Professional Documents
Culture Documents
Oregon Pipeline Management Project: Source Drawing Queries and Reports
Oregon Pipeline Management Project: Source Drawing Queries and Reports
Oregon Pipeline Management Project: Source Drawing Queries and Reports
Kelly Dell,
GIS and Geospatial Management Program Coordinator
Niagara College
135 Taylor Road
Please find within this report the completed source drawing queries and reports assignment.
For this deliverable, it was required that 3 provided layers of data be attached to an AutoCAD
drawing so that they could be queried by material and size. The purpose of this deliverable was
to conduct a cost analysis using the queries created for each of the pipe sizes. These cost
analyses would be based on the differences in size and materials for pipelines, as each required
a different cost.
There were no major issues encountered during the completion of this deliverable, the results
of the queries were exported into ArcGIS in order to enhance the quality and efficiency of
making a final map layout for this project.
Please contact me if there are any issues with the contents of the report and I will be happy to
assist with them.
Regards,
A.V./
4.0 Background
The city of Springfield, Oregon has request that an analysis be conducted on a set of provided
sewer pipelines data for a cost analysis. This analysis is to gain an estimate for the costs of
maintaining sewer pipelines in the area. Each pipeline has a series of different sizes, and thus
will cost a different amount to maintain. This is where the user will conduct a series of queries
in order to determine a summary of the costs of maintaining the pipelines. There are two
materials of pie being examined for this analysis: PVC and concrete. Each material has a range
of different sizes which will be separately queried to determine the cost to maintain each.
The data provided by the city of Springfield, Oregon consists of the following:
San_Sewer.dwg
Streets.dwg
Taxlots.dwg
These data were retrieved from the X: drive under the resources folder and were attached to
the AutoCAD by creating a custom alias.
This alias was created manually and refers to the X: drive in which the data was located; the data
could now be attached to the drawing. The three files provided (San_Sewer, Streets, and Taxlots)
Now that the material had been established a series of queries were created with the sizes of the
pipes changing with each, as larger pipe sizes cost more to maintain. In order to define the first
query, the definition expression for size was changed to “= 6” so that only pipes with a size of 6
could be selected. The colours were changed so that different selection could be visible and
differentiated. A report was next established to include the material, size and length of the
pipeline. This report would output a text file which would later be used in Microsoft Excel to
GISC9315-D3: Source Drawing Queries / Reports
Prepared by: Andrew Vsetula, B.A. 04/16/2018
8|Page
calculate final costs once the selection was completed. Now the query was ready to be executed,
a report was executed to obtain the text file, and the draw tool was also executed so that the
results would be displayed. Once the results were verified, the remaining queries of PVC type
could be created.
To create the remaining queries for this section, the above steps were repeated with the size
parameter, colour, and report filename being the only parameters which needed to be changed.
This was repeated until all of the required query results were obtained. Once all of the queries
were computed, the results were exported to an ESRI shapefile so that they could be analyzed
and placed on a proper map layout using ArcGIS. This final layout can be found in Appendix A.
Each of the created reports would be later loaded and combined using excel to determine final
costs. An example query, as well as the results in AutoCAD can also be seen in Figure 4 below.
The AND feature would ensure that the parameters were selection collectively rather than
separately. The colours were changed and the reports were created using appropriate file names
just as in the previous set of queries. All of the steps were then repeated as before with only the
range of sizes needing to be changed. A final map layout was also created using the same practice
as before, and can be found in Appendix B.
These result were found by loading each of the reports into Excel individually and then copying
them into a single Excel spreadsheet. The different resulting pipeline costs were individually
calculated based on the size differences. First the total length for each size of pipe was calculated
using the SUM function, and the total cost for each size was calculated by multiplying the cost
per foot by the total length. All of the results were then summarized in the table above.
7.2 Conclusions
Upon completion of this project, all of the report results were summarized in an MS Excel table
where the total quantities and cost values were calculated. The user has gained sufficient
experience in attaching source data to AutoCAD drawings and querying various types of
information based on different properties. Additionally more experience has been gained in
exporting data into different file formats, as well as creating reports which can be used for data
management.
7.3 Recommendations
The summary table which has been created from the outputted reports has been finalized to
display the results of the analysis. The final total costs for relining the PVC sewer pipelines
accumulated to $616,962.91, while the final cost for relining concrete pipelines came to
$75,697.37. Overall it was found that the cost of relining PVC pipelines was much greater than
that of concrete. It is worth noting however that there was a greater quantity of concrete
pipelines (191) compared to the number of PVC pipelines (143). This could also have an impact
on the final cost of relining the pipelines due to transportation of resources and labour. It
should also be noted that the final cost estimates summarized in this report are based on that
of the exact material length and do no account for additional lengths which may be required as
pipe materials do not always come in the exact measurements required for a project.
If the City of Springfield was to conduct a full relining of all of the suggested pipelines for both
PVC and concrete materials, the total cost would accumulate to approximately $692,660.28.
Figure 8: Final map summarizing all materials used for this project