Draft for public consultation

Guidelines for construction


specifications and reports
For landfills, leachate ponds, composting facilities and wastewater lagoons
Draft for public consultation

Guidelines for construction specifications and reports for landfills, leachate ponds, composting facilities and
wastewater lagoons

This draft has been released for public consultation. Comments are sought on the guideline, including areas where you
think it might be improved. To assist us in reviewing and improving the guideline, please:

• Identify issue/s of concern and reference the relevant section/s and page number/s in the guideline.

• Succinctly provide information regarding your issue/s of concern.

• Provide suggestions on how your issue/s of concern could be addressed.

• Provide any other information that you deem necessary to be included or excluded from the guideline.

Responses should be sent to the project manager:

Patrick Nganga
Environment Protection Authority
GPO Box 2607
Adelaide SA 5001

Telephone: (08) 8204 1639


Facsimile: (08) 8124 4674
Free call (country): 1800 623 445

Email: epainfo@epa.sa.gov.au (please mark it to the attention of Patrick Nganga)

Closing date for comments is 5 pm, 24 December 2009.

ISBN 978-1-921495-06-9

November 2009

Disclaimer

This publication is a guide only and does not necessarily provide adequate information in relation to every situation. This
publication seeks to explain your possible obligations in a helpful and accessible way. In doing so, however, some detail
may not be captured. It is important, therefore, that you seek information from the EPA itself regarding your possible
obligations and, where appropriate, that you seek your own legal advice.

© Environment Protection Authority

This document may be reproduced in whole or part for the purpose of study or training, subject to the inclusion of an
acknowledgment of the source and to it not being used for commercial purposes or sale. Reproduction for purposes other
than those given above requires the prior written permission of the Environment Protection Authority.
Table of contents
Summary ..............................................................................................................................................................................1

1 Introduction ...................................................................................................................................................................3

2 Key elements of the Technical Specifications document.........................................................................................4

3 As Constructed Report (ACR) ...................................................................................................................................13

4 Approval and commissioning....................................................................................................................................16

5 References...................................................................................................................................................................17

6 Glossary.......................................................................................................................................................................18

List of figures
Figure 1 Documentation and process for design, construction and commissioning of facilities........................................6
Summary
The Environment Protection Authority (EPA) has prepared this guideline to provide details on the preparation of the
following construction documents:

• Technical Specifications

• As Constructed Reports (ACR).

In general, Technical Specifications consists of Design Drawings of the project, a Construction Quality Assurance (CQA)
Plan and a Construction Management Plan (CMP). The drawings provide the project conceptual model to all
stakeholders. The CQA Plan ensures that quality measures are implemented and documented during construction,
whereas the CMP provides a means of managing potential environmental impacts during construction and potential risks
to people that may come into contact with the project.

The ACR provides details on project initiation, construction methodology and the testing regime of all the materials used
during the construction. The ACR documents the activities and quality assurance undertaken in relation to the
construction of the project.

Projects of environmental significance are required to submit the Technical Specifications document to the EPA for
assessment and approval prior to construction, and the ACR immediately after construction. The proponent should
receive written approval from the EPA that the ACR is satisfactory and before the facility is ready to be used.

This guideline has been prepared to assist project proponents, consultants, engineers, construction companies and
others in preparing Technical Specifications and the ACR for landfills, leachate ponds, composting pad liners and
wastewater lagoons.

This guideline is meant to promote the principles of ecologically sustainable development as provided in Part 2 of the
Environment Protection Act 1993.

1
Guidelines for construction specifications and reports

1 Introduction
The design of landfill cells, leachate ponds, composting facilities and wastewater lagoons depends on the proposed
capacity, site geology, separation distances to sensitive receptors, costs, etc. The types of materials used to construct
the various facilities and the testing regime varies accordingly. Despite the variability in the levels of design, construction
methodologies and materials used, it is the role of the EPA to ensure that the required standards necessary to protect
human health and the environment are met.

The purpose of this guideline is to provide consistency in the preparation of Technical Specifications and As Constructed
Reports (ACR). It has been developed to address large-scale developments and some of the details may not be
applicable to small-scale and low-risk developments.

The scope and detail of the reports will depend on the nature and complexity of the project. If the scale of the project is
such that Technical Specifications and ACR documents are required, then the relevant elements provided in this
guideline should be addressed.

1.1 Intended users

The intended users of this guideline are project proponents, consultants, engineers, construction companies and others
associated with the design and construction of:

• new landfill cells

• leachate ponds

• composting pad liners

• wastewater lagoons.

The above listed entities are hereafter referred to as facilities.

1.2 Further guidance

The guideline has been developed with due regard to the following standards and guidelines:

• Australian Standard AS 3798–2007 Guideline on earthworks for residential and commercial developments.

• EPA 2006, Draft landfill survey requirements (unpublished).

• EPA 2007, Draft guidelines for composting works in South Australia1

• EPA 2007, Environmental management of landfill facilities (municipal solid waste and commercial and industrial
general waste)2

• EPA 2009, Draft Guidelines for Wastewater and evaporation lagoon construction3.

1
<www.epa.sa.gov.au/xstd_files/Waste/Public%20consultation/composting_guidelines.pdf>
2
<www.epa.sa.gov.au/xstd_files/Waste/Guideline/guide_landfill.pdf>
3
In preparation.

3
Guidelines for construction specifications and reports

2 Key elements of the Technical Specifications document


The preparation of Technical Specifications documents related to the design, construction and commissioning of facilities
is outlined in Figure 1. At a minimum, the document should include:

• design drawings

• a Construction Quality Assurance (CQA) Plan

• a Construction Management Plan (safety/risk management plan and environmental management plan).

The level of adherence to the Technical Specifications ultimately determines the quality of the project and influences the
performance and the constructed facility.

The Technical Specifications document should be submitted to the EPA at least three months prior to the proposed
construction commencement date to allow sufficient time for review, amendments where required and approval.
Sufficiently clear and comprehensive detail needs to be provided to the EPA to allow meaningful review and to assist in
reducing the likelihood of further information requests and potential for resulting delays.

The Technical Specification document should be submitted to the EPA for assessment and approval prior to commencing
construction of the facility.

2.1 Design drawings

Final design drawings for construction contain all the information necessary for the contractor to bid and build a particular
project (Choi 2004).

Design drawings are to be provided within the Technical Specifications document and should show details on layout,
measurements, cross-sectional and vertical profiles. This information is required as scale drawings of the facility to be
constructed. Design concepts should be presented in such a way that:

• the project can easily be understood

• they visually communicate the concept to the facility owner and the contractor

• they are legible

• they include all information from previous revisions and updates.

Design drawings need to demonstrate to the EPA and other stakeholders that the project design complies with the
minimum requirements for the specific facility4 to be built to protect human health and the environment.

The engineering design drawings should include the following aspects:

• site layout and the location of the facility to be constructed

• plan views

• detailed designs and cross-sectional profiles of the facility

• dimensions and units

4
For example details on the design requirements for landfill cells are provided in the Environmental management of landfill
facilities (municipal solid waste and commercial and industrial general waste) [EPA 2007].

4
Guidelines for construction specifications and reports

• gradients

• titles and scales that meet the required standards and units

• adequate labelling

• all elevations should be referenced to metres Australian Height Datum (mAHD)

• be dated and signed by the designer.

5
Guidelines for construction specifications and reports

Key elements of the Technical Specifications document

Design drawings Construction Quality Assurance (CQA) Construction Management Plan (CMP):
• Layout plans Plan: – Safety/risk management:
• Horizontal • Scope of works • induction of employees
and • quality measures • hazard identification, risk
vertical • roles and responsibilities assessment and control.
profiles, etc. • inspection and testing • accident/incident investigation
• pre-qualification testing and reporting
• verification methods
– Environmental Management:
• use of geosynthetic materials
• traffic control
• CQA for geosynthetic materials
• fuel and chemical spill control and
• hold points, timeframes &
clean up
milestones
• erosion and sediment control
• non-conformance and corrective
• noise
action procedures
• dust
• EPA contact.
• excavation soil
• litter
• waste management.

Submit the Technical Specifications document to the EPA for assessment and approval prior to construction

Construct facility or entity in accordance with the approved Technical Specifications

Prepare an As Constructed Report


(ACR):
• scope of works
• site preparation earthworks
• geosynthetic materials
• daily inspection logs
• field tests data sheets
• laboratory tests data sheets
• photographs
• survey and as built drawings

Submit the As Constructed Report to the EPA for assessment and approval prior to
commencing use of facility

Figure 1 Documentation and process for design, construction and commissioning of facilities

6
Guidelines for construction specifications and reports

2.2 Construction Quality Assurance (CQA) Plan

A CQA Plan provides a means of managing quality during construction and demonstrating to the stakeholders (owner,
contractors, consultants, regulator, and the general public) that the construction complies with the project requirements.
The CQA Plan ensures that the materials used, construction methods and completed works will be able to achieve the
required outcomes for the facility in line with the Technical Specifications, the relevant standards and EPA Guidelines.

2.2.1 Scope of works

A brief description of the project should be provided that includes the scope of the construction works. The main
undertakings of the project that will determine hold points should be listed.

2.2.2 Quality measures

The CQA Plan should be developed to reflect the best quality management measures. The standards of the measures
should mirror those in other quality documents for example:

• Civil Contractors Federation (CCF)—CCF Civil Construction Management Code for the Civil Construction Industry,
TQCS International Pty Ltd, 2002.

• ISO 9001:2000 Quality Management Systems–Requirements.

• Project-specific Australian Standards, eg AS3798–2007 Guidelines on earthworks for commercial and residential
developments 5, and other standards for specific test methods.

2.2.3 Roles and responsibilities

The CQA Plan should define clear roles, responsibilities and communication lines for implementation of the plan and for
contact with the EPA.

2.2.4 Inspection and testing

Inspection and testing requirements for earthworks are provided in the Australian Standard AS 3798–2007 Guidelines on
earthworks for commercial and residential developments. The guidelines provide that the earthworks for a project should
be inspected and tested at regular and appropriate intervals to assess whether the quality of materials and workmanship
provided on a project are consistent with the design requirements. The level of inspection and testing required will
depend on the scale and scope of the project and the nature of the materials used.

Most earthworks will require Level 1 or Level 2 inspection and testing to be carried out by a Geotechnical Inspection and
Testing Authority (GITA). The GITA is usually a person independent from the company doing the works. The owner of the
project should retain a suitably qualified independent professional to regularly inspect the project during construction. The
EPA is however prepared to accept inspection and testing conducted by someone working for the owner of the project
provided it is undertaken in accordance with the standard and agreed plans. This person needs to be suitably qualified
and experienced to be able to conduct the requisite sampling, testing, record keeping including daily logs and standard of
reporting expected and associated with the requirements of the project.

The EPA requires Level 1 GITA supervision and testing at all projects that use clay as construction material for barrier
systems including liners and capping layers. The EPA reiterates that Level 1 supervision is a full-time commitment to
having the GITA or their representative on site at all times while earthwork operations are undertaken. The frequency and

5
Available from <www.saiglobal.com>

7
Guidelines for construction specifications and reports

nature of inspections and testing required for the project should be clearly stated. The standard also provides minimum
testing rates and examples of forms to be used.

Level 2 inspection and testing is similar to Level 1 except that a geotechnical testing authority (GTA) will be appointed to
carry out sampling and testing as required or specified. The Level 2 GTA may or may not be required to provide a report
at the completion of the project. The EPA may require Level 2 GTA supervision on small projects that require a limited
level of reporting but are not large enough to warrant Level 1 GITA supervision.

The requirements for Level 1 or 2 geotechnical authority inspections and testing will be determined by the nature of the
project, construction materials to be used and construction methodology. The testing and inspection plan should
document the nature of work activity and work performed during the inspection. The ACR report prepared by the
GITA/GTA needs to provide sufficient details, evidence, certification and sign-off by the GITA/GTA that the works have
been constructed in accordance with the Technical Specifications.

2.2.5 Pre-qualification testing

Materials testing should be undertaken prior to use to determine suitability for purpose. In the case of clay construction,
clay properties (Atterberg limits, plasticity, liquid limit, particle size distribution, Emerson class, permeability, calcium
carbonate content, acid solubility, clay content, etc) need to be provided in the design specifications and to the EPA for
assessment prior to construction.

2.2.6 Verification methods

The methods and procedures to verify compliance with the project plans and specifications need to be stated in the CQA
Plan including:

• verification procedures and/or standards to be used

• persons responsible to carry out the verification

• frequency of verification, eg daily, weekly, etc

• reporting.

2.2.7 Use of geosynthetic materials6

Geosynthetics may be defined as synthetic materials, mostly plastic, which are commonly used in place of, or enhance
the function of, natural soil materials (Sharma and Lewis 1994). The three types of geosynthetics commonly used in
landfills or wastewater lagoons are geomembranes, geosynthetic clay liners (GCLs) and geotextiles.

