ID Task Task Name Duration Start Finish Predecessors Resource Names Jan 14, '18

Mode S M T W T F
1 Initiation Phase 15 days Mon 1/15/18 Fri 2/2/18
2 Assigning Project 2 days Mon 1/15/18 Tue 1/16/18 Anu,Dibesh,Mahesh Anu,Dibesh,Mahesh
Manager
3 Identifying 3 days Mon 1/15/18 Wed 1/17/18 Anu Anu
Stakeholder
4 Requirement 0 days Wed 1/17/18 Wed 1/17/18 2,3 1/17
Gathering
5 Prepare business 4 days Fri 1/19/18 Wed 1/24/18 4,3 Anu,Dibesh,Mahesh Anu,
case
6 Preliminary Approval
0 days Thu 1/25/18 Thu 1/25/18 5
7 Preparing Project 3 days Fri 1/26/18 Tue 1/30/18 Anu,Dibesh,Mahesh
Charter

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: msproj11
Date: Mon 5/28/18 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary

Page 1
Jan 21, '18 Jan 28, '18 Feb 4, '18
F S S M T W T F S S M T W T F S S M T W T F S

,Dibesh,Mahesh

Anu

1/17

Anu,Dibesh,Mahesh

1/25
Anu,Dibesh,Mahesh

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: msproj11
Date: Mon 5/28/18 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary