DAILY PROGRAMME

Project Name: YAS SOUTH DEVELOPMENT-Infrastructure,Public Realm,Car Park''shell Ref No: YSD-P01-0005-PM-HIL-RP-000017
and Core'' and Dry Stack(Boat storage facility)
Client : MIRAL Date : February 11, 2017

Engineer : KBR Contract No: M-ZOZ-INFRA/025/TEN/16/001

Consultant: Hyder Consulting Middle East Limited

Contractor: Hilalco

Resource Availability / HSE statistics

EQUIPMENT DIRECT MANPOWER INDIRECT MANPOWER

Availability Availability
Name Active Idle Total Name Hrs Name Hrs
status status

Grader 0 Foreman 10 0 Project Director 10 0


Vibro Roller 0 Ganger 10 0 Project Manager 1 10 10
Dozer 0 Mason 2 10 20 Const. Manager 1 10 10
Trailer Water Tanker 0 Mason Helper 10 0 HSE Manager 10 0
Wheel Loader 0 Carpenter 2 10 20 Material Manager 10 0
Long body pickup 1 1 Carpenter Helper 10 0 Contracts Manager 1 10 10
Cargo Truck - 3 Ton 0 Steel Fixer 10 0 Quantity Surveyor 1 10 10
Double Cabin Pickup 0 Steel Fixer Helper 10 0 Sr. Planning Engineer 1 10 10
Heavy Bus 0 Pipe Fitter 1 10 10 Planning Engineer 1 10 10
HIAB 1 1 Welder 10 0 Sr. Site Engineer 1 10 10
Minibus 1 1 Labour 2 10 20 Jr. Engineer 1 10 10
Passeger Bus 0 Painter 10 0 QA / QC Engineer 1 10 10
Crane 0 Pump Operator 10 0 General Foreman 1 10 10
Water Tanker 0 LD Driver 2 10 20 Foreman 1 10 10
Excavator 0 HD Driver 1 10 10 Sr. Surveyor 1 10 10
Skid Loader 0 Operators 10 0 Surveyor 1 10 10
Loader Backhoe 0 Electrician 1 10 10 Asst. Surveyor 2 10 20
Cargo Truck - 7 Ton 0 Grade Checker 10 0 Draughtsman 3 10 30
Flat Bed Trailer 0 Rakeman 10 0 Safety Officer 10 0
Telehandler 0 Screw man 10 0 HSE Advisor 1 10 10
Plate Compactor 0 Chainman 5 10 50 Male Nurse 10 0
Air Compressor 0 Rigger 10 0 Material Engineer 10 0
Dewatering pump 0 Safety labour 10 0 Asst.Material Engineer 10 0
Tower light 0 10 0 Lab Technician 10 0
Trailer 0 10 0 Assist. Lab Technician 10 0
Hand Roller 0 10 0 Store Keeper 10 0
P.T.R 0 10 0 Secretary 1 10 10
Paver 0 10 0 Public Relation officer 10 0
0 10 0 Document Controller 2 10 20
0 10 0 Time Keeper 1 10 10
0 10 0 Office Boy 1 10 10
0 10 0

TOTAL 3 3 TOTAL 16 A 160 Total 24 B 240

TOTAL EQUIP. Hr
Total Manpower = 40 Total Manhour = A + B 400
HSE Statistics
Near Miss LTI Lost work day case MTC First Aid Reportable incident Property damage/Accident

Temperature Weather
Maximum : 27°c sunny ü
Minimum : 20°c foggy
Humidity : 59% windy
Dusty
Cloudy
Rainy
Sign: Sign:
Job Title:
Job Title: Sr. Planning Engineer Construction Manager.

02-073YSD-P01-0005-OA-HYD-FO-000017
Prepared By Senthil Murugan Checked/Approved by Dimitrios Liasidis
Page : 1

02-073YSD-P01-0005-OA-HYD-FO-000017
DAILY PROGRAMME :

Programme of works for 12-02-2017

System Area Activity Description Quantity Road

Area 1 OGL Recording 2 Roads - MC05 &


MC06
Survey Works
General Control Point shifting & traversing NA

Erection of Security cabin at gate no 3 NA

Miscelaneous
Works

Sewer

Storm water

Potable water

Irrigation

Street Light

Electrical

Gas network

Page : 2

YSD-P01-0005-OA-HYD-FO-000017
Planned V/s Actual for the Program of 11-02-2017

System Area /Road Activity Description Planned Qty Achieved Qty Remarks

Area 1 Topographic survey Partial Partial


Survey Works
General Control Point Shifting & traversing Planned In Progress

Erection of Security cabin at gate no


In Progress
3
Miscelaneous
Works

Sewer

Storm water

Potable water

Irrigation

Street light

Electrical

Page : 3

YSD-P01-0005-OA-HYD-FO-000017
we 27.01.17
Site office layout marking completed
Laydown area marking completed
Area-1 Marking of Plots as required by KBR
Area -4 centre line marking rd. No MB-13

26th centre line marking rd. No MB-13


27th No work
28th centre line marking rd. No MB-14
29th centre line marking rd. No MB-3/Area5
30th
Prepared by. Reviewed by. Approved by.