Geomembranes are flexible, polymeric sheets that have extremely low permeability and are typically used as liquid or
vapor barriers (Daniel and Koerner 1995). Base lining systems typically use a High-Density Polyethylene (HDPE)
geomembrane.

GCLs are very low permeability barriers consisting of a layer of unhydrated, loose granular or powdered bentonite which
is chemically or mechanically adhered to a geotextile or geomembrane (Sharma and Lewis 1994). GCLs are typically
5–10 mm thick and have approximately 5 kg/m2 of bentonite (Daniel and Koerner 1995). The rolls are 4–5 m wide,
30–60 m long, weigh up to 1,800 kg each and are wrapped in the factory to prevent premature hydration.

6
The use of geosynthetic materials in landfills is also provided in Guidelines for environmental management of landfill
facilities (municipal solid waste and commercial and industrial general waste) [EPA 2007].

8
Guidelines for construction specifications and reports

Geotextiles are permeable textiles made from polymeric fibres. They are used for various functions including filtration
above leachate collection systems, separation between clay liners and leak detection geonets, or for protection of
geomembranes beneath leachate collection or leak detection gravel.

Geosynthetic materials may be considered as an alternative or supplement to a compacted clay liner as part of an
engineered barrier layer especially in locations where low permeability clays are not readily available. Geosynthetics
used as part of the barrier system may include:

• geomebranes in conjunction with a compacted clay liner

• a geosynthetic clay liner (GCL) in conjunction with a compacted clay liner

• a geomembrane in conjunction with a GCL

• exclusive use of geosynthetic liner materials.

2.2.8 CQA for geosynthetic materials

The EPA requires that the installation of geosynthetic materials be undertaken or supervised by a person experienced in
installing such materials. Site conditions, material quality and installation procedures followed will determine the overall
field performance of the facility.

Most GCL manufacturers, for example, recommend the following factors to be considered as a means of improving GCL
field performance:

• compatibility/hydraulic performance with fluid to be contained

• compatibility with cover materials/gradation of cover materials

• gradient impacts on performance

• proper cover material thickness/confining pressure

• subgrade preparation/gradation

• construction/installation practices and detail construction

• physical damage during or subsequent to installation

• stability (while full/during draw-down)

• control over GCL hydration/desiccation

• hydraulic performance under site specific conditions

• design/product selection

• proper GCL selection, suitable subgrade materials, proper orientation of the GCL, geotextiles, diligent installation
techniques and reliance upon manufacturer experience are essential in project success.

Further information on the use and construction quality assurance requirements including for geosynthetic materials used
in landfill base liners and capping is provided in Chapters 7, 10 and 11 in the EPA’s Guidelines for Environmental
management of landfill facilities (municipal solid waste and commercial and industrial general waste) [EPA 2007].

2.2.9 Hold points, timeframes and milestones

The project should be broken down into the main phases or activities to allow evaluations and amendments that might be
required at the end of each phase. A timeframe for completing the main phases should be provided in the form of a Gantt
chart or other similar charts. The main phases in the construction of a landfill cell, for example, include:

• establishment of the cell layout

• bulk excavations

• sub-grade preparation

9
Guidelines for construction specifications and reports

• clay liner or composite liner construction

• leachate drainage layer construction.

The above referenced hold points allow the survey to be undertaken for comparison with design levels and to ascertain
the thicknesses of the clay liner and drainage aggregate. The hold points also allow corrective measures to be
undertaken.

2.2.10 Non-conformance and corrective action procedures

The CQA Plan needs to provide procedures for identifying non-conformance and for corrective action. The plan should
state that the project will at least address the following:

• the nature of the non-conformance and its level of effect on the project

• determination if the non-conformance is an isolated incident or a recurring problem

• how amendments to procedures to prevent future occurrences of the non-conformance will be implemented

• the nature of corrective action to be applied to rectify that specific non-conformance (eg re-compaction and testing)

• the procedures and persons to be notified of the non-conformance and corrective measures

• procedures for reporting to the EPA major exceptions/variations to the approved technical specifications.

2.2.11 EPA contact

The EPA should be provided with the opportunity to monitor and inspect elements of the construction. Notification should
occur at least two weeks prior to commencement of the key elements of the works, including set out, subgrade
preparation and construction of the other project elements.

2.3 Construction management plan (CMP)

The CMP provides a means of managing potential risks to people that may come into contact with the project during
construction and pollution management. Prior to commencement of construction activities, construction personnel and
others directly involved with the project should be inducted on the CMP plan which consists of:

• a risk management plan, and

• an environmental management plan.

