NELSON
May 15, 2018
Rob D. Daake
‘Abernathy Roeder Boyd & Hullett P.C.
P.O, Box 1210
McKinney, Texas 75070
File: McKinney Independent School District Stadium [Nelson File No: 20125
McKinney, Texas
Dear Mr. Daake:
Nelson Forensics, LLC (Nelson) was authorized by Mr. Rob Dake with Abernathy Roeder
Boyd & Hullett P.C. (client) to investigate cracking concrete flatwork at the concourse level
of the McKinney Independent School District Stadium in McKinney, Texas. Nelson was
tasked with determination of the potential cause(s) of the distress, as well as the effectis) of
the distress as related to strength and serviceability of the evaluated stadium components.
This initial report is preliminary in nature, and the findings presented herein are based upon
Nelson's preliminary investigation, a limited document review, as well as the results of an
initial testing protocol. Nelson reserves the right to supplement or change the opinions
presented herein upon further investigation, document review, testing, and/or analysis.
Nelson's scope of work, observations, discussion, analysis, and opinions presented in this
report pertain to the home side concourse level flatwork.
Scope of Work
Nelson performed a preliminary review of the received information pertaining to the
stadium including, but not limited to, construction drawings, specifications, concrete mix
designs, concrete field reports, and concrete materials test reports. Nelson observed the
exposed portions of the top surface of the home side concourse level concrete flatwork.
Nelson performed Ground Penetrating Radar (GPR) surveys at select locations of observed
distress. Nelson developed a distress map indicating locations, lengths, and approximate
widths of cracks in the home side concrete flatwork at the concourse level, as well as
photographically documented observed distress and general conditions.Preliminary Distress Evaluation Project Name: McKinney Independent School District Stadium
May 15, 2018 Nelson File No.: 20125
Page 2
The stadium is a multi-purpose facility, which incorporates a community event center at its
southern extent. The stadium consists of four distinct levels. The home side concourse
level is the subject of this report, and is the main assembly level for the stadium. Only
concourse areas with exterior exposure were evaluated by Nelson. Additional areas of the
concourse level enclosed within concession and service buildings were not subject to the
initial phase of Nelson's investigation.
Description of Home Side Concourse Concrete Flatwork
The flatwork at the home side of the concourse level is constructed of conventionally
reinforced concrete slabs-on-grade and an elevated, conventionally reinforced,
cast-in-place one-way concrete slab.
Observations
Nelson observed numerous cracks throughout the concourse level flatwork at the home
side of the stadium. The widths of the cracks varied throughout; however, they were
regularly observed to be greater than .02" in width. Concrete joints were located at the
home side's concourse flatwork. Joint spacing varied up to approximately 20' apart, and
joint depths were measured to not exceed approximately 3/4" in depth.
The observed joint spacing was irregular. For example, rectangular areas measuring
approximately 100 square feet were located directly adjacent areas measuring
approximately 400 square feet. Furthermore, numerous joints did not intersect to form
rectangular areas. Rather, some joints form trapezoidal or, in some instances, triangular
shaped areas, An illustration depicting the extent of the observed concourse level cracking;
as well as the locations of the concrete joints, test areas, and a general layout of the
stadium's concourse level is attached to this report.
Concourse Flatwork: Discussion and Analysis
Concrete shrinks as it cures, and thus steel reinforcement is provided within a concrete
cross section to control volumetric contraction due to the shrinkage. When shrinkage
reinforcement is inadequate or when the shrinkage of the concrete is excessive, the internal
tensile stresses in the shrinking concrete cross-section exceed the tensile capacity of the
material, and fractures develop in the concrete. In addition to shrinkage reinforcement,
joints are provided in on-grade concrete flatwork to control the location of cracking that
does occur.Preliminary Distress Evaluation Project Name: McKinney Independent School District Stadium
May 15, 2018 Nelson File No.: 20125
Page 3
The stadium's construction drawings, prepared by Stantec, specify the concrete joints for
the on-grade flatwork at the home side of the concourse. Detail B on sheet $302 of the
construction drawings indicates that joints shall be constructed with a maximum spacing
of 10 feet on-center in each direction where the concrete slab is exposed. Detail B further
indicates that the concrete joints shall be constructed with a depth of one-quarter of the
overall depth of the slab. Which, for the flatwork at the home side concourse level, equates
toa minimum required joint depth of 1 1/4", significantly greater than the greatest measured
depth of approximately 3/4”.
