Professional Documents
Culture Documents
Hulsey Cruz-Procedure
Hulsey Cruz-Procedure
where I am mentored with the lead project manager engineer, Mr. Ezra Richards, on a
needs and expectations of the project. I have blacked out the actual budget number for
confidentiality purposes. After the project outline is my continued research into a broader
Project Information
Currently, there is no adequate Substation backup plan for the Portland downtown core
network distribution systems sourced from Stephens and Canyon Substations. In
addition, much of the equipment at Stephens Substation – which currently serves
approximately 25 MVA of the load in the downtown core area – is antiquated and/or
non-standard and PGE does not carry an inventory of system spares to replace this
equipment.
The Marquam Substation project will mitigate the reliability concerns associated with
Stephens Substation serving the Portland downtown core area; will provide adequate
capacity for back-up service to the existing core area network systems served from
Canyon Substation, and will provide future capacity to align with the growth of the South
Waterfront District (currently served from Urban Substation).
The Marquam Substation project spans beyond design and construction of the
Marquam site. Other substations and transmission lines will be interconnected with
Marquam Substation, including Eastport, Harrison, and Urban substations. PacifiCorp
Substation's, Harrison PACW and Lincoln PACW, will also be affected by the Marquam
project. The project duration will span four-five years and is anticipated to be complete
in spring 2019.
The designs for Marquam Substation and the Substation 13kV underground feeder get-
a-ways were completed and the construction contract was awarded to Black & Veatch
Construction Inc. Harrison Substation and the gas insulated switchgear was completed
and energized in 2016. Permitting activities for Marquam and Eastport Substation were
completed in 2016. All major equipment for Marquam Substation has been ordered and
will be receipted in 2017. Engineering designs for the new Harrison-Marquam 115kV
transmission line are complete and have been sent out to bid in 2016. The design for
core area distribution system cutover from Stephens to Marquam is near completion.
In 2017, the work associated with building Marquam Substation and the 13kV feeder
get-a-ways sourced from Marquam will continue. The new Harrison-Marquam 115kV
transmission line pathway under the I-5 freeway will be constructed to the Marquam site
with the installation of the transmission cable occurring in mid-late 2017.
Construction will take place to route the Marquam 13kV distribution feeders from the
Marquam site to the downtown core area beginning in early 2017 with completion in
2018/2019.
The new Marquam 115/13kV GIS Substation in downtown Portland will complete in
2018 and will relocate the downtown core area network distribution system from
Stephens Substation on the east side of the Willamette River to the new Marquam site
on the west side of the river. The project will increase T&D reliability in the Portland
downtown core by standardizing to a13kV distribution system which will provide service
redundancy for the core area network as well as provide future capacity and
redundancy to the South Waterfront District.