2.3.1 Safety/risk management

Project proponents should determine from SafeWork SA the required safeguards that should be implemented and
observed during construction.

2.3.2 Induction of employees

All employees, labour hire workers and subcontractors should be inducted prior to the start of a project on the following:

• environmental management plans

• occupational health, safety and wellness (OHS&W)

• accidents/incident investigation and reporting

• hazard identification, risk assessment and control.

2.3.3 Hazard identification, risk assessment and control

Hazard identification is the process for identifying things that have the potential to cause human injury, ill health and/or
damage to property or the environment. Risk assessment defines the process of evaluating the severity and the

10
Guidelines for construction specifications and reports

probability (likelihood) of harm or damage occurring from exposure to a hazard and the likely consequence of that harm
or damage. The hazard management process includes:

• identifying the hazard

• assessing the risks

• evaluating risks

• controlling the risks

• monitoring and review.

2.3.4 Accident/incident investigation and reporting

Prior to commencement of a project, a plan should be developed and implemented that deals with the management of
accidents/incidents. Accidents/incidents involving actual (or near misses) should be reported, recorded and investigated
followed by remedial action to ensure that such accidents/incidents do not re-occur.

2.3.5 Environmental Management Plan (EMP)

Obligations on the general environmental duty are provided under section 25(1) of the Environment Protection Act 1993
as follows:

A person should not undertake an activity that pollutes, or might pollute, the environment unless the person
takes all reasonable and practicable measures to prevent or minimise any resulting environmental harm.

An EMP provides a means of managing environmental aspects and impacts to reduce potential pollution and should
include the following:

Traffic control

Traffic will be expected to increase during the construction phase of a project. The project contractor or superintendent
should ensure that a traffic control plan is developed and communicated to all personnel. Appropriate safety signs
including barricades should be understandable, visible and well positioned to provide clear directions and a safe working
environment.

Fuel and chemical spill control and clean up

If fuel or chemicals are to be stored on site, it should be in a bunded area as outlined in EPA Guideline, Bunding and spill
management (EPA 2007)7.

Erosion and sediment control

Site preparation works, excavations and the movement of traffic will erode and size-reduce in-situ materials and, in
particular, weathered soils. Fine-grained particles resulting from these activities thereafter become easily transported or
washed away as sediment in stormwater. In order to avoid sediment transport during rainfall periods, excavated areas
should remain open for the least amount of time. An erosion and sediment control plan should be developed prior to
starting a construction project. Such a plan should include a site sketch indicating the pathways and fate of stormwater.
Erosion and sediment control measures include but not limited to:

• sediment fences

• designated paths for traffic

7
<www.epa.sa.gov.au/xstd_files/Waste/Guideline/guide_bunding.pdf>

11
Guidelines for construction specifications and reports

• stormwater drains around work areas and ponds

• stabilisation of uncovered areas with vegetation or erosion mats.

The above measures would minimise the amount of disturbance to the in-situ soils and to aid in the separation of
contaminated stormwater. More information on erosion and sediment control can be obtained from the Code of practice
for the building and construction industry (EPA 1999)8.

Noise

Noise resulting from construction-related activities should be managed in accordance with the South Australian
Environment Protection (Noise) Policy 2007. Noise-generating construction activities, include for example, site
preparation work, demolition work, building maintenance or repair work, the operation of vehicles within, entering, or
leaving, a construction site, and any activities at or within the immediate vicinity of a construction site that is connected
with work at the site.

Dust

Dust management measures should be planned for areas and activities that are likely to be sources of dust during the
construction phase. Dust control measures should include:

• the use of dust suppressants in all dust generating areas

• minimising dust generating activities especially during periods of hot dry weather

• educating contractors and site personnel on measures to minimise dust

• monitoring of non-compliances and complaints regarding dust

• applying corrective measures.

Excavation soil

The soils referred to here are the naturally occurring soils resulting from bulk excavations and earthworks. Stockpiles
should be located at least 10 m from drainage swales. The EPA generally requires that maximum stockpile heights for
material management or resource recovery activities be in the range of 3–5 metres as provided in the Guideline for
stockpile Management: waste and waste derived products for recycling and reuse (EPA 2009)9. The management of
waste soils that result from bulk excavations are covered in this guideline.

Litter

Litter is defined as a disorderly accumulation of objects that may include carelessly discarded refuse, paper, bottles,
cigarette butts, etc. The contractor or the person responsible for the construction project should ensure that a litter
management plan is developed and implemented during the duration of the project.

