSA (LNG Services Agreement) discussions between SSGC/ISGS/QED and ETPL
28 November 2013 LSA discussions between SSGC/ISGS/QED and ETPL
28 November 2013 Meeting of PD with MP&NR to discuss issues raised by ETPL
29 November 2013 Meeting of SSGC Management to discuss the issues raised by ETPL
30 November 2013 LSA forwarded to SNGPL for their review and comments alongwith letter for
sharing of project risks and liabilities
2 December 2013 Meeting with ETPL for highlighting issues related to pipeline construction,
terminal setup and allied facilities for charting course of action
2 December 2013 Meeting with SNGPL regarding their observations on LSA
3 December 2013 Minutes of meeting with ETPL prepared and issued
3 December 2013 Letter to Ministry for highlighting financial risks associated with the project