Professional Documents
Culture Documents
06 Eva 2
06 Eva 2
1,300
Cost Performance Index Performance
1,200 Above Plan
EV
CPI =
AC 1,100
BCWP 1,000
CPI =
ACWP
0,900
0,800
Schedule Performance Index
EV 0,700
Performance
SPI =
PV 0,600 Below Plan
BCWP
SPI = 0,500
BCWS 1 2 3 4 5 6 7 8
CPI 1,000 0,875 0,857 0,915 0,892 0,881 0,867 0,882
SPI 1,000 0,875 0,889 0,843 0,846 0,817 0,816 0,825
EV. CPI and SPI
2.5 2.5
2 2
1.5 1.5
1 1
0.5
0.5
1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8
2.5 1.5
1.5 1
0.5 0.5
1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8
Selamat!
Saya memberi hmm... Sepanjang
5km, dalam 5 bulan,
Anda kontrak
maka akan selesai
“Pembangunan dengan total biaya
Jalan Rel“ baru $5,000
Planned Value (PV)
Total Budget = $ 5,000
Harus selesai dalam 5 bulan
Saya rencanakan setiap 1 track
selesai 1 bulan
Bulan 1 Bulan 2 Bulan 3 Dengan estimated cost of
PV = $1,000 PV = $1,000 PV = $1,000 $1,000./track/bulan
PV setiap bulan = $1,000
Bulan 4 Bulan 5
PV = $1,000 PV = $1,000
Month 1 2 3 4 5
Month 1 2 3 4 5
CONTROL POINT
at Control Point :
PV = $2,000 Planning Progress = 40%
Progress
Status
EV = $1,000 Actual Progress = 20%
Cost
AC = $2,400 Actual Cost Spent = $2,400 Status
The Measurenment
Cost Variance CV = EV - AC
CV = $1,000 - $2,400 = - $1,400
(-) = over budget
Schedule Variance SV = EV - PV
SV = $1,000 - $2,000 = - $1,000
(-) = behind schedule
Cost Performance Index CPI = EV/AC
CPI = $1,000/$1,400 = 0.71
<1 performance of cost not OK
Getting Rp.xx out of every Rp.1
Schedule Performance Index SPI = EV/PV
SPI = $1,000/$2,000 = 0.5
<1 performance of schedule not OK
Progressing at 50% of the rate originally plan
#2 Forecasting
Forecasting
Forecasting includes making estimates or
predictions of conditions in the projects’s
future, based on information and knowledge
available at the time of the forecast
Forecasting:
Estimate at Completion (EAC)
Estimate to Complete (ETC)
New estimates:
ETC = ETCbottom-up
Work performed at the budgeted rate:
ETC = BAC - EV
Considering both SPI and CPI factors:
ETC = [ BAC - EV ] / [ CPIcumulative x SPIcumulative ]
Ratio CPI/SPI = 80/20, 50/50, others
F. Estimate at Completion
EAC is a forecast of the most likely total value
based on project performance
New estimates:
EAC = AC + ETCbottom-up
Work performed at the budgeted rate:
EAC = AC + ( BAC - EV)
Considering both SPI and CPI factors:
EAC = AC + ( [ BAC - EV ] / [ CPIcumulative x SPIcumulative ] )
Ratio CPI/SPI = 80/20, 50/50, others
Work performed at the present CPI:
EAC = BAC / CPIcumulative
#3 To-Complete Performance Index
To-Complete Performance Index
TCPI is the calculated projection of cost
performance that must be achieved on the
remaining work to meet a specified
management goal, such as the BAC or the
EAC.
TCPI as the work remaining (BAC minus EV)
devided by the funds remaining (BAC minus
AC, or EAC minus AC)
Formula TCPI = [ BAC - EV ] / [ BAC - AC ]
Or TCPI = [ BAC - EV ] / [ EAC - AC ]