Waste management

Construction activities normally generate extraneous mixed waste that needs to be properly managed. The EPA
encourages waste resulting for construction or other activities to be managed with due regard to the waste hierarchy;
avoid, reduce, reuse, recycle. Waste reduction should be made a priority from the start to completion of a project.
Containers should be provided and clearly labelled for materials to be recycled and for disposal. Waste should be
removed for recycling or disposal on a regular basis.

8
<www.epa.sa.gov.au/xstd_files/Water/Code%20of%20practice/bccop1.pdf>
9
<www.epa.sa.gov.au/xstd_files/Waste/Guideline/guidelines_stockpile.pdf>

12
Guidelines for construction specifications and reports

3 As Constructed Report
The ACR is a documentation of activities during the construction of a project. It should be submitted for assessment once
construction has been completed and approval received before the facility is commissioned (Figure 1). It is the role of the
GITA or the person appointed by the project proponent to prepare the ACR document which should confirm that the
facility was constructed in accordance with the technical specifications.

3.1 Scope of works

The ACR should include sufficient information to demonstrate that the approved technical specification has been
complied with, including the following:

• Identification of the engineering components that were constructed including:

− a comparison of the constructed components to the technical specification

− a summary of how the construction was impacted by the weather and other difficulties

− a description of measures undertaken to ensure that constructed components were not damaged during
construction.

• Results of all observations, testing, and calculations necessary to comply with the technical specifications.

• All alterations that deviate from the approved technical specification as follows:

− a listing of all alterations and corresponding alternatives

− all alteration requests and supporting documentation

− detail of any reworking required and resulting tests to demonstrate ultimate compliance.

• Results of all surveys and survey maps as outlined in the Draft landfill survey requirements (unpublished).

• Exceptions and corrective actions.

• Report of independent Geotechnical Inspection and Testing Authority (GITA) in accordance with AS 3798–2007.

• A definitive statement by the GITA to confirm that the facility has been constructed in accordance with the technical
specification.

• A statement from an independent organisation that the construction complies with the specifications and drawings.

3.2 Site preparation earthworks

Details regarding site preparation earthworks should be provided, for example:

• Methods used to clear the site.

• Plant and equipment used, ie compactors, graders, excavators, etc.

• The fate of cover materials removed.

• Sub-grade preparation—the condition of the subgrade and if any improvements are required before liner
construction, HDPE or GCL installation.

• Sub-grade compaction requirements are provided in the relevant guidelines referenced in section 1.2.

• Sub-grade testing frequency.

• Survey level of the subgrade and its position relative to the groundwater table.

• Clay liner construction:

− liner construction methodology including that of key-in and overlap sections, placement of layers, etc.

− moisture conditioning

13
Guidelines for construction specifications and reports

− compaction methodology and caliber of equipment used

− moisture-density relationships.

3.3 Geosynthetic materials

If geosynthetic materials are used in any part of the construction, then the following information should be provided in the
ACR:

• Extent of the works.

• Preparation and condition of the subgrade prior to geosynthetic material installation.

• Geosynthetic material properties.

• To-scale as-built drawings with panel layout showing areas and types of HDPE placed including roll numbers,
sample, tests and repair locations.

• Sourcing, delivery and storage procedures.

• Labelling of rolls—roll number, batch number, product identification, thickness of material and types (eg smooth or
textured for the case of HDPEs), roll dimensions, direction to unroll and manufacturer’s name.

• Details on the construction of anchor trenches.

• Geosynthetic materials deployment procedures—works should be undertaken by an experienced geomembrane


installation specialist.

• Panel seams welding procedures (for HDPEs) or overlap construction procedures of GCLs.

• Manufacturer’s test certificates and specifications data:

− Quality Control (QC) certificates of the resin used to make the geomembrane

− A QC certification that property values given in the properties sheet are guaranteed by the geomembrane
manufacturer. The QC certificate shall include roll numbers and identification, resin lot, batch numbers,
sampling procedures and quality control tests.

3.4 Daily inspection logs

The geotechnical professional appointed by the licensee shall keep records of daily inspections that detail visual
observations including weather conditions, field testing, sampling, and other information pertaining to construction
activities. These logs should be provided as one of the appendices in the ACR or otherwise upon the request of the EPA.