The American Concrete Institute (ACI) is the construction industry authority on concrete
design and construction. ACI's document 224.3R-95: Joints in Concrete Construction
states:
Joints should be spaced so that the slab on grade is divided into small rectangular
areas. Squares are preferred, but the slab geometry may dictate otherwise. As a
general rule, ratios of the long to short side should not exceed 1.25 to 1.5... Odd
shapes should be avoided, but if they cannot be avoided, re-entrant comers should
be reinforced to limit the cracking at these locations.
Comparing the as-built layout of the joints to the foregoing criteria, many of the concrete
joints at the home side concourse flatwork were constructed in direct conflict with the
construction documents and best industry practices.
To further investigate the concourse flatwork, Nelson obtained ground penetrating radar
(GPR) measurements at select concourse level locations using a Geophysical Survey
Systems, Inc, (GSS!) StructureScan™ Mini HR. The GPR evaluation was performed to
investigate the locations of reinforcing steel within the concourse level flatwork at select
locations where concrete cracking was observed.
Nelson evaluated the concourse level at 11 locations on the home side flatwork as indicated
on the attached illustration, The GPR survey revealed that the majority of the evaluated
steel reinforcing bars were uniformly spaced and located at 2 uniform depth below the
surface of the concrete surface, in general conformance with the construction documents
and standard practice. However, multiple GPR anomalies occurred at a portion of the
home side concourse flatwork, near the main entryway, that are coincident with slab cracks
in the flatwork, These anomalies are consistent with the existence of utility conduits within
the concrete slab placement; however, further evaluation is necessary to confirm these
findings. To date, Nelson has been unable to identify any drawing or detail for in-slab
utility conduits within the received construction documents. The presence of in-slab
conduit in a relatively thin slab on grade increases the susceptibility for cracking at the
concrete cross section reduced by the area of the conduit within. Further, Nelson's GPR
survey did not reveal in-slab diagonal reinforcing at reentrant corners.Preliminary Distress Evaluation Project Name: Mckinney Independent School District Stadium
May 15, 2018 Nelson File No 20125
Page 4
‘The observed pervasive presentation of cracking is consistent with the accumulation of
tensile forces caused by restrained shrinkage. The tensile stresses that developed in the
concrete due to shrinkage have exceeded the tensile capacity of the concrete. The joints
in the concrete were constructed improperly and in direct conflict with the construction.
documents and best industry practices, which resulted in the manifestation of the
shrinkage cracking within the field of the concrete panels. Had the joints been properly
constructed, the cracks would have occurred at the joint locations, which is expected
behavior for concrete slabs-on-grade. An isolated portion of the cracks at the home side
concourse flatwork may be attributable to in-slab conduits or similar as revealed during
Nelson's GPR evaluation; however, additional testing is necessary to confirm these
findings.
The cracking at the home side concourse slab-on-grade is excessive and unsightly;
however, does not presently compromise the strength of the slabs or otherwise pose a life
safety concern. However, the cracks will allow water to migrate into the concrete cross
section and influence corrosion of the reinforcing steel. The cracks within the fields of the
flatwork planes will ravel, or widen, at their top surfaces, ultimately causing material loss
and potential tripping hazards. Vehicular traffic from lifts and carts will accelerate these
distress manifestations. The observed cracking poses both serviceability and durability
concerns.
The items observed and documented in this initial report are intended to be representative
of the condition of the concrete slabs at the home side concourse level of the stadium. No
attempt has been made to document the condition of each and every structural and
nonstructural element. Only visible items were observed and documented. The opinions
presented herein are based on site observations, field information and measurements taken,
written and verbal information, and experience, where applicable.
No complete review of this stadium's conformance to current building codes was
performed. This report should not be construed as an assessment of total damages to the
stadium at the time of site observation. In addition to the observed and documented items
of distress, hidden defects may exist that were not readily visible. Also, some damaged
areas may have been previously repaired and, unless otherwise noted, were not visible at
the time of observation. However, these areas may experience future distress. No
representation, guarantee, or warranty as to the future performance of this stadium is made,
intended, or implied.
In the event that additional information becomes available that could affect the conclusions
reached in this preliminary investigation, Nelson reserves the right to review and change
the opinions presented herein if required. This report has been prepared for exclusive use
of the client and its representatives. No unauthorized re-use or reproduction of this report,
in part or whole, shall be permitted without prior written consent.Preliminary Distress Evaluation Project Name: McKinney Independent School District Stadium
May 15, 2018 Nelson File No.: 20125
Page 5
Please do not hesitate to contact us with any questions or concerns.
With kindest regards,
NELSON FORENSICS, LLC
Texas Certificate of Registration F-17167
Pie
Ryan T. Chancey, Ph.D., P.E.
President
Wes OAL
MN ie /to
Nelson: Report2-20125.doc.