Project :Metro Bay 25mm 12mm

Subject :Revised structural estimate


Date :June 12,2018

Pile Cap
length width area depth volume V
PLC-1 16 units 4 2.8 11.2 1.15 12.88 206.08
PLC-2 6 units 4 4 16 1.15 18.4 110.4
PLC-3 45 units 2.8 2.8 7.84 1.15 9.016 405.72
PLC-4 1 units 16 1.15 18.4 18.4
PLC-5 2 units 2.8 4 11.2 1.15 12.88 25.76
Total V concrete 766.36

bars along length bars along width


pcs top pcs bottom pcs top pcs
PLC-1 16 units 13 5.3 13 5.3 15 4.2 15
PLC-2 6 units 18 5.3 18 5.3 15 5.3 15
PLC-3 45 units 11 4.2 11 4.2 13 4.2 13
PLC-4 1 units
PLC-5 2 units 14 4.2 14 4.2 15 5.3 15

Pedestal
length width area depth volume V

1 at ramp 1 unit 0.9 0.9 0.81 0.81


2 at ramp 1 unit 0.9 1.8 1.62 1.62
3 at ramp 1 unit 0.9 2.1 1.89 1.89

alternative!
70 units 0.9 0.9 0.81 2 1.62 113.4 30 pcs
10mm

ng width cont. bar


bottom pcs total 25mmtotal 12mm
4.2 2 2.65 263.8 5.3
5.3 2 3.85 349.8 7.7
4.2 2 2.65 201.6 5.3
0 0
5.3 2 3.85 276.6 7.7

vert. Bars hoop 1 hoop 2 hoop 3


2 3.5 2.85 2.75
25mm 12mm 10mm

lef
15 @ 100
Tie beam beam size cont. Top cont. Bot web stiffen hoops
TB-1 length b d pcs pcs
GL-1 9 units 9 0.7 0.8 4 4 1-12mm
GL-2 9 units 9 0.7 0.8 4 4
GL-3 9 units 9 0.7 0.8 4 4
GL-4 9 units 9 0.7 0.8 4 4
GL-5 9 units 9 0.7 0.8 4 4
GL-6 1 unit 11.5 0.7 0.8 4 4
1 unit 6.5 0.7 0.8 4 4
7 units 9 0.7 0.8 4 4
GL-7 1 unit 11.5 0.7 0.8 4 4
1 unit 6.5 0.7 0.8 4 4
7 units 9 0.7 0.8 4 4

TB-2
GL-a to jù 60 units 9 0.7 0.8 4 4
mid right
@150 15 @ 100
hoops