3.5 Field test data sheets

All field sampling and tests should be recorded in the daily inspection logs. Testing and sampling locations and the nature
of the tests should be clearly indicated on a site map.

3.6 Laboratory tests data sheets

Laboratory test results and the corresponding Australian Standards used should be provided for each construction
material and related tests as required.

3.7 Photographs

Photographs should be taken before, during and after completion of construction works and provided in a digital format
in the ACR. Photographs should be taken periodically during the entire duration of the construction and additional
pictures should be taken of items of specific interest. The captions of all photographs should contain the name of the
project, the date on which the photograph was taken and the identity of the feature being photographed.

14
Guidelines for construction specifications and reports

3.8 Survey and as built drawings

Surveys of constructed profiles (eg top of subgrade, base of sump, top of finished liner, top of drainage aggregate, etc)
need to be provided in order to:

• verify conformance to the engineering design drawings in relation to dimensions, units, tolerances and special
positions

• provide a record from which measurement of work or material volumes can be determined.

3.8.1 Qualifications of surveyor

Surveys need to be certified as being correct by a licensed or registered surveyor in accordance with the Survey Act
1992 and Regulations (Part 3—Licensing and Registration, Division 2: Licences and Registrations), or a person who is a
full member of the Institution of Surveyors, Australia Incorporated. All drawings shall include a statement of certification
signed by the licensed/registered surveyor.

3.8.2 Features to be surveyed, density of data

A survey should be a true and accurate representation of the feature(s) being surveyed. The density and location of
points need to be determined by the surveyor on site and selected appropriately to achieve this accuracy. Where the
surveyor determines that the surface being surveyed is not sufficiently regular (eg a gravel surface that has not been
closely levelled to limit damage to the underlying liner, or the surface of a sump), a greater density of points should be
used to characterise the surface. Notwithstanding the above, to ensure the quality of each survey, the following should be
performed as a minimum:

• The grid density used should be of no fewer points than typically 10 m x 10 m.

• All changes of grade need to be picked up by a survey string of points, with a minimum 10-m point spacing along the
strings. Changes of grade result from (but are not limited to) sumps, crest lines, drainage lines, interfaces with side
slopes, etc.

• A survey string defining the outer extent/limit of the survey should be included.

• All levels need to be in metres AHD. Drawings should state clearly the coordinate system that has been used for the
project. Levels and isopach values should be to two decimal places, eg 2.34 m.

15
Guidelines for construction specifications and reports

4 Approval and commissioning


Once the EPA is satisfied that the ACR satisfies the requirements of the project-specific technical specification, it will
provide written confirmation to permit commissioning of the facility. The proponent may not operate the facility until such
written approval is provided.

16
Guidelines for construction specifications and reports

5 References
Australian Standard AS 3798-2007, Guideline on earthworks for residential and commercial developments.

Choi, Ying-Kit 2004, Principles of applied civil engineering design, American Society of Civil Engineers, ASCE Press,
New York, 208 pp.

Civil Contractors Federation (CCF) 2002, CCF Civil Construction Management Code for the Civil Construction Industry,
TQCS International Pty Ltd.

Daniel, DE and RM Koerner 1995, Waste containment facilities –Guidance for construction, Quality Assurance and
Quality Control of Liner and Cover Systems, American Society of Civil Engineers, ASCE Press, New York, 354 pp.

Das BM 2002, Principles of Geotechnical Engineering, Brooks/Cole Thomson Learning, United States.

Environment Protection Act 1993 <www.legislation.sa.gov.au>.

Environment Protection Authority 1999, Code of practice for the building and construction industry, viewed 20 November
2009, EPA, Adelaide, <www.epa.sa.gov.au/xstd_files/Water/Code%20of%20practice/bccop1.pdf>.

–––2007, Draft guidelines for composting works in South Australia, viewed 20 November 2009, EPA, Adelaide,
<www.epa.sa.gov.au/xstd_files/Waste/Public%20consultation/composting_guidelines.pdf>.

–––2007, Environmental management of landfill facilities (municipal solid waste and commercial and industrial general
waste), viewed 20 November, EPA, Adelaide, <www.epa.sa.gov.au/xstd_files/Waste/Guideline/guide_landfill.pdf>.

–––2007, Bunding and spill management, viewed 20 November, EPA, Adelaide,


<www.epa.sa.gov.au/xstd_files/Waste/Guideline/guide_bunding.pdf>.