Signature

Name
Job Title
Date
DAILY PROGRAMME
Project Name: YAS SOUTH DEVELOPMENT-Infrastructure,Public Realm,Car Park''shell Ref No: YSD-P01-0005-PM-HIL-RP-000013
and Core'' and Dry Stack(Boat storage facility)
Client : MIRAL Date : February 6, 2017

Engineer : KBR Contract No: M-ZOZ-INFRA/025/TEN/16/001

Consultant: Hyder Consulting Middle East Limited

Contractor: Hilalco

Resource Availability / HSE statistics

EQUIPMENT DIRECT MANPOWER INDIRECT MANPOWER

Availability Availability
Name Active Idle Total Name Hrs Name Hrs
status status

Grader 0 Foreman 10 0 Project Director 10 0


Steel Roller 0 Ganger 1 10 10 Project Manager 10 0
Dozer 0 Mason 6 10 60 Const. Manager 1 10 10
Trailer Water Tanker 0 Mason Helper 10 0 HSE Manager 10 0
Wheel Loader 0 Carpenter 31 10 310 Material Manager 10 0
Long body pickup 1 1 Carpenter Helper 10 0 Contracts Manager 1 10 10
Cargo Truck - 3 Ton 0 Steel Fixer 24 10 240 Quantity Surveyor 1 10 10
Double Cabin Pickup 3 3 Steel Fixer Helper 10 0 Sr. Planning Engineer 2 10 20
Heavy Bus 0 Pipe Fitter 10 0 Planning Engineer 1 10 10
4x4 Cars/Car 0 Welder 10 0 Sr. Site Engineer 1 10 10
Minibus 1 1 Labour 14 10 140 Jr. Engineer 1 10 10
Passeger Bus 1 1 Painter 10 0 QA / QC Engineer 1 10 10
Crane 0 Pump Operator 10 0 General Foreman 1 10 10
Water Tanker 0 LD Driver 7 10 70 Foreman 2 10 20
Excavator 0 HD Driver 10 0 Sr. Surveyor 1 10 10
Skid Loader 0 Operators 10 0 Surveyor 1 10 10
Loader Backhoe 0 Electrician 1 10 10 Asst. Surveyor 2 10 20
Cargo Truck - 7 Ton 0 Grade Checker 10 0 Draughtsman 3 10 30
Flat Bed Trailer 0 Rakeman 10 0 Safety Officer 10 0
Telehandler 0 Screw man 10 0 HSE Advisor 2 10 20
Plate Compactor 0 Chainman 5 10 50 Male Nurse 10 0
Air Compressor 0 Rigger 10 0 Material Engineer 10 0
Dewatering pump 0 Safety labour 1 10 10 Asst.Material Engineer 10 0
Tower light 0 10 0 Lab Technician 10 0
Trailer 0 10 0 Assist. Lab Technician 10 0
Hand Roller 0 10 0 Store Keeper 10 0
P.T.R 0 10 0 Secretary 1 10 10
Paver 0 10 0 Public Relation officer 10 0
0 10 0 Document Controller 1 10 10
0 10 0 Office Boy 1 10 10
0 10 0 10 0
0 10 0

TOTAL 6 6 TOTAL 90 A 900 Total 24 B 240

TOTAL EQUIP. Hr
Total Manpower = 114 Total Manhour = A + B 1140
HSE Statistics
Near Miss LTI Lost work day case MTC First Aid Reportable incident Property damage/Accident

Temperature Weather
Maximum : 20°c sunny ü
Minimum : 15°c foggy
Humidity : 56% windy
Dusty
Cloudy
Rainy
Sign: Sign:
Job Title:
Job Title: Sr. Planning Engineer Construction Manager.

02-073YSD-P01-0005-OA-HYD-FO-000017
Prepared By Senthil Murugan Checked/Approved by Dimitrios Liasidis
Page : 1

02-073YSD-P01-0005-OA-HYD-FO-000017