DAILY STATUS FOLLOW UP SHEET
P Module
R Week Date Day HCM
I April 30 2018 Monday
What is done
Discussed organizational
management process flow
and organizational
May 18 2018 Friday structure.
May 19 2018 Saturday
May 20 2018 Sunday
Identified Time
May 21 2018 Monday Management process
4
finalized time
May 22 2018 Tuesday management process
Identified payroll process
Week 4
and discuss on payroll BBP
May 23 2018 Wednesday questioners
compiled business
processess we identified so
May 24 2018 Thursday far.
sent compiled HCM
process flow and
May 25 2018 Friday description
May 26 2018 Saturday
May 27 2018 Sunday
May 28 2018 Monday
PA BBP workshop
prepare process flow per the discussion
made at the workshop.
OM BBP workshop
Public Holiday
Delivered(sent) HCM master data template. Expecting full employee master data latest by June
15,2018.
For Identified PA actions, process work flow and process description first draft delivered(sent).
Comment/s required.
on 'tomorrow's discussion we should be able to finalize all pending issues so that we will be able to
wright the BBP on solid ground starting next week.
Public Holiday
HCM BBP Recap session planned for tomorrow 30th May. We have so many pending issues
including the BBP questioner, enterprise and personnel structure.... If we are not able to close
these issues in this session it might have an impact meeting our blue print dead line.
whole new processes added, incorporated that in our BBP (full and final settlement )
there were few issues Mr Dawit wanted to take some time before decision. He gave us his decision
today.