–––2009,Guideline for stockpile management: Waste and waste derived products for recycling and reuse, viewed 20
November 2009, EPA, Adelaide, <www.epa.sa.gov.au/xstd_files/Waste/Guideline/guidelines_stockpile.pdf>.

Environment Protection (Noise) Policy 2007 <www.legislation.sa.gov.au>.

Sharma HD and PL Sangeeta 1994, Waste Containment Systems, Waste Stabilization, and Landfills: Design and
Evaluation, John Wiley & Sons, New York.

Stam TG 2000, Geosynthetic Clay Liner–Field Performance, Bentofix Technologies Inc, Serrot International Inc,
Henderson, NV, USA..

US Environment Protection Agency 1999, Voluntary Guide for Industrial Waste Management, Chapter 7B–Designing and
Installing Liners–Technical Considerations for New Surface Impoundments, Landfills, and Waste Piles, USEPA.

17
Guidelines for construction specifications and reports

6 Glossary

AHD Australian Height Datum, the datum (adopted by the National Mapping
Council of Australia) to which all vertical control for mapping is to be
referred, where mean sea level is set as an elevation of 0 metres.

Atterberg limits10 The moisture content, in percent, at which the transition from solid to semi-
solid takes place is defined as the shrinkage limit. The moisture content at
the point of transition from semisolid to plastic state is the plastic limit, and
from plastic to liquid state is the liquid limit. These parameters are also
known as Atterberg limits.

Geosynthetics5 Fabric-like materials made from polymers such as polyester, polyethylene,


polypropylene, polyvinyl chloride (PVC), nylon, chlorinated polyethylene,
and others.

As Constructed Report An ‘As Constructed Report’ is a documentation of work performance,


Construction Quality Control (CQC) and Construction Quality Assurance
(CQA) associated with a construction project.

Composting Works The conduct of works at which mushroom or other compost is produced or
is capable of being produced at a rate exceeding 200 tonnes per year.

CQC are measures taken by the installer or contractor to ensure


Construction Quality Control (CQC)
compliance with the installation specifications.

Construction Quality Assurance (CQA) CQA is third party verification of quality. The objective of a CQA Plan is to
ensure that the construction materials used, construction methods and
completed works comply with the approved Technical Specifications.

Isopachytes (also known as isopachs) Contours showing lines of equal difference between two sets of data.

Leachate11 Liquid that has percolated through or drained from solid waste or other
man-emplaced materials and contains soluble, partially soluble, or miscible
components removed from such waste.

The final document should emphasise that areas of responsibility and/or


authority were clearly defined, understood, and accepted by all parties
involved in the project.

10
Das BM, 2002
11
Daniel ED and RM Koerner, 1995

18
Guidelines for construction specifications and reports

Level 1 GITA Supervision: AS 3798 The primary objective of Level 1 Geotechnical Inspection and Testing is for
(2007)12 the Geotechnical Inspection and Testing Authority (GITA) to be able to
express an opinion on the compliance of the work. The GITA is responsible
for ensuring that the inspection and testing is sufficient for this purpose.

The superintendent should agree on a suitable inspection and testing plan


prior to the commencement of the works.

On completion of the earthworks, the GITA will usually be required to


provide a report setting out the inspections, sampling and testing it has
carried out, and the locations and results thereof. Unless very unusual
conditions apply, the GITA should also be able to express an opinion that
the works (as far as it has been able to determine) comply with the
specification and drawings.

Level 2 GTA A Geotechnical Testing Authority (GTA) officer will be appointed to carry
out sampling and testing as required or specified. The GTA is responsible
for selecting the location of sampling and testing operations within each
visit made to the site. The superintendent is responsible for advice as to
when such visits are required and is responsible for ensuring that sufficient
samples and tests are taken over the project.

On completion of the earthworks, the GTA may be required to provide a


report, setting out the sampling and testing it has carried out, and the
locations and results thereof. The GTA will not be in a position to express
any opinion beyond this as to the compliance of the works with the
specification or their suitability for any particular purpose.

Suitably qualified consultant A person, who holds relevant qualifications, has demonstrated professional
experience and expertise encompassing an appropriate range of
competencies and is either a full member or is eligible for full membership
of one of the following or equivalent professional organizations:

1 The institution of Engineers Australia

2 The Association of Consulting Engineers Australia

3 The Australian Contaminated Land Consultants Association


Incorporated.

12
Detailed information on Level 1 and Level 2 supervision is provided in Australian Standard AS 3798-2007 Guideline on
earthworks for residential and commercial developments.